Blockage removal apparatus for ore bin

By designing the ore bin clearing equipment for coal mining, the combined action of vibration and drilling components is used to achieve automatic clearing of mineral materials in the ore bin, solving the problems of low coal transportation efficiency and operator safety, and improving Improve transportation efficiency and safety.

WO2024198472A1PCT designated stage expired Publication Date: 2024-10-03HUANENG COAL TECH RES CO LTD
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2023/136461
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-03-29
Filing Date
2023-12-05
Publication Date
2024-10-03

AI Technical Summary

Technical Problem

In the process of coal mining, large pieces of materials such as coal and gangue produced by the shearer during the coal cutting process are easy to accumulate on the loader, causing the conveyor to be blocked and affecting the transportation efficiency. In the existing technology, the scraper loader unloads the materials. The section opening cannot be closed, which affects the safety and convenience of workers and requires manual cleaning.

Method used

A mine silo clearing equipment is designed, including a vibration component, a drill pipe assembly and an intermediate transmission assembly. The main drive component drives the intermediate transmission assembly, the vibration connecting arm drives the vibration arm to vibrate reciprocally, and the drill pipe assembly drives the drill pipe movement to achieve control. The synchronous vibration and drilling of mineral materials in the ore bin automatically clear blockages.

Benefits of technology

It realizes the efficient removal of mineral materials in the ore silo without manual cleaning, maintains the transportation status of the conveyor, improves the efficiency of coal transportation, and ensures the safety of operators.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023136461_03102024_PF_FP_ABST
    Figure CN2023136461_03102024_PF_FP_ABST
Patent Text Reader

Abstract

A blockage removal apparatus for an ore bin, the apparatus comprising a vibration assembly (100), a drill rod assembly (200), an intermediate transmission assembly (300) and a main driving member (400), wherein the vibration assembly comprises a vibration arm (110) and a vibration connecting arm (120); the drill rod assembly comprises a drill rod (210) and a drill rod connecting arm (220); the intermediate transmission assembly comprises an intermediate driving member (310), a first intermediate power output end (311) of the intermediate driving member being in transmission connection with the vibration connecting arm, and a second intermediate power output end (312) of the intermediate driving member being in transmission connection with the drill rod connecting arm; and the main driving member is connected to the intermediate driving member, so as to drive the intermediate transmission assembly to move. By means of the apparatus, synchronous vibration and ore drilling can be achieved, such that accumulated ore in the ore bin is efficiently removed.
Need to check novelty before this filing date? Find Prior Art

Description

Ore bin clearing equipment Technical Field

[0001] The present application relates to the technical field of ore mining, and in particular to an ore bin blockage clearing device. Background Art

[0002] During the coal cutting process, the coal mining machine pushes the coal to the vicinity of the unloading port of the transfer machine, and it cannot fall directly onto the transfer machine chute. During the transportation process, large pieces of coal, metal anchors, gangue, etc. will accumulate at the transfer point and hinder the movement of the conveyor. Sometimes large pieces of coal unloaded from the conveyor are easily stuck in the fixed baffle opening of the middle trough of the transfer machine.

[0003] In existing technologies, the unloading section of a scraper transfer machine is open and cannot be fully enclosed. This prevents workers from working above the transfer machine during normal operation. This not only affects the worker's operational convenience but also fails to ensure their personal safety. Consequently, the machine must be stopped and manually cleaned before continuing operations, reducing transportation efficiency. Summary of the Invention

[0004] The purpose of this application is to provide a ore bin blockage clearing device to solve the technical problem of low coal transportation efficiency.

[0005] The ore bin blockage clearing equipment provided in this application includes:

[0006] A vibration assembly includes a vibration arm and a vibration connecting arm connected to the vibration arm, wherein the vibration connecting arm is slidably connected to the ore bin wall;

[0007] A drill rod assembly, comprising a drill rod and a drill rod connecting arm connected to the drill rod;

[0008] An intermediate transmission assembly includes an intermediate drive member having a first intermediate power output end and a second intermediate power output end, wherein the first intermediate power output end is transmission-connected to the vibration connecting arm, and the second intermediate power output end is transmission-connected to the drill pipe connecting arm; and

[0009] A main driving member, wherein the power output end of the main driving member is connected to the driving body of the intermediate driving member to drive the intermediate transmission assembly to move.

[0010] Optionally, the main driving member includes a first linear driving member and a first rotating driving member, the power output end of the first linear driving member is fixedly connected to the driving body of the intermediate driving member, the driving body of the first linear driving member is transmission-connected to the power output end of the first rotating driving member, and the driving body of the first transmission driving member is fixedly arranged relative to the transfer machine.

[0011] Optionally, in the intermediate driving member, the first intermediate power output end and the second intermediate power output end are independent of each other.

[0012] Optionally, the intermediate transmission assembly further includes an intermediate transfer seat, the driving body of the intermediate driving member is fixed on the intermediate transfer seat, and the intermediate transfer seat is fixed on the power output end of the first linear driving member.

[0013] Optionally, in the vibration assembly, the vibration connecting arm includes a first connecting rod and a second connecting rod, the first end of the first connecting rod is fixed to the vibration arm and is slidably connected to the wall of the ore bin, the second end of the first connecting rod is hinged to the first end of the second connecting rod, and the second end of the second connecting rod is hinged to the first intermediate power output end, and the vibration arm can perform reciprocating linear motion under the joint action of the main drive member, the intermediate drive member and the vibration connecting arm.

[0014] Optionally, in the vibration component, the vibration connecting arm also includes a third connecting rod, which is connected between the second connecting rod and the first intermediate power output end, the first end of the third connecting rod is hinged to the second end of the second connecting rod, and the second end of the third connecting rod is hinged to the first intermediate power output end.

[0015] Optionally, the vibration assembly further comprises a guide rod, the guide rod being fixed to the ore bin wall and slidably connected to the vibration arm, the guide rod being parallel to and spaced apart from the first connecting rod;

[0016] And / or, it further includes a buffer member, which is loosely sleeved on the first connecting rod and arranged in the gap between the vibrating arm and the ore bin wall.

[0017] Optionally, in the drill rod assembly, the drill rod connecting arm is a second linear drive member, the power output end of the second linear drive member is transmission-connected to the drill rod, the driving body of the second linear drive member is connected to the second intermediate power output end, and the drill rod can move to a preset position under the joint action of the main drive member, the intermediate drive member and the drill rod connecting arm.

[0018] Optionally, the drill rod assembly further includes a first drill rod driving component, the power output end of the first drill rod driving component is connected to the drill rod to drive the drill rod to rotate, and the driving body of the first drill rod driving component is transmission-connected to the power output end of the second linear driving component to drive the first drill rod driving component to move linearly.

[0019] Optionally, the drill rod assembly further includes a second drill rod driving member, which is arranged between the first drill rod driving member and the second linear driving member. The driving body of the first drill rod driving member is fixed to the power output end of the second drill rod driving member to drive the first drill rod driving member to rotate / swing. The driving body of the second drill rod driving member is fixed to the power output end of the second linear driving member to drive the second drill rod driving member and the first drill rod driving member to move linearly; the rotation axis of the drill rod is set at an angle to the rotation axis of the second drill rod driving member.

[0020] The ore bin blockage clearing equipment provided by this application has the following beneficial effects:

[0021] The ore bin blockage clearing equipment provided in the embodiment of the present application is used. During use, the main drive component drives the intermediate transmission component to move. At the same time, the intermediate transmission component drives the vibration arm to vibrate back and forth through the vibration connecting arm to loosen the ore in the ore bin. The intermediate transmission component also drives the drill rod to move through the drill rod connecting arm. At the same time, the drill rod can rotate around itself to drill the ore in the ore bin, thereby achieving synchronous vibration and drilling of the ore, thereby efficiently realizing the automatic clearing of the ore accumulated in the ore bin. There is no need for manual cleaning, so there is no need to shut down the equipment, and the conveying state of the conveyor can continue to be maintained, effectively improving the transportation efficiency of coal and other mineral materials. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are merely embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without any creative work.

[0023] FIG1 is a schematic structural diagram of a ore bin blockage clearing device according to an embodiment of the present application;

[0024] FIG2 is a schematic structural diagram of the intermediate transmission component portion in the ore bin blockage clearing device according to an embodiment of the present application, in the direction F2 in FIG1 ;

[0025] FIG3 is a schematic structural diagram of the drill rod assembly portion in the direction F1 in FIG1 in the ore bin blockage clearing device according to an embodiment of the present application;

[0026] FIG4 is a schematic structural diagram of the main drive component portion of the ore bin blockage clearing device according to an embodiment of the present application, in the direction F3 in FIG1 ;

[0027] FIG5 is a schematic structural diagram of the first support in the ore bin blockage clearing equipment according to an embodiment of the present application.

[0028] Description of reference numerals:

[0029] 010- ore bin wall; 020- conveyor belt;

[0030] 100-vibration component;

[0031] 110-vibrating arm;

[0032] 120-vibration connecting arm;

[0033] 121-first connecting rod; 122-second connecting rod; 123-third connecting rod;

[0034] 130-guide rod; 140-buffer;

[0035] 200-drill rod assembly;

[0036] 210-drill pipe;

[0037] 220-drill pipe connecting arm; 221-second linear drive member;

[0038] 230 - first drill rod driving member;

[0039] 240 - second drill rod driving member;

[0040] 250-first support;

[0041] 260-second support;

[0042] 300-intermediate transmission assembly;

[0043] 310-intermediate drive member;

[0044] 311-first intermediate power output end; 312-second intermediate power output end;

[0045] 320- transfer seat;

[0046] 400-main drive parts;

[0047] 410 - first linear drive member;

[0048] 420 - first rotating driving member;

[0049] 430-base.

[0050] in:

[0051] A: The direction of rotation of the drill rod driven by the first drill rod driving member;

[0052] B: The second drill rod driving member drives the first drill rod driving member / drill rod to rotate / swing in the direction;

[0053] C: The drill rod connecting arm (second linear drive member) drives the second drill rod drive member / drill rod in the linear motion direction;

[0054] D: The intermediate drive member drives the rotation / swing direction of the drill rod connecting arm / drill rod, and drives the rotation / swing direction of the vibration connecting arm;

[0055] E: the rotation / swing direction of the first linear drive member driven by the first rotary drive member;

[0056] F1, F2, and F3 are the viewing directions indicated in the figure. DETAILED DESCRIPTION

[0057] The following will clearly and completely describe the technical solution of this application in conjunction with the accompanying drawings. Obviously, the embodiments described are only part of the embodiments of this application, not all of them. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making any creative efforts are within the scope of protection of this application.

[0058] The present application is further described in detail below through specific embodiments and in conjunction with the accompanying drawings.

[0059] An embodiment of the present application provides an ore bin blockage clearing device, as shown in FIG1 to FIG5 , which includes: a vibration assembly 100 , a drill rod assembly 200 , an intermediate transmission assembly 300 and a main drive component 400 .

[0060] The vibration assembly 100 includes a vibration arm 110 and a vibration connecting arm 120 connected to the vibration arm 110. The vibration connecting arm 120 is slidably connected to the ore bin wall 010.

[0061] The drill rod assembly 200 includes a drill rod 210 and a drill rod connecting arm 220 connected to the drill rod 210;

[0062] The intermediate transmission assembly 300 includes an intermediate driving member 310 having a first intermediate power output end 311 and a second intermediate power output end 312. The first intermediate power output end 311 is transmission-connected to the vibration connecting arm 120, and the second intermediate power output end 312 is transmission-connected to the drill pipe connecting arm 220.

[0063] The power output end of the main driving member 400 is connected to the driving body of the intermediate driving member 310 to drive the intermediate transmission assembly 300 to move.

[0064] The ore bin blockage clearing device provided by the embodiment of the present application is used, taking coal mining as an example. This embodiment takes the coal accumulated at the coal bin loading and unloading port as an example. During use, the main drive member 400 works to drive the intermediate transmission assembly 300 to move. At the same time, the intermediate transmission assembly 300 drives the vibration arm 110 to vibrate back and forth through the vibration connecting arm 120 to loosen the coal in the coal bin. At the same time, the intermediate transmission assembly 300 moves through the drill rod connecting arm 220, thereby driving the drill rod 210 to move. The drill rod 210 can rotate around itself to drill. The coal in the coal bunker, that is, the main driving component 400 simultaneously drives the vibration component 100 and the drill rod component 100 to move synchronously, realizing synchronous vibration and drilling of the coal, thereby efficiently realizing automatic clearing of the coal accumulated in the coal bunker, which is equivalent to an automatic clearing robot arm device. When the coal in the coal bunker accumulates, the main driving component 400 can be controlled to synchronously realize vibration and drilling of the coal, without manual cleaning, so there is no need to shut down the equipment, and the conveying state of the conveyor can be maintained, which effectively improves the transportation efficiency of coal and other mineral materials.

[0065] In the ore bin blockage clearing device of the present embodiment, the main drive member 400 includes a first linear drive member 410 and a first rotary drive member 420. The power output end of the first linear drive member 410 is fixedly connected to the drive body of the intermediate drive member 310, which is in transmission connection with the power output end of the first rotary drive member 420. The drive body of the first transmission drive member 420 is fixed relative to the transfer machine. This arrangement enables the intermediate drive member 310 to not only undergo linear motion adjustment under the action of the first linear drive member 410, but also to rotate / swing under the action of the first rotary drive member 420. This makes the intermediate drive member 310 more flexible, with a wider adjustment range and greater adaptability, to accommodate blockages of different sizes and different storage locations. Furthermore, it facilitates remote manual control of the blockage clearing operation, improving the working environment and personal safety.

[0066] In the ore bin blockage clearing device of the present embodiment, the first intermediate power output end 311 and the second intermediate power output end 312 of the intermediate drive member 310 are independent of each other. This arrangement enables the intermediate drive member 310 to independently control the vibrating arm 110 and the drill rod 210 to independently loosen the coal, thereby flexibly controlling the operating states of both according to the actual accumulation of coal in the coal bin.

[0067] In the ore bin blockage clearing device of the embodiment of the present application, the intermediate transmission assembly 300 also includes a transfer seat 320. The drive body of the intermediate drive member 310 is fixedly mounted on the transfer seat 320, and the transfer seat 320 is fixedly mounted on the power output end of the first linear drive member 410. The configuration of the transfer seat 320 can be adaptively adjusted in structural design based on the structural characteristics of the intermediate drive member 310. When selecting the intermediate drive member 310 and the first linear drive member 410, there is no need to consider the adaptability of the mounting structure between the various drive members; it is only necessary to provide a connection structure on the transfer seat 320 that is compatible with the corresponding drive member. In this embodiment, the intermediate drive member 310 includes two independently arranged servo motors, both of which are mounted on the transfer seat 320. As shown in Figure 2, the first intermediate power output end 311 is the output shaft of one of the servo motors, and the second intermediate power output end 312 is the output shaft of the other servo motor.

[0068] In the ore bin blockage clearing device of the embodiment of the present application, in the vibration assembly 100, the vibration connecting arm 120 includes a first connecting rod 121 and a second connecting rod 122. The first end of the first connecting rod 121 is fixedly connected to the vibration arm 110 and is slidably connected to the ore bin wall 010. The second end of the first connecting rod 121 is hinged to the first end of the second connecting rod 122, and the second end of the second connecting rod 122 is hinged to the first intermediate power output end 311. The vibration arm 110 is capable of reciprocating linear motion under the combined action of the main driving member 400, the intermediate driving member 310, and the vibration connecting arm 120. With this arrangement, under the driving action of the intermediate driving member 310, the vibration arm 110 is driven by the second connecting rod 122 and the first connecting rod 121 to achieve reciprocating linear motion, thereby loosening the coal material. The structure is simple and easy to implement.

[0069] In the mine bin blockage clearing device of the embodiment of the present application, in the vibration assembly 100, the vibration connecting arm 120 further includes a third connecting rod 123. The third connecting rod 123 is connected between the second connecting rod 122 and the first intermediate power output end 311. The first end of the third connecting rod 123 is hinged to the second end of the second connecting rod 122, and the second end of the third connecting rod 123 is hinged to the first intermediate power output end 311. During operation, the intermediate driving member 310 can drive the third connecting rod 123 to rotate / swing, thereby driving the second connecting rod 122, the first connecting rod 121, and the vibration arm 110 to move. In this case, the third connecting rod 123 acts as a crank or rocker.

[0070] In the mine bin blockage clearing device of the embodiment of the present application, the vibration assembly 100 also includes a guide rod 130, which is fixed to the mine bin wall 010 and slidably connected to the vibration arm 110. The guide rod 130 is parallel to the first connecting rod 121 and is arranged at intervals; the setting of the guide rod can ensure the vibration direction of the vibration arm 110 and ensure the stability of its vibration operation.

[0071] In the ore bin blockage clearing device of the present embodiment, the vibration assembly 100 further includes a buffer member 140. The buffer member 140 is loosely mounted on the first connecting rod 121 and disposed in the gap between the vibration arm 110 and the ore bin wall 010. During vibration of the vibration arm 110, the buffer member 140 effectively cushions the impact of the vibration arm 110 on the ore bin wall 010, thereby ensuring the service life of the device.

[0072] In the ore bin blockage clearing device of the present embodiment, the vibration assembly 100 further includes a fixed block, which is fixedly mounted on the outer wall of the ore bin and has a guide hole. The first connecting rod 121 is loosely inserted into the guide hole. The provision of the fixed block effectively extends the length of the guide hole. In this case, the guiding function is not limited by the thickness of the ore bin wall 010. It should be noted that in addition to the aforementioned hinged connection, the first connecting rod 121 and the second connecting rod 122 can also be fixedly connected. In this case, the second connecting rod 122 is also loosely inserted into the fixed block.

[0073] In the mine bunker blockage clearing device of the present embodiment, in the drill rod assembly 200, the drill rod connecting arm 220 serves as a second linear drive 221. The power output end of the second linear drive 221 is transmission-connected to the drill rod 210, and the drive body of the second linear drive 221 is connected to the second intermediate power output end 312. The drill rod 210 is capable of moving to a predetermined position under the combined action of the main drive 400, the intermediate drive 310, and the drill rod connecting arm 220. When the drill rod connecting arm 220 is configured as the second linear drive, linear motion of the drill rod 210 is achieved, thereby further expanding the range of movement of the drill rod 210 within the coal bunker and thereby accommodating a wide range of coal accumulation conditions.

[0074] In the mine bin blockage clearing equipment of the embodiment of the present application, the drill rod assembly 200 also includes a first drill rod driving component 230. The power output end of the first drill rod driving component 230 is connected to the drill rod 210 to drive the drill rod 210 to rotate. The driving body of the first drill rod driving component 230 is transmission-connected to the power output end of the second linear driving component 221 to drive the first drill rod driving component 230 to move linearly.

[0075] In the coal bunker blockage clearing device of the present embodiment, the drill rod assembly 200 further includes a second drill rod driver 240, which is disposed between the first drill rod driver 230 and the second linear driver 221. The driving body of the first drill rod driver 230 is fixed to the power output end of the second drill rod driver 240 to drive the first drill rod driver 230 to rotate / swing. The driving body of the second drill rod driver 240 is fixed to the power output end of the second linear driver 221 to drive the second drill rod driver 240 and the first drill rod driver 230 to move linearly. The rotation axis of the drill rod 210 is arranged at an angle to the rotation axis of the second drill rod driver 240. This arrangement enables the drill rod 210 to not only rotate about itself but also rotate / swing about the rotation axis of the second drill rod driver 240, further expanding the range of motion of the drill rod 210 and enabling the drill rod 210 to adjust its position in the entire three-dimensional space within the coal bunker, thereby accommodating a wider range of coal accumulation conditions.

[0076] It should be noted that in the ore bin blockage clearing equipment of the embodiment of the present application, in order to adapt to the structure between the corresponding drive members, non-standard supports are provided between adjacent drive members in the drill rod assembly 200. For example, a first support 250 is provided between the first drill rod drive member 230 and the second drill rod drive member 240. Its structure only needs to be able to adapt to the connection part of the corresponding drive member, as shown in Figure 5, and its specific structure is not limited here. A second support 260 is provided between the second drill rod drive member 240 and the second linear drive member 221, and its specific structure is also not limited. The main drive member 400 is also provided with a base 430 to support the first rotating drive member 420. The base 430 can be fixedly mounted on the transfer machine.

[0077] The first drill rod driving member 230, the second drill rod driving member 240, and the first rotary driving member 420 can all be selected as servo motors. The first linear driving member 410 and the second linear driving member 221 can both be selected as electric cylinders.

[0078] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some or all of the technical features therein. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present application.

Claims

1. A mine silo clearing device, characterized in that: include: A vibration assembly (100) comprises a vibration arm (110) and a vibration connecting arm (120) connected to the vibration arm (110), wherein the vibration connecting arm (120) is slidably connected to a ore bin wall (010); A drill rod assembly (200) comprises a drill rod (210) and a drill rod connecting arm (220) connected to the drill rod (210); An intermediate transmission assembly (300) comprises an intermediate driving member (310) having a first intermediate power output end (311) and a second intermediate power output end (312), wherein the first intermediate power output end (311) is transmission-connected to the vibration connecting arm (120), and the second intermediate power output end (312) is transmission-connected to the drill rod connecting arm (220); as well as A main driving member (400), wherein a power output end of the main driving member (400) is connected to a driving body of the intermediate driving member (310) to drive the intermediate transmission assembly (300) to move.

2. The ore bin clearing equipment according to claim 1, characterized in that: The main driving member (400) includes a first linear driving member (410) and a first rotating driving member (420), wherein the power output end of the first linear driving member (410) is fixedly connected to the driving body of the intermediate driving member (310), the driving body of the first linear driving member (410) is transmission-connected to the power output end of the first rotating driving member (420), and the driving body of the first transmission driving member (420) is fixedly arranged relative to the transfer machine.

3. The ore bin clearing equipment according to claim 2, characterized in that: In the intermediate driving member (310), the first intermediate power output end (311) and the second intermediate power output end (312) are independent of each other.

4. The ore bin clearing equipment according to claim 3, characterized in that: The intermediate transmission assembly (300) further comprises an intermediate transfer seat (320), the driving body of the intermediate driving member (310) is fixedly mounted on the intermediate transfer seat (320), and the intermediate transfer seat (320) is fixedly mounted on the power output end of the first linear driving member (410).

5. The ore bin clearing equipment according to claim 1, characterized in that: In the vibration assembly (100), the vibration connecting arm (120) comprises a first connecting rod (121) and a second connecting rod (122); the first end of the first connecting rod (121) is fixedly connected to the vibration arm (110) and is slidably connected to a ore bin wall (010); the second end of the first connecting rod (121) is hinged to the first end of the second connecting rod (122); the second end of the second connecting rod (122) is hinged to the first intermediate power output end (311); and the vibration arm (110) is capable of reciprocating linear motion under the joint action of the main driving member (400), the intermediate driving member (310) and the vibration connecting arm (120).

6. The ore bin clearing equipment according to claim 5, characterized in that: In the vibration assembly (100), the vibration connecting arm (120) further comprises a third connecting rod (123), the third connecting rod (123) being connected between the second connecting rod (122) and the first intermediate power output end (311), the first end of the third connecting rod (123) being hinged to the second end of the second connecting rod (122), and the second end of the third connecting rod (123) being hinged to the first intermediate power output end (311).

7. The ore bin clearing equipment according to claim 6, characterized in that: The vibration assembly (100) further comprises a guide rod (130), wherein the guide rod (130) is fixedly mounted on the ore bin wall (010) and is slidably connected to the vibration arm (110), and the guide rod (130) is parallel to and spaced from the first connecting rod (121); And / or, it also includes a buffer member (140), wherein the buffer member (140) is loosely sleeved on the first connecting rod (121) and is arranged in the gap between the vibration arm (110) and the ore bin wall (010).

8. The ore bin clearing equipment according to claim 1, characterized in that: In the drill rod assembly (200), the drill rod connecting arm (220) is a second linear driving member (221); a power output end of the second linear driving member (221) is transmission-connected to the drill rod (210); a driving body of the second linear driving member (221) is connected to the second intermediate power output end (312); and the drill rod (210) can move to a preset position under the joint action of a main driving member (400), the intermediate driving member (310) and the drill rod connecting arm (220).

9. The ore bin clearing equipment according to the full coolant 8 is characterized in that: The drill rod assembly (200) further comprises a first drill rod driving component (230), wherein a power output end of the first drill rod driving component (230) is connected to the drill rod (210) to drive the drill rod (210) to rotate, and a driving body of the first drill rod driving component (230) is transmission-connected to a power output end of the second linear driving component (221) to drive the first drill rod driving component (230) to move linearly.

10. The ore bin clearing equipment according to claim 9, characterized in that: The drill rod assembly (200) further comprises a second drill rod driving member (240) which is arranged between the first drill rod driving member (230) and the second linear driving member (221); the driving body of the first drill rod driving member (230) is fixedly arranged at the power output end of the second drill rod driving member (240) to drive the first drill rod driving member (230) to rotate / swing; the driving body of the second drill rod driving member (240) is fixedly arranged at the power output end of the second linear driving member (221) to drive the second drill rod driving member (240) and the first drill rod driving member (230) to move linearly; and the rotation axis of the drill rod (210) is arranged at an angle to the rotation axis of the second drill rod driving member (240).

Citation Information

Patent Citations

  • Ore storage bin unblocking equipment

    CN116424724A

  • Discharging device of transfer bin

    CN212100249U

  • Blockage removing device for coal bunker inlet