Construction zone division device, construction zone division method, and program
By clustering construction blocks based on pre-construction heights and soil transport vectors, the method addresses inefficiencies in section division and soil transport, enhancing the earth distribution plan and construction efficiency.
Patent Information
- Application Number
- PCT/JP2023/015496
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-18
- Publication Date
- 2024-10-24
AI Technical Summary
In construction site earthwork, existing methods for dividing sections for cutting and filling often result in inefficiencies due to differences in soil transport directions and elevation differences at section boundaries, leading to inefficient soil transport and potential elevation discrepancies.
A device and method that cluster cut and embankment blocks into sections based on pre-construction heights and soil transport vectors to minimize work displacement, using a planning unit to determine optimal soil transport and a clustering unit to group blocks by dissimilarity, ensuring efficient section division for earth distribution planning.
This approach allows for efficient construction section division, minimizing soil transport differences and elevation discrepancies, thereby optimizing the earth distribution plan and improving construction efficiency.
Smart Images

Figure JP2023015496_24102024_PF_FP_ABST
Abstract
Description
Construction area division device, construction area division method and program
[0001] The present invention relates to a construction area division device, a construction area division method, and a program.
[0002] When creating a construction plan for land development work, the volume of earth to be cut and filled at the construction site is calculated, and an earthwork plan is created to allocate the volume of earth to the appropriate locations. When creating the earthwork plan, the construction area is divided into a cutting area where cutting will be performed and a filling area where filling will be performed.
[0003] Patent Document 1 discloses a method of dividing the current topography and the target topography into a plurality of element areas each having a cut attribute or a fill attribute, grouping adjacent element areas each having a cut attribute to generate a cut area, and grouping adjacent element areas each having a fill attribute to generate a fill area, or further dividing the cut area or fill area arbitrarily to generate a new cut area or fill area, and calculating the construction soil volume of each cut area and the construction soil volume of each fill area.
[0004] Japanese Patent Application Laid-Open No. 2021-101316
[0005] When dividing work sections, for example, if a boundary occurs within a cut section where the direction of earth movement to the filling section differs in two directions, the cut section may be divided at that boundary. However, when a cut section is divided at that boundary, the cutting and earth movement work in one cut section and the cutting and earth movement work in the other cut section are carried out separately. In this case, differences in the amount of earth moved may occur due to differences in work progress, etc. Here, if the cut height at the boundary is large, only one cut section may be cut and the other adjacent cut section may not, resulting in an elevation difference at the boundary. When cutting the other cut section, the work vehicle must again move to a higher elevation to perform cutting and earth movement work, which reduces work efficiency.
[0006] The present invention has been made in consideration of the above circumstances, and aims to divide construction areas appropriately when creating an earthwork plan.
[0007] In order to achieve the above object, the construction section division device of the present invention comprises: a planning unit that plans the amount of soil to be transported from each of a plurality of cut blocks whose pre-construction height is higher than the post-construction height to each of a plurality of fill blocks whose pre-construction height is lower than the post-construction height at a construction site divided into a plurality of blocks by minimizing the amount of work based on the length of the displacement vector from each cut block to each fill block under predetermined constraints; and a clustering unit that clusters the plurality of cut blocks into a first desired number of cut sections and clusters the plurality of fill blocks into a second desired number of fill sections, wherein the clustering unit calculates the degree of difference between the cut blocks and the degree of difference between the fill blocks using the pre-construction heights of the cut and fill blocks and the soil transport vectors that represent the amount and direction of soil to be cut from the cut blocks and piled into the fill blocks, and performs the clustering based on the calculated degree of difference.
[0008] According to the present invention, cut and fill blocks are clustered based on the degree of difference calculated using the pre-construction heights of the cut and fill blocks, thereby enabling appropriate division of construction areas when creating soil distribution plans.
[0009] 1 is a diagram showing the functional configuration of a construction zone division device according to an embodiment of the present invention. FIG. 2 is a diagram showing the hardware configuration of a construction zone division device according to an embodiment of the present invention. FIG. 3 is a flowchart showing the operation of construction zone division processing according to an embodiment of the present invention. FIG. 4 is a diagram showing a state in which a construction site has been divided into a plurality of meshes. FIG. 5 is a diagram showing a state in which the plurality of meshes into which the construction site has been divided have been classified as cut earth meshes or fill earth meshes. FIG. 6 is a diagram showing a state in which a construction site has been divided into a plurality of cut earth blocks and fill earth blocks. FIG. 7 is a diagram showing an example of soil transportation vectors. FIG. 8 is a diagram showing an example of dissimilarity calculation. FIG. 9 is a diagram showing an example of a process for agglomerating cut earth blocks and fill earth blocks based on dissimilarity. FIG. 10 is a diagram showing an example of a state in which work zones have been divided.
[0010] Hereinafter, a construction area dividing device according to an embodiment of the present invention will be described in detail with reference to the drawings.
[0011] As shown in Fig. 1, the construction section division device 1 includes a control unit 2 and a memory unit 3. The control unit 2 includes a current topography data acquisition unit 21 that acquires topography data showing the current topography of the land development construction site before construction, a designed topography data acquisition unit 22 that acquires topography data showing the designed topography of the land development construction site, a planning unit 23 that plans the amount of soil to be transported from a plurality of cut blocks to a plurality of fill blocks, and a clustering unit 24 that clusters the plurality of cut blocks and fill blocks into cut sections and fill sections.
[0012] The current topography data acquisition unit 21 retrieves two-dimensional or three-dimensional topography data showing the current topography of the proposed site before construction from a topography DB (database) 31 (described later) and acquires the necessary current topography data. The current topography data is used to calculate the cut and fill volumes and to determine the cut and fill blocks.
[0013] The design terrain data acquisition unit 22 reads two-dimensional or three-dimensional drawing data showing the final design surface of the proposed construction site from a design DB (database) 32 (described later) and acquires the necessary design terrain data. The design terrain data, together with the current terrain data, is used to calculate the cut and fill volumes and to determine the cut and fill blocks.
[0014] The planning unit 23 determines the optimal combination of cut earth blocks and fill earth blocks for transporting cut earth from a plurality of cut earth blocks and fill earth blocks. Specifically, the planning unit 23 divides the construction site into meshes based on the current topography data and the design topography data, and decomposes each mesh into cut earth elements or fill earth elements. The planning unit 23 generates cut earth blocks and fill earth blocks by combining the cut earth meshes and fill earth meshes that have been decomposed into cut earth elements or fill earth elements, and calculates the workload for each block from the distance from the cut earth block to the fill earth block and the amount of soil to be transported, and allocates the volume of soil so as to minimize the workload.
[0015] The clustering unit 24 groups a plurality of cut blocks to generate cut sections, and groups a plurality of fill blocks to generate fill sections, thereby clustering the construction site into cut sections and fill sections. Specifically, the clustering unit 24 calculates the dissimilarity between the cut blocks and between the fill blocks for a plurality of cut blocks and fill blocks, and clusters the cut blocks and fill blocks into cut sections and fill sections based on the calculation results. The dissimilarity is calculated based on the distance between the cut blocks and between the fill blocks, the vector length and direction (inner product) of the soil transport vector representing the amount and direction of soil transported from the cut blocks to the fill blocks, and the height of the blocks.
[0016] The storage unit 3 includes a topography DB 31 and a design DB 32. The topography DB 31 is a database that stores current topography data, and the design DB 32 is a database that stores designed topography data.
[0017] As shown in FIG. 2, the construction zone division device 1 includes a processor 41 that processes data according to a control program, a main memory 42 that functions as the processor's work area, an auxiliary memory 43 for long-term data storage, an input / output unit 44 that accepts and outputs data input, an operation unit 45, a display unit 46, a communication unit 47 for communicating with other devices, and a bus that interconnects these elements. The auxiliary memory 43 stores the control program executed by the processor 41. The operation unit 45 is a device for inputting various instructions to the control unit 2 and includes a keyboard, operation buttons, etc. The display unit 46 displays screens showing the execution results of various processes, operation screens, etc. The processor 41 reads the programs stored in the auxiliary memory 43 into the main memory 42 and executes them, thereby functioning as the current topography data acquisition unit 21, the design topography data acquisition unit 22, the planning unit 23, and the clustering unit 24 shown in FIG. 1.
[0018] FIG. 3 is a flowchart showing the construction area division process. As shown in FIG. 3, in step S101, the current topography data acquisition unit 21 of the control unit 2 accesses the topography DB 31 of the storage unit 3 to acquire current topography data for the site where land development is to be carried out. Next, in step S102, the design topography data acquisition unit 22 of the control unit 2 accesses the design DB 32 of the storage unit 3 to acquire design topography data for the site. Next, in step S103, the control unit 2 acquires the number of divisions for the construction area based on input from the operation unit 45 by the user. The construction area is divided into a cut area, which is an area where cutting will be performed, and a fill area, which is an area where filling will be performed. The user inputs desired values for each of the cut area and the fill area, and the cut area and the fill area are generated according to the input values. Once the construction area is generated, the volume of earth to be transported for the construction area is calculated and an earthwork plan is generated. Once the current topography data and the design topography data have been acquired, the planning unit 23 of the control unit 2 divides the current topography into meshes (step S104).
[0019] 4A shows the current topography of a construction site divided into multiple meshes. The meshes have, for example, a square shape. The meshes may have other shapes, such as triangles or hexagons. The square-shaped meshes have sides of 10 m. However, the present invention is not limited to this.
[0020] Once the land is divided into multiple meshes, the volume of cut and fill soil is calculated for each mesh. The planning unit 23 of the control unit 2 compares the current topography data with the design topography data. There are some locations where the height of the current topography (pre-construction height) is higher than the design topography (post-construction height), and other locations where it is lower. If the location is higher, that portion needs to be cut, and if the location is lower, that portion needs to be filled. The planning unit 23 determines whether each mesh needs to be cut or filled, and identifies meshes that need to be cut as cut meshes and meshes that need to be filled as fill meshes. Furthermore, the amount of cut soil is calculated for cut meshes, and the amount of fill soil is calculated for fill meshes. Figure 4B shows multiple meshes classified as cut meshes or fill meshes. Here, cut meshes are labeled C, and fill meshes are labeled F.
[0021] Returning to FIG. 3 , once mesh division is performed in step S104, the planning unit 23 of the control unit 2 generates cut blocks and fill blocks by grouping multiple cut meshes and fill meshes (step S105). FIG. 5A shows the state in which the construction site has been divided into multiple cut blocks and fill blocks. As shown in FIG. 5A , four adjacent meshes (2 vertical x 2 horizontal) are grouped to generate one block. The attributes of the generated block are identified based on the attributes of the meshes that make up the block. Block 51 in the upper left of FIG. 5A is identified as an fill block because all of the meshes that make up the block are fill meshes as shown in FIG. 4B. Block 52 is identified as both an fill block and a cut block because the upper two meshes and the lower two meshes that make up the block are fill meshes and cut meshes, respectively. Similarly to block 52, block 53 is identified as both an embankment block and a cut block because the upper two meshes of the meshes that make up the block are fill meshes and the lower two meshes are cut meshes. When the attributes of the other blocks are identified in the same manner as above, in the example of FIG. 5A, there are 21 cut blocks and 16 fill blocks. In FIG. 5A, cut blocks are assigned the symbol C, and fill blocks are assigned the symbol F. Blocks that are both cut blocks and fill blocks are assigned both the symbol C and the symbol F.
[0022] Once the blocks are generated, an earth transport vector is calculated in step S106. The earth transport vector represents the amount and direction of earth to be cut from the cut block and piled up in the fill block. The planning unit 23 calculates the optimal combination of cut block and fill block from which earth should be transported to which fill block.
[0023] Specifically, the minimum value of the objective function is found for the soil transport vector under certain constraints. The objective function is the product of the distance to transport soil and sand for a combination of cut and fill blocks and the volume of soil to be transported for each combination, i.e., the amount of work. Here, the distance between blocks is the straight-line distance. Note that this distance may also take into account the gradient.
[0024] The workload is Cutting Block C i (i = 1, 2, ..., N) to embankment block F j Volume of soil transported to (j = 1, 2, ..., M) V i,j ≧0 and Cutting block C i From embankment block F j Displacement vector d(C i , F j ) length L i,j = |d(C i , F j )| and, by Σ i=1 N Σ j=1 M V i,j L i,j It is defined as follows.
[0025] The following conditions are set as predetermined constraints: (1) Cut / fill difference of a certain cut block = total volume of soil transported from that cut block (2) Cut / fill difference of a certain fill block = total volume of soil transported to that fill block (3) Total volume of soil collected at each entrance = total volume of soil within the construction area with the plus and minus reversed (4) Total volume of soil exchanged between each entrance and a certain stockpile = total volume of soil in the stockpile
[0026] The condition (1) is to prevent the transport of soil into the cut block. Depending on the cut block, there may be a fill mesh that requires fill in addition to the cut mesh that requires cut. In this case, the fill in the fill mesh is not transported from a cut block other than the block in question, but is provided by the soil excavated from the cut mesh within the block in question. Therefore, soil cannot be transported into the cut block from other cut blocks.
[0027] Condition (2) is to prevent soil from being transported from the fill block. Depending on the fill block, there may be a cut mesh that requires cutting soil in addition to the fill mesh that requires filling. In this case, the cut soil excavated from the cut mesh is not transported to a block other than the block in question as soil, but is instead filled into the fill mesh within the block in question. Therefore, the fill block does not transport soil to other fill blocks.
[0028] Under the above constraints, the optimum soil transport vectors for the cut and fill blocks are calculated so that the volume and distance of soil are minimized. Figure 5B shows an example of the soil transport vectors calculated in this way. The line from the cut block to the fill block indicates the soil transport vector. For example, for cut block C, 5 is embankment block F 1 and F 6 The line is pointing towards the cut block C. 5 The excavated soil is placed in embankment block F. 1 and F 6 Also, cut earth block C 6 The excavated soil is placed in embankment block F. 1 , F 2 and F 5 Then, the cut earth block C 6 The excavated earth and sand is heading towards the entrance E. In the example of FIG. 5B, the total cut earth volume at the construction site is greater than the total fill earth volume. The earth and sand collected at the entrance E is transported to the outside. 1 The block has an embankment mesh in addition to the cut mesh, and the embankment block F 2 Here, from the above-mentioned constraint (1), the cut block C 1 The soil excavated from the cut mesh of the embankment block F 2 Block C is given priority in filling up the embankment mesh. 1 From embankment block F 2 The line pointing to indicates the earth moving vector for cutting and filling earth within the same block. 2 The required amount of fill in the cut block C 1Since the amount of excavated soil is greater than the amount of excavated soil from Block C, 2 and C 6 Excavated soil will also be transported.
[0029] Once the soil transport vectors have been calculated, the dissimilarity between the cut earth blocks and between the fill earth blocks is calculated in step S107. The dissimilarity between the cut earth blocks and between the fill earth blocks is calculated using the pre-construction heights of the cut earth blocks and the fill earth blocks and the soil transport vectors that represent the amount and direction of soil to be cut from the cut earth blocks and piled up into the fill earth blocks.
[0030] Cutting block and filling block X i and X j The difference Dif(X i , X j ) is calculated by the following formula: i , X j ) = d ij −α*dθ ij +β*max(h i , h j )
[0031] Here, d ij indicates the distance between the blocks. This distance may be the linear distance between the blocks or may be a distance that takes into account the gradient. ij indicates the cosine similarity of the vectors. i , h j) indicates the height of the tallest block. The above values are normalized. α and β are weights, and the user can set which elements to weight more appropriately. The dissimilarity is used as a criterion for grouping cut blocks and fill blocks into cut and fill areas. If the dissimilarity between blocks is small, that is, if the similarity between the two blocks is high, it is more efficient to group the two blocks together and perform cut or fill work as a whole. Therefore, if the dissimilarity is small, the blocks will be aggregated. On the other hand, if the dissimilarity between blocks is large, that is, if the similarity between the two blocks is low, the relationship between the two blocks is weak and there is little need to perform cut or fill work as a whole. Therefore, if the dissimilarity is large, the blocks will not be aggregated.
[0032] Cut Block C i and Cut Block C k The distance (k = 1, 2, ..., N) is the distance between the cut block C i Cut Block C k Displacement vector d(C i , C k ) length |d(C i , C k ) | Also, the embankment block F j and Embankment Block F h The distance (h = 1, 2, ..., M) is the embankment block F j From embankment block F h Displacement vector d(F j , F h ) length |d(F j , F h ) | is defined as
[0033] The distance between blocks is used as a factor in calculating the degree of difference. If this distance is small, the two blocks are located close to each other, and it is more efficient to combine the two blocks into one area and perform cut or fill work. Also, treating them as one area makes it easier to determine which areas of the entire construction site require cut and which areas require fill, and to plan the flow and amount of soil to be transported between areas. Also, if the distance between blocks is large, the two blocks are located far apart, and it is better to perform cut or fill work in each block, rather than combining the two blocks into one area.
[0034] The cosine similarity of vectors is also used as a factor in calculating the dissimilarity. Cosine similarity is an index that indicates how similar two soil transport vectors are, that is, a measure of the similarity between two soil transport vectors. If the cosine similarity is close to 1, the two vectors are similar, and if it is close to -1, the two vectors are not similar. In other words, the difference in the direction between soil transport vectors is calculated by reversing the positive and negative values of the cosine similarity between the soil transport vectors.
[0035] Cut Block C i The earth transport vector for is defined as follows: i =Σ j=1 M V i,j d(C i , F j )
[0036] Also, embankment block F j The soil transport vector for f is defined as follows: j =Σ i=1 N V i,j d(C i , F j )
[0037] If the cosine similarity is large, i.e., the difference in the direction of the soil transport vectors is small, the directions in which the soil will be transported in both blocks are close, and it is more efficient to combine the two blocks into one area and perform excavation or fill work. Treating them as one area also makes it easier to grasp the excavation and fill areas across the entire construction site, and makes it easier to plan the flow and amount of soil transport between areas. If the cosine similarity is small, i.e., the difference in the direction of the soil transport vectors is large, the directions in which the soil will be transported in both blocks are far apart, and it is better to perform excavation or fill work in each block, rather than combining the two blocks into one area.
[0038] The pre-construction height evaluation values of the blocks are also included as a factor in calculating the degree of difference between cut blocks and fill blocks. For example, if the elevation of the existing topography before construction is high for a cut block, cutting and earthmoving operations require a lot of effort. Furthermore, if a block exists that is higher in elevation than the surrounding cut blocks, even if a route to transport the excavated soil from the surrounding cut blocks is desired, the route involves a large elevation difference, and it may be necessary to avoid the high-elevation block and select a detour with a smaller elevation difference. Since a high-elevation block protruding from the surrounding blocks hinders work efficiency, cutting work must be carried out quickly. Therefore, it is more efficient to work on the high-elevation block separately from the surrounding blocks to eliminate the elevation difference with the surrounding blocks, allowing for subsequent work to be carried out together with the surrounding blocks. Therefore, the degree of difference is calculated based on the pre-construction height evaluation values.
[0039] In the above-mentioned calculation formula for the degree of difference, the evaluation value of the height of the blocks before construction is the height of the higher block max (h i , h j ) indicates the elevation of one block h i and the elevation h of the other block j For example, h i >h j If so, max(h i, h j ) = h i The pre-construction height, or elevation, can be the difference between the height of the current terrain before construction and the elevation of the designed terrain after construction. As mentioned above, to avoid high-elevation blocks protruding and to make the terrain flat overall, the higher the pre-construction height evaluation value, the greater the difference.
[0040] The evaluation value of the height of the blocks before construction is the height of the taller block max (h i , h j ), the sum or product of the heights of both blocks can also be used. As mentioned above, if the elevations of adjacent blocks are low, it is more efficient to work together, so it is better to combine the blocks into one. Therefore, the smaller the sum or product of the heights of both blocks, the higher the similarity, i.e., the lower the degree of difference.
[0041] The evaluation value is generalized as follows so that the evaluation value of the pre-construction height of blocks includes the sum, product, etc. of the heights of both blocks.
[0042] That is, the pre-construction height H(X) of the cut and fill block X and the two-variable function p(·,·) that is commutative and monotonically increasing with respect to the arguments are used to calculate the cut block C. i , C k The evaluation value of the height before construction is p(H(C i ), H(C k )) and the embankment block F j , F h The evaluation value of the height before construction is p(H(F j ), H(F h )) is defined as
[0043] Here, the two-variable function p(·,·) is one of the following: p(a, b) = max(a, b); p(a, b) = a + b; p(a, b) = ab; p(a, b) = (ab) 1/2 p(a, b) = a 2 +b 2 ; p(a, b) = (a 2 +b 2 ) 1/2 ;
[0044] The degree of difference between cut blocks and fill blocks is calculated based on the above factors. The degree of difference between multiple blocks is greater the greater the distance between the blocks, the greater the difference in the directions of the soil transport vectors related to the blocks, and the higher the evaluation value of the pre-construction heights of the blocks.
[0045] Next, an example of the degree of difference calculation will be described with reference to FIG. 6. FIG. 6 is a diagram showing the top 10 blocks among the blocks shown in FIG. 5B. Here, the cut earth block C 1 and Cut Block C 2 An example of calculating the difference between the cut block C and the 1 From here, we will look at the same block, embankment block F. 2 Towards the earth transport vector c 1 There is a cut block C. 1 The soil cut from this embankment block F 2 Cutting Block C 1 Cut block C adjacent to 2 From here, we will look at the same block, embankment block F. 3 Earth transport vector c 2 ' and embankment block F 2 Earth transport vector c 2 '' and embankment block F 4 Earth transport vector c 2 There is a cut block C. 1 and Cut Block C 2 The distance d between 12 is R. The cosine similarity of the vectors is 1 The earth transport vector c extending from 1 and Cut Block C 2 The earth transport vector c extending from 2 Cosine similarity dθ 12 Here, the earth transport vector c 2 is the earth transport vector c 2 ', c 2 '', c 2 ''' is the sum of (c 2 '+c 2 ''+c 2'''). Cutting Block C 1 The height before construction is h 1 Also, cut earth block C 2 The height before construction is h 2 is.
[0046] Cut Block C 1 and C 2 The difference Dif(C 1 , C 2 ) is calculated by the following formula: 1 , C 2 ) = d 12 −α*dθ 12 +β*max(h 1 , h 2 )
[0047] Returning to FIG. 3 , once the dissimilarity for all soil transport vectors has been calculated in step S107, construction section division is performed (step S108). In step S108, the clustering unit 24 divides the construction sections based on the number of construction section divisions obtained in step S103 and the calculated dissimilarity. The number of construction section divisions is the number of cut sections and the number of fill sections input by the user. The clustering unit 24 performs clustering by aggregating cut blocks and fill blocks in order of decreasing calculated dissimilarity. In the clustering, for the cut sections, the cut blocks are aggregated to the number of cut sections input by the user, and for the fill sections, the fill blocks are aggregated to the number of fill sections input by the user.
[0048] FIG. 7A shows an example of the process of aggregating cut earth blocks and fill earth blocks based on the degree of difference. Here, the number of divisions into the construction sections is set to divide the cut earth section into two and the fill earth section into two. First, clustering is performed on the cut earth sections. The calculated degree of difference between the cut earth blocks is sorted in ascending order. Assume that the result of sorting in ascending order of the degree of difference is as follows. Dif(C 5 , C 6 ) < Dif(C 1 , C 2 ) < Dif(C 2 , C 3 )…
[0049] Next, the cut earth blocks are aggregated in ascending order of dissimilarity. First, the cut earth block C 5 and C 6 Next, the cut earth block C with the second smallest dissimilarity is aggregated. 1 and C 2 and aggregated into cut block C. 5 and C 6 Next, the cut earth block C, which has the third smallest dissimilarity, forms a separate group from 2 and C 3 Regarding the combination of the above, the cut block C 2 Cut Block C 1 Since it is aggregated with cut earth block C 3 The aggregated cut earth block C 1 and C 2 The aggregation is repeated for the other cut earth blocks in ascending order of dissimilarity. 6 The blocks after this are omitted. Finally, the cut earth block C 1 , C 2 , C 3 The group containing this is generated as Cut Block A. Also, Cut Block C 5 , C 6 The group containing is generated as cut group B.
[0050] Next, clustering is performed on the embankment area. The calculated dissimilarity between the embankment blocks is sorted in ascending order. Assume that the result of sorting in ascending order of dissimilarity is as follows: Dif(F 4 , F 5 ) < Dif(F 1 , F 2 ) < Dif(F 2 , F 3 )…
[0051] Next, the embankment blocks are aggregated in ascending order of dissimilarity. First, the embankment block F with the smallest dissimilarity is aggregated. 4 and F 5 Next, the embankment block F with the second smallest dissimilarity is aggregated. 1 and F 2 and embankment block F4 and F 5 Next, the embankment block F, which has the third smallest dissimilarity, forms a separate group from 2 and F 3 Regarding the combination of the above, the embankment block F 2 is embankment block F 1 Since it is aggregated with embankment block F 3 The aggregated embankment block F 1 and F 2 The aggregation is repeated for the other embankment blocks in ascending order of dissimilarity. 5 The description of the subsequent blocks is omitted. Finally, the embankment block F 1 , F 2 , F 3 The group containing this will be generated as embankment block A. Also, embankment block F 4 , F 5 The group including the above is generated as the block B.
[0052] Figure 7B shows an example of the divided construction sections. The construction site is divided into two cut sections, cut section A and cut section B. The construction site is also divided into two fill sections, fill section A and fill section B. Here, there are blocks that are both cut blocks and fill blocks, for example, cut block C. 1 , C 2 , C 3 and Embankment Block F 2 , F 3 , F 4 The boundary between the cut and fill sections is divided into cut mesh and fill mesh units within the block. This allows the construction site to be divided into the number of construction sections specified by the user.
[0053] Furthermore, the functions of the construction area division device can be realized by dedicated hardware or by a normal computer system.
[0054] For example, a device that executes the above-described processing can be configured by storing and distributing the program executed by the processor 41 on a non-transitory computer-readable recording medium and installing the program on a computer. Examples of such recording media include flexible disks, CD-ROMs (Compact Disc Read-Only Memory), DVDs (Digital Versatile Discs), and MOs (Magneto-Optical Discs).
[0055] Alternatively, the program may be stored in a disk device of a server device on a communication network such as the Internet, and may be downloaded to a computer by superimposing the program on a carrier wave, for example.
[0056] The above process can also be achieved by starting and executing the program while transferring it via a communication network.
[0057] Furthermore, the above-described processing can also be achieved by executing all or part of the program on a server device, and executing the program while the computer sends and receives information about the processing via a communications network.
[0058] In addition, when the above-mentioned functions are shared and realized by an OS (Operating System) or by the OS working together with an application, only the parts other than the OS may be stored on a medium and distributed, or may be downloaded to a computer.
[0059] Furthermore, the means for realizing the functions of the construction area division device is not limited to software, and some or all of it may be realized by dedicated hardware including circuits.
[0060] The present invention allows various embodiments and modifications without departing from the broad spirit and scope of the present invention. Furthermore, the above-described embodiments are intended to illustrate the present invention and do not limit the scope of the present invention. In other words, the scope of the present invention is defined by the claims, not the embodiments. Various modifications made within the scope of the claims and within the meaning of the disclosure equivalent thereto are considered to be within the scope of the present invention.
[0061] The present invention can be widely applied to a construction area dividing device that divides a construction site into construction areas and uses the divided areas for soil distribution planning.
[0062] 1 Construction area division device, 2 Control unit, 3 Memory unit, 21 Current topography data acquisition unit, 22 Design topography data acquisition unit, 23 Planning unit, 24 Clustering unit, 31 Topography DB, 32 Design DB, 41 Processor, 42 Main memory unit, 43 Auxiliary memory unit, 44 Input / output unit, 45 Operation unit, 46 Display unit, 47 Communication unit, 51, 52, 53 Block, E Entrance.
Claims
1. A construction area division device comprising: a planning unit which plans the amount of soil to be transported from each of a plurality of cut blocks whose pre-construction height is higher than the post-construction height at a construction site divided into a plurality of blocks to each of a plurality of fill blocks whose pre-construction height is lower than the post-construction height by minimizing the amount of work based on the length of the displacement vector from each of the cut blocks to each of the fill blocks under specified constraints; and a clustering unit which clusters the plurality of cut blocks into a first desired number of cut sections and clusters the plurality of fill blocks into a second desired number of fill sections, wherein the clustering unit calculates the degree of difference between the cut blocks and the degree of difference between the fill blocks using the pre-construction heights of the cut and fill blocks and the soil transport vectors representing the amount and direction of soil to be cut from the cut blocks and piled up into the fill blocks, and performs the clustering based on the calculated degrees of difference.
2. The construction area division device described in claim 1, characterized in that the degree of difference between the multiple blocks is greater the greater the distance between the blocks, the greater the difference in the directions of the soil transport vectors related to the blocks, and the higher the evaluation values of the pre-construction heights of the blocks.
3. The construction area division device according to claim 2, characterized in that the clustering unit performs the clustering by agglomerating cut earth blocks and fill earth blocks in order of the smallest calculated dissimilarity.
4. The amount of work is as follows: Cutting block C i (i = 1, 2, ..., N) to embankment block F j Volume of soil transported to (j = 1, 2, ..., M) V i,j ≧0 and Cutting block C i From embankment block F j Displacement vector d(C i , F j ) length L i,j = |d(C i , F j )|, and by Σ i=1 N Σ j=1 M V i,j L i,j The construction area dividing device according to claim 2, characterized in that:
5. Cutting Block C i The earth transport vector related to i =Σ j=1 M V i,j d (C i , F j ) is defined as embankment block F j The earth transport vector related to f j =Σ i=1 N V i,j d (C i , F j 5. The construction area division device according to claim 4, characterized in that the difference in direction between the soil transport vectors is calculated by inverting the positive and negative of the cosine similarity between the soil transport vectors.
6. Cutting Block C i and Cut Block C k The distance of (k = 1, 2, ..., N) is the cutting block C i Cutting Block C k Displacement vector d(C i , C k ) length |d(C i , C k ) | is defined as embankment block F j and Embankment Block F h The distance (h = 1, 2, ..., M) is the embankment block F j From embankment block F h Displacement vector d(F j , F h ) length |d(F j , F h 5. The construction area dividing device according to claim 4, characterized in that the construction area dividing device is defined as follows:
7. The height H(X) of the cut and fill block X before construction and a two-variable function p(・, ・) that is commutative and increases monotonically with respect to the arguments are used to calculate the cut block C. i , C k The evaluation value of the pre-construction height is p(H(C i ), H(C k )) and the embankment block F j , F h The evaluation value of the pre-construction height is p(H(F j ), H(F h 7. The construction area dividing device according to claim 6, wherein the construction area dividing portion is defined as follows:
8. The two-variable function p(・,・) is: p(a,b)=max(a,b); p(a,b)=a+b; p(a,b)=ab; p(a,b)=(ab) 1/2 ; p(a,b)=a 2 +b 2 ; p(a, b)=(a 2 +b 2 ) 1/2 8. The construction area dividing device according to claim 7, characterized in that the construction area dividing device is any one of the above.
9. A method for dividing construction areas, comprising: a step of planning the amount of soil to be transported from each of a plurality of cut blocks whose pre-construction height is higher than the post-construction height at a construction site divided into a plurality of blocks, to each of a plurality of fill blocks whose pre-construction height is lower than the post-construction height, by minimizing the amount of work based on the length of the displacement vector from each cut block to each of the fill blocks under predetermined constraints; and a step of clustering the plurality of cut blocks into a first desired number of cut sections and clustering the plurality of fill blocks into a second desired number of fill sections, wherein the clustering step calculates the degree of difference between the cut blocks and the degree of difference between the fill blocks using the pre-construction heights of the cut and fill blocks and the soil transport vectors representing the amount and direction of soil to be cut from the cut blocks and piled into the fill blocks, and performing the clustering based on the calculated degrees of difference.
10. A program that causes a computer to execute the steps of: planning the amount of soil to be transported from each of a plurality of cut blocks, the pre-construction height of which is higher than the post-construction height, to each of a plurality of fill blocks, the pre-construction height of which is lower than the post-construction height, at a construction site divided into a plurality of blocks, by minimizing the amount of work based on the length of the displacement vector from each cut block to each fill block, under specified constraint conditions; and clustering the plurality of cut blocks into a first desired number of cut sections and clustering the plurality of fill blocks into a second desired number of fill blocks, wherein the clustering step calculates the degree of difference between the cut blocks and the degree of difference between the fill blocks using the pre-construction heights of the cut and fill blocks and soil transport vectors representing the amount and direction of soil to be cut from the cut blocks and piled up into the fill blocks, and performing the clustering based on the calculated degrees of difference.
Citation Information
Patent Citations
System and method for determining construction plan of work machine in construction site
JP2021101316A
Soil carriage plan management device, soil carriage plan management method and soil carriage plan management program
JP2021149395A
Work plan system and work plan method
JP2022011680A
Method of preparing earth-quantity allocation plan and method of estimating future landform
JP2022129923A
Hauling scheme management device, method and program
JP2022148987A