Program, information processing method, and information processing device
The program optimizes demand response control by determining suspension periods to limit execution to one hour within core time and two hours outside, addressing discomfort issues and managing peak power consumption through electricity price and weather-based adjustments.
Patent Information
- Application Number
- PCT/JP2026/008656
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2025-05-08
- Filing Date
- 2026-03-06
- Publication Date
- 2026-11-12
AI Technical Summary
Existing demand response control systems fail to determine the period for suspending control when the execution period exceeds a first period, leading to prolonged discomfort due to extended limitations on air conditioning, which can result in occupant complaints.
A program that determines a period for suspending demand response control so that the execution period becomes the first period, limiting it to one hour within core time and two hours outside core time, using electricity price thresholds and weather forecasts to optimize comfort while reducing power consumption.
Maintains indoor comfort by limiting demand response control periods to ensure minimal discomfort, while effectively managing power consumption during peak hours by adjusting control periods based on electricity prices and weather conditions.
Smart Images

Figure JP2026008656_12112026_PF_FP_ABST
Abstract
Description
Program, Information Processing Method, and Information Processing Apparatus
[0001] The present disclosure relates to a program, an information processing method, and an information processing apparatus.
[0002] Patent Document 1 discloses a technique for reducing the impact on the indoor environment caused by the discrepancy between the indoor temperature and a specified set temperature when the average power is reduced during a demand time period.
[0003] Japanese Patent No. 5668970
[0004] However, the invention according to Patent Document 1 has a problem in that when the period for executing demand response control exceeds a first period, it is not possible to determine the period for suspending the demand response control such that the period for executing the demand response control becomes the first period.
[0005] An object of the present invention is to provide a program or the like that, when the period for executing demand response control exceeds a first period, can determine the period for suspending the demand response control such that the period for executing the demand response control becomes the first period.
[0006] A program according to a first aspect causes a computer to execute processes of acquiring an electricity price, determining that demand response control is to be executed when the acquired electricity price exceeds a threshold, and when the period for executing the demand response control exceeds a first period, determining a period for suspending the demand response control such that the period for executing the demand response control becomes the first period.
[0007] A program according to a second aspect is the program according to the first aspect, wherein when the period for executing the demand response control within core time exceeds the first period, the period for suspending the demand response control is determined such that the period for executing the demand response control becomes the first period.
[0008] The third perspective program is a second perspective program that determines a period for suspending demand response control so that the period for which demand response control is performed becomes the first period, if the period during which demand response control is performed during the core time and predetermined time periods before and after the core time exceeds the first period.
[0009] In the program of the fourth perspective, the first core time in the first period and the second core time in the second period are different, and this is a program of the second or third perspective.
[0010] The program of the fifth perspective is the program of the first perspective, which determines a period for suspending demand response control so that the period for which demand response control is performed exceeds the second period, which is longer than the first period, when the period for which demand response control is performed exceeds the second period, excluding the first core time in the first period and predetermined time periods before and after the first core time, and the second core time in the second period and predetermined time periods before and after the second core time.
[0011] The program of the sixth perspective is a program of any of the first to fifth perspectives that acquires weather forecasts and, according to the acquired weather forecasts, decides whether to execute or discontinue demand response control for a group of time periods in which the period for executing demand response control is one consecutive period, and for time periods in which the demand response control is to be discontinued.
[0012] The seventh aspect of information processing is an information processing method that obtains the electricity price, determines whether to execute demand response control if the obtained electricity price exceeds a threshold, and determines a period for suspending demand response control so that the period for executing demand response control becomes the first period if the period for executing demand response control exceeds the first period.
[0013] The information processing device in the eighth aspect is an information processing device comprising a control unit, the control unit acquires the electricity price, determines that demand response control should be executed if the acquired electricity price exceeds a threshold, and determines a period for suspending demand response control so that the period for executing demand response control becomes the first period if the period for executing demand response control exceeds a first period.
[0014] According to the present invention, if the period for which demand response control is performed exceeds the first period, it is possible to determine a period for suspending demand response control so that the period for which demand response control is performed becomes the first period.
[0015] This is an explanatory diagram showing an overview of the information processing system. This is a block diagram showing the configuration of the server and computer. This is an explanatory diagram showing the relationship between electricity prices and the period for which demand response control is performed. This is an explanatory diagram showing the relationship between electricity prices and the period for which demand response control is performed in this embodiment. This is a flowchart showing an example of the processing procedure of the information processing system. This is a flowchart showing an example of the processing procedure of the information processing system. This is an explanatory diagram showing an example of a time-limited weather forecast. This is a flowchart showing an example of the processing procedure in the first period of the information processing system. This is a flowchart showing an example of the processing procedure in the second period of the information processing system.
[0016] (Embodiment 1) Embodiment 1 describes an information processing system that determines a period for suspending demand response control so that the period for which demand response control is performed becomes the first or second period, when the period for which demand response control is performed exceeds the first or second period.
[0017] Figure 1 is an explanatory diagram showing an overview of the information processing system. The information processing system comprises an information processing device 10 and one or more control devices 20. The information processing device 10 and one or more control devices 20 transmit and receive information via a network N.
[0018] The information processing device 10 outputs a demand response control instruction (hereinafter referred to as a DR control instruction) to the control device 20. The information processing device 10 is, for example, a server device, a personal computer (hereinafter referred to as a computer), or a general-purpose tablet PC (personal computer). The information processing device 10 may also be a cloud server device that provides the functions included in the information processing device 10 as a cloud service. In this embodiment, the information processing device 10 will be described as a server 10.
[0019] The control device 20 controls the equipment based on DR control instructions from the server 10. The control device 20 is an information processing device such as a personal computer (hereinafter referred to as "computer"), workstation, or server that controls the equipment. The equipment includes, for example, an air conditioner, a generator, an electric furnace, and a storage battery. In this embodiment, the control device 20 will be described as a computer 20, and the equipment will be described as an air conditioner.
[0020] Figure 2 is a block diagram showing the configuration of a server and a computer. The server 10 includes a control unit 11, a storage unit 12, a communication unit 13, and a reading unit 14. The above-mentioned units are interconnected via a bus. The control unit 11 is configured using one or more processors such as a CPU (Central Processing Unit), an MPU (Micro-Processing Unit), or a GPU (Graphics Processing Unit). The control unit 11 performs various information processing and control processing related to the server 10 by appropriately executing a control program 12P (program product) stored in the storage unit 12.
[0021] The storage unit 12 includes RAM (Random Access Memory) or ROM (Read Only Memory), etc. The storage unit 12 stores various data necessary for the control program 12P executed by the control unit 11. The storage unit 12 temporarily stores data generated when the control unit 11 executes the control program 12P. The communication unit 13 is a communication module that sends and receives information with the computer 20.
[0022] The reading unit 14 reads information stored in the portable storage medium 1a. The portable storage medium 1a is, for example, a CD (Compact Disc), DVD (Digital Versatile Disc), USB (Universal Serial Bus) memory, or SD (Secure Digital). The reading unit 14 reads the control program 12P from the portable storage medium 1a. The control unit 11 stores the read control program 12P in the storage unit 12.
[0023] The computer 20 includes a control unit 21, a storage unit 22, and a communication unit 23. The above-mentioned units are interconnected via a bus. The control unit 21 is configured using one or more processors such as a CPU, MPU, or GPU. The control unit 21 performs various information processing and control processing related to the computer 20 by appropriately executing control programs 22P (program products) stored in the storage unit 22.
[0024] The storage unit 22 includes RAM (Random Access Memory) or ROM (Read Only Memory), etc. The storage unit 22 stores various data necessary for the control program 22P executed by the control unit 21. The storage unit 22 temporarily stores data generated when the control unit 21 executes the control program 22P. The communication unit 23 is a communication module that sends and receives information with the server 10.
[0025] Figure 3 is an explanatory diagram showing the relationship between electricity prices and the period during which demand response control is implemented. The vertical axis of Figure 3 represents electricity prices (yen / kWh), and the horizontal axis represents time. The horizontal axis also shows the core time (12:00 to 15:00 in Figure 3) with an arrow. The core time indicates the period when the use of air conditioners, etc., is particularly necessary, and is set for each season, such as summer and winter. In Figure 3, the electricity price for "July 13, 2024" is displayed. The electricity price is, for example, the electricity price for an air conditioner operating day calculated by the Japan Electric Power Exchange (JEPX). Electricity prices are not constant but fluctuate. Therefore, in Figure 3, the electricity price every 30 minutes is shown as a line graph.
[0026] Furthermore, the graph in Figure 3 shows a horizontal line indicating a threshold. The threshold is a reference value for electricity price that determines whether or not to implement demand response control, and is determined by the administrator of the information processing system in this embodiment and the administrator of the building or other facility that uses the information processing system. The threshold is not constant throughout the year and may be determined on a monthly basis. In Figure 3, the period during which demand response control is implemented is illustrated by the upward-sloping hatched area and the downward-sloping hatched area.
[0027] The upward-sloping hatched areas indicate periods when demand response control is performed outside of core time, while the downward-sloping hatched areas indicate periods when demand response control is performed within core time. The execution or suspension of demand response control is decided on a per-period basis. A period is a 30-minute unit of time for the execution of demand response control. Therefore, a day is divided into 48 periods. Specifically, period 1 is "0:00 to 0:30", period 2 is "0:30 to 1:00", period 24 is "11:30 to 12:00", and period 48 is "23:30 to 24:00".
[0028] Conventionally, when electricity prices exceed a threshold (the upward-sloping and downward-sloping hatched areas in Figure 3), demand response control (downward DR) is implemented. Implementing demand response control reduces the power consumption of the customer's property, but also worsens the comfort level of the property by limiting the air conditioning capacity and temperature settings.
[0029] In particular, during periods when demand response control is implemented within core hours in summer and winter (the hatched area on the right in Figure 3), if indoor comfort deteriorates for extended periods due to limitations on air conditioning capacity and set temperatures, it could lead to complaints from facility occupants. During core hours (12:00 to 15:00 in Figure 3), if the period of implementing demand response control is about one hour, the air conditioning condition before the implementation of demand response control can be maintained to some extent. However, if the period of implementing demand response control continues for more than one hour, it is expected that complaints from facility occupants will increase sharply.
[0030] Figure 4 is an explanatory diagram showing the relationship between the electricity price and the period during which demand response control is implemented in this embodiment. The vertical axis, horizontal axis, electricity price, threshold, and core time in Figure 4 are the same as in Figure 3. In period A of Figure 4 (14:00 to 14:30), the period during which demand response control is implemented within the preceding core time has reached the first period (1 hour), so demand response control is stopped in the period immediately following the first period (period A). Also, in period B of Figure 4 (18:00 to 18:30), the period during which demand response control is implemented outside the preceding core time has reached the second period (2 hours), so demand response control is stopped in the period immediately following the second period (period B).
[0031] In other words, the period during which demand response control is performed is limited to a maximum of one hour within core time and a maximum of two hours outside core time, thus ensuring a minimum level of comfort. This embodiment describes a method for maintaining indoor comfort while suppressing an increase in power consumption during peak hours when electricity rates are high, by determining a period to suspend demand response control so that the period during which demand response control is performed exceeds the first or second period.
[0032] The control unit 11 reads the core time corresponding to the air conditioner's operating day from the storage unit 12 the day before the air conditioner's operating day. The core time includes, for example, the first core time "12:00 to 15:00" during the first period (summer period) and the second core time "9:00 to 11:00" during the second period (winter period). In other words, the first core time during the first period is different from the second core time during the second period. The core time may also include core times during periods other than the first and second periods (for example, spring and autumn).
[0033] Specifically, if the operating date of the air conditioner is "July 13, 2024, 15:45", the control unit 11 reads the first core time of the first period (summer period), "12:00 to 15:00", from the storage unit 12. On the other hand, if the operating date of the air conditioner is "December 13, 2024, 15:45", the control unit 11 reads the second core time of the second period (winter period), "9:00 to 11:00", from the storage unit 12. The following explanation will use an example where the control unit 11 reads the first core time, "12:00 to 15:00". The control unit 11 obtains electricity prices from the web. The control unit 11 may also obtain electricity prices for each region from the web.
[0034] First, the process for determining the time limit for activating (executing) the demand response control (hereinafter referred to as the DR activation time limit determination process) will be explained. The control unit 11 initializes a list that stores the time limits for activating (executing) the demand response control (hereinafter referred to as the DR activation time limit list). The DR activation time limit list is stored in the storage unit 12. The DR activation time limit list stores, for example, the time limits for activating (executing) the demand response control. Specifically, if the time limits for activating (executing) the demand response control are 25, 26, 28, and 30, then the DR activation time limit list stores 25, 26, 28, and 30.
[0035] Furthermore, if there are consecutive time periods in the DR activation time period list for activating (executing) demand response control (for example, time periods 25 and 26), these consecutive time periods will be described as consecutive time periods. The control unit 11 executes the following loop processing sequentially from time period 1 to time period 48. Hereafter, each time period that the control unit 11 is processing will be described as a "processing time period". The control unit 11 determines whether the electricity price for the acquired processing time period exceeds a threshold.
[0036] The control unit 11 does not store (add) the processing time to the DR activation time list if it determines that the power price of the processing time does not exceed the threshold. In other words, if the control unit 11 determines that the power price of the processing time does not exceed the threshold, it decides to cancel the demand response control for the processing time (to deactivate demand response control). If the control unit 11 determines that the power price of the processing time exceeds the threshold, it determines whether the processing time is greater than or equal to the start time of the read first core time, and less than or equal to the end time of the read first core time plus 2 hours. Specifically, since the first core time "12:00 to 15:00" is 25 hours to 30 hours, the start time of the first core time is 25 hours, and the end time of the first core time plus 2 hours is 32 hours.
[0037] Therefore, if the processing time is between 25 and 32 hours, the control unit 11 determines that the processing time is greater than or equal to the start time of the read first core time, and less than or equal to the end time of the read first core time plus 2 hours. On the other hand, if the processing time is different from between 25 and 32 hours, the control unit 11 determines that the processing time is not greater than or equal to the start time of the read first core time, and less than or equal to the end time of the read first core time plus 2 hours.
[0038] If the control unit 11 determines that the processing time is greater than or equal to the start time of the read first core time, and less than or equal to the end time of the read first core time plus 2 hours, it sets the maximum continuous time to 2. The maximum continuous time is, for example, the upper limit of the continuous time stored in the DR activation time list. When the control unit 11 stores (adds) the processing time to the DR activation time list, it determines whether the continuous time exceeds the maximum continuous time. Specifically, if the processing time is 29 hours and 28 hours are stored (added) to the DR activation time list, when the processing time "29 hours" is stored (added) to the DR activation time list, the continuous time becomes "2", which does not exceed the maximum continuous time of "2", so the control unit 11 determines that the continuous time does not exceed the maximum continuous time. When the control unit 11 determines that the continuous time does not exceed the maximum continuous time, it stores (adds) the processing time to the DR activation time list.
[0039] On the other hand, if the processing time is 29 hours, and the 27th and 28th hours are stored (added) to the DR activation time list, then storing (adding) the processing time "29 hours" to the DR activation time list would result in a continuous time of "3," which exceeds the maximum continuous time of "2." Therefore, the control unit 11 determines that the continuous time exceeds the maximum continuous time. If the control unit 11 determines that the continuous time exceeds the maximum continuous time, it does not store (add) the processing time to the DR activation time list.
[0040] In other words, the control unit 11 determines that demand response control will be executed when the electricity price exceeds a threshold, and if the period during which demand response control is executed within the first core time exceeds the first period (1 hour), it determines a period during which demand response control will be suspended so that the period during which demand response control is executed becomes the first period (1 hour). Also, the control unit 11 determines that demand response control will be executed when the electricity price exceeds a threshold, and if the period during which demand response control is executed within the first core time and predetermined time periods (for example, 1 hour) before and after the first core time exceeds the first period (1 hour), it determines a period during which demand response control will be suspended so that the period during which demand response control is executed becomes the first period (1 hour).
[0041] If the control unit 11 determines that the processing time is not greater than or equal to the start time of the read first core time, and less than or equal to the end time of the read first core time plus 2 hours, it sets the maximum continuous time to 4. When the control unit 11 stores (adds) the processing time to the DR activation time list, it determines whether the continuous time exceeds the maximum continuous time. Specifically, if the processing time is 37 hours, and hours 35 and 36 are stored (added) to the DR activation time list, when the processing time "37 hours" is stored (added) to the DR activation time list, the continuous time becomes "3", which does not exceed the maximum continuous time of "4", so the control unit 11 determines that the continuous time does not exceed the maximum continuous time. When the control unit 11 determines that the continuous time does not exceed the maximum continuous time, it stores (adds) the processing time to the DR activation time list.
[0042] On the other hand, when the processing time period is the 37th time period, and the 33rd, 34th, 35th, and 36th time periods are stored (added) in the DR activation time period list, storing (adding) the processing time period "37th time period" in the DR activation time period list results in a consecutive time period count of "5", which exceeds the maximum consecutive time period "4". Therefore, the control unit 11 determines that the consecutive time period exceeds the maximum consecutive time period. When determining that the consecutive time period exceeds the maximum consecutive time period, the control unit 11 does not store (add) the processing time period in the DR activation time period list.
[0043] That is, the control unit 11 determines to execute demand response control when the electricity price exceeds a threshold, and for time periods excluding the first core time in the first period and the predetermined time periods (1 hour) before and after the first core time, as well as the second core time in the second period and the predetermined time periods (1 hour) before and after the second core time, when the period during which demand response control is executed exceeds the second period (2 hours) that is longer than the first period (1 hour), the control unit 11 determines the period during which demand response control is suspended such that the period during which demand response control is executed becomes the second period (2 hours). The control unit 11 repeatedly executes the above-described loop processing for all time periods from the 1st time period to the 48th time period. Through the above steps, the DR activation time period determination processing is completed.
[0044] Next, processing for instructing activation (execution) of demand response control (hereinafter referred to as DR activation instruction processing) will be described. When a predetermined time is reached, the control unit 11 initializes the processing time period to the 1st time period. The predetermined time is, for example, a predetermined time (e.g., 25 minutes) before the time slot corresponding to each time period. The control unit 11 executes the following loop processing in order from the 1st time period for the processing time periods (from the 1st time period to the 48th time period) every 30 minutes. The control unit 11 determines whether or not the processing time period is included in the DR activation time period list. Specifically, when the processing time period is the "1st time period" and the 1st time period is stored (added) in the DR activation time period list, the control unit 11 determines that the processing time period is included in the DR activation time period list. When determining that the processing time period is included in the DR activation time period list, the control unit 11 transmits a DR control instruction to the computer 20 via the communication unit 13.
[0045] The communication unit 23 receives the DR control instruction transmitted from the server 10. The control unit 21 controls the air conditioner based on the received DR control instruction. After transmitting the DR control instruction to the computer 20, or when determining that the processing time period is not included in the DR activation time period list, the control unit 11 adds 1 to the processing time period. The control unit 11 performs the above-described loop processing for all time periods. Through the above steps, the DR activation instruction processing is completed.
[0046] FIG. 5 and FIG. 6 are flowcharts illustrating an example of the processing procedure of the information processing system. On the day before the operation day of the air conditioner, the control unit 11 reads the core time (for example, the first core time or the second core time) corresponding to the operation day of the air conditioner from the storage unit 12 (step S101). The control unit 11 acquires the electricity price from the Web (step S102). The control unit 11 initializes the DR activation time period list (step S103). Thereafter, the control unit 11 executes loop processing from step S104 to step S111 in order starting from the 1st time period for the processing time periods (from the 1st time period to the 48th time period).
[0047] The control unit 11 determines whether or not the electricity price for the processing time period exceeds a threshold value (step S104). When determining that the electricity price for the processing time period exceeds the threshold value (step S104: YES), the control unit 11 determines whether or not the processing time period is equal to or later than the start time period of the read first core time, and the processing time period is equal to or earlier than the end time period of the read first core time plus 2 time periods (step S105). When determining that the processing time period is equal to or later than the start time period of the read first core time, and the processing time period is equal to or earlier than the end time period of the read first core time plus 2 time periods (step S105: YES), the control unit 11 sets the maximum continuous time period to 2 (step S106).
[0048] If the control unit 11 determines that the processing time is not greater than or equal to the start time of the read first core time, and less than or equal to the end time of the read first core time plus 2 hours (step S105: NO), it sets the maximum continuous time to 4 (step S107). After step S106, or after step S107, the control unit 11 determines whether the continuous time will exceed the maximum continuous time if the processing time is stored (added) to the DR activation time list (step S108). If the control unit 11 determines that the continuous time will not exceed the maximum continuous time (step S108: NO), it stores (adds) the processing time to the DR activation time list (step S109). If the control unit 11 determines that the continuous time will exceed the maximum continuous time, it does not store (add) the processing time to the DR activation time list.
[0049] In other words, the control unit 11 determines that demand response control will be executed when the electricity price exceeds a threshold, and if the period of the demand response command within the first core time exceeds the first period (1 hour), it determines a period for suspending demand response control so that the period for which demand response control is executed becomes the first period. Also, the control unit 11 determines that demand response control will be executed when the electricity price exceeds a threshold, and if the period for which demand response control is executed within the first core time and predetermined time periods (for example, 1 hour) before and after the first core time exceeds the first period (1 hour), it determines a period for suspending demand response control so that the period for which demand response control is executed becomes the first period (1 hour). Furthermore, the control unit 11 determines that demand response control should be executed when the electricity price exceeds a threshold, and if the period during which demand response control is executed exceeds the second period (2 hours), excluding the first core time in the first period and predetermined time periods (1 hour) before and after the first core time, and the second core time in the second period and predetermined time periods (1 hour) before and after the second core time, the control unit 11 determines a period during which demand response control is suspended so that the period during which demand response control is executed becomes the second period.
[0050] After step S109, if the control unit 11 determines that the continuous time limit exceeds the maximum continuous time limit (step S108: YES), or if it determines that the power price for the processing time limit does not exceed a threshold (step S104: NO), it determines whether the processing time limit is 48 hours (S110). If the control unit 11 determines that the processing time limit is not 48 hours (S110: NO), it adds 1 to the processing time limit (step S111) and returns to step S104. If the control unit 11 determines that the processing time limit is 48 hours (S110: YES), it waits until a predetermined time (step S112).
[0051] The control unit 11 initializes the processing time limit to 1 when a predetermined time arrives (step S113). Thereafter, the control unit 11 executes the loop processing from steps S114 to S117 every 30 minutes for each processing time limit (from time limit 1 to time limit 48), starting from time limit 1. The control unit 11 determines whether the processing time limit is included in the DR activation time limit list (step S114). If the control unit 11 determines that the processing time limit is included in the DR activation time limit list (step S114: YES), it sends a DR control instruction to the computer 20 via the communication unit 13 (step S115).
[0052] The communication unit 23 receives a DR control instruction transmitted from the server 10 (step S201). The control unit 21 controls the air conditioner based on the received DR control instruction (step S202).
[0053] After step S115, or if the control unit 11 determines that the processing time is not included in the DR activation time limit list (step S114: NO), it determines whether the processing time limit is 48 hours (S116). If the control unit 11 determines that the processing time limit is not 48 hours (S116: NO), it adds 1 to the processing time limit (step S117) and returns to step S114. If the control unit 11 determines that the processing time limit is 48 hours (S116: YES), it terminates the process.
[0054] According to Embodiment 1, the information processing system can acquire electricity prices, determine to execute demand response control if the acquired electricity prices exceed a threshold, and determine a period for suspending demand response control so that the period for executing demand response control exceeds a first period if the period for executing demand response control exceeds a first period.
[0055] According to Embodiment 1, if the period during which demand response control is performed within the core time exceeds the first period (1 hour), the information processing system can determine a period for suspending demand response control so that the period during which demand response control is performed becomes the first period.
[0056] According to Embodiment 1, if the period during which demand response control is performed within the core time and predetermined time periods before and after the core time exceeds the first period, the information processing system can determine a period for suspending demand response control so that the period during which demand response control is performed becomes the first period.
[0057] According to Embodiment 1, the information processing system can determine a period for suspending demand response control if the period for which demand response control is performed exceeds a second period which is longer than the first period, excluding the first core time in the first period and predetermined time periods before and after the first core time, and the second core time in the second period and predetermined time periods before and after the second core time.
[0058] (Embodiment 2) Embodiment 2 describes a method by which an information processing system acquires weather forecasts and, in accordance with the acquired weather forecasts, decides whether to execute or cancel demand response control for a group of time periods in which the period for executing demand response control is a first period (1 hour) and for a time period immediately following the group of time periods in which demand response control is to be stopped. The same processes as in Embodiment 1 will not be described.
[0059] If the control unit 11 determines that the number of consecutive time periods exceeds the maximum number of consecutive time periods, it obtains weather forecasts for each time period from the web. Specifically, the control unit 11 obtains weather forecasts from the web for the time period two periods prior to the processing time period, the time period immediately prior to the processing time period, and the weather forecast corresponding to the processing time period. The weather forecasts to be obtained are not limited to weather forecasts for each time period. The control unit 11 may also obtain hourly weather forecasts and use those forecasts to infer weather forecasts for each time period.
[0060] Figure 7 is an explanatory diagram showing an example of a time-slot weather forecast. Figure 7 shows time-slot weather forecasts obtained during the second period (winter). The time-slot weather forecast includes temperature and solar radiation for each time slot. Solar radiation can be, for example, global solar radiation, direct solar radiation, or scattered solar radiation. In Figure 7, the time-slot temperature and solar radiation are associated with each time slot. For the time slots before sunrise and after sunset, the solar radiation for each time slot is marked as "-" because observation is not possible.
[0061] When the processing time is 23 hours as shown in Figure 7, the control unit 11 determines the temperature at 21 hours to be "10°C" and the solar radiation to be "0.81 (MJ / m²)". 2 ) ), temperature at 22 hours "8℃" and solar radiation "0.69 (MJ / m 2 ) and the temperature at 23 hours was "8°C" and the solar radiation was "0.74 (MJ / m²)". 2 The weather forecast is obtained from the web. The control unit 11 decides whether to execute or cancel demand response control for a group of time periods in which the period for executing demand response control is a first continuous period, and for a time period immediately following the group of time periods in which demand response control is to be stopped, according to the acquired weather forecast.
[0062] This section describes how to decide whether to execute or discontinue demand response control. First, an example is given where the air conditioner is operating during the first core time in the first period (summer period). The control unit 11 decides to execute demand response control preferentially for the time period with low temperature and low solar radiation (bad weather) among the three time periods (for example, the time period two before the processing time, the time period one before the processing time, and the processing time).
[0063] Specifically, if there are two time periods with the lowest temperature and one time period with the highest temperature among the two time periods prior to the processing time, the time period immediately prior to the processing time, and the processing time, the system will decide to execute demand response control for the two time periods with the lowest temperature and to cancel demand response control for the time period with the highest temperature. Furthermore, if there is one time period with the lowest temperature and two time periods with the highest temperature among the three time periods mentioned above, the system will decide to execute demand response control for the time period with the lowest temperature and for the time period with the lowest solar radiation (bad weather) among the two time periods with the highest temperature, and to cancel demand response control for the time period with the highest solar radiation (good weather) among the two time periods with the highest temperature.
[0064] Next, we will explain an example where the air conditioner is operating during the second core time in the second period (winter period). The control unit 11 decides to execute demand response control preferentially for the time period with high temperature and high solar radiation (good weather) among the three time periods (for example, the time period two before the processing time, the time period one before the processing time, and the processing time).
[0065] Specifically, if there are two time periods with the highest temperature and one time period with the lowest temperature among the two time periods prior to the processing time, the time period immediately prior to the processing time, and the processing time, the system will decide to execute demand response control for the two time periods with the highest temperature and to cancel demand response control for the time period with the lowest temperature. Furthermore, if there is one time period with the highest temperature and two time periods with the lowest temperature among the three time periods mentioned above, the system will decide to execute demand response control for the time period with the highest temperature and for the time period with the highest solar radiation (good weather) among the two time periods with the lowest temperature, and to cancel demand response control for the time period with the lowest solar radiation (bad weather) among the two time periods with the lowest temperature.
[0066] The control unit 11 repeatedly performs the loop processing described above for all time periods from the 1st to the 48th. The subsequent processing is the same as in Embodiment 1, so the explanation is omitted.
[0067] Embodiment 2 shows an example in which the control unit 11 decides to execute or cancel demand response control for a group of time periods in which demand response control is performed for a first consecutive period within the core time, and for a time period immediately following that group in which demand response control is to be stopped. However, the invention is not limited to this. The control unit 11 can also decide to execute or cancel demand response control for a group of time periods in which demand response control is performed for a second consecutive period even outside the core time, and for a time period immediately following that group in which demand response control is to be stopped.
[0068] Figure 8 is a flowchart showing an example of a processing procedure in the first phase of an information processing system. The flowchart in Figure 8 adds steps S301 to S307 between step S108: YES and step S110. Steps similar to those in Figure 5 are omitted from explanation.
[0069] When the control unit 11 adds a processing time to the DR activation time list, if it determines that the number of consecutive time periods exceeds the maximum number of consecutive time periods (step S108: YES), it obtains weather forecasts for each time period from the web (step S301). The control unit 11 may also obtain hourly weather forecasts and use them to estimate weather forecasts for each time period. The control unit 11 refers to the obtained weather forecasts for each time period (temperature and solar radiation) and determines whether the processing time period satisfies the conditions that the temperature for the processing time period is the highest and the solar radiation for the processing time period is the highest (step S302).
[0070] If the control unit 11 determines that the conditions of having the highest temperature and the highest solar radiation during the processing time are not met (step S302: NO), it identifies the time period with the highest temperature among the time periods other than the processing time (for example, the time period two before the processing time and the time period one before the processing time) (step S303). The control unit 11 determines whether the identified time period is singular (one) or not (step S304). If the control unit 11 determines that there are multiple identified time periods (step S304: NO), it identifies the time period with the highest solar radiation among the multiple time periods identified in step S303 (step S305).
[0071] After step S305, or if the control unit 11 determines that there is only one specified time period (step S304: YES), it decides to cancel the demand response control for the specified time period (for example, the time period two before the processing time period, or the time period one before the processing time period) (step S306). In other words, the control unit 11 removes the specified time period from the DR activation time period list. The control unit 11 decides to execute the demand response control for the processing time period (step S307). In other words, the control unit 11 stores (adds) the processing time period to the DR activation time period list. After step S307, or if the control unit 11 determines that the conditions are met where the temperature of the processing time period is the highest and the amount of solar radiation of the processing time period is the highest (step S302: YES), it proceeds to step S110.
[0072] Figure 9 is a flowchart showing an example of the processing procedure in the second phase of the information processing system. The flowchart in Figure 9 is a modified version of the flowchart in Figure 8, with steps S302 to S305 changed to steps S401 to S404. Steps similar to those in Figure 8 are omitted from explanation. After step S301, the control unit 11 refers to the acquired weather forecast (temperature and weather) for each time period and determines whether the processing time period satisfies the conditions that the temperature for the processing time period is the lowest and the amount of solar radiation for the processing time period is the lowest (step S401).
[0073] If the control unit 11 determines that the conditions of having the lowest temperature and the lowest solar radiation during the processing time are not met (step S401: NO), it identifies the time period with the lowest temperature among the time periods other than the processing time (for example, the time period two before the processing time and the time period one before the processing time) (step S402). The control unit 11 determines whether the identified time period is singular or not (step S403). If the control unit 11 determines that the identified time periods are not singular (there are multiple time periods) (step S403: NO), it identifies the time period with the lowest solar radiation among the multiple time periods identified in step S402 (step S404).
[0074] After step S404, or if the control unit 11 determines that the specified time period is singular (not plural) (step S403: YES), it decides to cancel the demand response control for the specified time period (for example, the time period two before the processing time period, or the time period one before the processing time period) (step S306). In other words, the control unit 11 removes the specified time period from the DR activation time period list. The control unit 11 decides to execute the demand response control for the processing time period (step S307). In other words, the control unit 11 stores (adds) the processing time period to the DR activation time period list. After step S307, or if the control unit 11 determines that the conditions are met that the temperature of the processing time period is the lowest and the amount of solar radiation of the processing time period is the lowest (step S401: YES), it proceeds to step S110.
[0075] According to Embodiment 2, the information processing system can acquire weather forecasts for each time period and, in accordance with the acquired weather forecasts, can decide whether to execute or cancel demand response control for a group of time periods in which the period for executing demand response control is a first consecutive period, and for time periods in which demand response control is to be suspended.
[0076] The embodiments disclosed herein should be considered in all respects to be illustrative and not restrictive. The scope of the invention is indicated by the claims, not in the sense described above, and all modifications within the meaning and scope equivalent to the claims are intended to be included.
[0077] The matters described in each embodiment can be combined with each other. Furthermore, the independent and dependent claims described in the claims can be combined with each other in any combination, regardless of the form of reference. In addition, the claims use a form in which claims referencing two or more other claims (multi-claim form), but are not limited to this. A form in which multi-claims referencing at least one multi-claim (multi-multi-claim) may also be used.
[0078] 10 Information processing device (server) 11 Control unit 12 Storage unit 12P Control program 13 Communication unit 14 Reading unit 1a Portable storage medium 20 Control device (computer) 21 Control unit 22 Storage unit 22P Control program 23 Communication unit
Claims
1. A program that causes a computer to execute a process to obtain the electricity price, determine whether to execute demand response control if the obtained electricity price exceeds a threshold, and determine a period to suspend demand response control so that the period for executing demand response control becomes the first period if the period for executing demand response control exceeds a first period.
2. The program according to claim 1, which determines a period for suspending demand response control so that the period for which demand response control is performed becomes the first period if the period for which demand response control is performed exceeds the first period within the core time.
3. The program according to claim 2, which determines a period for suspending demand response control so that the period for performing demand response control becomes the first period when the period for performing demand response control exceeds the first period during the core time and predetermined time periods before and after the core time.
4. The program according to claim 2 or 3, wherein the first core time in the first period and the second core time in the second period are different.
5. The program according to claim 1, which determines a period for suspending demand response control such that the period for which demand response control is performed exceeds a second period which is longer than the first period, excluding the first core time in the first period and predetermined time periods before and after the first core time, and the second core time in the second period and predetermined time periods before and after the second core time.
6. A program according to any one of claims 1 to 5, which acquires weather forecasts and determines whether to execute or discontinue demand response control for a group of time periods in which demand response control is executed for a first consecutive period, and for time periods in which demand response control is discontinued, in accordance with the acquired weather forecasts.
7. An information processing method that obtains the price of electricity, determines that demand response control should be executed if the obtained price of electricity exceeds a threshold, and determines a period for suspending demand response control so that the period for executing the demand response control becomes the first period if the period for executing the demand response control exceeds a first period.
8. An information processing device comprising a control unit, wherein the control unit acquires electricity prices, determines that demand response control should be executed if the acquired electricity prices exceed a threshold, and determines a period for suspending demand response control so that the period for executing the demand response control becomes the first period if the period for executing the demand response control exceeds a first period.