A low voltage distribution network early warning method, device, equipment and storage medium
Through the improved gray Markov prediction model, the problem of lack of real-time monitoring and accurate early warning in the traditional low-voltage distribution network fault detection method is solved, real-time fault monitoring and early warning of the low-voltage distribution network are realized, and the accuracy of fault prediction is improved. performance and reliability.
Patent Information
- Application Number
- CN202410692732.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-31
- Publication Date
- 2024-09-27
- Estimated Expiration
- 2044-05-31
AI Technical Summary
Traditional low-voltage distribution network fault detection methods rely on manual inspections and user repair reports. They lack real-time monitoring and accurate early warning mechanisms, cannot effectively prevent faults, and have limited data analysis capabilities, resulting in low accuracy and reliability of fault prediction.
The gray Markov prediction model is improved based on a combination of residual correction and metabolism. By collecting typical and real-time data of the low-voltage distribution network, a fault prediction model is constructed to achieve prediction of fault warning indicators and judgment of warning levels.
It improves the accuracy and reliability of low-voltage distribution network fault prediction, realizes real-time monitoring and early warning of faults, reduces false alarms and missed alarms, and improves the effectiveness of early warning.
Smart Images

Figure CN118444084B
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of low-voltage distribution networks, and in particular to a low-voltage distribution network early warning method, device, equipment and storage medium. Background Art
[0002] In the field of low-voltage distribution networks, with the continuous development of smart grid and Internet of Things technologies, big data analysis and prediction have become key means to improve the efficiency of grid operation and management.
[0003] However, the traditional low-voltage distribution network fault detection method has a series of shortcomings, including: 1) Reliance on manual inspection and regular maintenance: The traditional fault detection method needs to rely on manual regular inspection of low-voltage distribution network equipment and lines. The low-voltage distribution network is large in scale and has a complex operating environment. The inspection workload is large and time-consuming and labor-intensive, and it is impossible to monitor and predict faults in real time; 2) Fault reporting is not timely: The traditional fault detection method mainly relies on the user's fault reporting. If the user does not discover or feedback the fault in time, it may cause fault delays and losses; 3) Lack of accurate early warning mechanism: Traditional fault detection methods can often only be processed after the fault has occurred. There is a lack of accurate early warning mechanism and it is impossible to take measures to prevent the occurrence of faults in advance. 4) Limited data analysis capabilities: Traditional fault detection methods do not use big data analysis technology, and cannot quickly and accurately analyze and judge a large amount of real-time data, resulting in low accuracy and reliability of fault prediction; Therefore, a low-voltage distribution network early warning method is needed to make up for these shortcomings and realize real-time monitoring, abnormal prediction and fault early warning of the low-voltage distribution network status. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a low-voltage distribution network early warning method, device, equipment and storage medium, which can realize real-time monitoring and fault early warning of the low-voltage distribution network and improve the accuracy and reliability of the low-voltage distribution network.
[0005] In order to solve the above technical problems, the present invention provides a low voltage distribution network early warning method, comprising:
[0006] Collecting typical parameters of the low-voltage distribution network, performing data processing on the typical parameters, and obtaining pre-processed typical parameters;
[0007] Based on the typical preprocessing parameters, fault warning indicators are selected, and the grey Markov prediction model is improved by combining residual correction and metabolism to build a low-voltage distribution network fault prediction model.
[0008] Collect real-time data of the low-voltage distribution network, input the real-time data into the low-voltage distribution network fault prediction model, so that the low-voltage distribution network fault prediction model outputs a fault warning index prediction value, and performs a warning level judgment on the fault warning index prediction value, and generates corresponding warning level information based on the warning level judgment result.
[0009] In a possible implementation, data processing is performed on the typical parameters to obtain preprocessed typical parameters, specifically including:
[0010] Determine whether there is data missing in the typical parameter, and if so, determine the data missing point, obtain the adjacent data nodes of the data missing point, and generate a data node set based on the data missing point and the adjacent data nodes;
[0011] Obtaining a first number of the adjacent data nodes, determining a second number based on the first number, and selecting the second number of sample data groups from the typical parameters;
[0012] Substituting the sample data groups into a preset first linear regression model respectively, solving the partial correlation coefficient in the first linear regression model to obtain an estimated value of the partial correlation coefficient, and updating the first linear regression model based on the estimated value of the partial correlation coefficient to obtain a second linear regression model;
[0013] Acquire the perception data corresponding to each data node in the data node set, substitute all the perception data into the second linear regression model, and obtain the missing perception data estimation value corresponding to the data missing point;
[0014] The typical parameters are supplemented based on the estimated values of the missing perception data to obtain preprocessed typical parameters.
[0015] In a possible implementation, a fault warning indicator is selected based on the typical preprocessing parameters, and the grey Markov prediction model is improved by combining residual correction and metabolism to construct a low-voltage distribution network fault prediction model, which specifically includes:
[0016] Selecting a fault warning indicator from the preprocessing typical parameters, generating a first data sequence corresponding to the fault warning indicator, and performing accumulation processing on the first data sequence to obtain a second data sequence;
[0017] Determine whether the first data sequence and the second data sequence meet the modeling verification, and if so, construct a grey prediction model based on the first data sequence and the second data sequence, calculate model parameters of the grey prediction model, and establish an approximate differential equation based on the model parameters;
[0018] Based on the approximate differential equation, solving the original form of the grey prediction model to obtain a time response sequence of the grey prediction model, and based on the time response sequence, calculating a first grey prediction value of the grey prediction model;
[0019] The first data sequence is updated based on the first grey prediction value to determine a metabolism grey prediction model,
[0020] Acquire a residual sequence of the first data sequence, perform residual correction and restoration processing on the residual sequence, generate a residual correction model, and determine a second grey prediction value based on the residual correction model;
[0021] Divide the second grey prediction value into states to obtain a state interval, determine a third grey prediction value based on the state interval, and construct a grey Markov prediction model based on the third grey prediction value and the state interval;
[0022] Performing data prediction based on the grey Markov prediction model to obtain a fourth grey prediction value, updating the grey Markov prediction model based on the fourth grey prediction value, and obtaining a transition probability distribution matrix;
[0023] Based on the transition probability distribution matrix and the updated grey Markov prediction model, a low-voltage distribution network fault prediction model is determined.
[0024] In a possible implementation manner, determining whether the first data sequence and the second data sequence satisfy modeling verification specifically includes:
[0025] Inputting the first data sequence into a preset level ratio calculation formula to obtain a level ratio calculation result, comparing the level ratio calculation result with a preset level ratio threshold, and if the level ratio calculation result is not greater than the level ratio threshold, determining that the first data sequence satisfies the level ratio check; otherwise, performing a translation transformation process on the first data sequence until the first data sequence after the translation transformation satisfies the level ratio check;
[0026] The first data sequence and the second data sequence are input into a preset smoothness ratio calculation formula to obtain a smoothness ratio calculation result, and the smoothness ratio calculation result is compared with a preset smoothness ratio threshold. If the smoothness ratio calculation result is less than the smoothness ratio threshold, it is determined that the first data sequence and the second data sequence meet the modeling verification.
[0027] In a possible implementation, obtaining a residual sequence of the first data sequence, performing residual correction and restoration processing on the residual sequence, and generating a residual correction model specifically includes:
[0028] Acquire a residual sequence of the first data sequence, and perform residual correction on the residual sequence based on a preset residual correction formula to obtain a corrected residual sequence;
[0029] Performing restoration processing on the corrected residual sequence based on a preset restoration formula to obtain a restored residual sequence;
[0030] A residual correction model is determined based on the restored residual sequence and the first data sequence.
[0031] In a possible implementation, dividing the second grey prediction value into states to obtain a state interval specifically includes:
[0032] Based on the benchmark data of the fault warning indicator at each time point, a benchmark curve is generated, and based on each time point, an absolute error between the second grey prediction value and the true value is calculated;
[0033] Based on the reference curve and the absolute error, the fault warning indicator is divided into state regions to obtain a first state region and a second state region;
[0034] Based on the first state area and the second state area, a state interval is formed, wherein the state interval is as follows:
[0035] ;
[0036] ;
[0037] ;
[0038] In the formula, is the state interval, is the first state area, is the second state area, is the second grey prediction value, A and B are preset parameters, and i is the i-th time point.
[0039] In a possible implementation, real-time data of the low-voltage distribution network is collected, and the real-time data is input into the low-voltage distribution network fault prediction model so that the low-voltage distribution network fault prediction model outputs a fault warning index prediction value, specifically including:
[0040] Collecting real-time data of the fault warning indicator in the low-voltage distribution network, determining the current state of the fault warning indicator based on the real-time data, and determining the state probability distribution at the next moment based on the current state and the transition probability distribution matrix;
[0041] Determine the state of the fault warning indicator at the next moment according to the state probability distribution at the next moment and the state interval, and determine the next state interval of the fault warning indicator based on the state at the next moment;
[0042] Based on the next state interval and the grey Markov prediction model, a fault warning indicator prediction value is determined; wherein the grey Markov prediction model is as follows:
[0043] ;
[0044] In the formula, is the kth fault warning indicator prediction value output by the grey Markov prediction model, is the kth second grey prediction value, is the first state area, It is the second state area, A and B are preset parameters.
[0045] The present invention also provides a low-voltage distribution network early warning device, comprising: a data processing module, a low-voltage distribution network fault prediction model building module and an early warning module;
[0046] The data processing module is used to collect typical parameters of the low-voltage distribution network, perform data processing on the typical parameters, and obtain pre-processed typical parameters;
[0047] The low-voltage distribution network fault prediction model construction module is used to select fault warning indicators based on the preprocessing typical parameters, improve the grey Markov prediction model by combining residual correction and metabolism, and construct a low-voltage distribution network fault prediction model;
[0048] The early warning module is used to collect real-time data of the low-voltage distribution network, input the real-time data into the low-voltage distribution network fault prediction model, so that the low-voltage distribution network fault prediction model outputs a fault early warning index prediction value, and performs early warning level judgment on the fault early warning index prediction value, and generates corresponding early warning level information based on the early warning level judgment result.
[0049] In a possible implementation, the data processing module is used to perform data processing on the typical parameters to obtain preprocessed typical parameters, specifically including:
[0050] Determine whether there is data missing in the typical parameter, and if so, determine the data missing point, obtain the adjacent data nodes of the data missing point, and generate a data node set based on the data missing point and the adjacent data nodes;
[0051] Obtaining a first number of the adjacent data nodes, determining a second number based on the first number, and selecting the second number of sample data groups from the typical parameters;
[0052] Substituting the sample data groups into a preset first linear regression model respectively, solving the partial correlation coefficient in the first linear regression model to obtain an estimated value of the partial correlation coefficient, and updating the first linear regression model based on the estimated value of the partial correlation coefficient to obtain a second linear regression model;
[0053] Acquire the perception data corresponding to each data node in the data node set, substitute all the perception data into the second linear regression model, and obtain the missing perception data estimation value corresponding to the data missing point;
[0054] The typical parameters are supplemented based on the estimated values of the missing perception data to obtain preprocessed typical parameters.
[0055] In a possible implementation, the low-voltage distribution network fault prediction model construction module is used to select fault warning indicators based on the preprocessing typical parameters, improve the grey Markov prediction model by combining residual correction and metabolism, and construct a low-voltage distribution network fault prediction model, which specifically includes:
[0056] Selecting a fault warning indicator from the preprocessing typical parameters, generating a first data sequence corresponding to the fault warning indicator, and performing accumulation processing on the first data sequence to obtain a second data sequence;
[0057] Determine whether the first data sequence and the second data sequence meet the modeling verification, and if so, construct a grey prediction model based on the first data sequence and the second data sequence, calculate model parameters of the grey prediction model, and establish an approximate differential equation based on the model parameters;
[0058] Based on the approximate differential equation, solving the original form of the grey prediction model to obtain a time response sequence of the grey prediction model, and based on the time response sequence, calculating a first grey prediction value of the grey prediction model;
[0059] The first data sequence is updated based on the first grey prediction value to determine a metabolism grey prediction model,
[0060] Acquire a residual sequence of the first data sequence, perform residual correction and restoration processing on the residual sequence, generate a residual correction model, and determine a second grey prediction value based on the residual correction model;
[0061] Divide the second grey prediction value into states to obtain a state interval, determine a third grey prediction value based on the state interval, and construct a grey Markov prediction model based on the third grey prediction value and the state interval;
[0062] Performing data prediction based on the grey Markov prediction model to obtain a fourth grey prediction value, updating the grey Markov prediction model based on the fourth grey prediction value, and obtaining a transition probability distribution matrix;
[0063] Based on the transition probability distribution matrix and the updated grey Markov prediction model, a low-voltage distribution network fault prediction model is determined.
[0064] In a possible implementation, the low-voltage distribution network fault prediction model building module is used to determine whether the first data sequence and the second data sequence meet the modeling verification, specifically including:
[0065] Inputting the first data sequence into a preset level ratio calculation formula to obtain a level ratio calculation result, comparing the level ratio calculation result with a preset level ratio threshold, and if the level ratio calculation result is not greater than the level ratio threshold, determining that the first data sequence satisfies the level ratio check; otherwise, performing a translation transformation process on the first data sequence until the first data sequence after the translation transformation satisfies the level ratio check;
[0066] The first data sequence and the second data sequence are input into a preset smoothness ratio calculation formula to obtain a smoothness ratio calculation result, and the smoothness ratio calculation result is compared with a preset smoothness ratio threshold. If the smoothness ratio calculation result is less than the smoothness ratio threshold, it is determined that the first data sequence and the second data sequence meet the modeling verification.
[0067] In a possible implementation, the low-voltage distribution network fault prediction model building module is used to obtain a residual sequence of the first data sequence, perform residual correction and restoration processing on the residual sequence, and generate a residual correction model, specifically including:
[0068] Acquire a residual sequence of the first data sequence, and perform residual correction on the residual sequence based on a preset residual correction formula to obtain a corrected residual sequence;
[0069] Performing restoration processing on the corrected residual sequence based on a preset restoration formula to obtain a restored residual sequence;
[0070] A residual correction model is determined based on the restored residual sequence and the first data sequence.
[0071] In a possible implementation, the low-voltage distribution network fault prediction model construction module is used to divide the second grey prediction value into states to obtain state intervals, specifically including:
[0072] Based on the benchmark data of the fault warning indicator at each time point, a benchmark curve is generated, and based on each time point, an absolute error between the second grey prediction value and the true value is calculated;
[0073] Based on the reference curve and the absolute error, the fault warning indicator is divided into state regions to obtain a first state region and a second state region;
[0074] Based on the first state area and the second state area, a state interval is formed, wherein the state interval is as follows:
[0075] ;
[0076] ;
[0077] ;
[0078] In the formula, is the state interval, is the first state area, is the second state area, is the second grey prediction value, A and B are preset parameters, and i is the i-th time point.
[0079] In a possible implementation, the early warning module is used to collect real-time data of the low-voltage distribution network and input the real-time data into the low-voltage distribution network fault prediction model so that the low-voltage distribution network fault prediction model outputs a fault early warning index prediction value, specifically including:
[0080] Collecting real-time data of the fault warning indicator in the low-voltage distribution network, determining the current state of the fault warning indicator based on the real-time data, and determining the state probability distribution at the next moment based on the current state and the transition probability distribution matrix;
[0081] Determine the state of the fault warning indicator at the next moment according to the state probability distribution at the next moment and the state interval, and determine the next state interval of the fault warning indicator based on the state at the next moment;
[0082] Based on the next state interval and the grey Markov prediction model, a fault warning indicator prediction value is determined; wherein the grey Markov prediction model is as follows:
[0083] ;
[0084] In the formula, is the kth fault warning indicator prediction value output by the grey Markov prediction model, is the kth second grey prediction value, is the first state area, It is the second state area, A and B are preset parameters.
[0085] The present invention also provides a terminal device, comprising a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, wherein when the processor executes the computer program, the low-voltage distribution network early warning method as described in any one of the above items is implemented.
[0086] The present invention also provides a computer-readable storage medium, which includes a stored computer program, wherein when the computer program is running, the device where the computer-readable storage medium is located is controlled to execute the low-voltage distribution network early warning method as described in any one of the above.
[0087] The embodiments of the present invention provide a low-voltage distribution network early warning method, device, equipment and storage medium, which have the following beneficial effects compared with the prior art:
[0088] Typical parameters of a low-voltage distribution network are collected, and data processing is performed on the typical parameters to obtain pre-processed typical parameters; fault warning indicators are selected based on the pre-processed typical parameters, and a gray Markov prediction model is improved by adopting a method based on a combination of residual correction and metabolism to construct a low-voltage distribution network fault prediction model; real-time data of the low-voltage distribution network is collected, and the real-time data is input into the low-voltage distribution network fault prediction model, so that the low-voltage distribution network fault prediction model outputs a fault warning indicator prediction value, and a warning level judgment is performed on the fault warning indicator prediction value, and corresponding warning level information is generated based on the warning level judgment result; compared with the prior art, the technical solution of the present invention selects fault warning indicators based on pre-processed typical parameters, and improves the prediction model by combining residual correction and metabolism, which can improve the accuracy and reliability of model prediction, and by collecting real-time data of the low-voltage distribution network and combining the improved gray Markov prediction model, it is possible to realize real-time monitoring and fault prediction of the low-voltage distribution network, and generate corresponding warning level information, so as to realize more accurate fault warning, help reduce false alarms and missed alarms, and improve the effectiveness of warnings. BRIEF DESCRIPTION OF THE DRAWINGS
[0089] Figure 1 It is a flow chart of an embodiment of a low-voltage distribution network early warning method provided by the present invention;
[0090] Figure 2It is a structural schematic diagram of an embodiment of a low-voltage distribution network early warning device provided by the present invention;
[0091] Figure 3 It is a structural schematic diagram of a terminal device provided by the present invention. DETAILED DESCRIPTION
[0092] The following will be combined with the accompanying drawings in the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0093] Example 1, see Figure 1 , Figure 1 FIG. 1 is a flow chart of an embodiment of a low-voltage distribution network early warning method provided by the present invention. Figure 1 As shown, the method includes steps 101 to 103, which are specifically as follows:
[0094] Step 101: Collect typical parameters of a low-voltage distribution network, perform data processing on the typical parameters, and obtain pre-processed typical parameters.
[0095] In one embodiment, typical parameters of the low-voltage distribution network are obtained by installing sensors, smart meters and other equipment, and the collected typical parameters are transmitted to the data center through the communication network for storage and processing, thereby realizing real-time monitoring and data collection of the power grid operation status.
[0096] Specifically, the typical parameters include voltage U, current I, active load P, reactive load Q, etc.; based on sensors and smart meters and other devices, the voltage, current, frequency and other parameters of each node in the power grid can be sensed.
[0097] Specifically, the sampling interval and total sampling period of the data are set so that devices such as sensors and smart meters can obtain typical parameters of the low-voltage distribution network based on the sampling interval and total sampling period of the data; Example description: If the sampling interval of each data is set to 15 minutes and the total sampling period is 1 day, that is, within one total sampling period, a total of 96 typical parameters of the low-voltage distribution network are collected.
[0098] In one embodiment, after receiving the typical parameters transmitted by the sensors and the smart meters, the data center will also perform data processing on the typical parameters to obtain pre-processed typical parameters.
[0099] Specifically, data processing is performed on typical parameters, including supplementing missing typical parameters of the low-voltage distribution network to improve data quality, and extracting big data features to provide a reliable basis for subsequent anomaly cleaning; at the same time, based on the correlation between data, missing data in a specific environment can be completed; in addition to using real-time correlated data, the historical data characteristics of the data should also be considered for data completion; through the analysis of historical data, the trend, periodicity and other characteristics of the data can be understood, so as to better complete and adjust the data.
[0100] In one embodiment, the data processing includes: determining whether there is data missing in the typical parameter, and if so, determining the data missing point, and obtaining the adjacent data nodes of the data missing point, and generating a data node set based on the data missing point and the adjacent data nodes; obtaining a first number of the adjacent data nodes, determining a second number based on the first number, and selecting the second number of sample data groups from the typical parameter; substituting the sample data groups into a preset first linear regression model, solving the partial correlation coefficient in the first linear regression model, obtaining an estimated partial correlation coefficient, and updating the first linear regression model based on the estimated partial correlation coefficient to obtain a second linear regression model; obtaining the perception data corresponding to each data node in the data node set, substituting all the perception data into the second linear regression model, and obtaining an estimated value of the missing perception data corresponding to the data missing point; and completing the data of the typical parameter based on the estimated value of the missing perception data to obtain a preprocessed typical parameter.
[0101] Specifically, there will be a judgment on data collection and communication, such as communication interruption, data not being uploaded, etc. The underlying logic of the system will have a preliminary judgment. Some terminals are offline at the time of collection due to signal problems, collection equipment failure, etc., which will result in no data being sent by the terminal, resulting in missing data. When it is determined that missing data has occurred, it is judged that there is missing data in the typical parameters.
[0102] Specifically, since the typical parameter collection process is based on continuous collection at sampling intervals, when a certain data is missing, the data missing point is determined and the It means that there are a lot of historical data collected before and after it, so for the data missing points , there are b adjacent data nodes, which are , with a point As the center, generate a set of data nodes , wherein the selection of b adjacent data nodes is to take the data missing point as the center and take b / 2 on both sides; preferably, the b adjacent data nodes are not less than 10 data samples.
[0103] Specifically, based on the first number b of the adjacent data nodes, select Group Sample Data Group As sample data, and this set of data is known data. The purpose of taking the C value in this way is to solve the multivariate linear equations and have a solution. There will be a built-in loop, C=b+2+1, until the solution is found. Too large a C value (larger than b+2) will generally cause correlation or mutual expression between multiple arrays, so it usually starts from b+2; too small a C value (smaller than b+2) will generally make the equation unsolvable; the solution process is the process of solving the equation, b unknown quantities, at least b+2 data groups, directly solve.
[0104] Specifically, the preset first linear regression model is as follows:
[0105] ;
[0106] Among them, t represents the time, , Respectively indicate points , The data perceived at time t, where , It corresponds to The partial correlation coefficient of right The impact can be measured through To reflect.
[0107] Specifically, by substituting the c groups of sample data into the preset first linear regression model, the partial correlation coefficient of the sample data is calculated. Perform regression operation to obtain the estimated value of partial correlation coefficient , the estimated partial correlation coefficient Substitute it into the first linear regression model, update the first linear regression model, and obtain the second linear regression model.
[0108] Specifically, the second linear regression model is as follows:
[0109] in, for The estimated value of the missing sensed data perceived at time t, For the corresponding The estimated partial correlation coefficient of .
[0110] Specifically, the perception data corresponding to each data node in the data node set is substituted into the second linear regression model to obtain the data missing point. Corresponding missing-aware data estimates , and based on the estimated value of the missing perception data, the typical parameters are completed to obtain pre-processed typical parameters; creating conditions for subsequent feature extraction and detection.
[0111] In one embodiment, data cleaning is also performed on the preprocessing typical parameters.
[0112] Specifically, by setting a limit value to filter the data, those data that exceed or do not meet the pre-set range will be eliminated or marked; for example, for a certain parameter, if the value exceeds the normal range, it can be marked as abnormal data for subsequent processing.
[0113] Specifically, data cleaning is performed based on the logical relationship between data; that is, by analyzing the correlation and logical laws between data, the contradictory or erroneous data is identified and removed or marked; for example, if there is a logical contradiction between two parameters, it can be treated as abnormal data.
[0114] Specifically, power flow calculation is an important method for power system analysis, which is usually used to calculate the power and voltage distribution between various nodes in the power system. Through power flow calculation, the voltage, power and other parameters of each node can be obtained, and then the formula To calculate the error, and to eliminate or warn the corresponding data based on the error value.
[0115] Step 102: selecting fault warning indicators based on the preprocessing typical parameters, improving the grey Markov prediction model by combining residual correction with metabolism, and constructing a low-voltage distribution network fault prediction model.
[0116] In one embodiment, a fault warning indicator is selected from the preprocessing typical parameters, and a first data sequence corresponding to the fault warning indicator is generated, and the first data sequence is accumulated to obtain a second data sequence.
[0117] Specifically, based on the preprocessing typical parameters, important parameters or characteristics for predicting or monitoring faults are determined. These parameters are usually indicators closely related to the equipment status or performance. Through professional knowledge and experience, indicators suitable for fault warning are selected. The fault warning indicators include voltage U, current I, active load P, reactive load Q, etc.
[0118] Specifically, based on the selected fault warning indicator, corresponding data values are extracted from the collected preprocessing typical parameters to form a first data sequence. ,in, Indicates the nth data point of the fault warning indicator in the preprocessing typical parameters.
[0119] Specifically, for the first data sequence The second data sequence is generated cumulatively:
[0120] ;
[0121] ;
[0122] ;
[0123]
[0124] ;
[0125] In the formula, Indicates the nth data point in the cumulatively generated sequence, which is the sum of the first data sequence This cumulative generation method can be used to analyze the cumulative trend or total change of data, and is often used in time series analysis or trend forecasting.
[0126] In one embodiment, it is determined whether the first data sequence and the second data sequence satisfy the modeling verification. If so, a gray prediction model is constructed based on the first data sequence and the second data sequence, and the model parameters of the gray prediction model are calculated. Based on the model parameters, an approximate differential equation is established.
[0127] Specifically, when judging whether the first data sequence and the second data sequence satisfy the modeling verification, the first data sequence is input into a preset level ratio calculation formula to obtain a level ratio calculation result, and the level ratio calculation result is compared with a preset level ratio threshold value. If the level ratio calculation result is not greater than the level ratio threshold value, it is determined that the first data sequence satisfies the level ratio verification; otherwise, the first data sequence is subjected to a translation transformation until the first data sequence after the translation transformation satisfies the level ratio verification; the first data sequence and the second data sequence are input into a preset smoothness ratio calculation formula to obtain a smoothness ratio calculation result, and the smoothness ratio calculation result is compared with a preset smoothness ratio threshold value. If the smoothness ratio calculation result is less than the smoothness ratio threshold value, it is determined that the first data sequence and the second data sequence satisfy the modeling verification.
[0128] Specifically, the preset level ratio calculation formula is as follows:
[0129] ;
[0130] In the formula, is the level ratio of the kth data point, is the k-1th data point in the first data sequence, is the kth data point in the first data sequence, is the length of the first data sequence, is the base of natural logarithms, Used to limit the range of the level ratio value, that is, the level ratio threshold.
[0131] Specifically, the preset smoothness ratio calculation formula is as follows:
[0132] ;
[0133] In the formula, is the kth data point in the first data sequence, is the k-1th data point in the second data sequence, is the length of the first data sequence, is the smoothness ratio threshold.
[0134] Specifically, a grey prediction model is constructed based on the first data sequence and the second data sequence, wherein the original form of the grey prediction model GM (1,1) is: ; In the formula, is the development coefficient, representing the change and development trend of the behavior sequence estimate, It is a gray action quantity, which represents the relationship of the change of research data.
[0135] Specifically, the least squares method is used to calculate the model parameters in the grey prediction model GM (1,1) :
[0136] ;
[0137] Where:
[0138] .
[0139] Specifically, based on the model parameters, an approximate differential equation is established, and the approximate differential equation is as follows:
[0140] ;
[0141] In the formula, is the second data sequence; is the development coefficient, representing the change and development trend of the behavior sequence estimate, is the gray action, representing the relationship between the research data changes; t is the time parameter of the differential equation.
[0142] In one embodiment, based on the approximate differential equation, the original form of the grey prediction model is solved to obtain a time response sequence of the grey prediction model, and based on the time response sequence, a first grey prediction value of the grey prediction model is calculated.
[0143] Specifically, the differential equation is solved to obtain:
[0144] .
[0145] Specifically, the grey prediction model GM (1,1): The time response sequence of is:
[0146] ;
[0147] .
[0148] Specifically, when calculating the first grey prediction value of the grey prediction model, the time corresponding sequence is substituted into a preset grey prediction value calculation formula to obtain the first grey prediction value, wherein the grey prediction value calculation formula is as follows:
[0149]
[0150] .
[0151] In one embodiment, the first data sequence is updated based on the first grey prediction value to determine a metabolic grey prediction model.
[0152] Specifically, considering that the voltage is constantly evolving over time, in order to improve the prediction accuracy of the model, the metabolic GM (1, 1) model is introduced. The improvement of the GM (1, 1) model should use the latest information that the system itself can provide to improve the boundary conditions.
[0153] Specifically, for the original first data sequence , establish the GM (1, 1) prediction model to obtain the latest data , by removing , thereby updating the first data sequence and obtaining , which is the metabolic grey prediction model.
[0154] In one embodiment, a residual sequence of the first data sequence is obtained, residual correction and restoration processing is performed on the residual sequence to generate a residual correction model, and a second grey prediction value is determined based on the residual correction model.
[0155] Specifically, in order to improve the grey prediction accuracy of data series, a residual correction model is introduced to make up for the deficiency of the prediction value of the metabolic grey prediction model GM (1, 1) and achieve the purpose of improving accuracy and precision.
[0156] Specifically, in, is the first data sequence after update The residual sequence of .
[0157] Specifically, the residual sequence is subjected to residual correction based on a preset residual correction formula to obtain a corrected residual sequence, wherein the residual correction formula is as follows:
[0158] ;
[0159] In the formula, To correct the i+1th residual value in the residual sequence, is the residual sequence The residual value, and is the adjustment parameter of the residual sequence.
[0160] Specifically, the modified residual sequence is restored based on a preset restoration formula to obtain a restored residual sequence, wherein the restoration formula is as follows:
[0161] ;
[0162] In the formula, To restore the i+1th residual value in the residual sequence, is the residual sequence Residual values.
[0163] Specifically, based on the restored residual sequence and the first data sequence, a residual correction model is determined; wherein the residual correction model is as follows:
[0164] ;
[0165] In the formula, is the corrected i+1th data point in the first data sequence, that is, the second grey prediction value calculated according to the residual correction model.
[0166] In one embodiment, the second grey prediction value is divided into states to obtain a state interval, a third grey prediction value is determined based on the state interval, and a grey Markov prediction model is constructed based on the third grey prediction value and the state interval.
[0167] Specifically, based on the benchmark data of the fault warning indicator at each time point, a benchmark curve is generated, and based on each time point, the absolute error between the second grey prediction value and the true value is calculated; based on the benchmark curve and the absolute error, the fault warning indicator is divided into state areas to obtain a first state area and a second state area; and based on the first state area and the second state area, a state interval is constructed.
[0168] Preferably, the first state region and the second state region are parallel to the reference curve.
[0169] Specifically, the status interval is as follows:
[0170] ;
[0171] ;
[0172] ;
[0173] In the formula, is the state interval, is the first state area, is the second state area, is the second grey prediction value, A and B are preset parameters which can be determined based on experience, and i is the i-th time point.
[0174] Specifically, the second gray prediction value obtained based on the residual correction combined with the metabolic gray prediction model is combined with the state interval of the Markov model, and the middle value of the state interval is selected as the third gray prediction value. Through the third gray prediction value and the state interval, a gray Markov prediction model based on residual correction combined with metabolism is constructed.
[0175] In one embodiment, data prediction is performed based on the grey Markov prediction model to obtain a fourth grey prediction value, and based on the fourth grey prediction value, the grey Markov prediction model is updated to obtain a transition probability distribution matrix.
[0176] Specifically, historical data is selected from the data center, and gray Markov prediction is performed through the gray Markov prediction model to obtain a fourth gray prediction value, the fourth gray prediction value is added to the first data sequence, and the first data in the first data sequence is removed, and the fourth gray prediction value is used as the last data in the first data sequence to form a new data sequence, and the gray Markov prediction model is used again based on the new data sequence, that is, a new gray prediction value is obtained by cyclic recursion based on the above method, and the data sequence is continuously updated based on the new gray prediction value to update the gray Markov prediction model.
[0177] Specifically, status After n steps of transfer, the state is reached The number of data samples is recorded as , is the frequency of occurrence of each state, then the state transition probability is:
[0178] .
[0179] Example: Assume that the data is divided into 3 states. Assume that the state 1 occurs 4 times. After one-step transition, the states become state 3, state 1, state 1, and state 2. Therefore, it can be concluded that the probability of remaining in state 1 after one-step transition from state 1 is 1 / 2, and the probability of transitioning to state 2 and 4 is 1 / 4. These probabilities constitute the one-step transition probability matrix. The first row, and the remaining rows of elements are processed according to the above method and so on.
[0180] Specifically, in the process of establishing the grey Markov prediction model, a transition probability distribution matrix is obtained. , used to describe the state transition probability of historical data; this matrix contains the transition probabilities between various states and can help predict the development trend of future data; the transition probability distribution matrix As shown below:
[0181] .
[0182] Specifically, if the state at the previous moment is , then the probability distribution of the state at the next moment is determined as:
[0183] ;
[0184] in, The next moment state The one-step transition probability distribution matrix.
[0185] In one embodiment, a low voltage distribution network fault prediction model is determined based on the transition probability distribution matrix and the updated grey Markov prediction model.
[0186] Specifically, the state transition probability matrix P can be used to analyze the next transition law of each state of the fault warning indicator, and the data at the next moment can be predicted by the state transition probability matrix P and the state of the fault warning indicator; therefore, the state transition probability matrix is obtained, and combined with the method based on residual correction combined with metabolism, grey Markov prediction based on residual correction combined with metabolism can be performed.
[0187] Step 103: Collect real-time data of the low-voltage distribution network, input the real-time data into the low-voltage distribution network fault prediction model, so that the low-voltage distribution network fault prediction model outputs a fault warning index prediction value, and performs a warning level judgment on the fault warning index prediction value, and generates corresponding warning level information based on the warning level judgment result.
[0188] In one embodiment, real-time data of the fault warning indicator in the low-voltage distribution network is collected, and based on the real-time data, the current state of the fault warning indicator is determined, and based on the current state and the transition probability distribution matrix, the state probability distribution at the next moment is determined; according to the state probability distribution at the next moment and the state interval, the state of the fault warning indicator at the next moment is determined, and based on the state at the next moment, the next state interval of the fault warning indicator is determined; based on the next state interval and the grey Markov prediction model, the predicted value of the fault warning indicator is determined.
[0189] In one embodiment, the grey Markov prediction model is as follows:
[0190] ;
[0191] In the formula, is the kth fault warning indicator prediction value output by the grey Markov prediction model, is the kth second grey prediction value, is the first state area, It is the second state area, A and B are preset parameters.
[0192] In one embodiment, when judging the warning level of the predicted value of the fault warning indicator, the maximum allowable threshold, the minimum allowable threshold and the change rate range are set for the fault warning indicator; and the fault warning level is divided into level one warning, level two warning and level three warning.
[0193] For example, when the fault warning indicator is voltage, different voltage value ranges and change rate conditions are set according to different warning levels: Level 3 warning: the voltage value is in the range of 198-235.4V, and the change rate is greater than 10%; Level 2 warning: the voltage value is in the range of 180-198V; Level 1 warning: the voltage value is lower than 180V or greater than 235.4V.
[0194] In one embodiment, when it is detected that the predicted value of the fault warning indicator meets any warning level condition, the system automatically triggers the corresponding warning; the warning information can be sent to relevant personnel via SMS, email or mobile application to remind them of potential failure risks.
[0195] In one embodiment, after receiving the warning information, relevant personnel should take timely measures to diagnose and handle the fault; provide corresponding processing suggestions according to the warning level to reduce potential risks and ensure the safe operation of the distribution network.
[0196] In summary, this embodiment provides a low-voltage distribution network early warning method. By adopting real-time data acquisition and processing technology, it can realize real-time monitoring and prediction of the low-voltage distribution network. Compared with traditional patrol and manual maintenance methods, it has higher efficiency and accuracy; and at the same time, by using big data analysis technology, it can process massive data of the low-voltage distribution network, extract key features, and establish a gray Markov prediction model based on residual correction combined with metabolism; compared with traditional rule-based fault diagnosis methods, it has higher intelligence and adaptability; finally, through real-time monitoring and prediction, timely warning of potential fault risks can be given, which can improve the reliability and safety of the low-voltage distribution network and avoid economic losses and safety hazards caused by faults.
[0197] Example 2, see Figure 2 , Figure 2 : is a structural schematic diagram of an embodiment of a low-voltage distribution network early warning device provided by the present invention, such as Figure 2 As shown, the device includes a data processing module 201, a low-voltage distribution network fault prediction model building module 202 and an early warning module 203, which are specifically as follows:
[0198] The data processing module 201 is used to collect typical parameters of the low-voltage distribution network, perform data processing on the typical parameters, and obtain pre-processed typical parameters.
[0199] The low-voltage distribution network fault prediction model construction module 202 is used to select fault warning indicators based on the preprocessing typical parameters, improve the grey Markov prediction model by combining residual correction and metabolism, and construct a low-voltage distribution network fault prediction model.
[0200] The early warning module 203 is used to collect real-time data of the low-voltage distribution network, input the real-time data into the low-voltage distribution network fault prediction model, so that the low-voltage distribution network fault prediction model outputs a fault early warning index prediction value, and performs early warning level judgment on the fault early warning index prediction value, and generates corresponding early warning level information based on the early warning level judgment result.
[0201] In one embodiment, the data processing module 201 is used to perform data processing on the typical parameters to obtain preprocessed typical parameters, specifically including: determining whether there is data missing in the typical parameters, and if so, determining the data missing point, and obtaining the adjacent data nodes of the data missing point, and generating a data node set based on the data missing point and the adjacent data nodes; obtaining a first number of the adjacent data nodes, determining a second number based on the first number, and selecting the second number of sample data groups from the typical parameters; substituting the sample data groups into a preset first linear regression model, solving the partial correlation coefficient in the first linear regression model, obtaining an estimated value of the partial correlation coefficient, and updating the first linear regression model based on the estimated value of the partial correlation coefficient to obtain a second linear regression model; obtaining the perception data corresponding to each data node in the data node set, substituting all the perception data into the second linear regression model, and obtaining the estimated value of the missing perception data corresponding to the data missing point; and completing the data of the typical parameters based on the estimated value of the missing perception data to obtain preprocessed typical parameters.
[0202] In one embodiment, the low-voltage distribution network fault prediction model construction module 202 is used to select fault warning indicators based on the preprocessing typical parameters, improve the gray Markov prediction model by combining residual correction and metabolism, and construct a low-voltage distribution network fault prediction model, which specifically includes: selecting fault warning indicators from the preprocessing typical parameters, and generating a first data sequence corresponding to the fault warning indicator, accumulating the first data sequence to obtain a second data sequence; judging whether the first data sequence and the second data sequence meet the modeling verification, if so, constructing a gray prediction model based on the first data sequence and the second data sequence, and calculating the model parameters of the gray prediction model, and establishing an approximate differential equation based on the model parameters; solving the original form of the gray prediction model based on the approximate differential equation to obtain the time response sequence of the gray prediction model, and based on the time response sequence The invention discloses a method for determining a gray prediction model based on a gray prediction model, wherein the first data sequence is updated based on the first gray prediction value, a metabolic gray prediction model is determined, a residual sequence of the first data sequence is obtained, the residual sequence is corrected and restored, a residual correction model is generated, and a second gray prediction value is determined based on the residual correction model; the second gray prediction value is divided into states to obtain a state interval, a third gray prediction value is determined based on the state interval, and a gray Markov prediction model is constructed based on the third gray prediction value and the state interval; data prediction is performed based on the gray Markov prediction model to obtain a fourth gray prediction value, the gray Markov prediction model is updated based on the fourth gray prediction value, and a transfer probability distribution matrix is obtained; a low-voltage distribution network fault prediction model is determined based on the transfer probability distribution matrix and the updated gray Markov prediction model.
[0203] In one embodiment, the low-voltage distribution network fault prediction model building module 202 is used to determine whether the first data sequence and the second data sequence meet the modeling verification, specifically including: inputting the first data sequence into a preset level ratio calculation formula to obtain a level ratio calculation result, comparing the level ratio calculation result with a preset level ratio threshold, if the level ratio calculation result is not greater than the level ratio threshold, then determining that the first data sequence meets the level ratio verification, otherwise, performing a translation transformation on the first data sequence until the first data sequence after the translation transformation meets the level ratio verification; inputting the first data sequence and the second data sequence into a preset smoothness ratio calculation formula to obtain a smoothness ratio calculation result, comparing the smoothness ratio calculation result with a preset smoothness ratio threshold, if the smoothness ratio calculation result is less than the smoothness ratio threshold, then determining that the first data sequence and the second data sequence meet the modeling verification.
[0204] In one embodiment, the low-voltage distribution network fault prediction model construction module 202 is used to obtain the residual sequence of the first data sequence, perform residual correction and restoration processing on the residual sequence, and generate a residual correction model, specifically including: obtaining the residual sequence of the first data sequence, performing residual correction on the residual sequence based on a preset residual correction formula to obtain a corrected residual sequence; performing restoration processing on the corrected residual sequence based on a preset restoration formula to obtain a restored residual sequence; and determining the residual correction model based on the restored residual sequence and the first data sequence.
[0205] In one embodiment, the low-voltage distribution network fault prediction model construction module 202 is used to divide the second gray prediction value into states to obtain a state interval, specifically including: generating a reference curve based on the reference data of the fault warning indicator for each time point, and calculating the absolute error between the second gray prediction value and the true value based on each time point; dividing the fault warning indicator into state regions based on the reference curve and the absolute error to obtain a first state region and a second state region; and forming a state interval based on the first state region and the second state region, wherein the state interval is as follows:
[0206] ;
[0207] ;
[0208] ;
[0209] In the formula, is the state interval, is the first state area, is the second state area, is the second grey prediction value, A and B are preset parameters, and i is the i-th time point.
[0210] In one embodiment, the early warning module 203 is used to collect real-time data of the low-voltage distribution network, and input the real-time data into the low-voltage distribution network fault prediction model so that the low-voltage distribution network fault prediction model outputs a fault early warning index prediction value, specifically including: collecting real-time data of the fault early warning index in the low-voltage distribution network, determining the current state of the fault early warning index based on the real-time data, and determining the state probability distribution at the next moment based on the current state and the transition probability distribution matrix; determining the next moment state of the fault early warning index according to the next moment state probability distribution and the state interval, and determining the next state interval of the fault early warning index based on the next moment state; determining the fault early warning index prediction value based on the next state interval and the gray Markov prediction model; wherein the gray Markov prediction model is as follows:
[0211] ;
[0212] In the formula, is the kth fault warning indicator prediction value output by the grey Markov prediction model, is the kth second grey prediction value, is the first state area, It is the second state area, A and B are preset parameters.
[0213] The data processing device for multi-source data fusion can implement the data processing method for multi-source data fusion of the method embodiment. The options in the method embodiment are also applicable to this embodiment and will not be described in detail here.
[0214] Figure 3 FIG. 1 is a schematic diagram of the structure of a terminal device. Figure 3 As shown, the terminal device 3 of this embodiment includes: at least one processor 301 ( Figure 3 Only one is shown in the figure) a processor, a memory 302, and a computer program 303 stored in the memory 302 and executable on at least one processor 301, and when the processor 301 executes the computer program 303, the steps in any of the above method embodiments are implemented.
[0215] The terminal device 3 may be a computing device such as a smart phone, a laptop, a tablet computer, and a desktop computer. The terminal device may include but is not limited to a processor 301 and a memory 302. Those skilled in the art will appreciate that Figure 3 It is only an example of the terminal device 3 and does not constitute a limitation on the terminal device 3. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, it may also include input and output devices, network access devices, etc.
[0216] The processor 301 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.
[0217] In some embodiments, the memory 302 may be an internal storage unit of the terminal device 3, such as a hard disk or memory of the terminal device 3. In other embodiments, the memory 302 may also be an external storage device of the terminal device 3, such as a plug-in hard disk, a smart media card (SMC), a secure digital (SD) card, a flash card, etc. equipped on the terminal device 3. Further, the memory 302 may also include both an internal storage unit and an external storage device of the terminal device 3. The memory 302 is used to store an operating system, an application program, a boot loader (BootLoader), data, and other programs, such as program codes of a computer program, etc. The memory 302 may also be used to temporarily store data that has been output or is to be output.
[0218] In addition, an embodiment of the present application further provides a computer-readable storage medium, which stores a computer program. When the computer program is executed by a processor, the steps in any of the above method embodiments are implemented.
[0219] An embodiment of the present application provides a computer program product. When the computer program product is run on a terminal device, the terminal device implements the steps in the above-mentioned method embodiments when executing the computer program product.
[0220] In several embodiments provided in the present application, it is understood that each box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and a module, a program segment or a part of a code includes one or more executable instructions for realizing a specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from that marked in the accompanying drawings. For example, two consecutive boxes can actually be executed substantially in parallel, and they can sometimes also be executed in the opposite order, depending on the functions involved.
[0221] If the function is implemented in the form of a software function module and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including a number of instructions for a terminal device to execute all or part of the steps of each embodiment method of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program code.
[0222] In summary, the present invention provides a low-voltage distribution network early warning method, device, equipment and storage medium, which collect typical parameters of the low-voltage distribution network, perform data processing on the typical parameters, and obtain pre-processed typical parameters; select fault warning indicators based on the pre-processed typical parameters, and improve the grey Markov prediction model by combining residual correction and metabolism to construct a low-voltage distribution network fault prediction model; collect real-time data of the low-voltage distribution network, and input the real-time data into the low-voltage distribution network fault prediction model, so that the low-voltage distribution network fault prediction model outputs a fault warning indicator prediction value, and performs a warning level judgment on the fault warning indicator prediction value, and generates corresponding warning level information based on the warning level judgment result; compared with the prior art, the technical solution of the present invention can realize real-time monitoring and fault warning of the low-voltage distribution network, and improve the accuracy and reliability of the low-voltage distribution network.
[0223] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A low voltage distribution network early warning method, characterized in that: include: Collecting typical parameters of the low-voltage distribution network, performing data processing on the typical parameters, and obtaining pre-processed typical parameters; Based on the typical preprocessing parameters, fault warning indicators are selected, and the grey Markov prediction model is improved by combining residual correction and metabolism to build a low-voltage distribution network fault prediction model. Collecting real-time data of the low-voltage distribution network, inputting the real-time data into the low-voltage distribution network fault prediction model, so that the low-voltage distribution network fault prediction model outputs a fault warning index prediction value, and performing a warning level judgment on the fault warning index prediction value, and generating corresponding warning level information based on the warning level judgment result; Among them, the fault warning indicators are selected based on the typical parameters of the preprocessing, and the grey Markov prediction model is improved by combining residual correction and metabolism to construct a low-voltage distribution network fault prediction model, which specifically includes: Selecting a fault warning indicator from the preprocessing typical parameters, generating a first data sequence corresponding to the fault warning indicator, and performing accumulation processing on the first data sequence to obtain a second data sequence; Determine whether the first data sequence and the second data sequence meet the modeling verification, and if so, construct a grey prediction model based on the first data sequence and the second data sequence, calculate model parameters of the grey prediction model, and establish an approximate differential equation based on the model parameters; Based on the approximate differential equation, solving the original form of the grey prediction model to obtain a time response sequence of the grey prediction model, and based on the time response sequence, calculating a first grey prediction value of the grey prediction model; The first data sequence is updated based on the first grey prediction value to determine a metabolism grey prediction model, Acquire a residual sequence of the first data sequence, perform residual correction and restoration processing on the residual sequence, generate a residual correction model, and determine a second grey prediction value based on the residual correction model; Divide the second grey prediction value into states to obtain a state interval, determine a third grey prediction value based on the state interval, and construct a grey Markov prediction model based on the third grey prediction value and the state interval; Performing data prediction based on the grey Markov prediction model to obtain a fourth grey prediction value, updating the grey Markov prediction model based on the fourth grey prediction value, and obtaining a transition probability distribution matrix; Based on the transition probability distribution matrix and the updated grey Markov prediction model, a low-voltage distribution network fault prediction model is determined.
2. A low voltage distribution network early warning method as claimed in claim 1, characterized in that: The typical parameters are processed to obtain preprocessing typical parameters, which specifically include: Determine whether there is data missing in the typical parameter, and if so, determine the data missing point, obtain the adjacent data nodes of the data missing point, and generate a data node set based on the data missing point and the adjacent data nodes; Obtaining a first number of the adjacent data nodes, determining a second number based on the first number, and selecting the second number of sample data groups from the typical parameters; Substituting the sample data groups into a preset first linear regression model respectively, solving the partial correlation coefficient in the first linear regression model to obtain an estimated value of the partial correlation coefficient, and updating the first linear regression model based on the estimated value of the partial correlation coefficient to obtain a second linear regression model; Acquire the perception data corresponding to each data node in the data node set, substitute all the perception data into the second linear regression model, and obtain the missing perception data estimation value corresponding to the data missing point; The typical parameters are supplemented based on the estimated values of the missing perception data to obtain preprocessed typical parameters.
3. A low voltage distribution network early warning method as claimed in claim 1, characterized in that: Determining whether the first data sequence and the second data sequence satisfy modeling verification specifically includes: Inputting the first data sequence into a preset level ratio calculation formula to obtain a level ratio calculation result, comparing the level ratio calculation result with a preset level ratio threshold, and if the level ratio calculation result is not greater than the level ratio threshold, determining that the first data sequence satisfies the level ratio check; otherwise, performing a translation transformation process on the first data sequence until the first data sequence after the translation transformation satisfies the level ratio check; The first data sequence and the second data sequence are input into a preset smoothness ratio calculation formula to obtain a smoothness ratio calculation result, and the smoothness ratio calculation result is compared with a preset smoothness ratio threshold. If the smoothness ratio calculation result is less than the smoothness ratio threshold, it is determined that the first data sequence and the second data sequence meet the modeling verification.
4. A low voltage distribution network early warning method as claimed in claim 1, characterized in that: Acquiring a residual sequence of the first data sequence, performing residual correction and restoration processing on the residual sequence, and generating a residual correction model, specifically includes: Acquire a residual sequence of the first data sequence, and perform residual correction on the residual sequence based on a preset residual correction formula to obtain a corrected residual sequence; Performing restoration processing on the corrected residual sequence based on a preset restoration formula to obtain a restored residual sequence; A residual correction model is determined based on the restored residual sequence and the first data sequence.
5. A low voltage distribution network early warning method as claimed in claim 1, characterized in that: The second grey prediction value is divided into states to obtain a state interval, which specifically includes: Based on the benchmark data of the fault warning indicator at each time point, a benchmark curve is generated, and based on each time point, an absolute error between the second grey prediction value and the true value is calculated; Based on the reference curve and the absolute error, the fault warning indicator is divided into state regions to obtain a first state region and a second state region; Based on the first state area and the second state area, a state interval is formed, wherein the state interval is as follows: ; ; ; In the formula, is the state interval, is the first state area, is the second state area, is the second grey prediction value, A and B are preset parameters, and i is the i-th time point.
6. A low voltage distribution network early warning method as claimed in claim 1, characterized in that: Collecting real-time data of the low-voltage distribution network and inputting the real-time data into the low-voltage distribution network fault prediction model so that the low-voltage distribution network fault prediction model outputs a fault warning index prediction value, specifically including: Collecting real-time data of the fault warning indicator in the low-voltage distribution network, determining the current state of the fault warning indicator based on the real-time data, and determining the state probability distribution at the next moment based on the current state and the transition probability distribution matrix; Determine the state of the fault warning indicator at the next moment according to the state probability distribution at the next moment and the state interval, and determine the next state interval of the fault warning indicator based on the state at the next moment; Based on the next state interval and the grey Markov prediction model, a fault warning indicator prediction value is determined; wherein the grey Markov prediction model is as follows: ; In the formula, is the kth fault warning indicator prediction value output by the grey Markov prediction model, is the kth second grey prediction value, is the first state area, It is the second state area, A and B are preset parameters.
7. A low voltage distribution network early warning device, characterized in that: include: Data processing module, low voltage distribution network fault prediction model building module and early warning module; The data processing module is used to collect typical parameters of the low-voltage distribution network, perform data processing on the typical parameters, and obtain pre-processed typical parameters; The low-voltage distribution network fault prediction model construction module is used to select fault warning indicators based on the preprocessing typical parameters, improve the grey Markov prediction model by combining residual correction and metabolism, and construct a low-voltage distribution network fault prediction model; The early warning module is used to collect real-time data of the low-voltage distribution network, input the real-time data into the low-voltage distribution network fault prediction model, so that the low-voltage distribution network fault prediction model outputs a fault early warning index prediction value, and performs early warning level judgment on the fault early warning index prediction value, and generates corresponding early warning level information based on the early warning level judgment result; Among them, the fault warning indicators are selected based on the typical parameters of the preprocessing, and the grey Markov prediction model is improved by combining residual correction and metabolism to construct a low-voltage distribution network fault prediction model, which specifically includes: Selecting a fault warning indicator from the preprocessing typical parameters, generating a first data sequence corresponding to the fault warning indicator, and performing accumulation processing on the first data sequence to obtain a second data sequence; Determine whether the first data sequence and the second data sequence meet the modeling verification, and if so, construct a grey prediction model based on the first data sequence and the second data sequence, calculate model parameters of the grey prediction model, and establish an approximate differential equation based on the model parameters; Based on the approximate differential equation, solving the original form of the grey prediction model to obtain a time response sequence of the grey prediction model, and based on the time response sequence, calculating a first grey prediction value of the grey prediction model; The first data sequence is updated based on the first grey prediction value to determine a metabolism grey prediction model, Acquire a residual sequence of the first data sequence, perform residual correction and restoration processing on the residual sequence, generate a residual correction model, and determine a second grey prediction value based on the residual correction model; Divide the second grey prediction value into states to obtain a state interval, determine a third grey prediction value based on the state interval, and construct a grey Markov prediction model based on the third grey prediction value and the state interval; Performing data prediction based on the grey Markov prediction model to obtain a fourth grey prediction value, updating the grey Markov prediction model based on the fourth grey prediction value, and obtaining a transition probability distribution matrix; Based on the transition probability distribution matrix and the updated grey Markov prediction model, a low-voltage distribution network fault prediction model is determined.
8. A terminal device, characterized in that: The method comprises a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, wherein when the processor executes the computer program, the low-voltage distribution network early warning method according to any one of claims 1 to 6 is implemented.
9. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored computer program, wherein when the computer program is executed, the device where the computer-readable storage medium is located is controlled to execute the low-voltage distribution network early warning method according to any one of claims 1 to 6.