Dry dock entrance structure with dock gate leakage test function and construction method

By setting up docking ports between the dry docking area and the cofferdam area, and filling water in the cofferdam area to conduct leak test experiments between docking doors and docking ports, the problem of leak testing in the existing technology is solved, and construction efficiency is improved Cost-effective, reducing construction errors and waste.

CN118895727AInactive Publication Date: 2024-11-05GUANGZHOU MUNICIPAL ENG DESIGN & RES INST CO LTD

Patent Information

Application Number
CN202411079086.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-07
Publication Date
2024-11-05
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing dry dock construction method cannot conduct leakage tests on the coordination relationship between the dock door and the dock port in advance, resulting in construction errors that lead to water leakage and difficulty in draining the dry dock, wasting time and cost.

Method used

Set up a dock port between the dry dock area and the cofferdam area, and fill water in the cofferdam area to conduct trial assembly and leakage detection of the dock door and dock port. Use the water pump to inject water to test the sealing relationship between the dock door and dock port until there is no After the leakage point, prefabricate and transport the immersed tube.

Benefits of technology

The problem of trial leakage in the cooperation relationship between the dock door and the dock port is effectively solved, reducing construction errors, and improving construction efficiency and cost-effectiveness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118895727A_ABST
    Figure CN118895727A_ABST
Patent Text Reader

Abstract

The invention relates to a dry dock entrance structure with a dock gate leakage test function and a construction method, and belongs to the technical field of large component prefabricated dry docks. According to the scheme, a cofferdam area is arranged, after a dock gate and a dock entrance are connected and matched with each other, water is injected into the cofferdam area through a water pump, and after the water surface height is flush with the top surface height of the dock entrance, the cofferdam area is closed; a leakage test experiment is carried out on the connection cooperation relation between the dock gate and the dock entrance, and the problem that a traditional construction mode cannot carry out the leakage test experiment on the cooperation relation between the dock gate and the dock entrance in advance is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of large-scale component prefabricated dry dock, and in particular relates to a dry dock port structure with a dock door leak testing function and a construction method. Background Art

[0002] During the construction of the cross-river tunnel, a dry dock needs to be excavated near the water, and immersed tubes are prefabricated in the dry dock. After the immersed tubes are completed, they are transported to the designated construction site for installation by water filling and floating. Due to the limited construction area on the shore, it is impossible to complete the prefabrication of all immersed tubes at one time, so the dry dock needs to be used repeatedly, which requires the cycle steps of opening the door to fill water, undocking the immersed tubes, closing the door to pump water, and constructing the immersed tubes.

[0003] The existing dry dock is constructed by excavating a foundation pit at the water's edge to form the main body of the dry dock. A space is reserved inside the dry dock to make a floating dock door. After the prefabrication of the first batch of immersed tubes is completed, the foundation pit is dug and water is injected on the water side to form a dock opening that allows the immersed tubes to enter and exit. After the first batch of immersed tubes are all out of the dock, the floating dock door floats up and moves to the dock opening for placement, the water in the dry dock is drained, and the prefabrication of the next batch of immersed tubes is carried out.

[0004] The problem with existing dry docks is that the floating dock door is used between the last batch of immersed tubes being undocking and the next batch of immersed tubes being constructed. At this time, the dry dock is filled with water, and the dock door and the dock opening must be sealed to achieve the purpose of pumping out the water. Once there is a construction error between the prefabricated dock door and the dock opening, the dock opening will leak, making it difficult to drain the inside of the dry dock. In addition, the remedial operation of the underwater leak point is extremely difficult, which seriously wastes time and costs. Summary of the invention

[0005] In order to solve the problem that the traditional construction method cannot perform a leak test on the matching relationship between the dock door and the dock opening in advance, the present invention provides a dry dock dock opening structure with a dock door leak test function and a construction method.

[0006] The purpose of the present invention can be achieved through the following technical solutions:

[0007] A dry dock construction method with a dock door leak testing function comprises the following steps:

[0008] S1: excavating a dry dock area for making prefabricated immersed tubes on the bank near the water, wherein the dry dock area is not connected to the river water;

[0009] S2: Setting up a cofferdam area in the water and draining the water in the cofferdam area to provide a construction environment;

[0010] S3: excavating a dock opening on the water side of the dry dock area so that the dry dock area and the cofferdam area are connected through the dock opening to form a dry dock body;

[0011] S4: prefabricate a dock door near the dock entrance in the cofferdam area;

[0012] S5: Before the dry dock is filled with water, the dock door and the dock opening are assembled for trial, and water is injected into the cofferdam area to detect the leakage point between the dock opening and the dock door.

[0013] As a preferred technical solution of the present invention, in S5, if no leaks are detected, the cofferdam area is dismantled, water is poured into the dry dock area, and the dock door is removed to transport the first batch of prefabricated immersed tube segments. After the first batch of immersed tube segments are floated out of the dock, the dock door is moved to the dock port to be assembled with it, the dry dock area is pumped out, and the second batch of immersed tube segments are prefabricated after the water is drained. After the second batch of immersed tube segments are prefabricated, water is poured into the dry dock area, and the dock door is removed to transport the second batch of prefabricated immersed tube segments. By analogy, the dock port can be repeatedly closed and opened to cooperate with the prefabrication and transportation of immersed tube segments out of the dock.

[0014] As a preferred technical solution of the present invention, in S5, if a leak is detected, the water in the cofferdam area is drained and the leak is repaired, and the operation of S5 is repeated to detect the leak again until there is no leak.

[0015] As a preferred technical solution of the present invention, in S2, the cofferdam area includes a plurality of steel pipe piles and two support assemblies, the plurality of steel pipe piles are placed vertically, and the steel pipe piles are watertightly connected to each other to form a rectangular steel pipe group with an open end, the open end of the rectangular steel pipe group is interconnected with the dock port, and the rectangular steel pipe group and the dry dock area are sealed and connected to each other, and the two support assemblies are respectively arranged at two diagonal positions of the rectangular steel pipe group away from its open end, for reinforcing the structure of the rectangular steel pipe group.

[0016] As a preferred technical solution of the present invention, the support assembly includes a plurality of connecting plates, which are horizontally arranged, and the two ends of the connecting plates are respectively connected to the adjacent two side walls at the diagonals corresponding to the rectangular steel pipe group, and the plurality of connecting plates are arranged at equal intervals from the direction close to the diagonal point to the direction away from the diagonal point.

[0017] A dry dock structure with a dock door leak test function is applicable to a dry dock construction method with a dock door leak test function, and is characterized in that it includes a dry dock area, a cofferdam area, a dock and a dock door, the dry dock area is arranged on a waterfront shore, the cofferdam area is arranged in offshore waters, the dock is located on the waterside of the dry dock area, and the cofferdam area is connected with the dry dock area through the dock, and the dock door and the dock are detachable and matched; the cofferdam area is used for storing water to test the leakage points of the dock door and the dock and can be removed.

[0018] As a preferred technical solution of the present invention, the dry dock area includes two piers, both of which are arranged on the water side of the shore, the piers are watertightly connected to the side wall of the shore, the setting direction of the piers is parallel to the setting direction of the shore, an interval space is formed between the two piers, the dock opening is connected to the interval space, the two ends of the rectangular steel pipe group are respectively watertightly connected to the two piers, and the open end of the rectangular steel pipe group is connected to the interval space.

[0019] As a preferred technical solution of the present invention, the dry dock area also includes a dock sill, which is arranged on the bottom surface of the water side, and the dock sill is located in the interval space. The setting direction of the dock sill is parallel to the setting direction of the dock piers, and the two ends of the dock sill are respectively watertightly connected to the two dock piers. When the two ends of the dock door are respectively locked in a watertight fitting relationship with the two dock piers, the side wall surface of the dock door is watertightly fitted with the side wall surface of the dock sill.

[0020] As a preferred technical solution of the present invention, it also includes a plurality of waterstops, which are respectively arranged on the dock sill and the dock pier, and the plurality of waterstops are located at positions where the dock sill and the dock pier are respectively arranged in contact with the dock door.

[0021] The beneficial effects of the present invention are:

[0022] This solution sets up a cofferdam area. After the dock gate and the dock opening are connected and matched with each other, a water pump is used to inject water into the cofferdam area. After the water level is flush with the top surface of the dock opening, a leak test is performed on the connection and matching relationship between the dock gate and the dock opening, thereby solving the problem that the traditional construction method cannot perform a leak test on the matching relationship between the dock gate and the dock opening in advance. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings.

[0024] Figure 1 It is a top view of a dry dock structure with a dock door leak testing function according to the present invention;

[0025] Figure 2 This is a cofferdam area diagram of a dry dock structure with a dock door leak testing function according to the present invention.

[0026] Description of main symbols

[0027] In the figure: 1. dry dock area; 101. dock pier; 102. dock sill; 103. water stop; 2. cofferdam area; 201. rectangular steel pipe group; 202. connecting plate; 3. dock mouth; 4. dock door. DETAILED DESCRIPTION

[0028] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation methods, structures, features and effects of the present invention are described in detail below in conjunction with the accompanying drawings and preferred embodiments.

[0029] See also Figure 1-2 This embodiment provides a dry dock construction method with a dock door leak testing function, comprising the following steps:

[0030] S1: A dry dock area 1 for making prefabricated immersed tubes is excavated on the bank near the water. The dry dock area 1 is not connected to the river water;

[0031] S2: Setting up a cofferdam area 2 in the water and draining the water in the cofferdam area 2 to provide a construction environment;

[0032] S3: a dock opening 3 is excavated on the water side of the dry dock area 1, so that the dry dock area 1 and the cofferdam area 2 are connected through the dock opening 3 to form the main body of the dry dock;

[0033] S4: prefabricate a dock door 4 near the dock entrance 3 in the cofferdam area 2;

[0034] S5: Before the dry dock is filled with water, the dock door 4 and the dock opening 3 are assembled for trial, and water is injected into the cofferdam area 2 to detect the leakage point between the dock opening 3 and the dock door 4.

[0035] This solution is provided with a cofferdam area 2. After the dock gate 4 and the dock opening 3 are connected and matched with each other, water is pumped into the cofferdam area 2 by using a water pump. After the water level is flush with the top surface height of the dock opening 3, a leak test is performed on the connection and matching relationship between the dock gate 4 and the dock opening 3, thereby solving the problem that the traditional construction method cannot perform a leak test on the matching relationship between the dock gate 4 and the dock opening 3 in advance.

[0036] Specifically, in S5, if no leaks are detected, the cofferdam area 2 is dismantled, water is poured into the dry dock area 1, and the dock door 4 is removed to transport the first batch of prefabricated immersed tube segments. After the first batch of immersed tube segments are floated out of the dock, the dock door 4 is moved to the dock port 3 to be assembled with it, the dry dock area 1 is pumped out, and the second batch of immersed tube segments are prefabricated after the water is drained. After the second batch of immersed tube segments are prefabricated, water is poured into the dry dock area 1, and the dock door 4 is removed to transport the second batch of prefabricated immersed tube segments. Similarly, the dock port 3 can be closed and opened repeatedly to cooperate with the prefabrication and transportation of immersed tube segments out of the dock.

[0037] Specifically, in S5, if a leak is detected, the water in the cofferdam area 2 is drained and then the leak is repaired, and the operation of S5 is repeated to detect the leak again until there is no leak.

[0038] It is worth noting that in S2 of the present scheme, the cofferdam area 2 includes a plurality of steel pipe piles and two supporting assemblies, the plurality of steel pipe piles are placed vertically, and the plurality of steel pipe piles are watertightly connected to each other to form a rectangular steel pipe group 201 with an open end, the open end of the rectangular steel pipe group 201 is interconnected with the dock opening 3, and the rectangular steel pipe group 201 is watertightly connected to the dry dock area 1, and the two supporting assemblies are respectively arranged at two diagonals of the rectangular steel pipe group 201 away from its open end, so as to reinforce the structure of the rectangular steel pipe group 201.

[0039] In addition, the specific structure of the support assembly of the present solution is that the support assembly includes a plurality of connecting plates 202, the connecting plates 202 are arranged horizontally, and the two ends of the connecting plates 202 are respectively connected to the adjacent two side walls at the diagonal positions corresponding to the rectangular steel pipe group 201, and the plurality of connecting plates 202 are arranged at equal intervals from the direction close to the diagonal position to the direction away from the diagonal position. It should be noted that the end face of the rectangular steel pipe group 201 of the present solution away from its open end and the two side wall surfaces adjacent to the end face will be impacted by water pressure. In order to ensure that the rectangular steel pipe group 201 will not be deformed due to the force of water pressure, the present solution is provided with connecting plates 202, which are used to reinforce the structure of the end face of the rectangular steel pipe group 201 away from its open end and the two side wall surfaces adjacent to the end face, so as to ensure that the structure of the rectangular steel pipe group 201 will not be deformed.

[0040] A dry dock port 3 structure with a dock door 4 leak testing function comprises a dry dock area 1, a cofferdam area 2, a dock port 3 and a dock door 4, wherein the dry dock area 1 is arranged on a waterfront bank, the cofferdam area 2 is arranged in offshore waters, the dock port 3 is located on the waterfront side of the dry dock area 1, and the cofferdam area 2 is connected to the dry dock area 1 through the dock port 3, and the dock door 4 and the dock port 3 are detachable and matched; the cofferdam area 2 is used for storing water to test the leaking points of the dock door 4 and the dock port 3 and can be removed.

[0041] Specifically, the dry dock area 1 of the present solution includes two dock piers 101, both of which are arranged on the water side of the shore, the dock piers 101 are watertightly connected to the side wall of the shore, the setting direction of the dock piers 101 is parallel to the setting direction of the shore, a spacing space is formed between the two dock piers 101, the dock opening 3 is connected to the spacing space, the two ends of the rectangular steel pipe group 201 are respectively connected to the two dock piers 101 in a watertight manner, and the open end of the rectangular steel pipe group 201 is connected to the spacing space;

[0042] In addition, the dry dock area 1 of the present scheme also includes a dock sill 102, which is arranged on the bottom surface of the water side, and the dock sill 102 is located in the interval space. The setting direction of the dock sill 102 is parallel to the setting direction of the dock pier 101, and the two ends of the dock sill 102 are respectively connected to the two dock piers 101 in a watertight manner. When the two ends of the dock door 4 are respectively locked in a watertight fitting relationship with the two dock piers 101, the side wall surface of the dock door 4 is watertightly fitted with the side wall surface of the dock sill 102. Through such a setting, it is ensured that the dock door 4 is respectively sealed and fitted with the two dock piers 101 and the dock sill 102, and the dock door 4, the two dock piers 101, the dock sill 102 and the side wall of the water side jointly form a sealed space.

[0043] Furthermore, the present solution also includes a plurality of waterstops 103, which are respectively arranged on the dock sill 102 and the pier 101, and the plurality of waterstops 103 are located at positions where the dock sill 102 and the pier 101 are respectively fitted with the dock door 4, ensuring that the dock door 4 is watertightly connected to the two dock piers 101 and the dock sill 102.

[0044] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.

Claims

1. A dry dock construction method with dock door leak testing function, characterized in that: The following steps are involved: S1: excavating a dry dock area for making prefabricated immersed tubes on the bank near the water, wherein the dry dock area is not connected to the river water; S2: Setting up a cofferdam area in the water and draining the water in the cofferdam area to provide a construction environment; S3: excavating a dock opening on the water side of the dry dock area so that the dry dock area and the cofferdam area are connected through the dock opening to form a dry dock body; S4: prefabricate a dock door near the dock entrance in the cofferdam area; S5: Before the dry dock is filled with water, the dock door and the dock opening are assembled for trial, and water is injected into the cofferdam area to detect the leakage point between the dock opening and the dock door.

2. A dry dock construction method with dock door leak testing function according to claim 1, characterized in that: In S5, if no leaks are detected, the cofferdam area is dismantled, water is poured into the dry dock area, and the dock door is removed to transport the first batch of prefabricated immersed tube segments. After the first batch of immersed tube segments are floated out of the dock, the dock door is moved to the dock port to be assembled with it, the dry dock area is pumped out, and the second batch of immersed tube segments are prefabricated after the water is drained. After the second batch of immersed tube segments are prefabricated, water is poured into the dry dock area, and the dock door is removed to transport the second batch of prefabricated immersed tube segments. In this way, the dock port can be closed and opened repeatedly to cooperate with the prefabrication and transportation of immersed tube segments out of the dock.

3. A dry dock construction method with dock door leak testing function according to claim 1, characterized in that: In S5, if a leak is detected, the water in the cofferdam area is drained and the leak is repaired, and the operation of S5 is repeated to detect the leak again until there is no leak.

4. A dry dock construction method with dock door leak testing function according to claim 1, characterized in that: In S2, the cofferdam area includes a plurality of steel pipe piles and two supporting assemblies. The plurality of steel pipe piles are placed vertically, and the plurality of steel pipe piles are watertightly connected in pairs to form a rectangular steel pipe group with an open end. The open end of the rectangular steel pipe group is interconnected with the dock opening, and the rectangular steel pipe group is sealed and connected to the dry dock area. The two supporting assemblies are respectively arranged at two diagonal positions of the rectangular steel pipe group away from its open end, so as to reinforce the structure of the rectangular steel pipe group.

5. A dry dock construction method with dock door leak testing function according to claim 4, characterized in that: The support assembly includes a plurality of connecting plates, which are arranged horizontally. The two ends of the connecting plates are respectively connected to the adjacent two side walls at the diagonals corresponding to the rectangular steel pipe group. From the direction close to the diagonal to the direction away from the diagonal, the plurality of connecting plates are arranged at equal intervals.

6. A dry dock structure with a dock door leak test function, suitable for the dry dock construction method with a dock door leak test function according to claim 5, characterized in that: It includes a dry dock area, a cofferdam area, a dock entrance and a dock gate, wherein the dry dock area is arranged on a waterfront shore, the cofferdam area is arranged in offshore waters, the dock entrance is located on the waterfront side of the dry dock area, and the cofferdam area is connected with the dry dock area through the dock entrance, and the dock gate and the dock entrance are detachable and compatible; the cofferdam area is used for storing water to test the leakage points of the dock gate and the dock entrance and can be removed.

7. A dry dock structure with dock door leak testing function according to claim 6, characterized in that: The dry dock area includes two piers, both of which are arranged on the water side of the shore, the piers are watertightly connected to the side wall of the shore, the setting direction of the piers is parallel to the setting direction of the shore, an interval space is formed between the two piers, the dock opening is connected to the interval space, the two ends of the rectangular steel pipe group are respectively watertightly connected to the two piers, and the open end of the rectangular steel pipe group is connected to the interval space.

8. A dry dock structure with dock door leak testing function according to claim 7, characterized in that: The dry dock area also includes a dock sill, which is arranged on the bottom surface of the water side. The dock sill is located in the interval space. The setting direction of the dock sill is parallel to the setting direction of the dock piers. The two ends of the dock sill are respectively watertightly connected to the two dock piers. When the two ends of the dock door are respectively locked in a watertight fitting relationship with the two dock piers, the side wall surface of the dock door is watertightly fitted with the side wall surface of the dock sill.

9. A dry dock structure with dock door leak testing function according to claim 8, characterized in that: It also includes a plurality of waterstops, which are respectively arranged on the dock sill and the dock pier, and are located at positions where the dock sill and the dock pier are respectively arranged in contact with the dock door.

Citation Information

Patent Citations

  • Method for installing and testing leakage of dry dock steel dock gate

    CN112709196A

  • Immersed tunnel axis dry dock opening structure

    CN203429665U

  • Dock entrance water stop structure

    CN214832805U

Cited By

  • In-situ dismantling method for waste invalid floating dock gate

    CN119615866A