Separated assembly type elastic curing ballast bed track structure and construction and adjustment method thereof

By setting up assembly grooves and adjustment layers on the polyurethane cured track bed, a separate assembly structure is achieved, which solves the problem of maintenance difficulties in high altitude and seismic activity fault zone environments, reduces maintenance difficulty and improves applicability, and is suitable for harsh environments. Railway tracks.

CN118958060APending Publication Date: 2024-11-15RAILWAY CONSTR RES INST OF CHINA ACAD OF RAILWAY SCI CO LTD +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411326205.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing polyurethane cured track beds are difficult to maintain and repair under harsh environments such as high altitude, low oxygen, large temperature difference and seismic active fault zones, and the integrated structure is not suitable for railway tracks in seismic active fault zones.

Method used

Using a separate assembled elastic cured track bed structure, by setting assembly grooves on the cured track bed block and filling the adjustment layer, the gap between the sleeper and the cured track bed block is filled, realizing the maintenance and repair of the split structure, which is convenient for high altitude areas. Replace sleepers, curing tray bed blocks or adjustment layers separately to reduce maintenance difficulties and enhance structural adaptability through liquid curing materials and elastic curing layers.

Benefits of technology

It significantly reduces the difficulty of maintenance and repair, improves operating efficiency, is suitable for railway tracks at high altitudes and mountainous areas, maintains mechanical properties similar to traditional cured track beds, reduces maintenance frequency, and is suitable for harsh environmental conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958060A_ABST
    Figure CN118958060A_ABST
Patent Text Reader

Abstract

The invention discloses a separated assembly type elastic curing ballast bed track structure which comprises curing ballast bed blocks, adjusting layers and sleepers, the curing ballast bed blocks are provided with assembling grooves, the adjusting layers are located at the bottoms of the assembling grooves, and the sleepers are located on the adjusting layers; the gap between the bottom of the sleeper and the bottom of the assembling groove is filled with the adjusting layer. The invention provides a separated assembly type elastic solidified ballast bed track structure, aims to solve the problem that an integral polyurethane solidified ballast bed is difficult to maintain and repair when being used in a mountainous area or a high-altitude area with earthquake activity in the prior art, and realizes less maintenance and easy maintenance of the track structure. And the polyurethane curing ballast bed is more suitable for being used in an earthquake active fault zone.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of rail transportation, and in particular to a separated assembled elastic solidified ballast track structure. Background Art

[0002] For earthquake-prone areas, railway lines crossing seismic active fault zones pose a greater challenge to the adaptability of track structures. The Railway Track Design Code (TB10082-2017) stipulates: "Ballasted tracks should be used in areas with special geological conditions where deformation is difficult to control, such as active fault zones, areas with severe ground subsidence, seasonal frozen soil areas with large freezing depths and high groundwater levels, and thick soft soils." Therefore, existing railway lines crossing active fault zones mainly use ballasted tracks. However, ballasted tracks are difficult to maintain because the ballast bed is a granular structure and requires frequent maintenance; when used in low-altitude, easy-to-maintain roadbeds or bridge sections, they can also be easily maintained, but for some mountain railways with complex environmental and traffic conditions, especially in high-altitude areas with low oxygen, large temperature differences, and many ultra-long tunnels, the maintenance conditions of the track structure are extremely poor. If the traditional ballasted track structure is still used, there will be great difficulty in maintenance, and even the problem of being unable to maintain the required maintenance frequency.

[0003] In recent years, a polyurethane-cured ballast bed has been proposed in the prior art, which combines the characteristics of ballasted track structure, such as granular material and strong deformation adaptability, with the characteristics of ballastless track structure, such as good integrity.

[0004] However, the existing polyurethane-cured ballasts are all of an integrated structure, and their preparation process is to place gravel particles and sleepers in a mold, and then inject polyurethane raw materials to solidify the sleepers and ballast blocks into a whole. When this integral structure is used in mountainous areas such as high altitudes, low oxygen, large temperature differences, and ultra-long tunnels, it is restricted by harsh operating conditions and difficulties in transporting large maintenance equipment. It still has the defect of being difficult to maintain and repair, and in actual operation is not suitable for use on railway tracks in seismically active fault zones. Summary of the invention

[0005] The present invention provides a separated assembled elastic cured ballast track structure to solve the problem in the prior art that the integral polyurethane cured ballast is difficult to maintain and repair when used in mountainous areas or high-altitude areas with seismic activity, thereby achieving low maintenance and easy repair of the track structure, making the polyurethane cured ballast more suitable for use in seismic active fault zones.

[0006] The present invention is achieved through the following technical solutions:

[0007] A separated assembled elastic solidified ballast track structure comprises a solidified ballast block, an adjustment layer and a sleeper, wherein an assembly groove is provided on the solidified ballast block, the adjustment layer is located at the bottom of the assembly groove, and the sleeper is located on the adjustment layer; the adjustment layer fills the gap between the bottom of the sleeper and the bottom of the assembly groove.

[0008] In view of the maintenance and repair difficulties of the polyurethane cured ballast in the prior art when it is used in mountainous areas or high-altitude areas with seismic activity, the present invention first proposes a separate assembled elastic cured ballast track structure. Those skilled in the art should understand that the cured ballast block in this structure is a polyurethane cured ballast block. The present application provides an assembly groove for installing sleepers on the cured ballast block, and provides an adjustment layer at the bottom of the assembly groove so that the sleepers are seated on the adjustment layer. The gap between the bottom of the sleeper and the bottom of the assembly groove is filled by the adjustment layer, so that the track structure of the present application has similar mechanical properties to the traditional one-piece cured ballast.

[0009] The present application creatively sets the elastic cured ballast track structure as an assembled split structure, abandoning the technical idea that the existing polyurethane cured ballast needs to be connected to the sleepers as an integral structure. The sleepers, cured ballast blocks or adjustment layers can be repaired or replaced separately, which significantly reduces the difficulty of maintenance and repair. The present application ensures the integrity of the mechanical properties between the sleepers and the cured ballast blocks through the adjustment layer. When the track structure needs to be adjusted vertically, it can be achieved by simply replacing different adjustment layers. The operation efficiency is extremely high and does not rely on large equipment. It is more suitable for use in railway tracks in high-altitude areas, mountainous areas, etc. In addition, since the present application maintains good mechanical properties similar to those of the existing polyurethane cured ballast, the maintenance frequency is relatively low, and it is more suitable for use in harsh environmental conditions such as high altitude, low oxygen, large temperature difference, mountainous areas or ultra-long tunnels where maintenance conditions are extremely poor.

[0010] The present solution does not impose any specific restrictions on the material and type of the adjustment layer, and it only needs to be able to fill the gap between the bottom of the sleeper and the bottom of the assembly groove.

[0011] Furthermore, the adjustment layer includes a perfusion bag filled with liquid solidifying material. The adjustment layer in this solution is obtained by filling the liquid solidifying material into the perfusion bag and waiting for it to solidify; this kind of adjustment layer is easy to construct and very convenient for later maintenance and replacement, which is conducive to the rapid adjustment of the vertical height of the track in the later stage.

[0012] The liquid curing material can be made of any existing curing material, curing agent, etc., and is not specifically limited here.

[0013] Furthermore, the adjustment layer includes a pad, and an elastic solidified layer partially or completely covering the outer surface of the pad. The adjustment layer in this solution is obtained by first placing the pad, and then injecting liquid elastic material to solidify it; this adjustment layer can also be easily and quickly maintained and replaced, and the elastic solidified layer is elastic, which is more conducive to enhancing the deformation adaptability of the track structure and reducing the maintenance frequency.

[0014] The elastic cured layer can be made of any existing material that has elasticity after curing, and is not specifically limited here.

[0015] Furthermore, a transverse limiting mechanism is provided between the sleeper and the cured roadbed block. The transverse limiting mechanism is used to improve the transverse stability between the sleeper and the cured roadbed block to prevent them from lateral displacement. The transverse limiting mechanism can be any limiting device, limiting structure or detachable connection structure in the prior art, such as a temporary fixing connection method such as a slot, a buckle, a mortise and tenon joint or even a bolt.

[0016] A construction method for a separated assembled elastic solidified ballast track structure, comprising:

[0017] Foundation leveling;

[0018] Lay the solidified ballast blocks one by one on the crushed stone cushion layer at set intervals;

[0019] The sleepers and the assembled rail panel frame are hoisted to the sleeper distribution platform respectively, and the rails and sleepers are connected by fasteners to obtain an assembly of the rail panel frame and the sleepers;

[0020] The assembly is hoisted and laid so that the sleeper enters the assembly groove; at this time, there is a gap between the bottom of the sleeper and the bottom of the assembly groove;

[0021] Adjust the track frame;

[0022] The adjustment layer is constructed between the bottom of the sleeper and the bottom of the assembly groove, so that the adjustment layer fills the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0023] Fill the gaps between the solidified ballast blocks with graded crushed stone and vibrate to compact them;

[0024] Adjust rail accuracy.

[0025] It can be seen that the construction method of the present application is to first lay the cured ballast blocks, and then after the track frame is in place and positioned and adjusted, construct the adjustment layer between the sleeper and the bottom of the assembly groove, so that the adjustment layer can fill the gap between the sleeper and the cured ballast block. During the entire construction process, the cured ballast blocks, the adjustment layer, and the sleepers are constructed separately, which is completely different from the construction method of the polyurethane cured ballast blocks in the prior art. This construction method is specially designed for the separated assembled elastic cured ballast track structure of the present application, filling the gap in the prior art. Among them, the operations on the separate sleeper platform, the hoisting of the assembly, the adjustment of the track frame, etc. can all be completed using existing technologies.

[0026] Furthermore, the method for constructing the adjustment layer between the bottom of the sleeper and the bottom of the assembly groove includes:

[0027] Insert the pouring bag into the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0028] Pour liquid solidifying material into the pouring bag, so that the pouring bag gradually expands until the pouring bag fills the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0029] and allowing the liquid solidifying material to solidify.

[0030] When the adjustment layer adopts a perfusion bag filled with solidifying material, the method of this scheme can be used to construct it.

[0031] Furthermore, the method for constructing the adjustment layer between the bottom of the sleeper and the bottom of the assembly groove includes:

[0032] Insert the backing plate into the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0033] pouring liquid elastic material onto the pad until the liquid elastic material fills the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0034] The liquid elastic material is solidified to obtain an elastic solidified layer.

[0035] When the adjustment layer adopts a combined structure of a pad and an elastic solidification layer, the method of this solution can be used to construct it.

[0036] A method for adjusting a separated assembled elastic solidified ballast track structure, comprising a lateral adjustment step and a vertical adjustment step;

[0037] The lateral adjustment step includes: moving the solidified ballast block according to the required lateral adjustment distance;

[0038] The vertical adjustment step includes: extracting the original adjustment layer, adjusting the height of the sleeper according to the required vertical adjustment distance, and setting a new adjustment layer between the bottom of the sleeper and the bottom of the assembly groove.

[0039] During the maintenance of the track structure, when the track structure needs to be adjusted horizontally, the lateral adjustment step is implemented; when the track structure needs to be adjusted vertically, the vertical adjustment step is implemented.

[0040] It can be seen that the vertical adjustment step of the present application only requires extracting the adjustment layer between the sleeper and the solidified ballast block, and then replacing the adjustment layer of different thicknesses or replacing a new adjustment layer according to maintenance needs. The entire maintenance process is very simple and convenient, and can achieve accurate and rapid maintenance and adjustment of a single sleeper. It is particularly suitable for use under harsh working conditions such as high altitude, low oxygen, large temperature difference or ultra-long tunnels with extremely poor maintenance conditions.

[0041] Further, the method of setting a new adjustment layer between the bottom of the sleeper and the bottom of the assembly groove includes:

[0042] Insert a new pouring bag into the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0043] Pour liquid curing material into the new pouring bag, so that the pouring bag gradually expands until the pouring bag fills the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0044] and allowing the liquid solidifying material to solidify.

[0045] When the adjustment layer adopts a perfusion bag filled with solidified material, the method of this solution can be used to update the adjustment layer.

[0046] Further, the method of setting a new adjustment layer between the bottom of the sleeper and the bottom of the assembly groove includes:

[0047] Insert a pad of specified thickness into the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0048] pouring liquid elastic material onto the pad until the liquid elastic material fills the gap between the bottom of the sleeper and the bottom of the assembly groove;

[0049] The liquid elastic material is solidified to obtain an elastic solidified layer.

[0050] When the adjustment layer adopts a combined structure of a backing plate and an elastic solidification layer, the method of this solution can be used to update the adjustment layer.

[0051] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0052] 1. The present invention proposes a separated assembled elastic cured ballast track structure, which creatively sets the elastic cured ballast track structure as an assembled split structure, abandoning the technical idea that the existing polyurethane cured ballast needs to be connected with the sleeper as an integral structure. The sleeper, cured ballast block or adjustment layer can be repaired or replaced separately, which significantly reduces the difficulty of maintenance and repair.

[0053] 2. The present invention ensures the integrity of the mechanical properties between the sleeper and the solidified ballast block through the adjustment layer. When the track structure needs to be adjusted vertically, it can be achieved by simply replacing different adjustment layers. The operation efficiency is extremely high and does not rely on large equipment. It is more suitable for use in railway tracks in high-altitude areas, mountainous areas, etc.

[0054] 3. The separated assembled elastic cured ballast track structure of the present invention maintains good mechanical properties similar to those of the existing polyurethane cured ballast, so the maintenance frequency is relatively low, and it is more suitable for use in harsh environmental conditions such as high altitude, low oxygen, large temperature difference, mountainous area or ultra-long tunnel where the maintenance conditions are extremely poor.

[0055] 4. The present invention proposes a special construction method for a separated assembled elastic solidified ballast track structure, which is significantly different from the prior art and can achieve fast and efficient laying operations for the separated assembled elastic solidified ballast track.

[0056] 5. The present invention proposes a special adjustment method for the separated assembled elastic solidified ballast track structure, which makes the maintenance process simple and convenient, and can realize accurate and rapid maintenance and adjustment of a single sleeper. It is particularly suitable for track maintenance and repair under harsh working conditions such as high altitude, low oxygen, large temperature difference or ultra-long tunnels with extremely poor maintenance conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0057] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention. In the drawings:

[0058] Figure 1 It is a cross-sectional view of a rail section of a specific embodiment of the present invention;

[0059] Figure 2 It is a cross-sectional view through the rail axis of a specific embodiment of the present invention;

[0060] Figure 3 It is a schematic diagram of a specific embodiment of the present invention;

[0061] Figure 4 It is an exploded schematic diagram of the track structure in a specific embodiment of the present invention.

[0062] Marks and corresponding parts names in the attached drawings:

[0063] 1- solidified roadbed block, 2- adjustment layer, 3- sleeper, 4- fastener, 5- rail, 6- leveling layer, 7- crushed stone ballast. DETAILED DESCRIPTION

[0064] In order to make the objects, technical solutions and advantages of the present invention clearer, the present invention is further described in detail below in conjunction with the examples and the accompanying drawings. The schematic embodiments of the present invention and the description thereof are only used to explain the present invention and are not intended to limit the present invention. In the description of the present application, it should be understood that the orientation or positional relationship indicated by terms such as "front", "rear", "left", "right", "up", "down", "vertical", "horizontal", "high", "low", "inside", "outside", etc. is based on the orientation or positional relationship shown in the accompanying drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the scope of protection of the present application.

[0065] Embodiment 1:

[0066] like Figures 1 to 4 A separated assembled elastic cured ballast track structure shown includes a cured ballast block 1, an adjustment layer 2 and a sleeper 3. An assembly groove is provided on the cured ballast block 1, the adjustment layer 2 is located in the assembly groove, and the sleeper 3 is located on the adjustment layer 2; the adjustment layer 2 fills the gap between the bottom of the sleeper 3 and the bottom of the assembly groove.

[0067] The top of the sleeper 3 is higher than the top surface of the solidified ballast block 1 .

[0068] In this embodiment, for a single sleeper 3, there are two matching cured ballast blocks 1, and the two ends of the sleeper 3 are respectively located in the assembly grooves of the two cured ballast blocks 1.

[0069] Preferably, a special-shaped structure is provided at the bottom of the sleeper 3, and the groove shape of the assembly groove matches the shape of the bottom of the sleeper 3, so that after the sleeper 3 enters the assembly groove, it cannot move relative to the cured ballast block 1 in any lateral direction.

[0070] When this embodiment is used, the railway track maintenance and adjustment is performed by the following method:

[0071] Lateral adjustment: moving the solidified roadbed block 1 according to the required lateral adjustment distance;

[0072] Vertical adjustment: pull out the original adjustment layer 2, adjust the height of the sleeper 3 (up or down) according to the required vertical adjustment distance, and set a new adjustment layer 2 between the bottom of the sleeper 3 and the bottom of the assembly groove.

[0073] Embodiment 2:

[0074] A separate assembled elastic solidified ballast track structure, based on the first embodiment, the adjustment layer 2 of the present embodiment is a pouring bag filled with liquid solidified material. The liquid solidified material may be mortar, concrete, etc., preferably fine stone concrete, which has the advantage of not being easy to clog the pouring holes on the pouring bag in the present embodiment.

[0075] In the vertical adjustment process of this embodiment, a new adjustment layer is provided between the bottom of the sleeper 3 and the bottom of the assembly groove by the following method:

[0076] Pull out the original adjustment layer;

[0077] Insert a new filling bag into the gap between the bottom of the sleeper 3 and the bottom of the assembly groove;

[0078] Pour the liquid solidifying material into the new pouring bag, so that the pouring bag gradually expands until the pouring bag fills the gap between the bottom of the sleeper 3 and the bottom of the assembly groove;

[0079] Wait until the liquid solidified material reaches the set strength.

[0080] Embodiment 3:

[0081] A separate assembled elastic solidified ballast track structure. Based on Example 1, the adjustment layer 2 of this embodiment is a pad liquid boot structure, which includes a pad and an elastic solidified layer partially or completely covering the outer surface of the pad, and the elastic solidified layer is solidified from a liquid elastic material.

[0082] Preferably, the pad is made of elastic material, such as rubber, silicone and the like. For example, a rubber pad or a polyurethane pad can further enhance the overall deformation adaptability of the sub-rail structure.

[0083] In the vertical adjustment process of this embodiment, a new adjustment layer is provided between the bottom of the sleeper 3 and the bottom of the assembly groove by the following method:

[0084] Pull out the original adjustment layer;

[0085] Insert a pad of a thickness corresponding to the adjusted height into the gap between the bottom of the sleeper 3 and the bottom of the assembly groove;

[0086] Pouring liquid elastic material onto the pad until the liquid elastic material fills the gap between the bottom of the sleeper 3 and the bottom of the assembly groove;

[0087] The liquid elastic material is solidified to obtain an elastic solidified layer.

[0088] The liquid elastic material in this embodiment can be realized by using existing materials, and it only needs to have elasticity after curing, such as room temperature curing water-based polyurethane.

[0089] Embodiment 4:

[0090] A track construction method, used for constructing a separated assembled elastic solidified ballast track structure in any of the above embodiments, comprises the following steps:

[0091] S1. Foundation leveling: including steps such as assembling formwork, pouring concrete, finishing concrete, and curing concrete.

[0092] S2, laying the solidified ballast blocks 1 one by one on the gravel cushion layer at a set interval; specifically including:

[0093] Prefabricated solidified ballast blocks 1 are brought into the site for stacking. The stacking height shall not exceed three layers, and flexible cushion layers such as wooden pads are set between the layers. Small machines are used to move the solidified ballast blocks 1 from the storage site to the railway line, and the solidified ballast blocks 1 are spread on the gravel cushion layer at a spacing of approximately 0.6m.

[0094] S3, hoisting the sleeper 3 and the assembled rail frame to the sleeper platform respectively, connecting the rail 5 to the sleeper 3 through the fastener 4, and obtaining an assembly of the rail frame and the sleeper; specifically comprising:

[0095] Set up the gantry crane, install the special sleeper lifting equipment, lift the sleepers, and hoist the sleepers to the sleeper distribution platform; hoist the assembled rail frame to the sleeper distribution platform, and connect the rails to the sleepers with fasteners.

[0096] S4, hoisting and laying the assembly so that the sleeper 3 enters the assembly groove; specifically comprising:

[0097] Use the rail hoist to hoist the rail frame and sleeper assembly to the construction line, position it according to the center line and elevation, use clamps to connect adjacent rails, install at least 4 sets of bolts at each joint, tighten them initially, and leave 6 to 10 mm between the rails;

[0098] The track adjuster is installed on site, one end of which is connected to the steel bar anchored to the ground, and the other end is supported on the stud leg;

[0099] Place the sleeper in the assembly groove in a suspended manner so that there is a gap between the sleeper and the bottom of the assembly groove.

[0100] S5. Adjust the track frame, including rough adjustment and fine adjustment of the track frame;

[0101] Rough adjustment of the track frame: After the rail support frame is in place and the template is erected, the centerline and elevation of the track are roughly adjusted by means of a right-angle track ruler, a universal track ruler, a total station, etc., through the track adjustment struts and elevation adjustment screws; the track is required to be visually straight or round, and the elevation, track gauge, horizontal and directional deviations must meet the design requirements. The inner and outer rail fastener systems are aligned, the joint bolts are tightened and the track joints are kept connected. Among them, the adjustment and positioning procedure of the track is: first adjust the reference rail, then adjust the track gauge, first adjust the level, then adjust the elevation, and adjust repeatedly until it meets the standard.

[0102] Track frame fine-tuning: The total station observes 4 pairs of continuous CPⅢ points, automatically adjusts and calculates to determine the station location. If the deviation is greater than 1mm, the station should be reset. After changing the station location, at least 4 control points used in the back must be cross-observed. If the deviation is greater than 2mm, the station should be reset. To speed up the progress, each working face should be equipped with 2 total stations with automatic search, tracking, calculation, and data transmission functions;

[0103] The track state measuring instrument is placed on the track and the prism is installed; the prism of the track state measuring instrument is measured using a total station. The track inspection trolley automatically measures the track gauge, superelevation, and horizontal position, receives the observation data, and calculates the track plane position, level, superelevation, track gauge and other data through the supporting software, and quickly feeds back the error value to the computer display screen of the track state measuring instrument to guide the track adjustment.

[0104] During the fine-tuning operation of the track frame, due to the rigid linkage of the rails when the rail support frame is adjusted, the track adjustment work often needs to be repeated many times and adjusted repeatedly to meet the requirements.

[0105] S6. construct an adjustment layer 2 between the bottom of the sleeper 3 and the bottom of the assembly groove, so that the adjustment layer 2 fills the gap between the bottom of the sleeper 3 and the bottom of the assembly groove.

[0106] When the adjustment layer 2 is a pouring bag filled with liquid curing material, the method for constructing the adjustment layer 2 is: insert the pouring bag into the gap between the bottom of the sleeper 3 and the bottom of the assembly groove; pour the liquid curing material into the pouring bag to make the pouring bag gradually expand until the pouring bag fills the gap between the bottom of the sleeper 3 and the bottom of the assembly groove; and wait for the liquid curing material to solidify.

[0107] When the adjustment layer 2 is a pad liquid boot structure, the method for constructing the adjustment layer 2 is: insert the pad into the gap between the bottom of the sleeper 3 and the bottom of the assembly groove; pour the liquid elastic material onto the pad until the liquid elastic material fills the gap between the bottom of the sleeper 3 and the bottom of the assembly groove; and solidify the liquid elastic material to obtain an elastic solidified layer. Preferably, before pouring the liquid elastic material, a corresponding template can be set to reduce the waste of raw materials.

[0108] S7. Fill the gaps between the solidified ballast blocks 1 with graded crushed stones, and use small rolling and vibrating equipment to make the structure dense to ensure the longitudinal resistance of the ballast.

[0109] S8. Adjust the rail 5 accuracy to ensure the smoothness of the line.

[0110] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

[0111] It should be noted that, in this article, terms such as "include", "comprise" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In addition, the term "connected" used in this article can be directly connected or indirectly connected via other components without special explanation.

Claims

1. A separate assembled elastic solidified ballast track structure, characterized in that: The invention comprises a solidified ballast block (1), an adjustment layer (2) and a sleeper (3); the solidified ballast block (1) is provided with an assembly groove, the adjustment layer (2) is located at the bottom of the assembly groove, and the sleeper (3) is located on the adjustment layer (2); the adjustment layer (2) fills the gap between the bottom of the sleeper (3) and the bottom of the assembly groove.

2. The separated assembled elastic solidified ballast track structure according to claim 1, characterized in that: The adjustment layer (2) comprises a perfusion bag filled with liquid solidifying material.

3. The separated assembled elastic solidified ballast track structure according to claim 1, characterized in that: The adjustment layer (2) comprises a backing plate and an elastic solidified layer partially or completely covering the outer surface of the backing plate.

4. The separated assembled elastic solidified ballast track structure according to claim 1, characterized in that: A transverse limiting mechanism is provided between the rail sleeper (3) and the cured ballast block (1).

5. A construction method for a separated assembled elastically cured ballast track structure according to any one of claims 1 to 4, characterized in that: include: Foundation leveling; Laying the solidified ballast blocks (1) one by one on the crushed stone cushion layer at a set interval; The sleepers (3) and the assembled rail frame are hoisted to the sleeper distribution platform respectively, and the rails (5) are connected to the sleepers (3) by fasteners (4) to obtain an assembly of the rail frame and the sleepers; Lifting and laying the assembly so that the sleeper (3) enters the assembly groove; Adjust the track frame; The adjustment layer (2) is constructed between the bottom of the sleeper (3) and the bottom of the assembly groove, so that the adjustment layer (2) fills the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; Filling the gaps between the solidified ballast blocks (1) with graded crushed stone and vibrating and compacting them; Adjust the rail (5) accuracy.

6. The construction method of a separated assembled elastic solidified ballast track structure according to claim 5, characterized in that: The method for constructing the adjustment layer (2) between the bottom of the sleeper (3) and the bottom of the assembly groove comprises: Inserting a pouring bag into the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; Pouring liquid solidifying material into the pouring bag, causing the pouring bag to gradually expand until the pouring bag fills the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; and allowing the liquid solidifying material to solidify.

7. The construction method of a separated assembled elastic solidified ballast track structure according to claim 5, characterized in that: The method for constructing the adjustment layer (2) between the bottom of the sleeper (3) and the bottom of the assembly groove comprises: Inserting a pad into the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; pouring liquid elastic material onto the pad until the liquid elastic material fills the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; The liquid elastic material is solidified to obtain an elastic solidified layer.

8. A method for adjusting a separated assembled elastically cured ballast track structure according to any one of claims 1 to 4, characterized in that: It includes a lateral adjustment step and a vertical adjustment step; The lateral adjustment step comprises: moving the solidified ballast block (1) according to the required lateral adjustment distance; The vertical adjustment step comprises: extracting the original adjustment layer (2), adjusting the height of the sleeper (3) according to the required vertical adjustment distance, and setting a new adjustment layer (2) between the bottom of the sleeper (3) and the bottom of the assembly groove.

9. The method for adjusting a separated assembled elastic solidified ballast track structure according to claim 8, characterized in that: The method for arranging a new adjustment layer (2) between the bottom of the sleeper (3) and the bottom of the assembly groove comprises: Insert a new filling bag into the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; Pour the liquid solidifying material into the new pouring bag, so that the pouring bag gradually expands until the pouring bag fills the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; and allowing the liquid solidifying material to solidify.

10. The method for adjusting a separated assembled elastic solidified ballast track structure according to claim 8, characterized in that: The method for arranging a new adjustment layer (2) between the bottom of the sleeper (3) and the bottom of the assembly groove comprises: Inserting a pad of a specified thickness into the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; pouring liquid elastic material onto the pad until the liquid elastic material fills the gap between the bottom of the sleeper (3) and the bottom of the assembly groove; The liquid elastic material is solidified to obtain an elastic solidified layer.