Electromechanical equipment allocation method and system based on intelligent decision

Through the intelligent decision-making system combining inventory and progress data, it automatically matches the allocation plan, and solves the problem of low allocation efficiency of electromechanical equipment in the existing technology, and achieves more efficient equipment allocation and progress control.

CN118966607APending Publication Date: 2024-11-15CHINA THREE GORGES CORPORATION
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202410928470.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing electromechanical equipment allocation methods are inefficient and mainly rely on manual inventory query, making it difficult to effectively control the overall progress of the project, and there is a lack of optimization solutions in different allocation scenarios.

Method used

Using an electronic and mechanical equipment allocation method based on intelligent decision-making, the allocation plan is generated through an expert knowledge system, combined with inventory quantity and project progress data, it automatically matches the allocation scenario and priority, and provides allocation plan, including normal allocation, misappropriation allocation and ununboxing. Allocation methods.

Benefits of technology

The efficiency of electromechanical equipment allocation management is improved, ensuring the smooth implementation of the project, and through automated decision-making and optimization of allocation plans, the efficiency and progress control of equipment allocation are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118966607A_ABST
    Figure CN118966607A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of electromechanical equipment management, in particular to an electromechanical equipment allocation method and system based on intelligent decision making. According to the method, the electromechanical equipment allocation knowledge base is established, and the allocation schemes are matched based on different allocation scenes and used for assisting decision making; and constructing an allocation priority model based on the stock and the project progress priority, and giving an allocation scheme according to an allocation application demand. By establishing the electromechanical equipment allocation knowledge base, the allocation scheme is automatically matched based on the allocation priority model according to different allocation scenes and allocation requirements, the allocation efficiency of the electromechanical equipment is improved, and smooth implementation of a project is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of electromechanical equipment management, and in particular to an electromechanical equipment allocation method and system based on intelligent decision-making. Background Art

[0002] The management of large-scale hydropower projects often involves many different types of complete sets of electromechanical equipment. After the equipment is inspected and accepted upon arrival, it is necessary to store the equipment in the corresponding warehouse according to the equipment type. The general inventory types can be divided into: Class A insulation warehouse, Class B closed warehouse, Class C open warehouse, Class D / E open-air warehouse, Class H dangerous goods warehouse, etc. All electromechanical equipment components correspond to complete sets of electromechanical equipment, such as generator 1 of unit 1, generator 2 of unit 2, and generator 3 of unit 3. Generally, when equipment is transferred, the electromechanical equipment components corresponding to the equipment are transferred according to the installation progress of a specific complete set of equipment. However, in the actual acceptance and transfer management, there may be a situation where the components of a certain unit fail to arrive in time. At this time, according to the project installation plan, the same model components of other units can be used for transfer in priority to ensure the normal progress of the project installation. In addition, in the case of normal transfer, there are also many situations such as full box transfer, box transfer, and unopened box transfer. Different transfer methods are adopted for different transfer scenarios.

[0003] The existing equipment allocation method mainly relies on allocation demands initiated by various construction sites, and professionals query the current inventory status and allocate inventory based on the inventory volume as the main measurement factor.

[0004] This method of manually querying inventory is inefficient and only uses inventory as the main measurement factor, which easily ignores the control of the overall progress of the project. Therefore, how to determine the allocation plan according to different allocation scenarios and allocation priorities to improve the efficiency of equipment allocation management is a problem that needs to be solved in current equipment allocation management. Summary of the invention

[0005] In view of the above problems, the present invention provides a method and system for allocating electromechanical equipment based on intelligent decision-making.

[0006] In a first aspect, a method for allocating electromechanical equipment based on intelligent decision-making, the method comprising:

[0007] Generate a transfer application form based on the transfer application initiated by the demander;

[0008] According to the transfer application form, query the relevant data of the unit equipment inventory quantity and the unit project installation progress, send the relevant data to the expert knowledge system, and obtain the transfer plan;

[0009] Carry out the allocation of electromechanical equipment according to the allocation plan.

[0010] Furthermore, the expert knowledge base system includes a rule generation module, a rule management module and an intelligent decision-making module;

[0011] A rule generation module is used to generate expert knowledge base rules, including transfer scenario matching rules and transfer priority matching rules;

[0012] The rule management module is used to manage the rule base, including querying, updating, adding, and deleting the rules of the expert knowledge base;

[0013] The intelligent decision-making module is used to determine the allocation scenario and allocation priority and give allocation plan suggestions based on the rules of the expert knowledge base, the acquired allocation demand information, the corresponding inventory quantity and the project progress data.

[0014] Furthermore, the expert knowledge base system is preset with expert knowledge base rules and allocation priority model;

[0015] The allocation priority model is used to formulate allocation plans based on different allocation scenarios.

[0016] Furthermore, the relevant data is sent to the expert knowledge system to obtain the allocation plan for decision-making in the allocation review process, including:

[0017] Query the inventory status according to the transfer application form requirements, and automatically select the transfer scenario and determine the transfer method based on the "transfer scenario priority rule" of the expert knowledge base system: normal transfer, diversion transfer, and unopened full-box transfer; normal transfer, diversion transfer, and unopened full-box transfer include full-box transfer, unboxed transfer, and full-box transfer + unboxed transfer;

[0018] In different transfer scenarios, the transfer priority model is automatically matched according to the queried inventory quantity and project schedule, based on the "transfer execution priority rules" of the expert knowledge base system, to come up with an transfer plan.

[0019] Furthermore, the allocation scenario priority rules include:

[0020] When receiving a transfer request form, extract the transfer request form information;

[0021] When the inventory status of the required electromechanical equipment is 1, query the inventory of the supporting units;

[0022] When the inventory status of the supporting unit is 1, select the supporting unit inventory transfer;

[0023] When the demand for goods = n*box inventory, the whole box is transferred;

[0024] Wherein, n is a positive integer;

[0025] When the demand for goods is less than the inventory of a single box, the box will be taken out for transfer;

[0026] When the demand for goods is greater than the inventory of a single box, full box transfer + box-out transfer are used;

[0027] When the inventory status of the matching unit is 0, query the inventory of the same type of equipment in other units;

[0028] When the inventory status of the same type of equipment in other units is 1, it can be appropriated and transferred;

[0029] When the demand for goods = n*box inventory, the whole box is transferred;

[0030] When the demand for goods is less than the inventory of a single box, the box will be taken out for transfer;

[0031] When the demand for goods is greater than the inventory of a single box, full box transfer + box-out transfer are used;

[0032] When the inventory status of the same type of equipment in other units is 0, query the equipment arrival information;

[0033] When the equipment arrival status is 1 and the demand for goods = n*box inventory, the whole box is transferred without unpacking;

[0034] When the equipment arrival status is 1 and the cargo demand is less than the single box inventory, the equipment will be unpacked and transferred after the initial inspection;

[0035] When the equipment arrival status is 1 and the demand for goods is greater than the inventory of a single box, unpacked full boxes are allocated + unpacked boxes are allocated after initial inspection;

[0036] When the equipment arrival status is 0, the goods are tracked and expedited, and the transfer is executed after the equipment arrives.

[0037] Furthermore, the transfer execution priority rules include:

[0038] When the requested amount of electromechanical equipment transfer is less than or equal to the inventory of supporting units, normal transfer is adopted to transfer the inventory of supporting units;

[0039] When the amount of electromechanical equipment transfer application required is greater than the inventory of supporting units, the transfer is carried out by using the inventory of supporting units plus the inventory of the same type of equipment of other units;

[0040] When the inventory status of the same type of equipment in other units is 1, query the inventory of other units;

[0041] When there is a unit inventory that meets the allocation demand, an allocation plan is obtained based on the allocation priority model 1;

[0042] When the inventory of the units does not meet the allocation demand, query the progress of other unit projects and derive an allocation plan based on the allocation priority model 2.

[0043] Furthermore, the allocation priority model 1 includes:

[0044] When there is inventory Y in units A, B, C, etc. i To meet the transfer demand X, transfer based on the inventory of the same type of units:

[0045] Y i =max(Y A ,Y B ,Y C ,……);

[0046] According to Y i According to the size of the equipment, the inventory equipment corresponding to unit i will be allocated first, i = A, B, C...

[0047] Furthermore, the second allocation priority model includes:

[0048] When the inventory of units A, B, C, etc. does not meet the transfer demand, the weighted coefficient P is determined based on the project progress of each unit. j , and perform weighted combination to obtain the allocation plan:

[0049] X={P A Y A +P B Y B +P C Y C +......},j=A,B,C......;

[0050] Y A , Y B , Y C is the inventory of units A, B, and C.

[0051] In a second aspect, an electromechanical equipment allocation system based on intelligent decision-making includes: an allocation application unit, an allocation decision unit and an allocation outbound unit;

[0052] The transfer application unit is used to generate a transfer application form based on the transfer application initiated by the demander;

[0053] The transfer decision unit is used to query the inventory quantity of unit equipment and the relevant data of the unit project installation progress according to the transfer application form, and send the relevant data to the expert knowledge system to obtain the transfer plan;

[0054] The transfer outbound unit is used to transfer electromechanical equipment according to the transfer plan.

[0055] In a third aspect, an electronic device includes a processor, a communication interface, a memory, and a communication bus, wherein the processor, the communication interface, and the memory communicate with each other via the communication bus;

[0056] a memory storing a computer program;

[0057] The processor is used to implement the above-mentioned method for allocating electromechanical equipment based on intelligent decision-making when executing the computer program stored in the memory.

[0058] In a fourth aspect, a computer-readable storage medium stores a computer program, which, when executed by a processor, implements the above-mentioned method for allocating electromechanical equipment based on intelligent decision-making.

[0059] The present disclosure includes at least the following beneficial effects:

[0060] The present invention establishes a knowledge base for the allocation of electromechanical equipment, matches allocation plans based on different allocation scenarios, and assists in decision-making; constructs an allocation priority model based on inventory volume and project progress priority, and provides an allocation plan based on allocation application requirements.

[0061] By establishing a knowledge base for electromechanical equipment allocation, we can automatically match allocation plans according to different allocation scenarios and allocation needs based on the allocation priority model, thereby improving the efficiency of electromechanical equipment allocation and ensuring the smooth implementation of the project.

[0062] Other features and advantages of the present disclosure will be described in the following description, and partly become apparent from the description, or be understood by implementing the present disclosure. The purpose and other advantages of the present disclosure can be realized and obtained by the structures indicated in the description and the drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0063] In order to more clearly illustrate the embodiments of the present disclosure or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0064] Figure 1 This is a flowchart of the allocation method according to the embodiment of the present disclosure;

[0065] Figure 2 This is a schematic diagram of the expert knowledge base system;

[0066] Figure 3 It is a schematic diagram of the rule principle;

[0067] Figure 4 This is a schematic diagram of the structure of the allocation system according to the embodiment of the present disclosure;

[0068] Figure 5 A schematic diagram of the electronic device structure. DETAILED DESCRIPTION

[0069] In order to make the purpose, technical solution and advantages of the embodiments of the present disclosure clearer, the technical solution in the embodiments of the present disclosure will be clearly and completely described below in conjunction with the drawings in the embodiments of the present disclosure. Obviously, the described embodiments are part of the embodiments of the present disclosure, not all of the embodiments. Based on the embodiments in the present disclosure, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present disclosure.

[0070] Complete set of electromechanical equipment: mostly refers to large-scale equipment used in engineering construction. Manufacturers produce parts / components according to design drawings. After arriving at the site, they need to be installed and debugged by professionals, such as hydro-turbine generator sets, electrical equipment, etc.

[0071] Box: During transportation, the equipment will be packed in containers, corrugated boxes, crates, pallets or bare pieces as needed. Each box / pallet may correspond to one or more types / pieces of equipment, and bare pieces are generally transported separately for each piece of equipment. Whether it is boxed (pallet packaging is considered a special form of boxed) or bare pieces, they should be numbered to facilitate differentiation during transportation and arrival. This number is uniformly called the box number. The box number is generally compiled by the manufacturer.

[0072] Equipment: Based on the design documents of the design institute, the manufacturer conducts factory acceptance and delivers the components / assemblies with relatively independent functions in generators, turbines, and public equipment. Such components / assemblies are generally called equipment.

[0073] Normal transfer: transfer the electromechanical equipment from the warehouse to the construction site of the corresponding unit.

[0074] Misappropriation and transfer: Transferring the same type of electromechanical equipment from the warehouse to the construction site of other units.

[0075] Full box transfer: Full boxes of electromechanical equipment are transferred according to transfer requirements.

[0076] Unpack and allocate: allocate the required equipment in the box according to the allocation requirements.

[0077] Transfer of whole boxes without unpacking: In case of urgent construction period, the equipment will not be inspected and put into the warehouse upon arrival, but will be directly transferred according to the transfer demand, and then unpacked and inspected during installation.

[0078] like Figure 1 As shown, a method for allocating electromechanical equipment based on intelligent decision-making, the method comprising:

[0079] S101, generating a transfer application form according to the transfer application initiated by the demander;

[0080] S102, according to the transfer application form, query the relevant data of the unit equipment inventory quantity and the unit project installation progress, send the relevant data to the expert knowledge system, and obtain the transfer plan;

[0081] S103, executing the allocation of electromechanical equipment according to the allocation plan.

[0082] The specific implementation is as follows:

[0083] It mainly includes transfer application, transfer decision, transfer review and transfer out of warehouse.

[0084] Transfer application: The demander initiates a transfer application and generates a transfer application form. The transfer application form mainly includes the unit type, required equipment type, transfer quantity, required arrival time, etc.

[0085] Transfer decision: The system automatically extracts the transfer application related information, and queries the unit equipment inventory quantity (d), unit project installation progress (p) and other related data, and sends the relevant data to the expert knowledge system to obtain the transfer plan and multiple (2-5) alternative transfer plans to assist professionals in making decisions;

[0086] Specifically, the expert knowledge base system is preset with knowledge base rules and allocation priority models. The knowledge base rules and allocation priority models can be based on machine learning to achieve real-time optimization and adjustment of scheduling priorities according to different allocation scenarios and weight indicators.

[0087] And based on the knowledge base rules and allocation priority model, it provides allocation plans to assist professionals in making decisions.

[0088] Transfer review: The system provides transfer plans and multiple (2-5) alternative transfer plans based on the transfer decision. Professionals can select and implement the plans provided by the system, check the transfer items, and initiate the review process. After all relevant departments have reviewed and approved them, arrangements will be made for the equipment to be shipped out.

[0089] Transfer out of warehouse: Carry out the transfer of electromechanical equipment according to the transfer plan, and transport the specified electromechanical equipment to the required construction site.

[0090] like Figure 2 As shown, the expert knowledge base system includes a rule generation module, a rule management module, and an intelligent decision-making module.

[0091] Rule generation module: Generates expert knowledge base rules, including transfer scenario matching rules and transfer priority matching rules;

[0092] Rule management module: manage the rule base, such as querying, updating, adding, and deleting expert knowledge base rules.

[0093] Intelligent decision-making module (inference engine): Based on the rules of the expert knowledge base, the acquired transfer demand information, corresponding inventory quantity, project progress and other data are inferred to determine the transfer scenario and transfer priority, and provide transfer plan recommendations.

[0094] like Figure 3 As shown in the figure, after the arrival of electromechanical equipment, the inventory status is queried according to the transfer demand, and the transfer scenario is automatically selected according to the "transfer scenario priority rule" of the expert knowledge base system to determine the transfer method: full box transfer, box transfer, normal transfer, misappropriation transfer, and unopened full box transfer. In different transfer scenarios, according to the queried inventory quantity, project schedule, etc., according to the "transfer execution priority rule" of the expert knowledge base system, the transfer priority model is automatically matched to obtain the transfer plan and execute the transfer.

[0095] The knowledge base of the electromechanical equipment transfer system is established by using production rule representation. Its basic form is: PQ or IFP THEN Q;

[0096] Meaning: If premise P is satisfied, then conclusion Q can be drawn or the operation specified by Q can be performed.

[0097] The main rules for the allocation scenario priority are as follows:

[0098] R1: IF a transfer demand order is received THEN extract the transfer demand order information;

[0099] R2: IF the inventory status of the required electromechanical equipment is 1THEN query the inventory of the supporting units;

[0100] R3:IF the inventory status of the supporting unit is 1THEN normal transfer;

[0101] R4: IF the demand for goods = n*box inventory (n = 1, 2, 3...) THEN transfer the whole box;

[0102] R5: IF the demand for goods is less than the inventory of a single box THEN transfer the goods by unpacking the box;

[0103] R6: IF the demand for goods > the inventory of single boxes THEN transfer by full boxes + transfer by empty boxes;

[0104] (Note: Generally, all equipment units are matched, so in normal transfer, choose matching equipment unit inventory transfer to avoid mismatching of mechanical and electrical equipment transfer models and confusion in inventory statistics.)

[0105] R7: IF the inventory status of the supporting unit is 0 THEN query the inventory of the same type of equipment in other units;

[0106] R8: IF the inventory status of the same type of equipment in other units is 1THEN diversion and transfer;

[0107] R9: IF the demand for goods = n*box inventory (n = 1, 2, 3...) THEN transfer the whole box;

[0108] R10: IF the demand for goods is less than the inventory of a single box THEN transfer the goods by unpacking the box;

[0109] R11: IF the demand for goods > the inventory of a single box THEN transfer by full box + transfer by empty box;

[0110] (Note: When the inventory of the supporting units does not meet the transfer demand, in order to ensure the installation progress of the unit, the required electromechanical equipment can be transferred from the inventory of the same type of equipment of other units on a priority basis without affecting the installation progress of other units.)

[0111] R12: IF the inventory status of the same type of equipment in other units is 0THEN query the equipment arrival information;

[0112] R13: IF the equipment arrival status is 1 AND the goods demand = n*box inventory (n = 1, 2, 3...) THEN the whole box transfer is not opened;

[0113] R14: IF the equipment arrival status is 1 AND the cargo demand is less than the single box inventory THEN the box is unpacked and transferred after initial inspection;

[0114] R15: IF the equipment arrival status is 1 AND the goods demand quantity > the single box inventory quantity THEN unopened box transfer + unpacking box transfer after initial inspection;

[0115] (Note: If the inventory of the same type of equipment in other units is 0, the arrival status of all the same type of equipment will be queried first. According to the order of arrival, the boxes that arrived first will be allocated first. In order to improve the efficiency of acceptance and ensure the progress of project installation, the unopened boxes can be directly allocated and unpacked and accepted after arriving at the construction site.)

[0116] R15: If the equipment arrival status is 0THEN, track the goods and execute the goods expediting. After the equipment arrives, execute R13-R15;

[0117] (Note: If the arrival status of the equipment (such as factory, transportation and other related information) is not found, it is necessary to trace the goods and execute the goods expediting process. After the equipment arrives, respond to the transfer demand as soon as possible and execute transfer R13-R15.)

[0118] The transfer execution priority rules are as follows:

[0119] R16: IF the demand for mechanical and electrical equipment transfer application quantity ≤ the supporting unit inventory quantity THEN transfer the supporting unit inventory (normal transfer);

[0120] R17: IF the amount of transfer application for electromechanical equipment required > the inventory of supporting units THEN transfer the inventory of supporting units + the inventory of the same type of equipment of other units (diversion transfer);

[0121] R18: IF the inventory status of the same type of equipment in other units is 1 THEN query the inventory of other units;

[0122] R19: IF the inventory of units (A, B, C...) meets the transfer demand THEN the transfer plan (inventory priority principle) is derived based on the transfer priority model 1;

[0123] R20: IF the inventory of units (A, B, C...) does not meet the transfer demand THEN query the project progress of other units and derive the transfer plan based on the transfer priority model 2 (project progress priority principle);

[0124] The allocation priority model is constructed as follows:

[0125] After the system determines the allocation scenario, it comprehensively considers factors such as the unit equipment inventory quantity (Y) and the unit project installation progress (P), formulates an allocation plan based on the weight of each factor, and realizes real-time optimization and adjustment of scheduling priorities based on machine learning.

[0126] Transfer priority model 1-inventory priority principle:

[0127] When any inventory quantity Y of unit (A, B, C...) i To meet the transfer demand X, the inventory of units of the same type will be given priority:

[0128] Y i =max(Y A ,Y B ,Y C ,……);

[0129] According to Y i The size of the equipment will be allocated first, and the inventory equipment corresponding to unit i will be allocated first.

[0130] X={Y i},i=A,B,C......;

[0131] Allocation priority model 2-project progress priority principle:

[0132] When the inventory of units (A, B, C...) does not meet the transfer demand, the project schedule of each unit will be given priority:

[0133] P j =max(P A ,P B ,P C ,……);

[0134] According to P j The size of the equipment is prioritized and the inventory equipment corresponding to unit j is allocated.

[0135] X={P A Y A +P B Y B +P C Y C +......},j=A,B,C......。

[0136] like Figure 4 As shown, a mechanical and electrical equipment allocation system based on intelligent decision-making includes: an allocation application unit 401, an allocation decision unit 402 and an allocation out-of-stock unit 403;

[0137] The transfer application unit 401 is used to generate a transfer application form according to the transfer application initiated by the demander;

[0138] The transfer decision unit 402 is used to query the relevant data of the unit equipment inventory quantity and the unit project installation progress according to the transfer application form, send the relevant data to the expert knowledge system, and obtain the transfer plan;

[0139] The allocation and out-of-warehouse unit 403 is used to execute the allocation of electromechanical equipment according to the allocation plan.

[0140] like Figure 5 As shown, the present disclosure provides an electronic device, including a processor 501, a communication interface 502, a memory 503 and a communication bus 504, wherein the processor 501, the communication interface 502 and the memory 503 communicate with each other through the communication bus 504;

[0141] Memory 503, storing computer programs;

[0142] The processor 501 is configured to implement the above method when executing the computer program stored in the memory 503 .

[0143] The present disclosure provides a computer-readable storage medium storing a computer program, wherein the computer program implements the above method when executed by a processor.

[0144] The computer-readable storage medium may be included in the device / apparatus described in the above embodiment; or it may exist independently without being assembled into the device / apparatus. The above computer-readable storage medium carries one or more programs, and when the above one or more programs are executed, the method according to the embodiment of the present disclosure is implemented.

[0145] According to an embodiment of the present disclosure, a computer-readable storage medium may be a non-volatile computer-readable storage medium, for example, may include but is not limited to: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination thereof. In the present disclosure, a computer-readable storage medium may be any tangible medium containing or storing a program that may be used by or in conjunction with an instruction execution system, apparatus, or device.

[0146] Although the present disclosure has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present disclosure.

Claims

1. A method for allocating electromechanical equipment based on intelligent decision-making, characterized in that: The method comprises: Generate a transfer application form based on the transfer application initiated by the demander; According to the transfer application form, query the relevant data of the unit equipment inventory quantity and the unit project installation progress, send the relevant data to the expert knowledge system, and obtain the transfer plan; Carry out the allocation of electromechanical equipment according to the allocation plan.

2. According to the method of claim 1, the electromechanical equipment allocation method based on intelligent decision-making is characterized in that: Expert knowledge base system, including rule generation module, rule management module and intelligent decision-making module; A rule generation module is used to generate expert knowledge base rules, including transfer scenario matching rules and transfer priority matching rules; The rule management module is used to manage the rule base, including querying, updating, adding and deleting the rules of the expert knowledge base; The intelligent decision-making module is used to determine the allocation scenario and allocation priority and give allocation plan suggestions based on the rules of the expert knowledge base, the acquired allocation demand information, the corresponding inventory quantity and the project progress data.

3. The method for allocating electromechanical equipment based on intelligent decision-making according to claim 1 is characterized in that: The expert knowledge base system is preset with expert knowledge base rules and allocation priority model; The allocation priority model is used to formulate allocation plans based on different allocation scenarios.

4. The method for allocating electromechanical equipment based on intelligent decision-making according to claim 1 is characterized in that: Send relevant data to the expert knowledge system to obtain the allocation plan for decision-making in the allocation review process, including: Query the inventory status according to the transfer application form requirements, automatically select the transfer scenario according to the transfer scenario priority rules of the expert knowledge base system, and determine the transfer method: normal transfer, diversion transfer, and unopened full-box transfer; normal transfer, diversion transfer, and unopened full-box transfer include full-box transfer, unboxed transfer, and full-box transfer plus unboxed transfer; In different allocation scenarios, according to the queried inventory quantity and project schedule, the allocation execution priority rules are automatically matched according to the expert knowledge base system, and the allocation priority model is obtained.

5. The method for allocating electromechanical equipment based on intelligent decision-making according to claim 4 is characterized in that: The allocation scenario priority rules include: When receiving a transfer request form, extract the transfer request form information; When the inventory status of the required electromechanical equipment is 1, query the inventory of the supporting units; When the inventory status of the supporting unit is 1, select the supporting unit inventory transfer; When the demand for goods = n*box inventory, the whole box is transferred; Wherein, n is a positive integer; When the demand for goods is less than the inventory of a single box, the box will be taken out for transfer; When the demand for goods is greater than the inventory of a single box, full box transfer plus box-out transfer will be performed; When the inventory status of the matching unit is 0, query the inventory of the same type of equipment in other units; When the inventory status of the same type of equipment in other units is 1, it can be appropriated and transferred; When the demand for goods = n*box inventory, the whole box is transferred; When the demand for goods is less than the inventory of a single box, the box will be taken out for transfer; When the demand for goods is greater than the inventory of a single box, full box transfer plus box-out transfer will be performed; When the inventory status of the same type of equipment in other units is 0, query the equipment arrival information; When the equipment arrival status is 1 and the demand for goods = n*box inventory, the whole box is transferred without unpacking; When the equipment arrival status is 1 and the cargo demand is less than the single box inventory, the equipment will be unpacked and transferred after the initial inspection; When the equipment arrival status is 1 and the demand for goods is greater than the inventory of a single box, the whole box transfer is carried out without unpacking and the box transfer is carried out after initial inspection; When the equipment arrival status is 0, the goods are tracked and expedited, and the transfer is executed after the equipment arrives.

6. The method for allocating electromechanical equipment based on intelligent decision-making according to claim 4 is characterized in that: The transfer execution priority rules include: When the requested amount of electromechanical equipment transfer is less than or equal to the inventory of supporting units, normal transfer is adopted to transfer the inventory of supporting units; When the amount of mechanical and electrical equipment transfer application required is greater than the inventory of supporting units, the transfer is made by using the inventory of supporting units plus the inventory of the same type of equipment of other units; When the inventory status of the same type of equipment in other units is 1, query the inventory of other units; When there is a unit inventory that meets the allocation demand, an allocation plan is obtained based on the allocation priority model 1; When the inventory of the units does not meet the allocation demand, query the progress of other unit projects and derive an allocation plan based on the allocation priority model 2.

7. The method for allocating electromechanical equipment based on intelligent decision-making according to claim 6 is characterized in that: Allocation priority model 1, including: When there is inventory Y in units A, B, C, etc. i To meet the transfer demand X, transfer based on the inventory of the same type of units: AND i =max(Y A ,AND B ,AND C ,……); According to Y i According to the size of the equipment, the inventory equipment corresponding to unit i will be allocated first, i = A, B, C...

8. The method for allocating electromechanical equipment based on intelligent decision-making according to claim 6 is characterized in that: Allocation priority model 2, including: When the inventory of units A, B, C, etc. does not meet the transfer demand, the weighted coefficient P is determined based on the project progress of each unit. j , and perform weighted combination to obtain the allocation plan: X={P A Y A +P B Y B +P C Y C +......},j=A,B,C......; Y A , Y B , Y C is the inventory of units A, B, and C.

9. An electromechanical equipment allocation system based on intelligent decision-making, characterized in that: include: Transfer application unit, transfer decision unit and transfer outbound unit; The transfer application unit is used to generate a transfer application form based on the transfer application initiated by the demander; The transfer decision unit is used to query the inventory quantity of unit equipment and the relevant data of the unit project installation progress according to the transfer application form, and send the relevant data to the expert knowledge system to obtain the transfer plan; The transfer outbound unit is used to transfer electromechanical equipment according to the transfer plan.

10. An electronic device, characterized in that: It includes a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other via the communication bus; a memory storing a computer program; The processor is used to implement a method for allocating electromechanical equipment based on intelligent decision-making as described in any one of claims 1 to 8 when executing a computer program stored in a memory.

11. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, an electromechanical equipment allocation method based on intelligent decision-making according to any one of claims 1 to 8 is implemented.

Citation Information

Patent Citations

  • IT equipment allocation management and control system and allocation method thereof

    CN111612341A

  • Medicine inventory allocation system

    CN112016875A

  • Inventory allocation system, method and equipment and readable storage medium

    CN112819361A

  • Inventory scheduling method based on intelligent terminal

    CN114781971A

  • Resource scheduling method and device based on big data and electronic equipment

    CN116562474A