Sampling and point distribution method for soil pollution condition survey in geophysical exploration

By measuring the difference in soil resistivity and establishing a three-dimensional geological model, the potential pollution areas are determined, and the problem of inconsistent sampling results in the existing technology is solved, and more efficient and accurate soil pollution investigation is achieved, reducing the investigation cost and workload.

CN119006724AActive Publication Date: 2024-11-22NANJING HEXIXINCHENG CONSTRUCT DEV CO LTD +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411018297.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-11-22
Estimated Expiration
2044-07-29

AI Technical Summary

Technical Problem

When sampling and testing contaminated soil, the prior art is prone to miss other contaminated areas in the contaminated soil, making the sampling results inconsistent with the actual pollution situation.

Method used

By obtaining the stratigraphic structure and soil layer properties of the plot to be explored and the surrounding stratigraphic structure and soil layer properties, measuring the resistivity differences of the soil, establishing a three-dimensional geological model, determining potential pollution areas, and enhancing sampling points in high-risk areas, combining with geophysics Exploration and engineering geological survey technology to accurately identify and locate polluted areas.

Benefits of technology

It improves the efficiency and accuracy of pollution investigation, avoids omissions in polluted areas, reduces waste of invalid points, reduces investigation costs, and achieves a more comprehensive and accurate sampling and distribution.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119006724A_ABST
    Figure CN119006724A_ABST
Patent Text Reader

Abstract

The invention provides a geophysical exploration soil pollution condition investigation sampling and point distribution method, and belongs to the technical field of polluted soil sampling and point distribution. According to the method, a potential pollution area in a land parcel where soil to be explored is located is obtained through a resistivity method, a high-risk area in the land parcel is obtained according to an original function layout of the land parcel, and sampling points are arranged in the potential pollution area and the high-risk area. The method solves the problem that in the prior art, when an area related to production in polluted soil is used as a high-risk area for sampling and point distribution, other polluted areas in the polluted soil are prone to being omitted, so that the sampling result does not conform to the actual pollution condition, and the method has the advantages that most of the polluted areas in the polluted soil covered by the sampling points, and the sampling effect is good. And the sampling result conforms to the actual pollution condition.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of sampling and point arrangement for contaminated soil, and in particular to a sampling and point arrangement method for investigating soil contamination status in geophysical exploration. Background Art

[0002] When soil is polluted, its color changes, generally turning into black, dark brown, dark gray, brown red, apricot red, or with rust spots, etc., which is different from the color of normal soil; the state also changes accordingly, such as the original plastic hard plastic state will turn into soft plastic or fluid plastic; the contaminated soil layer often has a honeycomb structure, dispersed particles, rough surface, and even local holes.

[0003] Before sampling and testing contaminated soil, existing technologies often use the original functional layout of the contaminated soil to arrange sampling points in production-related areas as high-risk areas. However, the above sampling point arrangement method is prone to miss other contaminated areas in the contaminated soil, making the sampling results inconsistent with the actual pollution situation. Summary of the invention

[0004] The technical problem solved by the present invention is that the prior art uses production-related areas in contaminated soil as high-risk areas for sampling, which easily misses other contaminated areas in the contaminated soil, making the sampling results inconsistent with the actual pollution situation.

[0005] To solve the above problems, the technical solution of the present invention is as follows:

[0006] A method for sampling and arranging points for soil pollution status investigation in geophysical exploration, comprising:

[0007] Obtain the stratigraphic structure and soil properties of the plot where the soil to be explored is located and the surrounding areas;

[0008] Obtain the resistivity difference between the soil in the plot and the surrounding normal soil. When there is a difference between the two, measure the resistivity of the soil in the plot by the resistivity method;

[0009] Determine the three-dimensional geological model of the plot including the distribution range of abnormal soil according to the resistivity of the plot soil, extract the edge coordinates of the distribution range of abnormal soil in the three-dimensional geological model of the plot, project the edge coordinates onto the map of the plot, and obtain the potential contaminated area of ​​the plot;

[0010] Based on the original functional layout map of the plot, obtain the high-risk area of ​​the plot;

[0011] Sampling points are set up in the potential contaminated area of ​​the plot, sampling points are set up in the high-risk area of ​​the plot, and sampling points are densely deployed in the area where the potential contaminated area of ​​the plot overlaps with the high-risk area of ​​the plot.

[0012] As one aspect of the present invention, obtaining the resistivity difference between the soil of a plot and the surrounding normal soil includes:

[0013] Obtain characteristic pollutants related to the resistivity of the plot, set up soil test groups according to the characteristic pollutants, measure the soil resistivity of each soil test group respectively, obtain the difference between the soil resistivity of the plot soil and the soil resistivity of the normal soil around the plot to be measured, and preliminarily judge whether there is landfill in the plot based on the difference, and obtain a preliminary judgment result. When the preliminary judgment result is that there is landfill in the plot, proceed to the next step;

[0014] Among them, the relevant data of characteristic pollutants include the types of characteristic pollutants and the pollution equivalents of characteristic pollutants; the soil test groups include blank control group, one times pollution equivalent test group, three times pollution equivalent test group and five times pollution equivalent test group; the blank control group is the normal soil around the plot soil, the one times pollution equivalent test group is the plot soil, the three times pollution equivalent test group is the plot soil with three times the pollution equivalents of the characteristic pollutants, and the five times pollution equivalent test group is the plot soil with five times the pollution equivalents of the characteristic pollutants.

[0015] As another aspect of the present invention, the resistivity of soil of a plot of land is measured by a resistivity method, comprising:

[0016] A plurality of measuring lines are equidistantly set in the plot, a plurality of measuring points are equidistantly set on the measuring lines, the resistivity of all the measuring points is measured by the resistivity method, and the resistivity of all the measuring points is determined as the resistivity of the soil in the plot.

[0017] As another aspect of the present invention, based on the original functional layout diagram of the land parcel, obtaining the high-risk area of ​​the land parcel includes:

[0018] Based on the original functional layout map of the plot, the production-related areas in the plot are identified as high-risk areas of the plot through professional judgment.

[0019] As another aspect of the present invention, the production-related area in the plot includes the original production area and the wastewater treatment facility area.

[0020] As another aspect of the present invention, sampling points are arranged in a potential contaminated area of ​​a plot of land, sampling points are arranged in a high-risk area of ​​the plot of land, and sampling points are arranged densely in an area where the potential contaminated area of ​​the plot of land overlaps with the high-risk area of ​​the plot of land, including:

[0021] Divide the potential contaminated area and the high-risk area of ​​the plot into multiple sampling units, and arrange a sampling point in each of the multiple sampling units;

[0022] Sampling points are densely deployed in each sampling unit in the area where the potential contaminated area of ​​the land plot overlaps with the high-risk area of ​​the land plot.

[0023] As another aspect of the present invention, obtaining the stratum structure and soil layer properties of the plot where the soil to be explored is located and the surrounding area of ​​the plot includes:

[0024] Collect engineering geological survey reports of the soil plot to be explored and its surrounding areas, and analyze the stratigraphic structure and soil properties of the plot and its surrounding areas based on the engineering geological survey reports.

[0025] As another aspect of the present invention, the abnormal soil distribution range includes the planar distribution information and the longitudinal distribution information of the abnormal soil.

[0026] As another aspect of the present invention, the sampling depth and position of the sampling point are obtained based on the resistivity measurement results of the land block combined with the adjustment of the stratum structure of the land block.

[0027] The beneficial effects of the present invention are:

[0028] (1) By combining the latest geophysical analysis, conductivity testing and sensor testing methods, we will establish a precise survey and three-dimensional identification system that can be widely applied. At the same time, we will draw on the technical advantages of the geological department in physical and chemical exploration, rock and mineral testing, engineering construction, etc., and use them for the investigation of contaminated plots to improve the efficiency and accuracy of the investigation;

[0029] (2) Combined with the results of geophysical exploration and interpretation, the soil or landfill with different physical properties in the region can be quickly located and identified, the plane distribution range can be delineated, and sampling can be arranged in areas with suspected contaminated soil or landfill, which can effectively avoid missing contaminated areas and solve the problem of "touching the edge" in pollution investigation; based on the results of geophysical exploration and combined with hydrogeological conditions, the sampling depth can be reasonably determined to solve the problem of difficulty in determining the sampling depth and avoid the problem of sampling depth being unable to "probe and cover the bottom";

[0030] (3) Based on the results of geophysical exploration and the functional layout of the land, targeted sampling is carried out to achieve more comprehensive and accurate sampling, avoid the waste of a large number of invalid points, reduce workload and detection cycle, and reduce survey costs. This method can produce significant economic and environmental benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 This is a flow chart of a sampling point arrangement method for geophysical exploration soil pollution status investigation provided by an embodiment of the present application;

[0032] Figure 2 is a schematic diagram of a three-dimensional geological model in an embodiment of the present application;

[0033] Figure 3is a schematic diagram of landfill layers in potential contaminated areas and high-risk areas within a three-dimensional geological model in an embodiment of the present application;

[0034] Figure 4 is a schematic diagram of the pond mud layer in the potential contaminated area and the high-risk area in the three-dimensional geological model in the embodiment of the present application;

[0035] Figure 5 It is a schematic diagram of pond mud layer landfill in potential contaminated areas and high-risk areas in the three-dimensional geological model in the embodiment of the present application;

[0036] Figure 6 It is a schematic diagram of the potential pollution range of the potential pollution area and the high-risk area in the three-dimensional geological model in the embodiment of the present application;

[0037] Figure 7 It is the original functional layout diagram of the plot in the embodiment of this application;

[0038] Figure 8 It is a schematic diagram of the sampling layout points in the embodiment of the present application. DETAILED DESCRIPTION

[0039] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0040] The terms used in the embodiments of the present invention are only for the purpose of describing specific embodiments, and are not intended to limit the present invention. The singular forms "a", "said" and "the" used in the embodiments of the present invention and the appended claims are also intended to include plural forms, unless the context clearly indicates other meanings, and "multiple" generally includes at least two.

[0041] The embodiment of the present application records a method for sampling points in geophysical exploration soil pollution status investigation, which is used to solve the problem proposed in the background technology that the prior art uses production-related areas in contaminated soil as high-risk areas for sampling points, which easily misses other contaminated areas in the contaminated soil, resulting in the sampling results being inconsistent with the actual pollution situation.

[0042] like Figure 1 As shown, a sampling point arrangement method for soil pollution status investigation in geophysical exploration recorded in an embodiment of the present application is implemented by S101-S105.

[0043] S101. Obtain the stratigraphic structure and soil properties of the plot of land where the soil to be explored is located and the surrounding areas of the plot.

[0044] In the embodiment of the present application, S101 includes:

[0045] Collect engineering geological survey reports of the soil plot to be explored and its surrounding areas, and analyze the stratigraphic structure and soil properties of the plot and its surrounding areas based on the engineering geological survey reports.

[0046] S102, obtaining the resistivity difference between the soil of the plot and the surrounding normal soil, and when there is a difference between the two, measuring the resistivity of the soil of the plot by using a resistivity method.

[0047] In the embodiment of the present application, obtaining the resistivity difference between the soil of the plot and the surrounding normal soil includes:

[0048] Obtain characteristic pollutants related to the resistivity of the plot, set up soil test groups according to the characteristic pollutants, measure the soil resistivity of each soil test group respectively, obtain the difference between the soil resistivity of the plot soil and the soil resistivity of the normal soil around the plot to be measured, and preliminarily judge whether there is landfill in the plot based on the difference, and obtain a preliminary judgment result. When the preliminary judgment result is that there is landfill in the plot, proceed to the next step;

[0049] Among them, the relevant data of characteristic pollutants include the types of characteristic pollutants and the pollution equivalents of characteristic pollutants; the soil test groups include blank control group, one times pollution equivalent test group, three times pollution equivalent test group and five times pollution equivalent test group; the blank control group is the normal soil around the plot soil, the one times pollution equivalent test group is the plot soil, the three times pollution equivalent test group is the plot soil with three times the pollution equivalents of the characteristic pollutants, and the five times pollution equivalent test group is the plot soil with five times the pollution equivalents of the characteristic pollutants.

[0050] It can be understood that in the embodiment of the present application, the pollution equivalent of the characteristic pollutant is a pollution equivalent based on the risk screening value of the first type of land in the "Soil Environmental Quality Construction Land Soil Pollution Risk Control Standard (Trial)" (GB 36600-2018), which is the current mandatory standard in soil pollution status surveys.

[0051] In the embodiment of the present application, the process of obtaining the one-time pollution equivalent test group, the three-time pollution equivalent test group and the five-time pollution equivalent test group is as follows.

[0052] (1) Select normal soil from the surrounding area and conduct tests. The natural background value of its characteristic pollutants is used as the control value, and the moisture content is measured for future use.

[0053] (2) Preparation of test soil: Based on the Class I risk screening value of GB36600-2018 as one pollution equivalent, test soil with 1, 3, and 5 times the pollution equivalent was prepared for testing.

[0054] (3) Before the test begins, prepare enough deionized water solution of characteristic pollutants at concentrations of 1, 3, and 5 times the pollution equivalent to meet the usage of one treatment for all replicate groups.

[0055] (4) Add appropriate amounts of liquid medicine of each concentration into the artificial soil, supplement with deionized water so that the final moisture content of the soil reaches the moisture content level of the surrounding normal soil, mix well and place in the test container for later use.

[0056] Optionally, in an embodiment of the present application, a preliminary judgment is made based on the difference whether there is landfill on the land parcel, and the preliminary judgment result is obtained through a difference threshold. When the difference is greater than the difference threshold, the preliminary judgment result is that there is landfill on the land parcel.

[0057] Optionally, the difference threshold may be 20%.

[0058] In the embodiment of the present application, the resistivity of the soil of the plot is measured by the resistivity method, including:

[0059] A plurality of measuring lines are equidistantly set in the plot, a plurality of measuring points are equidistantly set on the measuring lines, the resistivity of all the measuring points is measured by the resistivity method, and the resistivity of all the measuring points is determined as the resistivity of the soil in the plot.

[0060] Optionally, the spacing between the multiple measuring lines may be 10 m, and the spacing between the multiple measuring points may be 5 m.

[0061] S103, determining a three-dimensional geological model of the plot including an abnormal soil distribution range according to the resistivity of the plot soil, extracting edge coordinates of the abnormal soil distribution range in the three-dimensional geological model of the plot, projecting the edge coordinates onto a map of the plot, and obtaining a potential contaminated area of ​​the plot.

[0062] Optionally, in the implementation of the present application, the three-dimensional geological model of the plot containing the abnormal soil distribution range is determined according to the resistivity of the soil of the plot, including:

[0063] The resistivity of the soil of the plot and the map of the plot are input into the three-dimensional geological model to obtain a three-dimensional geological model of the plot that includes the soil layer structure of the plot and shows the distribution range of abnormal soil. Among them, the map includes the longitudinal structural information of the soil layer of the plot.

[0064] The three-dimensional geological model obtained in the present embodiment is as follows Figure 2 As shown in Figure 2, the landfill layer in the 3D geological model is as follows: Figure 3As shown. Since part of the landfill will be exposed on the surface, it can be identified by the naked eye, but the scope and depth cannot be determined. For example, a garbage dump that appears to be only 10 square meters on the surface may be a trapezoid, and may expand to 20 square meters downwards, and the depth cannot be predicted. The distribution of landfill solid waste and the depth of landfill can be identified by the method of the embodiment of the present application. In addition, landfill buried in vacant land, roads and other easily overlooked areas can also be identified by this method.

[0065] Furthermore, the pond mud layer in the 3D geological model is Figure 4 As shown in Figure 2, the landfill in the pond mud layer is as follows: Figure 5 As shown. The pond mud layer is the silt layer of a pond, river or lake, and here it is a pond. Generally speaking, the silt layer at the bottom of a natural water body is the original soil layer and has not been disturbed by humans. This is the maximum sampling depth during the investigation. It can be seen here that in actual situations, there are landfills embedded in the lower part of the pond mud layer, which cannot be identified through traditional experience and is easy to be missed.

[0066] In the embodiment of the present application, the abnormal soil distribution range includes the plane distribution information and the vertical distribution information of the abnormal soil.

[0067] S104. Based on the original functional layout map of the land parcel, obtain the high-risk area of ​​the land parcel.

[0068] In the embodiment of the present application, S104 includes:

[0069] Based on the original functional layout map of the plot, the production-related areas in the plot are identified as high-risk areas of the plot through professional judgment.

[0070] Optionally, the production-related areas in the above-mentioned plots of land include the original production area and the wastewater treatment facility area.

[0071] In the present application example, the potential contamination range in the plot is as follows: Figure 6 As shown, the original functional layout of the plot is as follows Figure 7 shown.

[0072] S105. Sampling points are arranged in the potential contaminated area of ​​the land parcel, sampling points are arranged in the high-risk area of ​​the land parcel, and sampling points are arranged more densely in the area where the potential contaminated area of ​​the land parcel overlaps with the high-risk area of ​​the land parcel.

[0073] In the embodiment of the present application, S105 includes:

[0074] Divide the potential contaminated area and the high-risk area of ​​the plot into multiple sampling units, and arrange a sampling point in each of the multiple sampling units;

[0075] Sampling points are densely deployed in each sampling unit in the area where the potential contaminated area of ​​the land plot overlaps with the high-risk area of ​​the land plot.

[0076] Optionally, the sampling depth and position of the above-mentioned sampling points are obtained based on the resistivity measurement results of the land block and the adjustment of the stratum structure of the land block.

[0077] Optionally, the sampling unit in the embodiment of the present application is 40m*40m, and the sampling points are densely arranged so that at least two sampling points are arranged in each sampling unit.

Claims

1. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration, characterized in that: include: Obtain the stratigraphic structure and soil properties of the plot where the soil to be explored is located and the surrounding areas; Obtaining the resistivity difference between the soil of the plot and the surrounding normal soil, and when there is a difference between the two, measuring the resistivity of the soil of the plot by using the resistivity method; Determine a three-dimensional geological model of the plot containing an abnormal soil distribution range according to the resistivity of the soil of the plot, extract edge coordinates of the abnormal soil distribution range in the three-dimensional geological model of the plot, project the edge coordinates onto a map of the plot, and obtain a potential contaminated area of ​​the plot; Based on the original functional layout diagram of the plot, obtaining a high-risk area of ​​the plot; Sampling points are arranged in the potential contaminated area of ​​the plot of land, sampling points are arranged in the high-risk area of ​​the plot of land, and sampling points are arranged more densely in the area where the potential contaminated area of ​​the plot of land overlaps with the high-risk area of ​​the plot of land.

2. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration according to claim 1, characterized in that: The method of obtaining the resistivity difference between the soil of the plot and the surrounding normal soil includes: Acquire characteristic pollutants related to the resistivity of the plot of land, set soil test groups according to the characteristic pollutants, measure the soil resistivity of each soil test group respectively, obtain the difference between the soil resistivity of the soil of the plot of land and the soil resistivity of normal soil around the plot of land to be measured, and preliminarily judge whether there is landfill in the plot of land according to the difference, and obtain a preliminary judgment result. When the preliminary judgment result is that there is landfill in the plot of land, proceed to the next step; Among them, the relevant data of the characteristic pollutants include the types of the characteristic pollutants and the pollution equivalents of the characteristic pollutants; the soil test groups include a blank control group, a one-time pollution equivalent test group, a three-time pollution equivalent test group and a five-time pollution equivalent test group; the blank control group is the normal soil around the soil of the plot, the one-time pollution equivalent test group is the soil of the plot, the three-time pollution equivalent test group is the soil of the plot with three times the pollution equivalent of the characteristic pollutant, and the five-time pollution equivalent test group is the soil of the plot with five times the pollution equivalent of the characteristic pollutant.

3. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration according to claim 1 or 2, characterized in that: The method of measuring the resistivity of the soil of the plot of land by a resistivity method comprises: A plurality of measuring lines are equidistantly arranged in the plot, a plurality of measuring points are equidistantly arranged on the measuring lines, the resistivity of all the measuring points is measured by a resistivity method, and the resistivity of all the measuring points is determined as the resistivity of the soil of the plot.

4. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration according to claim 1, characterized in that: The obtaining of the high-risk area of ​​the land parcel based on the original functional layout diagram of the land parcel includes: Based on the original functional layout map of the land parcel, the production-related areas in the land parcel are determined as high-risk areas of the land parcel through professional judgment.

5. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration according to claim 4, characterized in that: The production-related areas in the said plot of land include the original production area and the wastewater treatment facility area.

6. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration according to claim 1 or 2, characterized in that: The arranging of sampling points in the potential contaminated area of ​​the plot, the arranging of sampling points in the high-risk area of ​​the plot, and the intensive arranging of sampling points in the area where the potential contaminated area of ​​the plot overlaps with the high-risk area of ​​the plot include: Dividing the potentially contaminated area of ​​the plot of land and the high-risk area of ​​the plot of land into a plurality of sampling units respectively, and arranging a sampling point in each of the plurality of sampling units; Sampling points are densely arranged for each sampling unit in the area where the potential contaminated area of ​​the plot of land overlaps with the high-risk area of ​​the plot of land.

7. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration according to claim 1 or 2, characterized in that: The obtaining of the stratum structure and soil properties of the plot of land where the soil to be explored is located and the surrounding areas of the plot includes: Collect engineering geological survey reports of the soil plot to be explored and its surrounding areas, and analyze the stratigraphic structure and soil properties of the plot and its surrounding areas based on the engineering geological survey reports.

8. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration according to claim 1 or 2, characterized in that: The abnormal soil distribution range includes the plane distribution information and the vertical distribution information of the abnormal soil.

9. A method for sampling and arranging points for soil pollution status investigation in geophysical exploration according to claim 1 or 2, characterized in that: The sampling depth and position of the sampling point are obtained based on the resistivity measurement result of the land block and the adjustment of the stratum structure of the land block.

Citation Information

Patent Citations

  • Rapid diagnosis method for polluted site soil

    CN105203599A

  • Agricultural producing area soil monitoring point arrangement method based on step-by-step grid refinement

    CN105701250A

  • RBM regression-based water TOC concentration analysis method

    CN105911003A

  • Method for accurately positioning soil contamination based on geophysical exploration and accurate estimation method

    CN107544097A

  • Landfill geological survey method

    CN108205160A