Portable device and method applied to ultra-long-distance engineering measurement control point

By designing a portable device, using welded frames and LED light strips for lossless installation and orientation, the problem of engineering measurement control points destroying the directional accuracy of waterproof layer and long-distance rearview when laid on the roof of a high-rise building is solved, and high efficiency and losslessness are achieved Installation and precise orientation of measurement control points.

CN119509497APending Publication Date: 2025-02-25SHANGHAI FOUNDATION ENGINEERING GROUP CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411702766.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-26
Publication Date
2025-02-25

AI Technical Summary

Technical Problem

In urban construction, the layout of engineering measurement control points needs to be carried out on the roof of high-rise buildings, resulting in damage to the waterproof layer and making it difficult to achieve high accuracy in long-distance rear-view orientation.

Method used

Design a portable device, including a welded frame, top strut, forced center disc, prism, light strip power cord, custom target plate and LED light strip, fixed device on the roof through lossless installation, using LED light strip Orientation of the total station.

Benefits of technology

It realizes the installation and maintenance of engineering measurement control points without destroying the roof waterproof layer and building structure, and improves the accuracy and reliability of long-distance rearview orientation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119509497A_ABST
    Figure CN119509497A_ABST
Patent Text Reader

Abstract

The invention relates to a portable device and method applied to an ultra-long distance engineering measurement control point, and the device comprises a welding frame, a top supporting rod, a forced centering disc, a prism, a lamp strip power line, a customized target board, and an LED lamp strip, the top supporting rod is welded at the top position of the welding frame, and the center of the top supporting rod is fixedly provided with the forced centering disc; the forced centering disc is used as a forced centering point for erecting a total station and a prism; the LED lamp strip is pasted to the center of the customized target board and connected with the power bank through the lamp strip connecting power line, so that the LED lamp strip is lightened, and the total station aims at the LED lamp strip to complete orientation. The portable device is convenient to operate and simple in structure, lossless installation can be achieved during roof operation, point location layout work can be rapidly and efficiently completed, and the construction progress and quality are guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a surveying device for making engineering survey control points, in particular to a portable device and method for ultra-long distance engineering survey control points. Background Art

[0002] In urban construction, control networks need to be laid out at the beginning of building construction, tunnels, bridges, and pipeline projects. When measuring control network points, it is usually necessary to set up measurement control points on the roof of a building or on a bridge. There are many high-rise buildings in the city. Placing control points on the top of a building has a wide field of view and is not easily blocked or damaged. The receiver signal is stable during GNSS measurement, and the points can be preserved for a long time. The entire line of the subway design route and the viaduct can be measured. Total station backsight orientation is a method to ensure measurement accuracy. It requires that the distance between the station and the backsight point be greater than the distance between the station and the layout point. The accuracy of the oriented side will directly affect the accuracy of the side to be measured, ensuring that the long side controls the short side, that is, the backsight point should be farther than the measurement target point to reduce error accumulation.

[0003] Making control points is the basis for measuring control networks in engineering construction. In general, in order to lay out and maintain these control points, it may be necessary to carry out construction activities such as burying expansion screws on the roof of the building, which may involve damaging the waterproof layer; in rear-sight orientation, the longer the distance, the lower the resolution of the telescope, the lower the clarity, and it is difficult for the aiming part to capture the target point. How to solve this problem in the measurement process, and how to control the long distance of the rear-sight point in engineering construction.

[0004] This is an issue that needs to be handled with caution. The waterproof layer is an important part of the building. It prevents moisture from penetrating into the structure of the building and causing corrosion, mildew, leakage or other potential structural problems. Therefore, if the waterproof layer needs to be destroyed to set or maintain the roof control point, appropriate measures must be taken to protect the structural integrity of the building; the shorter the distance of the backsight orientation edge, the worse the orientation accuracy will be. The measurement error of the short side leading the long side will double. How to complete high-precision orientation when encountering a long-distance backsight orientation edge? In order to meet the design requirements of engineering measurement control points, it is also imperative to study and do a good job of measuring points that can meet the needs of the project.

[0005] At present, there are two methods for laying out measurement control points in urban construction. One is to bury iron nails on the ground or make forced centering points. The points laid out on the ground are not conducive to long-term protection, and the visibility is poor. They are easily blocked by vehicles and pedestrians. Long-term rolling by vehicles will cause point changes and settlement displacement. The second is to lay out points on the roof of high-rise buildings. In the past, the points laid out required the tripod to be buried on the top floor of the building with expansion screws. The use of expansion screws will destroy the roof waterproof layer, which is not conducive to the later waterproofing of the building.

[0006] Therefore, the layout of engineering control points is the key to urban construction and a long-term activity. Long-distance rear-view marker targets play an important role in engineering measurement and can be used to determine and control key points in the control network, thereby ensuring the accuracy and quality of the entire project. How to provide a non-destructive device to solve this technology has become an urgent technical problem in this field. Summary of the invention

[0007] The purpose of the present invention is to solve the problem of not damaging the roof structure and waterproof layer and long-distance rear-sight orientation when the above-mentioned engineering survey control points are arranged on the roof, and to provide a portable device and method for ultra-long-distance engineering survey control points.

[0008] In order to solve the above technical problems, the present invention adopts the following technical solutions: a portable device used for ultra-long distance engineering measurement control points, comprising: a welding frame, a top support rod, a forced centering disk, a prism, a light strip power cord, a customized target board, and an LED light strip. The top support rod is welded at the top position of the welding frame, and the center of the top support rod is fixedly installed with a forced centering disk, which serves as a forced centering point for setting up a total station and a prism; the LED light strip is pasted at the center position of the customized target board, and is connected to a power bank by connecting the light strip power cord to light up the LED light strip, and the total station is aimed at the LED light strip to complete the orientation.

[0009] Furthermore, the welded frame is made of angle iron, and its size is determined by parameter size data obtained through field survey.

[0010] Furthermore, a reserved hole for installing a forced centering disk is provided at the center of the top support rod, which is used to install and fix the forced centering disk.

[0011] Furthermore, an intermediate support rod is installed in the middle of the welding frame to bear pressure and tension of the welding frame, making the welding frame structure more stable when subjected to stress.

[0012] Furthermore, fixing nuts are welded at the four corner points at the bottom of the welding frame, screw rods are screwed into the nuts, and gaskets are welded on the top of the screw rods; the screw rods are perpendicular to the outside of the wall and are used to fix the welding frame.

[0013] Further, the centering plate is fixed at the top support rod position by nuts and washers.

[0014] Furthermore, the customized target plate is used when the original target cannot meet the measurement work requirements. It is replaced with a customized target plate so that it can be easily found and effectively identified during long-distance observation and orientation.

[0015] A method for manufacturing a portable device for ultra-long distance engineering measurement control points, the specific steps of which are as follows:

[0016] Step 1: Survey and select the site, obtain the parameter size data of the welding frame, the width and height of the parapet wall at the top of the building, and the size of the welding frame required, determine the site location, and start making the frame;

[0017] Step 2: After the welding of the welding frame is completed, select and make the top support rod, which is used to support the forced centering plate and the measuring instrument. The center position of the top support rod is reserved with a hole for installing the forced centering plate, and the top support rod is welded to the middle position of the top of the manufactured frame;

[0018] Step 3: Weld four nuts to the four corner points at the bottom of the frame, screw the screw rods into the four nut positions, and then weld the washers to the screw ends of the four screw rods. The direction of the nuts is facing the wall. The screw rods pass through the nuts. The washers are welded to the top of the screw rods to increase the force-bearing area between the screw rods and the wall and protect the wall surface. The screw rods are perpendicular to the outside of the wall. Tighten the screw rods with a wrench so that the top of the screw rods is against the wall to tighten the force to fix the welded frame.

[0019] Step 4: After the welding frame is fixed, install the forced centering plate and fix it to the top support rod position with nuts and washers as the forced centering point for setting up the total station and prism;

[0020] Step 5: When the original target cannot meet the measurement requirements, replace it with a customized target according to the bottom of the original target and the matching size of the prism, so that it is easier to find the target during long-distance rear-view orientation. The LED light strip is pasted on the center of the customized target, and the customized target is lit through the power cord of the light strip. The total station only needs to aim at the light strip to complete the orientation.

[0021] The beneficial effects of the present invention are:

[0022] The device and method of the present invention adopt a non-destructive device to avoid damaging the waterproof layer of the roof and the integrity of its building structure. The device is installed at the parapet of the top of the building, and the control point is made into a frame-shaped riding-style riding on the top of the facade of the parapet. The welded frame is firmly fixed on the parapet by tightening and pressing with screws based on the principle of mechanics. If the original target cannot meet the measurement requirements, the target plate is heightened and lengthened according to the bottom of the original target of the rear-view prism and the matching size of the prism, so that it is easy to find the observation target when looking backward and oriented at a long distance. The portable device is easy to operate and has a simple structure. It can be installed non-destructively when working on the roof, and can quickly and efficiently complete the point layout work to ensure the construction progress and quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a schematic diagram of a portable device for ultra-long distance engineering survey control points and a manufacturing method of the present invention;

[0024] Figure 2 It is a schematic diagram of a method for making control points for engineering surveying according to the present invention;

[0025] Figure 3 This is a schematic diagram of the installation of the forced centering disk of the present invention;

[0026] Figure 4 It is a schematic diagram of a screw rod installation device of the present invention;

[0027] Figure 5 It is a schematic diagram of a method for making a customized target sign and an LED light strip of the present invention;

[0028] Figure 6 It is a flow chart of the method for making control points for engineering surveying of the present invention;

[0029] In the figure: 1. welding frame, 2. top support rod, 3. middle support rod, 4. forced centering plate, 5. forced centering plate gasket, 6. forced centering plate nut, 7. screw rod, 8. nut, 9. gasket, 10. wrench, 11. prism, 12. light strip power cord, 13. original target, 14. customized target plate, 15. LED light strip. DETAILED DESCRIPTION

[0030] The implementation method of the present invention will be further described in detail below with reference to the accompanying drawings.

[0031] like Figures 1 to 5As shown, a portable device for ultra-long distance engineering measurement control points of the present invention includes: a welding frame 1, a top support rod 2, an intermediate support rod 3, a forced centering plate 4, a forced centering plate gasket 5, a forced centering plate nut 6, a screw rod 7, a nut 8, a gasket 9, a wrench 10, a prism 11, a light strip power cord 12, an original target 13, a customized target plate 14, and an LED light strip 15.

[0032] Welding frame 1 is made of angle iron. When surveying and selecting the site, field survey is conducted to obtain parameter size data, such as the parapet wall width and height at the top of the building, as well as the size of the welding frame required. After the on-site location is determined, the frame is made. The production and use of roof control points must comply with relevant laws, regulations and safety regulations.

[0033] The top support rod 2 is welded to the top position of the manufactured frame. The center of the top support rod 2 is a reserved hole for installing the forced centering disk, which is used to install and fix the forced centering disk 4.

[0034] The middle support rod 3 is installed in the middle position of the welding frame 1. The middle support rod 3 is used for the pressure-bearing and tension-resisting effects of the welding frame, and makes the welding frame structure more stable when subjected to force.

[0035] The nuts 8 are welded and fixed at the four corner points at the bottom of the frame. After the screw rods 9 are screwed into the four nut 8 positions with a wrench 10, the washers 9 are welded and fixed at the screw ends of the four screw rods 7. The direction of the nuts 8 faces the wall position, the screw rods 7 pass through the nuts 8, and the washers 9 are welded to the top of the screw rods 7 to increase the force-bearing area between the screw rods 7 and the wall and protect the wall surface. The screw rods 7 are perpendicular to the outside of the wall and are used to fix the welded frame 1.

[0036] Forced centering plate 4 is fixed to the top support rod 2 with nuts 8, washers 9 and wrenches 10, serving as the forced centering point for setting up the total station and prism 11.

[0037] The size of the customized target plate 14 should be large enough. When the original target 13 cannot meet the measurement work requirements, it is replaced with the customized target plate 14 so that it can be easily found and effectively identified during long-distance observation and orientation.

[0038] The LED light strip 15 is pasted on the center of the customized target 14. By connecting the LED light strip power cord 12, the LED light strip 15 can be lit through a power bank. The light strip customized target 14 can also be used for nighttime construction needs. The total station only needs to aim at the light strip to complete the orientation.

[0039] The device of the present invention does not damage the roof waterproof layer structure when it is installed. All structures are prefabricated structures, which can be installed quickly and without damage. When used, the structure is subjected to forces in four directions, and the structure is stable, ensuring the accuracy and quality of the project. The device is used at the point, which can be installed quickly and without damage, greatly saving time and cost.

[0040] like Figure 6 As shown, a method for manufacturing a portable device for ultra-long distance engineering measurement control points of the present invention specifically comprises the following steps:

[0041] Step 1: Obtain the parameter size data required to make the welding frame 1, measure the parapet wall width and height at the top of the building, and the size of the welding frame 1 required, determine the on-site location, and start making the frame.

[0042] Step 2: After the welding frame 1 is welded, select and manufacture the top support rod 2, pre-install the hole position of the forced centering plate 4 at the center position of the top support rod 2, and weld the top support rod 2 to the middle position of the top of the manufactured frame.

[0043] Step 3. Weld four nuts 8 to the four corner points at the bottom of the frame 1 respectively. After screwing the screw rod 7 into the four nuts 8, weld and fix the gasket 9 to the screw ends of the four screw rods 7. The direction of the nut 8 faces the wall. The screw rod 7 passes through the nut 8. The gasket 9 is welded to the top of the screw rod 7 to increase the force-bearing area between the screw rod 7 and the wall and protect the wall surface. The screw rod 7 is perpendicular to the outside of the wall. Tighten the screw rod 7 with a wrench 10 so that the top of the screw rod is against the wall and tightened to fix the welded frame 1.

[0044] Step 4: After the welding frame 1 is fixed, install the forced centering plate 4, and fix the forced centering plate 4 to the top support rod 2 with nuts 6 and washers 5, which serves as the forced centering point for setting up the total station and prism 11.

[0045] in, Figure 3 After the welding frame 1 shown is fixed, the forced centering plate 4 is installed and fixed to the top support rod 2 with nuts 6 and washers 5 as the forced centering point for setting up the total station and prism 11.

[0046] in, Figure 4 The four nuts 8 shown are welded to the four corner points at the bottom of the frame 1 respectively. After the screw rod 7 is screwed into the four nuts 8, the gasket 9 is welded and fixed to the screw ends of the four screw rods 7. The direction of the nut 8 faces the wall. The screw rod 7 passes through the nut 8 and the gasket 9 is welded to the top of the screw rod 7. The screw rod 7 is perpendicular to the outside of the wall. Use a wrench 10 to tighten the screw rod 7 so that its top is against the wall and tightened to bear the force. At this time, the welded frame 1 is fixed.

[0047] Step 5: Figure 5 If the original target 13 shown cannot meet the measurement requirements, the bottom of the original target 13 of the rear-view prism is replaced with a customized target plate 14 according to the matching size of the prism, so that the target can be found more easily during long-distance rear-view orientation. The LED light strip 12 is pasted on the center of the customized target plate 14, and the customized target plate 14 is lit by the light strip power cord 12. The total station only needs to aim at the LED light strip 15 to complete the orientation.

[0048] Step 6: After all steps are completed, the points are connected to the ground wire for lightning protection, and the layout and installation of the points are completed.

[0049] Please note that making a portable device for ultra-long distance engineering survey control points is a task that requires professional skills and experience, and should ensure that the operation is standardized, accurate, and in compliance with relevant standards and regulations. At the same time, safety should always be put first to avoid accidents during the survey process.

[0050] In addition, after the production is completed, the control network points should be regularly inspected and maintained to ensure their stability and accuracy. For any factors that may affect the stability of the points, timely measures should be taken to repair or re-select the points.

[0051] The above is a production device for engineering measurement control points. It is simple and convenient to make, quick to install, protects the integrity of the building, and makes full use of the mechanical principles. The frame structure made by the clever use of action and reaction force. The specific implementation steps may be adjusted according to the actual situation and measurement tasks. Therefore, in actual operation, it should be flexibly adjusted according to the specific situation and follow the relevant measurement specifications and standards.

[0052] The above-described embodiments are merely descriptions of preferred embodiments of the present invention and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field shall fall within the protection scope of the claims of the present invention.

Claims

1. A portable device for ultra-long distance engineering survey control points, characterized in that: It includes a welding frame, a top support rod, a forced centering disk, a prism, a light strip power cord, a customized target board, and an LED light strip. The top support rod is welded at the top of the welding frame. The center of the top support rod is installed and fixed with a forced centering disk. The forced centering disk serves as the forced centering point for setting up the total station and the prism. The LED light strip is pasted at the center of the customized target board. The light strip power cord is connected to a power bank to light up the LED light strip, and the total station is aimed at the LED light strip to complete the orientation.

2. The portable device for ultra-long distance engineering survey control point according to claim 1 is characterized in that: The welded frame is made of angle iron, and its size is determined by parameter size data obtained through on-site survey.

3. The portable device for ultra-long distance engineering survey control point according to claim 1 is characterized in that: A reserved hole for installing a forced centering plate is arranged at the center of the top support rod, which is used for installing and fixing the forced centering plate.

4. The portable device for ultra-long distance engineering survey control point according to claim 1 is characterized in that: An intermediate support rod is installed in the middle of the welding frame to bear pressure and tension of the welding frame, making the welding frame structure more stable when subjected to stress.

5. The portable device for ultra-long distance engineering survey control point according to claim 1 is characterized in that: Fixing nuts are welded at the four corner points at the bottom of the welding frame, screw rods are screwed into the nuts, and gaskets are welded on the top of the screw rods; the screw rods are perpendicular to the outside of the wall and are used to fix the welding frame.

6. The portable device for ultra-long distance engineering survey control point according to claim 1 is characterized in that: The forced centering plate is fixed at the top support rod position with nuts and washers.

7. The portable device for ultra-long distance engineering survey control point according to claim 1 is characterized by: Customized target plates are used when the original targets cannot meet the measurement requirements. They are replaced with customized target plates so that they can be easily found and effectively identified during long-distance observation and orientation.

8. A method for manufacturing a portable device for ultra-long distance engineering survey control points according to any one of claims 1 to 7, characterized in that: The specific steps are as follows: Step 1: Survey and select the site, obtain the parameter size data of the welding frame, the width and height of the parapet wall at the top of the building, and the size of the welding frame required, determine the site location, and start making the frame; Step 2: After the welding of the welding frame is completed, select and make the top support rod, which is used to support the forced centering plate and the measuring instrument. The center position of the top support rod is reserved with a hole for installing the forced centering plate, and the top support rod is welded to the middle position of the top of the manufactured frame; Step 3: Weld four nuts to the four corner points at the bottom of the frame, screw the screw rods into the four nut positions, and then weld the washers to the screw ends of the four screw rods. The direction of the nuts is facing the wall. The screw rods pass through the nuts. The washers are welded to the top of the screw rods to increase the force-bearing area between the screw rods and the wall and protect the wall surface. The screw rods are perpendicular to the outside of the wall. Tighten the screw rods with a wrench so that the top of the screw rods is against the wall to tighten the force to fix the welded frame. Step 4: After the welding frame is fixed, install the forced centering plate and fix it to the top support rod position with nuts and washers as the forced centering point for setting up the total station and prism; Step 5: When the original target cannot meet the measurement requirements, replace it with a customized target plate according to the bottom of the rearview prism and the matching size of the prism, so that it is easier to find the target during long-distance rearview orientation. The LED light strip is pasted on the center of the customized target. The customized target is illuminated by the power cord of the light strip. The total station only needs to aim at the light strip to complete the orientation.