Intelligent prediction system for gas overrun of coal roadway driving face and prediction method thereof

By intelligently analyzing the low-gas flow monitoring data of extraction drilling holes and ground stress monitoring data, an intelligent prediction system was established, and the problem of the inability of the existing technology to achieve accurate early warning of gas disasters was achieved, real-time early warning of the risk of gas exceeding the limit of coal mine excavation working faces, ensuring the production safety of the mine.

CN119531949AActive Publication Date: 2025-02-28CHINA UNIV OF MINING & TECH
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411607744.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-12
Publication Date
2025-02-28
Estimated Expiration
2044-11-12

AI Technical Summary

Technical Problem

The existing gas concentration monitoring equipment cannot achieve accurate early warning of gas disasters, and there are problems such as single measurement parameters, inaccurate measurements, and untimely responses, making it difficult to effectively prevent gas exceeding the limit of the coal tunnel excavation surface.

Method used

By intelligently analyzing the high-precision low-gas flow monitoring data of extraction drilling holes and ground stress monitoring data, an intelligent prediction system is established to achieve non-contact continuous intelligent early warning of the risk of gas exceeding the limit of coal mining boring working faces.

Benefits of technology

In-depth excavation of mine gas monitoring data and ground stress while drilling monitoring data is realized, providing accurate measurement of single holes of gas extraction drilling and real-time monitoring and analysis of ground stress, ensuring real-time early warning of gas exceeding the limit of excavation tunnels, effectively ensuring the production safety of mine.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119531949A_ABST
    Figure CN119531949A_ABST
Patent Text Reader

Abstract

The invention relates to an intelligent prediction system and method for gas overrun of a coal roadway driving face. The intelligent prediction system comprises a data acquisition system (single-hole gas accurate metering and crustal stress measurement while drilling), a gas concentration analysis module, a crustal stress analysis module and a gas overrun early warning module. The method comprises the following steps: acquiring gas concentration and while-drilling ground stress data of a coal roadway driving working face in real time, extracting a gas monitoring value Mt at the current moment and gas monitoring data at time periods T1 and T2 before the current moment, and extracting coal seam roof rock stratum ground stress while-drilling monitoring data; calculating gas monitoring indexes Nt and Pt; calculating crustal stress monitoring indexes; when the index Nt is larger than a threshold value N0, gas overrun short-term early warning is carried out; and when the gas monitoring data Mt is greater than a threshold value M0 or the ground stress monitoring data Z is greater than a threshold value alpha0, carrying out emergency early warning on gas overrun. Dynamic intelligent early warning of gas overrun of the coal roadway driving face is achieved, and safe production of a coal mine is effectively guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of gas disaster prediction, and in particular to an intelligent prediction system and a prediction method for gas over-limit in a coal tunnel excavation working face. Background Art

[0002] With the long-term large-scale development of coal resources, deep mining with a depth of more than 800m has become the new normal for coal resource development. Affected by factors such as burial depth, high ground stress, and high ground temperature, deep coal mining faces a series of problems such as increased gas outburst, increased gas pressure, and sudden abnormal outburst of local gas, which directly lead to the increased threat of gas disasters in mines. Coal mine gas outburst accidents mainly occur at the coal tunnel excavation working face. Coal mine gas overlimit is an abnormal phenomenon in which the gas concentration in the underground working environment of coal mines exceeds the prescribed safety limit. Gas overlimit is prone to cause catastrophic accidents such as coal and gas outburst and gas explosion. Therefore, avoiding underground gas accumulation or gas overlimit is a key link in preventing and controlling coal and gas outburst and gas explosion, and it is also a necessary means to provide workers with a good working environment. In order to prevent such accidents, coal mines are generally equipped with safety monitoring systems to realize online monitoring of environmental gas concentration in key areas underground, as well as automatic alarm after gas overlimit.

[0003] The prevention and control of gas over-limit is a key link in the prevention and control of gas disasters in coal mines. However, there are many factors affecting gas disasters, the causes are complex, and they are prone to forming coupled disasters. The existing gas concentration monitoring equipment and means cannot achieve accurate early warning of gas disasters, and there are problems such as single measurement parameters, inaccurate measurements, and untimely responses. Therefore, there is an urgent need for a method to intelligently predict gas over-limit in working faces by combining various gas monitoring data. Summary of the invention

[0004] The purpose of the present invention is to overcome the above-mentioned shortcomings and provide an intelligent prediction system and prediction method for gas over-limit in coal mine excavation working faces. Through intelligent analysis of high-precision low gas flow monitoring data of extraction boreholes and ground stress drilling monitoring data, non-contact continuous intelligent early warning of the risk of gas over-limit in coal mine excavation working faces can be achieved, which is conducive to the advance prevention and control of coal mine gas accidents.

[0005] The object of the present invention is achieved in that: An intelligent prediction system for gas over-limit in coal tunnel excavation working face, comprising a data acquisition module, a gas concentration analysis module, a ground stress analysis module and a gas over-limit early warning module, wherein the data acquisition module collects single-hole precise metering data of gas extraction drilling and ground stress while drilling measurement data during the working face excavation process; the gas concentration analysis module and the ground stress analysis module perform corresponding fitting analysis on the collected single-hole precise metering data of gas extraction drilling and ground stress while drilling monitoring data to obtain gas and ground stress early warning indicators; the gas over-limit early warning module collaboratively warns of gas over-limit accidents during the excavation process according to the fitting results; The data acquisition module is used to collect monitoring data and provide early warning basic data for other modules; the data acquisition module mainly includes a single-hole gas precision meter and a drilling ground stress measuring instrument, and is connected to the corresponding analysis module through a wireless sensor; The drilling rig is connected to a gas over-limit warning module, the gas over-limit warning module is respectively connected to a ground stress analysis module and a gas concentration analysis module, the ground stress analysis module is connected to each ground stress measuring instrument while drilling, and the gas concentration analysis module is connected to each single-hole gas precision meter, thereby obtaining gas single-hole precision metering data and ground stress measurement data while drilling in real time while extracting gas; The pre-extraction tunnel is a high tunnel or a bottom tunnel. A drilling rig is used in the drilling site of the pre-extraction tunnel to construct through-layer holes in the heading tunnel arranged in the coal seam. All through-layer holes within the range of 3 drilling sites ahead of the current heading head are installed with single-hole gas precision meters and drilling stress measuring instruments.

[0006] Furthermore, the gas concentration analysis module is used to analyze the changes in the gas concentration characteristics of the tunneling tunnel in real time, and predict the gas concentration sequence of the tunneling tunnel for a period of time in the future, to obtain the real-time change curve of the ultra-low gas concentration, the predicted curve of the gas concentration change and the maximum value of the gas concentration that may appear in the future, and obtain the prediction index of the gas concentration; The geostress analysis module is used to analyze the changes in the geostress of hard and soft rocks, and calculate the in-situ geostress of soft and hard rocks by combining the output energy of the drill rig, the amount of drill cuttings and the particle size distribution of drill cuttings during the drilling process, so as to obtain the in-situ geostress change curve and the prediction curve as well as the maximum value of the future geostress, and obtain the prediction index of the geostress while drilling; The gas over-limit early warning module identifies the gas over-limit risk based on the gas concentration analysis module and the ground stress analysis module, and provides an early warning result of the gas over-limit risk.

[0007] Furthermore, the through-layer drilling holes are arranged in the entire excavation tunnel and the tunnel to be excavated, including the area within 15 m outside the contour lines of the two tunnels of the excavation tunnel and the tunnel to be excavated.

[0008] Furthermore, the spacing between the through-layer drill holes is 2R, where R is the drilling extraction radius.

[0009] Furthermore, a drilling site is arranged every 4 to 6 rows of through-layer boreholes, and the distance between each drilling site does not exceed 10 m.

[0010] Furthermore, the single-hole gas precision meter is arranged in the middle of the through-layer borehole, and the drilling stress measuring instrument is arranged on the coal seam.

[0011] An intelligent prediction method for gas over-limit in a coal tunnel excavation working face is based on the above-mentioned intelligent prediction system for gas over-limit in a coal tunnel excavation working face, and includes the following contents: Step 1: Drilling and collecting data; Drill holes through the coal seam in the pre-extraction tunnel to obtain the single-hole gas data and ground stress monitoring data of at least 3 drilling sites ahead of the current tunneling machine in the entire tunneling tunnel in real time, and collect drill cuttings; Step 2: extracting gas monitoring data and ground stress while drilling monitoring data; Extract the current gas monitoring value M t and Before the current time T 1. T 2. Gas monitoring data for the time period, extracting the in-situ stress monitoring data of the coal seam roof rock layer; Step 3: Calculate indicators N t ; Index N t is the average value of the gas monitoring data in the T1 period before the current moment, according to T 1 Gas monitoring data for a certain period of time, gas concentration analysis module calculation indicators N t ;index N t The calculation method is: ; Step 4: Calculate indicators P t and in situ stress α t ; according to T 2 Gas monitoring data for a certain period of time, gas concentration analysis module calculation indicators P t ,index P t Before the current time T 2The average value of gas monitoring data in a time period; indicator P t The calculation method is: ; in, y i for T 2. Gas monitoring data of the working face at different times within a time period; v is the working face advancement speed; l is the working face advancement distance; according to T 2 The in-situ ... α t and send the above index data to the ground for backup; in-situ ground stress α t The calculation method is: ; Step 5: Determine and warn; Gas short-term over-limit warning threshold N 0 Get the time before the current time T 1 Indicators for time periods N t ;Threshold M 0 before the current time T 2 Average value of gas monitoring data in the time period P t 200% of ;Threshold α 0The calculation method is: ; in, z i for T 2 In-situ ground stress monitoring data of rock formations in different boreholes over a period of time; v is the working face advancement speed; l is the working face advancement distance; When the indicator N t Greater than threshold N 0 When the gas over-limit warning module issues a short-term gas over-limit warning, M t Greater than threshold M At 0:00, an emergency warning for gas exceeding the limit is issued; When the ground stress monitoring data of the rock formation to be tested is greater than the threshold α0, and issue an emergency warning for gas exceeding the limit; after the warning is triggered, the gas electric interlocking operation is immediately implemented.

[0012] Furthermore, the time period T 1 Take 15~20 min; time period T 2 Determined according to the advancement speed of the working face.

[0013] Furthermore, in step 5, if N t Greater than N 0, a short-term warning of gas exceeding the limit for 10 to 15 minutes is carried out; this step is repeated continuously. If there are 2 or more consecutive short-term warnings of gas exceeding the limit, the gas electric interlocking operation is immediately implemented; if the current gas monitoring value is M t Greater than M 0, an emergency warning of gas exceeding the limit is issued, and the gas-electric interlock operation is immediately implemented to cut off the power supply of the tunnel boring machine and stop the tunnel boring machine.

[0014] Furthermore, the gas concentration range obtained by the single-hole gas precise metering data is 0~100%.

[0015] Compared with the prior art, the present invention has the following beneficial effects: The present invention realizes in-depth mining of mine gas monitoring data and ground stress while drilling monitoring data, and realizes single-hole precise measurement of gas extraction boreholes and ground stress while drilling monitoring based on the real-time monitoring and analysis of gas parameters and ground stress parameters ahead of at least 3 drilling sites in the working face of the tunnel (including the 15 m range outside the contour lines of the two tunnels). Based on the monitoring data of gas and ground stress, the present invention coordinates the monitoring of gas flow in the tunnel, realizes real-time early warning of gas exceeding the limit in the tunnel, and effectively ensures the production safety of the mine. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the structure of the prediction system of the present invention.

[0017] Figure 2 This is a schematic diagram of the layout inside the drilling site of Example 1 of the present invention.

[0018] Figure 3 This is a schematic plan view of the hole arrangement of Example 1 of the present invention.

[0019] Figure 4 It is the front view of the hole arrangement of embodiment 1 of the present invention.

[0020] Figure 5 It is a side view of the hole arrangement of embodiment 1 of the present invention.

[0021] Figure 6This is a schematic diagram of the internal layout of a drilling site according to Embodiment 2 of the present invention.

[0022] Figure 7 This is a schematic plan view of the hole arrangement of Example 2 of the present invention.

[0023] Figure 8 This is a front view of the hole arrangement of embodiment 2 of the present invention.

[0024] in: Excavation tunnel 1, drilling site 2, through-layer drilling 3, tunnel to be excavated 4, high-extraction tunnel 5, advance drilling site 6, coal seam 7, single-hole gas precision meter 8, while-drilling ground stress measuring instrument 9, directional drilling rig 10, ground stress analysis module 11, gas concentration analysis module 12, gas over-limit warning module 13, bottom extraction tunnel 14. DETAILED DESCRIPTION

[0025] In order to better understand the technical solution of the present invention, the following will be described in detail in conjunction with the relevant illustrations. It should be understood that the following specific embodiments are not intended to limit the specific implementation of the technical solution of the present invention, and are only implementations that can be adopted by the technical solution of the present invention. It should be noted that the description of the positional relationship of each component in this article, such as component A being located above component B, is based on the description of the relative positions of the components in the illustration, and is not intended to limit the actual positional relationship of the components. Example 1

[0026] See also Figure 1-Figure 5 , Figure 1 A structural schematic diagram of an intelligent prediction system for gas over-limit in coal tunnel excavation working face is drawn. As shown in the figure, an intelligent prediction system for gas over-limit in coal tunnel excavation working face of this embodiment 1 includes a data acquisition module, a gas concentration analysis module 12, a ground stress analysis module 11 and a gas over-limit warning module 13. The data acquisition module collects borehole gas parameter data (i.e., gas extraction drilling single hole precise metering data) and ground stress while drilling measurement data during the excavation of the working face; the gas concentration analysis module 12 and the ground stress analysis module 11 perform corresponding fitting analysis on the collected gas extraction drilling single hole precise metering data and ground stress while drilling monitoring data to obtain gas and ground stress warning indicators; the gas over-limit warning module 13 coordinates and warns of gas over-limit accidents during the excavation process according to the fitting results.

[0027] The data acquisition module is used to collect monitoring data and provide basic early warning data for other modules; the data acquisition module mainly includes a single-hole gas precision meter 8 and a drilling-while-drilling ground stress meter 9, and is connected to the corresponding analysis module through a wireless sensor.

[0028] The gas concentration analysis module 12 is mainly used to analyze the changes in the gas concentration characteristics of the excavation tunnel in real time, and predict the gas concentration sequence of the excavation tunnel in the future, to obtain the real-time change curve of the ultra-low gas concentration and the gas concentration change prediction curve and the maximum value of the gas concentration that may appear in the future, and to obtain the prediction index of the gas concentration; the gas concentration analysis module 12 can use the YZC6 gas extraction pipeline multi-parameter measuring instrument software (2023SR1201469) on the market.

[0029] The geostress analysis module 11 is mainly used to analyze the changes in the geostress of hard and soft rocks, and calculate the in-situ geostress of soft and hard rocks in combination with the output energy of the drill rig, the amount of drill cuttings and the particle size distribution of drill cuttings during the drilling process, to obtain the in-situ geostress change curve and the prediction curve as well as the maximum value of the future geostress, and obtain the prediction index of the geostress while drilling; the geostress analysis module 11 can adopt the YZC6 gas extraction pipeline multi-parameter measuring instrument software (2023SR1201469), and can also refer to a downhole geostress measurement system while drilling provided by Chinese patent CN202322197718.1.

[0030] The gas over-limit warning module 13 performs gas over-limit risk identification based on the gas concentration analysis module 12 and the ground stress analysis module 11 , and provides a warning result of the gas over-limit risk magnitude.

[0031] In this embodiment 1, high-extraction tunnel 5 is used for extraction drilling. A directional drill rig 10 is used in the drilling site 2 of the high-extraction tunnel 5 to construct a through-layer drill hole 3 in the driving tunnel 1 in the coal seam 7. The hole arrangement position is the entire driving tunnel 1 and the tunnel to be excavated 4, including the range of 15 m outside the contour lines of the two tunnels of the driving tunnel 1 and the tunnel to be excavated 4. The hole arrangement spacing is 2R, R is the drilling extraction radius, and R is 2.5 m in this embodiment 1.

[0032] A drilling site 2 is arranged for every 4 to 6 rows of through-layer boreholes 3, and the spacing between the drilling sites 2 is generally not more than 10 m. In this embodiment 1, one drilling site 2 is arranged for every 4 rows of through-layer boreholes 3; and a single-hole gas precision meter 8 and a drilling-while-drilling ground stress measuring instrument 9 are installed for all the through-layer boreholes 3 within the range of 3 drilling sites ahead of the current position of the tunneling machine; the single-hole gas precision meter 8 is arranged in the middle of the through-layer borehole 3, and the drilling-while-drilling ground stress measuring instrument 9 is arranged on the coal seam 7.

[0033] The directional drilling rig 10 is connected to a gas over-limit warning module 13, and the gas over-limit warning module 13 is respectively connected to a ground stress analysis module 11 and a gas concentration analysis module 12, the ground stress analysis module 11 is connected to each downhole ground stress measuring instrument 9, and the gas concentration analysis module 12 is connected to each single-hole gas precision meter 8, thereby obtaining gas single-hole precision metering data and ground stress downhole measurement data in real time while extracting gas.

[0034] The intelligent prediction method for gas over-limit in a coal tunnel excavation working face of the present invention is based on the intelligent prediction system for gas over-limit in a coal tunnel excavation working face described above, and includes a gas concentration early warning method and a ground stress measurement while drilling early warning method. The gas concentration early warning method includes the following contents: S1. Drill holes through the coal seam in the high-extraction tunnel to obtain real-time gas monitoring data within the coal tunnel excavation working face (including the 15 m range outside the two tunnel contours) and gas monitoring data of at least three advanced drilling sites 6; the advanced drilling site 6 is the drilling site ahead of the current tunneling machine; the gas concentration range of the single-hole gas precise measurement data is 0~100%; S2. Extract the current gas monitoring value M t Before the current time T 1 , T 2 Gas monitoring data for a certain period of time; The time period T 1 is 15~20min; time period T 2. Determined according to the advancing speed of the working face; S3. According to T Gas monitoring data for a period of time, gas concentration analysis module calculation indicators N t ; index N t is the average value of the gas monitoring data in the T1 period before the current moment, and the calculation method is: ; Gas short-term over-limit warning threshold N 0 Get the time before the current time T 1 Indicators for time periods N t If the indicator N t Greater than N 0, a short-term warning of gas over-limit is issued for 10 to 15 minutes; this step is repeated continuously. If there are two or more consecutive short-term warnings of gas over-limit, the gas electric interlock operation is immediately implemented; S4. According to T Gas monitoring data for 2 time periods, gas concentration analysis module calculates the calculation index P t ; index P t Before the current time T 2The average value of gas monitoring data in a time period is calculated as follows: ; in, y i for T 2. Gas monitoring data of the working face at different times within a time period; v is the working face advancement speed; l The working face advancement distance is generally 30~50 m; S5. When the indicator N t Greater than threshold N 0:00, a short-term warning of gas exceeding the limit is issued; when the gas monitoring value M t Greater than threshold M At 0:00, an emergency warning for gas exceeding the limit is issued; Threshold M 0 before the current time T 2 Average value of gas monitoring data in the time period P t 200%, that is, the average gas concentration is 25%, the threshold M 0 takes 50%, threshold M 0The calculation method is: ; like M t Greater than M 0, an emergency warning of gas over-limit is issued and the gas electric interlocking operation is immediately implemented; S6. As the excavation working face advances, repeat steps 1 to 5 to provide dynamic real-time warnings for excessive gas in the working face.

[0035] In this embodiment 1, T 1 Take 15min, T 2 Take 2 days and calculate N t =18.8%, P t =20.15%, M t =16.2%, M 0=40.3%.

[0036] The early warning of geostress measurement while drilling includes the following contents: S1. Drill holes in the coal seam high-drawn tunnel to obtain real-time ground stress monitoring data Z in the tunnel to be excavated and the tunnel to be excavated (including the 15 m range outside the contour lines of the two tunnels) and at least 3 drilling sites ahead. Extract the stress data before the current time. T 1. T2. Monitoring the in-situ stress of the coal seam roof strata during the time period while drilling, and collecting drill cuttings; T 1 is 15~20 min; time period T 2. Determined according to the advancing speed of the working face; S2, as the tunneling progresses, step S2 is continuously repeated; according to T 2 The in-situ ... α t and send the above indicators to the ground for backup; When the rock formation stress monitoring data Z to be measured is greater than the threshold α 0, carry out emergency warning of gas over-limit, and immediately implement gas electric interlocking operation after the warning is triggered; α t and α 0The calculation method is: ; in, z i for T 2 Rock formation in-situ stress monitoring data of different boreholes within a time period; v is the working face advancement speed; l The distance of the working face advancement.

[0037] In this embodiment 1, it is calculated that: α t =11.1 MPa, α 0=22.2 MPa.

[0038] During the excavation of the working face, the extraction drilling holes are arranged in the entire excavation tunnel 1 and the tunnel to be excavated 4 (including the 15 m range outside the contour lines of the two tunnels). The installation position of the intelligent early warning system for excessive gas limit in this embodiment is all the through-layer drill holes within the range of 3 drilling sites ahead of the current position of the excavation head. When the tunneling machine passes the location of the drilling site, the comprehensive intelligent early warning and analysis system for excessive gas limit can be removed and moved to the drilling site in front, so that the comprehensive intelligent early warning and analysis system for excessive gas limit always covers all the through-layer drill holes within the range of 3 drilling sites ahead of the current location of the tunneling machine.

[0039] When constructing multiple high-extraction tunnels and drilling through layers to measure ground stress while drilling, the spacing between the boreholes should be large enough to avoid the construction boreholes affecting other adjacent boreholes. ξ Conduct experimental testing and verification independently. Example 2

[0040] See also Figure 6-Figure 8 , Figure 6 A layout diagram of the inside of a drilling site of an intelligent prediction system for gas over-limit in a coal tunnel excavation working face is drawn. As shown in the figure, the intelligent prediction system for gas over-limit in a coal tunnel excavation working face of this embodiment 2 is different from that of embodiment 1 in that: In this embodiment 2, a bottom extraction tunnel 14 is used for extraction drilling. A directional drill rig 10 is used in the drilling site 2 of the bottom extraction tunnel 14 to construct a through-layer drill hole 3 in the driving tunnel 1 arranged in the coal seam 7. The hole layout position is the entire driving tunnel 1 and the tunnel to be excavated 4 (including the range of 15 m outside the contour lines of the two tunnels).

[0041] Working principle: The present invention provides an intelligent prediction system and method for gas over-limit in a coal tunneling working face. The system combines single-hole gas metering data with drilling-based ground stress data to collaboratively warn of gas over-limit accidents in the coal tunneling working face. Through-layer drilling is carried out from a high-extraction tunnel or a bottom-extraction tunnel (gas pre-extraction tunnel) to the coal tunneling working face, and drilling is arranged within 15 m on both sides of the tunneling tunnel and at least 3 drilling sites ahead of the tunneling tunnel. Single-hole gas data and drilling-based ground stress data of the coal tunneling working face are obtained in real time, and the gas over-limit threshold is fit-analyzed by a gas concentration analysis module and a ground stress analysis module and compared with the real-time monitoring data, and then the gas over-limit warning module is used to collaboratively warn of gas over-limit accidents in the coal tunneling working face.

[0042] The above are only specific application examples of the present invention and do not constitute any limitation on the protection scope of the present invention. Any technical solution formed by equivalent transformation or equivalent replacement shall fall within the protection scope of the present invention.

Claims

1. An intelligent prediction system for gas over-limit in coal tunneling working face, characterized by: It comprises a data acquisition module, a gas concentration analysis module (12), a ground stress analysis module (11) and a gas over-limit early warning module (13). The data acquisition module collects precise metering data of a single gas extraction drilling hole and ground stress while drilling measurement data during the excavation of the working face; the gas concentration analysis module (12) and the ground stress analysis module (11) perform corresponding fitting analysis on the collected precise metering data of a single gas extraction drilling hole and ground stress while drilling monitoring data to obtain gas and ground stress early warning indicators; the gas over-limit early warning module (13) coordinates early warning of gas over-limit accidents during the excavation process based on the fitting results; The data acquisition module is used to collect monitoring data and provide early warning basic data for other modules; the data acquisition module mainly includes a single-hole gas precision meter (8) and a drilling-while-drilling ground stress measuring instrument (9), and is connected to the corresponding analysis module through a wireless sensor; The drilling rig (10) is connected to a gas over-limit warning module (13), the gas over-limit warning module (13) is respectively connected to a ground stress analysis module (11) and a gas concentration analysis module (12), the ground stress analysis module (11) is connected to each while-drilling ground stress measuring instrument (9), and the gas concentration analysis module (12) is connected to each single-hole gas precision meter (8); The pre-extraction tunnel is a high tunnel or a bottom tunnel. A drilling rig (10) is used in the drilling site (2) of the pre-extraction tunnel to construct a through-layer borehole (3) in the heading tunnel (1) arranged in the coal seam (7). All through-layer boreholes (3) within the range of the drilling site 3 ahead of the current heading head position are installed with a single-hole gas precision meter (8) and a drilling-while-drilling ground stress measuring instrument (9).

2. The intelligent prediction system for gas over-limit in coal tunneling working face according to claim 1 is characterized by: The gas concentration analysis module (12) is used to analyze the change of the gas concentration characteristics of the tunneling tunnel in real time, and predict the gas concentration sequence of the tunneling tunnel in the future, to obtain the real-time change curve of the ultra-low gas concentration, the gas concentration change prediction curve and the maximum value of the gas concentration that may appear in the future, and to obtain the prediction index of the gas concentration; The geostress analysis module (11) is used to analyze the change of geostress in hard and soft rocks, and calculate the in-situ geostress of soft and hard rocks by combining the output energy of the drilling rig, the amount of drill cuttings and the particle size distribution of drill cuttings during the drilling process, so as to obtain the in-situ geostress change curve and the prediction curve as well as the maximum value of the future geostress, and obtain the prediction index of geostress while drilling; The gas over-limit early warning module (13) performs gas over-limit risk identification based on the gas concentration analysis module (12) and the ground stress analysis module (11), and provides an early warning result of the magnitude of the gas over-limit risk.

3. The intelligent prediction system for gas over-limit in coal tunneling working face according to claim 1 is characterized by: The through-layer drill holes (3) are arranged in the entire excavation tunnel (1) and the tunnel to be excavated (4), including the area within 15 m outside the contour lines of the two tunnels of the excavation tunnel (1) and the tunnel to be excavated (4).

4. The intelligent prediction system for gas over-limit in coal tunneling working face according to claim 3 is characterized by: The spacing between the through-layer drill holes (3) is 2R, where R is the drilling hole extraction radius.

5. The intelligent prediction system for gas over-limit in coal tunneling working face according to claim 3 is characterized by: A drilling site (2) is arranged every 4 to 6 rows of through-layer boreholes (3), and the distance between each drilling site (2) does not exceed 10 m.

6. The intelligent prediction system for gas over-limit in coal tunneling working face according to claim 3 is characterized by: The single-hole gas precision meter (8) is arranged in the middle of the through-layer borehole (3), and the while-drilling ground stress measuring instrument (9) is arranged on the coal seam (7).

7. An intelligent prediction method for gas over-limit in coal roadway excavation working face, based on the intelligent prediction system for gas over-limit in coal roadway excavation working face according to claim 1, characterized in that: Includes the following: Step 1: Drilling and collecting data; Drill holes through the coal seam in the pre-extraction tunnel to obtain the single-hole gas data and ground stress monitoring data of at least 3 drilling sites ahead of the current tunneling machine in the entire tunneling tunnel in real time, and collect drill cuttings; Step 2: extracting gas monitoring data and ground stress while drilling monitoring data; Extract the current gas monitoring value M t and Before the current time T 1. T 2. Gas monitoring data for the time period, extracting the in-situ stress monitoring data of the coal seam roof rock layer; Step 3: Calculate indicators N t ; according to T 1 Gas monitoring data for a certain period of time, gas concentration analysis module calculation indicators N t ; Index N t is the average value of the gas monitoring data in the T1 period before the current moment, Index N t The calculation method is: ; Step 4: Calculate indicators P t and in situ stress α t ; according to T 2 Gas monitoring data for a certain period of time, gas concentration analysis module calculation indicators P t ,index P t Before the current time T 2 Average value of gas monitoring data in a certain period of time, index P t The calculation method is: ; in, y i for T 2. Gas monitoring data of the working face at different times within a time period; v is the working face advancement speed; l is the working face advancement distance; according to T 2 The in-situ ... α t and send the above index data to the ground for backup; in-situ ground stress α t The calculation method is: ; Step 5: Determine and warn; Gas short-term over-limit warning threshold N 0 Get the time before the current time T 1 Indicators for time periods N t ;Threshold M 0 before the current time T 2 Average value of gas monitoring data in the time period P t 200% of ;Threshold α 0The calculation method is: ; in, z i for T 2 In-situ ground stress monitoring data of rock formations in different boreholes over a period of time; v is the working face advancement speed; l is the working face advancement distance; When the indicator N t Greater than threshold N 0 When the gas over-limit warning module issues a short-term gas over-limit warning, M t Greater than threshold M At 0:00, an emergency warning for gas exceeding the limit is issued; When the rock formation stress monitoring data Z to be measured is greater than the threshold α 0, and issue an emergency warning for gas exceeding the limit; after the warning is triggered, the gas electric interlocking operation is immediately implemented.

8. The intelligent prediction method for gas over-limit in coal roadway excavation working face according to claim 7 is characterized by: Time period T 1 Take 15~20 min; time period T 2 Determined according to the advancement speed of the working face.

9. The intelligent prediction method for gas over-limit in coal roadway excavation working face according to claim 7 is characterized by: In step 5, if the indicator N t Greater than N 0, a short-term warning of gas exceeding the limit for 10 to 15 minutes is carried out; this step is repeated continuously. If there are 2 or more consecutive short-term warnings of gas exceeding the limit, the gas electric interlocking operation is immediately implemented; if the current gas monitoring value is M t Greater than M 0, an emergency warning of gas exceeding the limit is issued and the gas electric interlock operation is immediately implemented.

10. The intelligent prediction method for gas over-limit in coal roadway excavation working face according to claim 7, characterized in that: The gas concentration range of the single-hole gas precise metering data is 0~100%.

Citation Information

Patent Citations

  • Forecasting method of coal and gas outburst

    CN102926810A

  • Method for analyzing coal and gas outburst risk in real time

    CN102979579A

  • Outburst elimination method for deep high-gas high-geostress multi-structure coal roadway

    CN110107343A

  • Gas extraction method

    CN114483163A

  • Multi-information coupling prediction method of coal and gas outburst danger

    US20140019047A1