Rail transit station construction progress management method
By setting the total progress plan and the monthly progress plan, and calculating the theoretical and actual construction progress, the authenticity and accuracy of construction progress management in the existing technology are solved, and effective progress risk warning and management are achieved.
Patent Information
- Application Number
- CN202411676316.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-21
- Publication Date
- 2025-04-15
AI Technical Summary
The construction progress management methods in the prior art cannot guarantee the authenticity and accuracy of the construction progress, and there is a lack of an effective progress risk warning plan.
By setting the total progress plan and the monthly progress plan, the material entry data is automatically accumulated to calculate the theoretical construction progress, and the actual construction progress is obtained based on the on-site construction situation, and the progress matching, pre-position and deviation warning are formed through comparison.
Effectively control construction progress, prevent major deviations, and improve the accuracy and reliability of construction progress management.
Smart Images

Figure CN119831129A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction progress management, and in particular to a method for managing the construction progress of a rail transit station. Background Art
[0002] Urban rail transit projects have the characteristics of large construction scale, long construction period, complex surrounding environment, and multiple disciplines involved. There are a large amount of engineering data with a long time span, complex and diverse data, complex relationship between engineering construction and the surrounding geological environment and existing structures (buildings), and inconsistent interface information between various disciplines. As a result, the information in the construction and operation and maintenance stages of urban rail transit projects cannot form a unified data architecture, and data resources cannot be associated and shared, which affects the progress and efficiency of engineering construction, and in serious cases, it will also affect the quality and safety of engineering construction.
[0003] Construction progress is the main dimension of on-site management in the construction industry. The quality, safety, technology, cost, materials, machinery, and contracts of construction are all related to the construction progress. The current mainstream progress management method mainly measures the construction progress by manually observing whether key nodes are completed or not. The construction progress is vague and difficult to quantify, and cannot be used for computer calculations, and the authenticity and accuracy of the construction progress cannot be guaranteed. Moreover, there are often no signs before the progress risk explodes, and it can only be predicted through the management experience of managers, and there is a lack of effective progress risk early warning plans. Summary of the invention
[0004] The present invention proposes a rail transit station construction progress management method, which solves the problems that the progress management method in the prior art cannot guarantee the authenticity and accuracy of the construction progress and lacks an effective progress risk early warning solution.
[0005] The technical solution of the present invention is achieved in this way:
[0006] A first aspect of the present invention provides a rail transit station construction progress management method, comprising the following steps:
[0007] Enter the overall schedule according to the project data;
[0008] Break down the overall schedule into monthly schedules;
[0009] Calculate theoretical construction progress and actual construction progress based on the overall progress plan, monthly progress plan, material delivery status, and on-site construction status;
[0010] Analyze whether the theoretical construction progress matches the actual construction progress. If not, issue an early warning for progress deviation. Finally, generate a progress analysis report based on the matching results.
[0011] Specifically, after the overall schedule is broken down into monthly schedules, the monthly schedules need to be approved. If the approval is not passed, the monthly schedules need to be broken down again.
[0012] Specifically, the theoretical construction progress is equal to the ratio of the total amount of materials entering the site to the total amount of materials, and the total amount of materials entering the site is the cumulative value of the monthly amount of materials entering the site;
[0013] The actual construction progress is the ratio of the cumulative construction progress to the total construction progress, and the cumulative construction progress is the accumulated value of the monthly construction progress.
[0014] Specifically, if the difference between the theoretical construction progress and the actual construction progress is within a preset range, the theoretical construction progress matches the actual construction progress.
[0015] Specifically, the progress analysis report includes:
[0016] Basic information, including: analysis form number, analysis date, unit, applicant, bidding section, project manager, and analysis month;
[0017] Theoretical construction progress analysis, including: monthly planned material delivery, monthly actual material delivery, monthly material delivery rate, total material delivery, cumulative total material delivery, and cumulative material delivery rate;
[0018] Actual construction progress analysis, including: monthly construction progress plan, monthly actual construction progress, monthly construction progress completion rate, total construction progress plan, cumulative construction progress, and cumulative construction progress completion rate;
[0019] The progress analysis results include: actual construction progress, the difference between theoretical construction progress and actual construction progress, whether the on-site progress matches, and whether warnings are issued for construction progress deviations.
[0020] Specifically, analyze the factors affecting the construction progress based on the progress analysis report, and propose construction progress rectification measures.
[0021] A second aspect of the present invention provides an electronic device, including a memory and a processor, wherein the memory stores a computer program that can be run on the processor, and the processor implements the steps of the progress management method when executing the computer program.
[0022] A third aspect of the present invention provides a computer-readable storage medium, wherein the storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the progress management method are implemented.
[0023] Compared with the prior art, the present invention has the following beneficial effects:
[0024] The present invention sets a total progress plan and a monthly progress plan, automatically accumulates the material delivery data accumulated each month, and calculates the theoretical construction progress; then the actual construction progress is obtained according to the completion status of the on-site work surface, and finally, through comparison, progress matching, progress advancement and progress deviation warning are formed. By comparing the theoretical construction progress with the actual construction progress, the construction progress can be effectively controlled to prevent major deviations. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0026] Figure 1 The present invention is a flow chart of a method for managing the construction progress of a rail transit station. DETAILED DESCRIPTION
[0027] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0028] Reference Figure 1 According to a first aspect of an embodiment of the present invention, a method for managing the construction progress of a rail transit station is provided, comprising the following steps:
[0029] Enter the overall schedule according to the project data;
[0030] Break down the overall schedule into monthly schedules;
[0031] Calculate theoretical construction progress and actual construction progress based on the overall progress plan, monthly progress plan, material delivery status, and on-site construction status;
[0032] Analyze whether the theoretical construction progress matches the actual construction progress. If not, issue an early warning for progress deviation. Finally, generate a progress analysis report based on the matching results.
[0033] Specifically, the project data refers to a data set related to the task items included in the construction project. A task item set may include multiple task items. Taking a construction project of a building engineering as an example, its task item set may include multiple task items such as building a foundation, building a main structure (for example, walls, columns, ceilings, etc.), building an elevator, building a drainage structure, building an electrical structure, and decoration. The task item set can be decomposed into a monthly progress plan according to the construction sequence and theoretical time consumption of each task item, so as to facilitate the subsequent accumulation of the monthly progress to calculate whether the actual construction progress matches the theoretical construction progress.
[0034] Specifically, after the overall schedule is broken down into monthly schedules, the monthly schedules need to be approved. If the approval is not passed, the monthly schedules need to be broken down again to ensure the rationality and feasibility of the monthly schedules.
[0035] Specifically, the theoretical construction progress is equal to the ratio of the total amount of materials entering the site to the total amount of materials (i.e., the cumulative material entry rate), and the cumulative total amount of materials entering the site is the cumulative value of the monthly material entry amount;
[0036] The actual construction progress is the ratio of the cumulative construction progress to the total construction progress (i.e. the cumulative construction progress completion rate), and the cumulative construction progress is the accumulated value of the monthly construction progress.
[0037] Specifically, if the difference between the theoretical construction progress and the actual construction progress is within a preset range, the theoretical construction progress matches the actual construction progress.
[0038] Specifically, the progress analysis report includes:
[0039] Basic information, including: analysis form number, analysis date, unit, applicant, bidding section, project manager, and analysis month;
[0040] Theoretical construction progress analysis, including: monthly planned material delivery, monthly actual material delivery, monthly material delivery rate, total material delivery, cumulative total material delivery, and cumulative material delivery rate;
[0041] Actual construction progress analysis, including: monthly construction progress plan, monthly actual construction progress, monthly construction progress completion rate, total construction progress plan, cumulative construction progress, and cumulative construction progress completion rate;
[0042] The progress analysis results include: actual construction progress, the difference between theoretical construction progress and actual construction progress, whether the on-site progress matches, and whether warnings are issued for construction progress deviations.
[0043] The progress analysis report is shown in Table 1 below:
[0044] Table 1 Progress analysis report
[0045]
[0046] Specifically, the factors affecting the construction progress are analyzed according to the progress analysis report, and rectification measures for the construction progress are proposed; if the actual construction progress is ahead of the theoretical construction progress or the difference is within the preset range, no warning will be issued and the on-site progress will be matched; if the actual construction progress lags behind the theoretical construction progress and the deviation value exceeds the preset range, a warning will be issued and the on-site progress will not match. It is necessary to further analyze the factors affecting the construction progress (such as total resources, work surface or other factors), and propose rectification measures for the construction progress.
[0047] A second aspect of an embodiment of the present invention provides an electronic device, including a memory and a processor, wherein the memory stores a computer program that can be run on the processor, and the processor implements the steps of the progress management method when executing the computer program.
[0048] A third aspect of an embodiment of the present invention provides a computer-readable storage medium, wherein the storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the progress management method are implemented.
[0049] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0050] The present invention is described with reference to flowcharts and / or block diagrams of methods, platforms (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0051] This specification may be described in the general context of computer-executable instructions executed by a computer, such as program modules. Generally, program modules include routines, programs, objects, components, data structures, etc. that perform specific tasks or implement specific abstract data types. This specification may also be practiced in distributed computing environments where tasks are performed by remote processing devices connected through a communication network. In a distributed computing environment, program modules may be located in local and remote computer storage media, including storage devices.
[0052] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0053] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 In a typical configuration, a computer includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.
[0054] The memory may include non-permanent storage in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.
[0055] Computer-readable media include permanent and non-permanent, removable and non-removable media that can be used to store information by any method or technology. Information can be computer-readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disc read-only memory (CD-ROM), digital versatile disc (DVD) or other optical storage, magnetic cassettes, disk storage, quantum memory, graphene-based storage media or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer-readable media does not include temporary computer-readable media (transitory media), such as modulated data signals and carrier waves.
[0056] In the description of this specification, the description with reference to the terms "one embodiment", "certain embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials, or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0057] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the technical solutions of the embodiments of the present invention.
Claims
1. A rail transit station construction progress management method, characterized in that: The following steps are involved: Enter the overall schedule according to the project data; Break down the overall schedule into monthly schedules; Calculate theoretical construction progress and actual construction progress based on the overall progress plan, monthly progress plan, material delivery status, and on-site construction status; Analyze whether the theoretical construction progress matches the actual construction progress. If not, issue an early warning for progress deviation. Finally, generate a progress analysis report based on the matching results.
2. A rail transit station construction progress management method as claimed in claim 1, characterized in that: After the overall schedule is broken down into monthly schedules, the monthly schedules need to be approved. If the approval is not passed, the monthly schedules need to be broken down again.
3. A rail transit station construction progress management method as claimed in claim 1, characterized in that: The theoretical construction progress is equal to the ratio of the total amount of materials entering the site to the total amount of materials, and the total amount of materials entering the site is the cumulative value of the monthly amount of materials entering the site; The actual construction progress is the ratio of the cumulative construction progress to the total construction progress, and the cumulative construction progress is the accumulated value of the monthly construction progress.
4. A rail transit station construction progress management method as claimed in claim 1, characterized in that: If the difference between the theoretical construction progress and the actual construction progress is within a preset range, the theoretical construction progress matches the actual construction progress.
5. A rail transit station construction progress management method as claimed in claim 1, characterized in that: The progress analysis report includes: Basic information, including: analysis form number, analysis date, unit, applicant, bidding section, project manager, and analysis month; Theoretical construction progress analysis, including: monthly planned material delivery, monthly actual material delivery, monthly material delivery rate, total material delivery, cumulative total material delivery, and cumulative material delivery rate; Actual construction progress analysis, including: monthly construction progress plan, monthly actual construction progress, monthly construction progress completion rate, total construction progress plan, cumulative construction progress, and cumulative construction progress completion rate; The progress analysis results include: actual construction progress, the difference between theoretical construction progress and actual construction progress, whether the on-site progress matches, and whether warnings are issued for construction progress deviations.
6. A rail transit station construction progress management method as claimed in claim 1, characterized in that: Analyze the factors affecting the construction progress based on the progress analysis report, and propose measures to correct the construction progress.
7. An electronic device comprising a memory and a processor, wherein the memory stores a computer program that can be run on the processor, characterized in that: When the processor executes the computer program, the steps of the progress management method according to any one of claims 1 to 6 are implemented.
8. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the progress management method according to any one of claims 1 to 6 are implemented.