Box culvert settlement joint structure
By using the chute and push-pull rod mechanism in the box culvert settlement joint structure, the waterproof plate is flexibly displaced, and combined with the use of double-sided adhesive paste and polyurethane sealant, the problem of waterproof plate hindering maintenance and poor sealing effect is solved, and the waterproof plate is realized Efficient maintenance and sealing effects reduce costs.
Patent Information
- Application Number
- CN202323451924.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-18
- Publication Date
- 2025-01-10
- Estimated Expiration
- 2033-12-18
AI Technical Summary
In the existing box culvert settlement joint structure, fixed waterproof steel plates may hinder the work efficiency of staff during maintenance, inspection or emergency repair, and the sealing effect is not ideal, resulting in water penetration problems.
A box culvert settlement joint structure was designed, using chutes and push-pull rod mechanisms to allow the waterproof plate to move freely, and the flexible displacement of the waterproof plate is achieved through limiting components, balls and springs; at the same time, double-sided adhesive tape and polyurethane sealing are used The glue is sealed, and the double seal is combined with asphalt hemp floe and oil felt.
The free movement of the waterproof plate during maintenance is achieved, the working efficiency is improved, and the water penetration is effectively prevented through the double sealing layer, reducing cost consumption.
Smart Images

Figure CN222332778U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a box culvert settlement joint structure. Background Art
[0002] Settlement joints, seismic joints and expansion joints are generally referred to as deformation joints. Buildings often deform under the influence of external factors, resulting in cracks or even damage. Deformation joints are structural joints reserved for this situation. In related technologies, urban underground pipe corridors are generally composed of several box culverts, which are prefabricated box culverts. During the construction of box culverts, several box culverts are usually connected one by one by using a cylinder jacking method. During the connection of box culverts, a deformation joint will be reserved between two adjacent box culverts. Sealant is filled in the deformation joint to achieve a sealed connection between two adjacent box culverts.
[0003] A box culvert construction joint is disclosed in the announcement number CN218147883U, including a wall, at least one waterproof steel plate is installed in the wall, a pouring hole is opened at the joint of the wall, the pouring hole is connected to the joint, and the joint and the pouring hole are filled with resin material, the opening of the pouring hole is sealed and connected to the waterproof layer. In this application, a waterproof steel plate is added at the joint, but the fixed waterproof steel plate is not flexible enough, which may cause obstacles in certain maintenance, inspection or emergency repair situations, affecting the work efficiency of the staff to a certain extent. Utility Model Content
[0004] In order to make up for the above deficiencies, the utility model provides a box culvert settlement joint structure, which improves the problem that the waterproof baffle at the settlement joint structure may hinder the maintenance of workers during maintenance.
[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a box culvert settlement joint structure, including a first box body, a second box body is arranged on one side of the first box body, a slide groove is opened on the top of the first box body, a push-pull rod is slidably connected inside the first box body, one end of the push-pull rod is fixedly connected to a waterproof plate, a push-pull block is fixedly connected to the upper surface of the push-pull rod, the push-pull block is slidably connected to the inside of the slide groove, a cavity is opened inside the first box body, a spring is fixedly connected inside the first box body, the spring is arranged inside the cavity, one end of the spring is fixedly connected to a sliding column, a ball bearing is arranged on one side of the sliding column, and limiting components are arranged on both sides of the sliding column.
[0006] Through the above technical solution, the waterproof board can be moved freely when the staff is carrying out maintenance work, so as not to hinder the maintenance work of the staff.
[0007] As a further description of the above technical solution:
[0008] The limiting assembly comprises a limiting groove and a limiting block, and the limiting block is slidably connected inside the limiting groove.
[0009] Through the above technical solution, the movement trajectory of the limiting block will be constrained by the limiting groove.
[0010] As a further description of the above technical solution:
[0011] The limiting groove is arranged inside the first box body, and the limiting block is fixedly connected to the outer wall of the sliding column.
[0012] Through the above technical solution, the movement trajectory of the sliding column will be limited by the limit block.
[0013] As a further description of the above technical solution:
[0014] A groove is arranged between the first box body and the second box body.
[0015] Through the above technical solution, the reserved groove can be used to prevent the first box body and the second box body from deforming due to thermal expansion and contraction.
[0016] As a further description of the above technical solution:
[0017] A first sealing layer is arranged inside the groove, and a second sealing layer is arranged on the top of the first sealing layer.
[0018] Through the above technical solution, the first sealing layer and the second sealing layer are used together to allow the groove to be sealed for the first time.
[0019] As a further description of the above technical solution:
[0020] A double-sided adhesive tape is arranged between the first sealing layer and the second sealing layer. The first sealing layer is filled by injecting asphalt hemp, and the second sealing layer is filled by injecting oil felt.
[0021] Through the above technical solution, asphalt hemp can be prefabricated with double-sided adhesive before use, so as to speed up the work efficiency of the staff when filling the contents.
[0022] As a further description of the above technical solution:
[0023] A third sealing layer is arranged at the bottom of the first sealing layer.
[0024] Through the above technical solution, the third sealing layer can be sealed twice.
[0025] As a further description of the above technical solution:
[0026] The interior of the third sealing layer is filled with polyurethane sealant.
[0027] Through the above technical solution, polyurethane sealant has excellent adhesion and elasticity, and is suitable for sealing various indoor and outdoor structures. Therefore, the effect of secondary sealing is better than that of the first sealing. The reason why it is not fully adopted is to consider cost consumption.
[0028] The utility model has the following beneficial effects:
[0029] 1. In the utility model, the push-pull rod and the waterproof plate are firstly driven to move synchronously by pushing and pulling the push-pull block. At this time, the ball will be squeezed, thereby squeezing the spring through the sliding column, so that the push-pull rod can slide smoothly in the cavity, thereby achieving the effect that the waterproof plate can move freely during maintenance.
[0030] 2. In the present invention, the first sealing layer and the second sealing layer are bonded in advance by double-sided adhesive tape, which can save the time of the workers when filling the groove. The added third sealing layer can better seal the groove and is only set in a partial area, which can also save costs to a certain extent. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 A three-dimensional diagram of a box culvert settlement joint structure proposed by the utility model;
[0032] Figure 2 A schematic diagram of the internal structure of a first box body and a second box body of a box culvert settlement joint structure proposed by the utility model;
[0033] Figure 3 for Figure 2 Enlarged view of point A in the middle;
[0034] Figure 4 The utility model provides a schematic diagram of the internal structure of a groove of a box culvert settlement joint structure.
[0035] Legend:
[0036] 1. First box body; 2. Second box body; 3. Slide groove; 4. Push-pull block; 5. Push-pull rod; 6. Waterproof board; 7. Cavity; 8. Spring; 9. Sliding column; 10. Ball; 11. Limiting groove; 12. Limiting block; 13. Groove; 14. First sealing layer; 15. Second sealing layer; 16. Double-sided adhesive tape; 17. Third sealing layer. DETAILED DESCRIPTION
[0037] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0038] Reference Figure 1-3 , the utility model provides an embodiment: a box culvert settlement joint structure, including a first box body 1, a second box body 2 is arranged on one side of the first box body 1, a slide groove 3 is opened on the top of the first box body 1, a push-pull rod 5 is slidably connected inside the first box body 1, one end of the push-pull rod 5 is fixedly connected to a waterproof plate 6, a push-pull block 4 is fixedly connected to the upper surface of the push-pull rod 5, and the push-pull block 4 is slidably connected inside the slide groove 3, a cavity 7 is opened inside the first box body 1, a spring 8 is fixedly connected inside the first box body 1, the spring 8 is arranged inside the cavity 7, one end of the spring 8 is fixedly connected to a sliding column 9, a ball 10 is arranged on one side of the sliding column 9, and a limiting component is arranged on both sides of the sliding column 9, the limiting component includes a limiting groove 11 and a limiting block 12, the limiting block 12 is slidably connected inside the limiting groove 11, the limiting groove 11 is opened inside the first box body 1, and the limiting block 12 is fixedly connected to the outer wall of the sliding column 9;
[0039] Specifically, when the waterproof plate 6 hinders the maintenance of the staff, the push-pull rod 5 and the waterproof plate 6 can be driven to move synchronously by pushing and pulling the push-pull block 4. When the push-pull rod 5 moves, the ball 10 will be squeezed and disengaged from the reserved hole of the push-pull rod 5, so that the space occupied by the spring 8 in the cavity 7 can be reduced through the sliding column 9. In this way, the sliding column 9 and the ball 10 can be immersed in the depth of the cavity 7 so as not to hinder the sliding of the push-pull rod 5. When the maintenance is completed, when the push-pull block 4 pushes the push-pull rod 5 and the waterproof plate 6 back to their original position, the ball 10 is aligned with the reserved hole in the push-pull rod 5, so that the force on the ball 10 disappears. At this time, the spring 8 generates a reaction force due to its own restorability, and pushes the ball 10 back to the reserved hole of the push-pull rod 5 through the sliding column 9 to achieve engagement.
[0040] Reference Figure 2 and 4 A groove 13 is provided between the first box body 1 and the second box body 2, a groove 13 is provided between the first box body 1 and the second box body 2, a double-sided adhesive tape 16 is provided between the first sealing layer 14 and the second sealing layer 15, the first sealing layer 14 is filled with asphalt hemp, the second sealing layer 15 is filled with oil felt, a third sealing layer 17 is provided at the bottom of the first sealing layer 14, and the inside of the third sealing layer 17 is filled with polyurethane sealant;
[0041] Specifically, the first sealing layer 14 and the second sealing layer 15 can be pre-bonded together by a double-sided tape 16 to save time for the workers during the filling operation, and the first sealing layer 14 and the second sealing layer 15 bonded together can cooperate to achieve a sealing effect, thereby realizing the first sealing at the groove 13, and then a second sealing is performed by a third sealing layer 17 filled with polyurethane sealant to prevent the first sealing layer 14 and the second sealing layer 15 from insufficiently waterproof and tight, thereby preventing water from penetrating. In addition, the third sealing layer 17 is provided to some extent, which can reduce industrial costs to a certain extent.
[0042] Working principle: When the waterproof plate 6 hinders the maintenance of the staff, the push-pull block 4 can be pushed to drive the push-pull rod 5 and the waterproof plate 6 to move synchronously. When the push-pull rod 5 moves, the ball 10 will be squeezed and thus disengaged from the reserved hole of the push-pull rod 5, so that the slide column 9 and the ball 10 can all enter the cavity 7, allowing the push-pull rod 5 to slide smoothly. When the maintenance is completed, the push-pull rod 5 and the waterproof plate 6 are pushed back to their original positions by the push-pull block 4, and the ball 10 will be aligned with the reserved hole in the push-pull rod 5, so that the force on the ball 10 disappears. At this time, the spring 8 generates a reaction force due to its own restorability, and pushes the ball 10 back through the slide column 9 The push-pull rod 5 is engaged with the reserved hole, and the groove 13 is blocked by the waterproof plate 6 to prevent rainwater from directly eroding it. The interior is made of rubber material, and will not hinder the first box body 1 and the second box body 2 when they expand and contract due to heat and cold. When filling things into the groove 13, the first sealing layer 14 and the second sealing layer 15 can be pre-bonded together by the double-sided tape 16, so that the staff can directly fill it to achieve the first seal, and the third sealing layer 17 filled with polyurethane sealant can be used for secondary sealing, so as to prevent the problem of water penetration caused by insufficient waterproof sealing of the first sealing layer 14 and the second sealing layer 15.
[0043] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A box culvert settlement joint structure, comprising a first box body (1), characterized in that: A second box body (2) is arranged on one side of the first box body (1); a slide groove (3) is provided on the top of the first box body (1); a push-pull rod (5) is slidably connected inside the first box body (1); one end of the push-pull rod (5) is fixedly connected to a waterproof plate (6); a push-pull block (4) is fixedly connected to the upper surface of the push-pull rod (5); the push-pull block (4) is slidably connected inside the slide groove (3); a cavity (7) is provided inside the first box body (1); a spring (8) is fixedly connected inside the first box body (1); the spring (8) is arranged inside the cavity (7); one end of the spring (8) is fixedly connected to a slide column (9); a ball (10) is provided on one side of the slide column (9); and limit assemblies are provided on both sides of the slide column (9).
2. A box culvert settlement joint structure according to claim 1, characterized in that: The limiting assembly comprises a limiting groove (11) and a limiting block (12), wherein the limiting block (12) is slidably connected inside the limiting groove (11).
3. A box culvert settlement joint structure according to claim 2, characterized in that: The limiting groove (11) is provided inside the first box body (1), and the limiting block (12) is fixedly connected to the outer wall of the sliding column (9).
4. A box culvert settlement joint structure according to claim 1, characterized in that: A groove (13) is provided between the first box body (1) and the second box body (2).
5. A box culvert settlement joint structure according to claim 4, characterized in that: A first sealing layer (14) is arranged inside the groove (13), and a second sealing layer (15) is arranged on the top of the first sealing layer (14).
6. A box culvert settlement joint structure according to claim 5, characterized in that: A double-sided adhesive tape (16) is provided between the first sealing layer (14) and the second sealing layer (15); the first sealing layer (14) is filled by injecting asphalt hemp wool, and the second sealing layer (15) is filled by injecting asphalt felt.
7. A box culvert settlement joint structure according to claim 5, characterized in that: A third sealing layer (17) is provided at the bottom of the first sealing layer (14).
8. A box culvert settlement joint structure according to claim 7, characterized in that: The interior of the third sealing layer (17) is filled with polyurethane sealant.
Citation Information
Patent Citations
Box culvert construction joint
CN218147883U