Method for producing a flat steel product having cathodic corrosion protection, system for producing a flat steel product provided with cathodic corrosion protection, and use

EP4448824A1Pending Publication Date: 2024-10-23THYSSENKRUPP STEEL EUROPE AG PATENTE PATENT DEPARTMENT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
EP2022793683
Authority / Receiving Office
EP · EP
Patent Type
Applications
Current Assignee / Owner
Priority Date
2021-12-14
Filing Date
2022-09-19
Publication Date
2024-10-23

AI Technical Summary

Technical Problem

Existing methods for providing flat steel products with cathodic protection against corrosion, such as hot-dip treatments using Zn, Al, or Mg alloys, face challenges with high suitability for oxidation, leading to impractical or unfavorable results, particularly during hot forming processes where scaling occurs.

Method used

A method employing a PVD coating process to apply anti-corrosion coatings on steel flat products, involving thermal pre-treatment in a continuous furnace followed by gas phase deposition using a device with a vaporization and nozzle section, ensuring dense and well-adhering layers that maintain quality under stress, including hot forming.

Benefits of technology

The PVD coating method produces high-quality, large-area anti-corrosion layers with excellent adhesion and durability, preventing defects like delamination or powdering, even under high stress conditions, while maintaining a high throughput and cost-effectiveness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 1.1
    Figure 1.1
Patent Text Reader

Abstract

The invention relates to a method for producing a flat steel product (2) having cathodic corrosion protection. The method comprises the following steps: A. providing the flat steel product; B. optionally: thermal pretreatment; C. transporting the flat steel product into a coating chamber. The invention additionally relates to a system (1) having a conveying assembly (3a, 3b) for conveying in the direction of the arrow (5), a pretreatment furnace (10) having a furnace inlet (11) and a furnace outlet (12), and a coating chamber (4) having a device (6, 7, 8, 9) for gas-phase deposition of material.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] Process for producing a flat steel product with cathodic corrosion protection, plant for producing a flat steel product provided with cathodic corrosion protection and use

[0002] The invention relates to a method for producing a flat steel product with cathodic corrosion protection. The invention further relates to a plant for producing a flat steel product provided with cathodic corrosion protection. A further concept of the invention is a use.

[0003] When reference is made to a flat steel product, this refers to steel strips, steel sheets, blanks obtained therefrom, and the like. In particular, flat steel products in the form of steel strips are the subject of the invention.

[0004] It is known to provide flat steel products with a metallic coating to protect them from scaling during the hot forming process. Coatings chosen for this purpose act as cathodic corrosion protection for the flat steel product. Examples of known coating materials include zinc, aluminum, magnesium, and alloys thereof.

[0005] Alloys that have been further improved for their suitability as corrosion protection often contain additional alloying elements, for example, in addition to the aforementioned Ca, Na, or Li. Due to the high susceptibility of these elements to oxidation, hot-dip treatment is not practical or only produces unfavorable results.

[0006] Against this background, the invention was based on the object of being able to provide flat steel products with good corrosion protection coatings despite the aforementioned obstacles. This object is achieved by a method for producing a flat steel product with cathodic corrosion protection.

[0007] The procedure includes the following steps:

[0008] A. Providing the flat steel product;

[0009] B. optional: thermal pretreatment of the flat steel product;

[0010] C . Transporting the flat steel product into a

[0011] coating chamber and through it.

[0012] A device for vapor deposition of material is arranged on or in the coating chamber. The device for vapor deposition of material is operated to coat a surface of the flat steel product conveyed through the coating chamber with a corrosion protection coating. The device for vapor deposition of material is designed as a PVD coating device.

[0013] The fundamental core idea of ​​the invention is that, in contrast to known hot-dip processes, the corrosion protection coating is applied by depositing a material on the surface using a PVD coating process. The use of a PVD coating process in the present context has the specific advantage that a coating with a sufficiently high coating rate and diffusion of the particles impacting the surface is present during the layer formation process, that dense and well-adhering corrosion protection layers can be produced over large areas, which surprisingly retain their high quality even under the high stress of a subsequent forming process, in particular hot forming. In particular, tests have shown that coating defects such as delamination or powdering did not occur or only occurred to a small extent.Preferably, a thermal pretreatment is carried out before the flat steel product is transported into the coating chamber in step B. The thermal pretreatment comprises:

[0014] Bl . Passing the flat steel product through a continuous furnace;

[0015] B2 . Heating the flat steel product ;

[0016] B3 . Conveying the flat steel product out of the continuous furnace .

[0017] Particularly preferably, the surface is coated on a heat-treated flat steel product, resulting in particularly good coating adhesion. The coating properties and adhesion are particularly good when the coating is applied while the flat steel product is still heated, i.e., step C is carried out immediately after heating in step B.

[0018] For the heat treatment, a continuous furnace known from practice is used with the advantage that a continuous process of a sequence of pretreatment and coating with potentially high throughput is achieved.

[0019] Particularly preferably, the heating of step B2 comprises the steps:

[0020] B2a . a pre-oxidation step ,

[0021] B2b . a reduction annealing step carried out after the pre-oxidation step .

[0022] Pre-oxidation purifies the coating through the induced combustion processes. The subsequent reduction eliminates the resulting oxides. Furthermore, the flat steel product is left with a surface with a high proportion of reactive iron, which ensures good adhesion of the coating applied in step 0.

[0023] For example, it may be provided that the

[0024] Pre-oxidation step B2a is carried out in an atmosphere with 0.1 to 10 vol. percent O2, preferably 0.1 to 4.0 vol. percent O2, the remainder being a protective gas, the remainder preferably consisting of H2 and N2, the remainder particularly preferably consisting of 0 to 10 vol. percent H2 and 90 to 100 vol. percent N2.

[0025] Good properties of the corrosion protection coating were obtained in a preferred process variant in which the pre-oxidation step B2a was carried out at a temperature between 650 degrees Celsius and 750 degrees Celsius.

[0026] The reduction annealing step B2b is preferably carried out in a protective gas atmosphere containing H2, which is preferably composed of H2 and N2. The atmosphere particularly preferably consists of 0 to 10 vol. percent H2 and 90 to 100 vol. percent N2.

[0027] For the reduction annealing step B2b, it was found to be advantageous that this is carried out at a temperature between 750 degrees Celsius and 900 degrees Celsius, preferably between 750 degrees Celsius and 850 degrees Celsius, preferably with a holding time greater than 180, particularly preferably less than 300 seconds.

[0028] According to one possible process variant, it may be advantageous for the reduction annealing step B2b to be supplemented by a subsequent annealing step, which is carried out at a temperature between 420 and 520 degrees Celsius, preferably with a holding time of more than 30 seconds, particularly preferably less than 150 seconds. The annealing step ensures that excessively rapid cooling does not occur during the transition to the subsequent coating step C, thus avoiding adverse structural changes.

[0029] In each of the above-mentioned processes and combinations of processes, dew points of between -15 degrees Celsius and -25 degrees Celsius, for example -20 degrees Celsius, have proven advantageous. During reduction annealing, heating and cooling ramps between 5 degrees Celsius / second and 15 degrees Celsius / second are particularly advantageous. Preferably, the flat steel product exits the continuous furnace immediately after step B2 and enters the coating chamber, and the coating is applied to the still-warm surface of the flat steel product.

[0030] Preferably, the temperature of the flat steel product is still close to the pretreatment temperature, for example, between 150 and 250 degrees Celsius for pure zinc systems or between 560 and 710 degrees Celsius for aluminum coatings. Generally, a temperature between 60 percent and 80 percent of the melting point or, alternatively, the solidus temperature (each on the Kelvin scale) of the coating is preferred.

[0031] The corrosion protection coating is preferably an Al-based or a Zn-based corrosion protection coating.

[0032] In a case where the corrosion protection coating is Zn-based, it preferably contains, in addition to Zn and unavoidable impurities, additionally: optionally 12-60 atomic percent Mg, optionally 15-60 atomic percent Al, optionally 8-50 atomic percent Mn,

[0033] Remainder to 100 wt%: Zn and unavoidable impurities.

[0034] The composition is particularly preferably such that the solidus temperature is > 700 degrees Celsius.

[0035] If the corrosion protection coating is Al-based, it preferably contains, in addition to Al and unavoidable impurities, optionally 0.1-30 wt. percent Fe, preferably 5-30 wt. percent Fe, optionally 0.1-5 wt. percent Mg, optionally 0.1-5 wt. percent Ti, optionally 0.1-10 wt. percent Si, optionally 0.1-10 wt. percent Li, optionally 0.1-10 wt. percent Ka, remainder to 100 wt. percent: Al and unavoidable

[0036] Impurities . The composition is particularly preferably such that the

[0037] Solidus temperature > 770 degrees Celsius is .

[0038] During coating, the coating chamber is preferably maintained at a protective gas pressure of less than 100 mbar above a technical vacuum with a residual gas pressure of 20 mbar. Under these conditions, coatings with good coating properties can be produced at a comparatively high coating speed and with comparatively low equipment expenditure.

[0039] Different mechanisms can be used to evaporate the material to be applied as a corrosion protection coating in the evaporation section. A conceptually simple approach is the thermal evaporation of a starting material, which is then fed to and through the nozzle section. A pressure difference between the evaporation section and the coating chamber, for example, contributes to the movement of the material in the gas phase. Optionally, a carrier gas stream, for example consisting of an inert gas, can also be used to transport the evaporated material through the evaporation section and then through the nozzle section.

[0040] An example of a device for the gas phase deposition of material is a jet vapor deposition system, which the person skilled in the art understands to be a system in which the coating material is brought into the gas phase by means of thermal evaporation and is then transported to the substrate, for example - typically, but not necessarily - with a carrier gas stream of inert gas, preferably with a gas stream velocity above the speed of sound, preferably above 500 m / s. The mode of operation can be found, for example, in the review article in Handbook of Deposition Technologies for Films and Coatings (Third Edition), Science, Applications and Technology, 2010, pages 881-901, https: / / doi.org / 10.1016 / B978-0-8155-2031-3.00018-1 (linked on the date of filing). The present invention can also be implemented with such jet vapor deposition systems.

[0041] In addition, the present invention can be used quite generally for all coating devices of the type mentioned at the outset, i.e. for all coating devices in which the material intended for the anti-corrosive coating is brought into its gas phase within an evaporation section having a crucible and the material in the gas phase is then discharged through a nozzle section and out of the outlet of the nozzle section towards a surface of the object to be coated, then moves towards the surface, condenses on the surface and thereby forms the anti-corrosive coating.

[0042] In particular, the present invention is intended for the subgenus of coating devices in which a carrier gas stream leads into the evaporation section for supplying a carrier gas stream of a carrier gas into the evaporation section and through it for carrying the coating material towards the substrate surface. A variant of a coating device of this type is known, for example, from WO 2016 / 042079 A1. In this coating device, two wires are continuously fed in as coating material. The coating material reaches a spray head in which the two material wires are connected to an electrical DC voltage source as a cathode and anode.As a result of the direct electrical voltage between the cathode and anode, an electric arc forms between the two material wires, whereby the supplied starting material in the form of the two material wires is vaporized and / or liquefied. A gas stream is passed through the spray head, which entrains the vaporized and / or liquefied coating material and transports it via an injector tube into a crucible. The coating material conveyed into the crucible then vaporizes completely within the heated crucible and is guided out of the crucible and directed towards the substrate to be coated. This coating device has a combination of elements that are also known from jet vapor deposition systems and elements that are known from systems that operate according to the principle of arc evaporation.The device is based on transporting the coating material with a carrier gas stream. To provide the coating material in the gas phase, this coating device uses an evaporation section consisting of a pre-evaporation section and a post-evaporation section designed as a crucible. The pre-evaporation section prepares the material in the spray head and the injector tube and makes it available to the crucible for post-evaporation, i.e., converting at least the majority of the remaining solid or liquid components into the gas phase.

[0043] The systems of the type mentioned above all have in common that, due to their conceptual implementation with a coating chamber for carrying out the object to be coated, they can be used in particular for large-scale implementations and unfold their advantages. Due to the resulting boundary conditions, such as the corresponding size of the coating chamber and effort- and cost-dependent limits in providing a technical vacuum, a particular challenge when operating the coating system is to be able to guarantee a high level of process reliability when coating the objects. For example, it is desirable to be able to guarantee high reproducibility of the properties of the coatings produced and / or economical operation of the system and / or high quality of the layers produced.

[0044] Particularly preferably, the device for vapor deposition of material comprises:

[0045] - an evaporation section for evaporating the material into the gas phase,

[0046] - a nozzle section coupled to the evaporation section.

[0047] The nozzle section, in turn, has a nozzle with a nozzle outlet opening into the coating chamber, in order to direct the material in the gas phase out of the nozzle outlet and to cause it to move towards the surface of the flat steel product to be coated, whilst the flat steel product is continuously guided through the coating chamber past the nozzle outlet. As a result, the surface of the flat steel product, which is preferably a steel strip, is continuously coated with material in the gas phase flowing out of the nozzle outlet, in that this material condenses on the surface and thereby forms the coating.

[0048] The evaporation section comprises all the equipment in the coating system that converts the starting material intended for coating into the gas phase. For this purpose, the evaporation section has a feeder for the starting material, through which the evaporation section is supplied with the starting material for evaporation.

[0049] Throughout the description, the terms gas phase and evaporation are used, as they are common in the field of the described technology. The term gas phase includes that a small proportion by weight, for example up to 30 wt.%, preferably not more than 10 wt.%, of the

[0050] The gas phase material may not be a pure gas in the physical sense, but instead may be present as vapor components, such as an aerosol and / or cluster. The term evaporation includes that, depending on the material and technology used, the transition of the particles into the gas phase takes place at least partly by means of other mechanisms, for example by sublimation. The term evaporation therefore includes, in addition to evaporation in the strictly physical sense, i.e. a transition from liquid to liquid. Gas phase, also other mechanisms, such as sublimation.

[0051] The coating chamber preferably has an inlet passage and an outlet passage, as well as a coating channel, which is particularly preferably arranged within the coating chamber and has an inlet opening and an outlet opening for introducing and removing the object. For example, if the coating system is intended for coating metallic strip, the coating chamber can be a strip coating system with transport and support rollers arranged outside the coating chamber, so that the strip is guided through the coating chamber.

[0052] Particularly preferably, the evaporation section has a pre-evaporation section and a post-evaporation section, preferably designed as a crucible.

[0053] The pre-evaporation section has a spray head for preparing the coating material present as starting material and an injector tube, wherein the injector tube is designed to conduct the coating material prepared in the spray head to the post-evaporation section and is coupled to the post-evaporation section for guiding the prepared coating material into the post-evaporation section for bringing it into the gas phase there. The spray head is particularly preferably designed as a so-called wire sprayer, which refers to a device in which starting material introduced as wire is prepared by means of arc melting and / or arc evaporation and brought into the gas phase. The coating rate is adjusted by a feed rate of a feed of starting material into the spray head. The starting material is fed to the spray head, preferably in wire or strip form.The starting material is prepared in the spray head, which means that components of the starting material are evaporated and / or separated from the starting material as particles in the liquid phase, preferably by means of arc evaporation between the starting material connected as the cathode and the starting material connected as the anode. The prepared starting material is not completely in the gas phase, but consists of a mixture, in particular of a gas phase and liquid or partially liquid particles, which is suitable for being passed through the crucible in order to be re-evaporated there, i.e. to pass completely or largely completely into the gas phase as a result of the heating that takes place there.

[0054] The pre-evaporation section comprises, in particular, a spray head for preparing the coating material present as starting material and an injector tube. The injector tube is coupled to the crucible and designed to guide the coating material prepared in the spray head to the crucible. The prepared coating material enters the crucible. Components of the coating material that are not yet in the gas phase evaporate within the crucible, which is heated for this purpose to a temperature above the evaporation temperature of the starting material.

[0055] The crucible is heated to convert the prepared starting material into the gas phase. The temperature to which the crucible is heated depends on the coating material.

[0056] The crucible is preferably designed as a cyclone, as a cyclone shape is a space-saving design that allows for efficient guidance of the gas flow through the crucible. A further advantage of a cyclone-shaped crucible is its high reliability in the almost complete evaporation of the material flowing through it, thus ensuring a high quality of the deposited coating. Bombardment of the strip with coating material still in the liquid phase can be virtually eliminated with proper use.

[0057] In one variant, a carrier gas flow supply pointing into the evaporation section is arranged on the evaporation section for supplying a carrier gas flow of a carrier gas into the evaporation section and through it for carrying the coating material.

[0058] A preferred embodiment of an embodiment explained at the outset is one in which the pre-evaporation section has a spray head, wherein the carrier gas flow supply is arranged in the spray head, so that the carrier gas is passed through the spray head and entrains processed starting material, for example in the form of particles or clusters, and passes this through the injector tube into the crucible.

[0059] For example, the spray head can be designed as a wire sprayer, which refers to a spray head into which the starting material is introduced in wire or strip form in order to then prepare it within the spray head by means of arc melting and / or arc evaporation, i.e. to prepare it for further evaporation.

[0060] Alternatively or additionally, the device for vapor deposition of the material is a jet vapor deposition coating device, or JVD coating device for short. Within the scope of the present invention, JVD coating is considered a subtype of PVD coating. One idea that can be considered independently or in combination with the developments described above is a system for coating a flat steel product provided with cathodic corrosion protection.

[0061] In order to provide a provided flat steel product with effective corrosion protection, the system has:

[0062] - A conveyor arrangement for transporting the flat steel product along the individual treatment stations of the plant. Such a conveyor arrangement can, for example, be a conventional arrangement of transport rollers, with which a flat steel product in the form of a steel strip can be transported through the individual stations of the plant.

[0063] - A pretreatment furnace for the thermal pretreatment of the flat steel product, wherein the pretreatment furnace is preferably designed as a continuous furnace. If the pretreatment furnace is designed as a continuous furnace, it preferably has a furnace inlet and a furnace outlet located at the other end of the continuous furnace, so that the flat steel product can be fed into the continuous furnace through the furnace inlet, passed through the furnace, and then out through the furnace outlet.

[0064] - A coating chamber with a device for the vapor deposition of material, the coating chamber being arranged behind the furnace outlet in the transport direction of the flat steel product, with a chamber inlet for introducing the flat steel product in order to guide it past a nozzle outlet of a nozzle of the device for the vapor deposition of material and through the chamber.

[0065] The device for the vapor deposition of material is operable to coat one of the surfaces of the flat steel product being guided through the coating chamber, in that a nozzle of the device for the vapor deposition is oriented with a nozzle outlet in such a way that material in the vapor phase emerging from the nozzle outlet strikes the flat steel product being guided through the chamber and, as a result of the continuous movement of the flat steel product, continuously provides it with a coating whose composition is derived from the composition of the starting material which is brought into the vapor phase in the device for the vapor deposition of material.

[0066] Preferably, the device for vapor deposition of material is a PVD coating device and / or

[0067] - the device for vapor deposition of material is a JVD coating device.

[0068] In one variant, the device for vapor deposition of material comprises:

[0069] - an evaporation section for evaporating the material into the gas phase,

[0070] - a nozzle section coupled to the evaporation section, the nozzle section having a nozzle with a nozzle outlet opening into the coating chamber, for the directed guidance and discharge of the material in the gas phase from the nozzle outlet to a surface of the flat steel product to be coated, which surface is to be coated and is guided through the coating chamber past the nozzle outlet, for the continuous coating of the surface with material in the gas phase flowing out of the nozzle outlet, in that this material condenses on the surface and thereby forms the coating. Reference is made to the explanations set out above in connection with the corresponding method, in which the units present in this variant are described in detail. The evaporation section particularly preferably has a pre-evaporation section and a post-evaporation section, preferably designed as a crucible.

[0071] The pre-evaporation section has a spray head for preparing the coating material present as starting material and an injector tube, wherein the injector tube is designed to conduct the coating material prepared in the spray head to the post-evaporation section and is coupled to the post-evaporation section for guiding the prepared coating material into the post-evaporation section for bringing it into the gas phase there. The spray head is preferably designed as a wire sprayer for the arc melting and / or arc vaporization of starting material introduced into the wire sprayer. The coating rate can then be adjusted in particular by a feed rate of a feed of starting material into the spray head. Reference is made to the explanations presented above in connection with the corresponding method, in which the units present in this variant are described in detail.

[0072] The pretreatment furnace and the coating chamber are preferably directly coupled to one another, wherein the furnace outlet and the chamber inlet can, for example, be designed to merge into one another or can be connected to one another by means of a transition piece.

[0073] It is particularly preferred to use a plant according to one of the embodiments described above for coating a surface of a flat steel product with an Al-based or Zn-based cathodic corrosion protection coating by means of a process of vapor deposition of material.

[0074] Further details, features, and advantages of the subject matter of the invention will become apparent from the following description taken in conjunction with the figure, which illustrates an exemplary embodiment of the invention. It is understood that the features mentioned above and those explained below can be used not only in the respective combinations specified, but also in other combinations or on their own.

[0075] It shows :

[0076] Fig . 1 : Example embodiment of a coating system .

[0077] Fig. 1 shows an exemplary embodiment of a plant for producing a flat steel product 1 provided with cathodic corrosion protection for coating a flat steel product 2, which is designed here as a strip 2. The plant designed as a strip coating plant for producing a flat steel product 1 provided with cathodic corrosion protection has a coating chamber 4 in which a technical vacuum prevails and through which the strip 2 is guided in the direction of arrow 5 by means of the transport rollers 3a and 3b. The coating plant has a device for the gas phase deposition of material 6. This is composed of an evaporation section 7 for evaporating the material into the gas phase and a nozzle section 8, 9, which is composed of a nozzle 8 and a coupling member 9 serving as an adapter.Material evaporated in the evaporation section 7, which is designed as a crucible, for example, is guided through the nozzle section 8, 9 into the coating chamber 4, where it reaches the strip 2 and thereby forms the coating. A pretreatment furnace 10 for the thermal pretreatment of the flat steel product 2 is positioned in front of the coating chamber 4 in the strip transport direction. The pretreatment furnace 10 is designed as a continuous furnace with a furnace inlet 11 and a furnace outlet 12 located at the other end of the continuous furnace, so that the flat steel product can be fed into the continuous furnace 10 through the furnace inlet 11, passed through the furnace and then out through the furnace outlet 12. The pretreatment furnace and the coating chamber 4 are directly coupled to one another, so that the strip enters the coating chamber 4 immediately upon exiting the pretreatment furnace 10.

Claims

Patent claims 1. A method for producing a steel flat product with cathodic corrosion protection, the method comprising the following steps: A. Provision of the steel flat product; B. optional: thermal pretreatment of the steel flat product; C. Transporting the steel flat product to a coating chamber and through it, wherein the coating chamber has a device for the vapor deposition of material which is operated to coat a surface of the steel flat product passed through the coating chamber with a corrosion protection coating, wherein the device for the vapor deposition of material is a PVD coating device.

2. The method of claim 1, wherein the thermal pretreatment of step B is carried out, comprising the following steps: Bl. Passing the steel flat product through a continuous furnace; B2. Heating the steel flat product; B3. Transporting the steel flat product from the Flow of the machine out.

3. The method of claim 2, wherein the heating of step B2 comprises the steps: B2a. a pre-oxidation step, B2b. a step carried out after the pre-oxidation step Reduction annealing step.

4. The method of claim 3, wherein the pre-oxidation step B2a is carried out in an atmosphere containing 0.1 to 10 vol. percent O2, preferably 0.1 to 4.0 vol. percent O2, the remainder being a protective gas, the remainder preferably consisting of H2 and N2, the remainder particularly preferably consisting of 0 to 10 vol. percent H2 and 90 to 100 vol. percent N2; and / or the pre-oxidation step B2a is carried out at a temperature between 650 degrees Celsius and 750 degrees Celsius.

5. A method according to claim 3 or claim 4, wherein the reduction annealing step B2b is carried out in a protective gas atmosphere, preferably consisting of H2 and N2, more preferably consisting of 0 to 10 vol. percent H2 and 90 to 100 vol. percent N2; and / or the reduction annealing step B2b is carried out at a temperature between 750 degrees Celsius and 900 degrees Celsius, more preferably between 750 degrees Celsius and 850 degrees Celsius, more preferably with a holding time greater than 180, more preferably less than 300 seconds.

6. Method according to claim 5, wherein the reduction annealing step B2b comprises a subsequent decay annealing at a temperature between 420 and 520 degrees Celsius, preferably with a holding time greater than 30, particularly preferably less than 150 seconds.

7. Method according to one of the preceding claims, wherein immediately after step B2, with the removal of step B3 from the flow oven, the entry into the The coating process takes place in the coating chamber, and the coating of the still warm flat steel product is carried out.

8. Method according to claim 7, wherein the coating is carried out at a temperature of the steel flat product which is between 60 percent and 80 percent of the melting point or alternatively the solidus temperature (each on the Kelvin scale) of the material used as a corrosion protection coating.

9. Method according to any of the preceding claims, wherein the corrosion protection coating is an Al-based or a Zn-based corrosion protection coating.

10. Method according to any of the preceding claims, wherein the corrosion protection coating is Zn-based, preferably with a solidus temperature > 700 degrees Celsius, in addition to Zn and unavoidable impurities, optionally comprising 12-60 atomic percent Mg, optionally 15-60 atomic percent Al, optionally 8-50 atomic percent Mn.

11. A method according to any of the preceding claims, wherein the corrosion protection coating is aluminum-based, preferably with a solidus temperature > 770 degrees Celsius, and, in addition to aluminum and unavoidable impurities, optionally comprising 0.1–30 wt. percent Fe, preferably 5–30 wt. percent Fe, optionally 0.1–5 wt. percent Mg, optionally 0.1–5 wt. percent Ti, optionally 0.1–10 wt. percent Si. 21 optional 0, 1-10 wt. -percent Li, optional 0, 1-10 wt. -percent Ka.

12. Method according to one of the preceding claims, wherein a protective gas pressure of less than 100 mbar is set in the coating chamber during coating above a technical vacuum with a residual gas pressure of 20 mbar.

13. Method according to any of the preceding claims, wherein the device comprises: - an evaporation section for evaporating the material into the gas phase, - a nozzle section coupled to the evaporation section, wherein the nozzle section has a nozzle with a nozzle outlet opening into the coating chamber, for the directed guiding and discharge of the material present in gas phase from the nozzle outlet to a surface to be coated of the steel flat product, which is guided through the coating chamber past the nozzle outlet, for the continuous coating of the surface with material present in gas phase flowing out of the nozzle outlet, by condensing it on the surface and thereby forming the coating.

14. Method according to claim 13, wherein - the evaporation section comprises a pre-evaporation section and a post-evaporation section preferably designed as a crucible, wherein the pre-evaporation section comprises a spray head for preparing the coating material present as starting material and an injector tube, wherein the injector tube supplies the material prepared in the spray head 22 The coating material is designed to be conductive to the post-evaporation section and is coupled to the post-evaporation section for guiding the processed coating material into the post-evaporation section to bring it into the gas phase there, wherein preferably the spray head is a wire sprayer for arc melting and / or arc evaporation of the starting material introduced into the wire sprayer, wherein the coating rate is adjusted by adjusting the feed rate of the starting material into the spray head and / or - the device for gas phase deposition of the material is a jet vapor deposition coating device, or JVD coating device for short.

15. Plant (1) for the manufacture of a steel flat product (2) provided with cathodic corrosion protection, wherein the plant (1) comprises: - a transport arrangement (3a, 3b) for the transport of the steel flat product (2) along the individual treatment stations of the plant (1) , - a pretreatment furnace (10) for the thermal pretreatment of the steel flat product, wherein the pretreatment furnace is preferably designed as a continuous furnace with a furnace inlet (11) and a furnace outlet (12) located at the other end of the continuous furnace (10), so that the steel flat product can be fed into the continuous furnace (10) through the furnace inlet (11), passed through the continuous furnace (10) and then discharged through the furnace outlet (12), - a coating chamber (4) with a device (6) for gas phase deposition of material, wherein the coating chamber (4) is arranged in the transport direction (5) of the steel flat product (2) behind the furnace outlet (12), with a chamber inlet for introducing the steel flat product (2) in order to then guide it through the chamber (4), wherein the device (6) for gas phase deposition of material is operable for coating one of the surfaces of the steel flat product (2) guided through the coating chamber (4).

16. Annex (1) according to claim 15, wherein - the device for gas phase deposition of material is a PVD coating device and / or - the device for gas phase deposition of material is a JVD coating device.

17. System (1) according to claim 15 or according to claim 16, wherein the device comprises: - an evaporation section for evaporating the material into the gas phase, - a nozzle section (8, 9) coupled to the evaporation section (7), wherein the nozzle section (8, 9) has a nozzle with a nozzle outlet opening into the coating chamber (4), for the directed guiding and discharge of the material present in the gas phase from the nozzle outlet to a surface to be coated of the steel flat product, which is guided through the coating chamber past the nozzle outlet, for continuous Coating the surface with material in the gas phase flowing from the nozzle outlet, by applying this 24 condenses on the surface, thereby forming the coating.

18. Plant (1) according to one of claims 15 to 17, wherein the evaporation section (7) comprises a pre-evaporation section and a post-evaporation section preferably designed as a crucible, wherein the pre-evaporation section comprises a spray head for preparing the coating material present as the starting material and an injector tube, wherein the injector tube is designed to conduct the coating material prepared in the spray head to the post-evaporation section and is coupled to the post-evaporation section for guiding the prepared coating material into the post-evaporation section to bring it into the gas phase there, wherein preferably the spray head is a wire sprayer for arc melting and / or arc evaporation of starting material introduced into the wire sprayer, wherein the coating rate is adjusted by a feed rate of starting material into the spray head.

19. Plant according to one of claims 15 to 18, wherein the pretreatment furnace ( 10 ) and the coating chamber ( 4 ) are directly coupled to each other, preferably the furnace outlet ( 12 ) and the chamber inlet are designed to merge seamlessly into each other.

20. Use of a system (1) according to any one of claims 15 to 19 for coating a surface of a steel flat product with an Al-based or Zn-based 25 cathodic corrosion protection coating using a process of gas phase deposition of material .