Method for constructing modular building having expandable load-bearing body

The method of stacking hexahedral PC modules with guide pins and shear connectors addresses the inefficiencies in prefabricated building construction by reducing joints and optimizing load-bearing structures, enhancing structural integrity and scalability for high-rise buildings.

WO2024262850A1PCT designated stage expired Publication Date: 2024-12-26NRB INC
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
PCT/KR2024/007836
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-06-22
Filing Date
2024-06-10
Publication Date
2024-12-26

AI Technical Summary

Technical Problem

Existing prefabricated building construction methods face increased defect rates and prolonged construction periods due to excessive assembly locations and overdesign of load-bearing structures, particularly in high-rise buildings, where beam and column specifications are not efficiently scalable.

Method used

The method involves stacking hexahedral PC modules with minimized load-bearing specifications, utilizing guide pins, shear connectors, and tensile bonding to create an expandable modular building structure that allows for adjustable pillar and beam dimensions, reducing the number of joints and enhancing structural integrity.

Benefits of technology

This approach minimizes defects and construction time by allowing for flexible expansion of load-bearing structures, optimizing module dimensions, and maximizing space while ensuring structural integrity, suitable for high-rise permanent buildings.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure KR2024007836_26122024_PF_FP_ABST
    Figure KR2024007836_26122024_PF_FP_ABST
Patent Text Reader

Abstract

The present invention relates to a method for constructing a building by stacking hexahedral PC modules manufactured in a factory, the method comprising the steps of: a) preparing the ground; b) providing a foundation; c) pouring concrete onto a part of the upper surface of the foundation and providing a PC module on the upper surface of the foundation; d) providing the PC module to the uppermost layer by repeating the step in which concrete is poured onto the upper surface of the provided PC module and the PC module of the upper layer is provided; and e) providing a roof module on the upper surface of the uppermost layer PC module, and thus the present invention can minimize the size of a load-bearing body such as a column or a load-bearing wall provided in the PC module itself, and expand the size of the load-bearing body during on-site construction according to the size of the building to be constructed.
Need to check novelty before this filing date? Find Prior Art

Description

Method of constructing a modular building with expandable internal structure

[0001] The present invention relates to a method for constructing a building by stacking hexahedral PC modules manufactured in a factory, and more specifically, to a method for constructing a modular building in which the size of load-bearing bodies such as columns or load-bearing walls provided in the PC modules manufactured in the factory is minimized, and the size of the load-bearing bodies can be expanded during the construction process on site according to the size of the building to be constructed.

[0002] Prefabricated buildings are completed by assembling prefabricated components on-site, thereby minimizing on-site work and shortening construction periods.

[0003] The most common method for constructing these prefabricated structures involves prefabricating each component—columns, beams, walls, and so on—in a factory and then assembling them on-site. However, this method, with its numerous assembly points, not only increases the defect rate in construction but also extends the construction period.

[0004] Another method of constructing prefabricated buildings involves prefabricating hexahedral modules, such as containers, in a factory and then assembling them on site. However, this is mainly used for on-site offices or temporary structures that are only used for a certain period of time.

[0005] As an example of such a temporary structure, an invention entitled “Horizontal large-space type prefabricated building module and construction method thereof” was proposed through Patent Publication No. 10-0660210.

[0006] The above registration number 10-0660210, as shown in Fig. 1, is constructed by assembling a building module (10) supported by a pillar (13) and a beam member (14) by connecting them in the left-right direction and stacking them in the up-down direction, thereby constructing a building with a large indoor space or a large building with multiple floors.

[0007] However, the above-mentioned building module is manufactured in advance at a factory and transported to the site for installation, and the structural design for major structures such as columns (13) and beam members (14) is calculated based on one building module (10) and the dimensions of each member are determined.

[0008] In addition, when constructing a two-story building using this, as shown in (a) of Fig. 1, the beam member (14) of the upper building module (10) and the beam member (14) of the lower building module (10) are simply overlapped, and as a means to connect the two building modules (10), the overlapped upper and lower beam members (14) are fastened with bolts.

[0009] Accordingly, since the upper and lower beam members (14) above do not have structural integrity, the specifications of the beam members (14) cannot but be over-designed, and this problem also appears for the columns (13) when connecting the building modules (10) in the horizontal direction.

[0010] The present invention is intended to solve the above-mentioned problems of the prior art, and the purpose of the present invention is to provide a method for constructing a modular building with expandable load-bearing body that can be applied to high-rise permanent buildings by minimizing the number of joints by stacking hexahedral PC modules to construct a building, while allowing the specifications of load-bearing bodies such as columns, walls, or braced structures to be expanded during the assembly process at the site, thereby minimizing the specifications of load-bearing bodies of PC modules manufactured in a factory, and improving the structural integrity by the joints between each PC module.

[0011] According to the most preferred embodiment of the present invention for solving the above-mentioned problem, there is provided a step of: a) preparing the ground; b) installing a foundation; c) pouring concrete on a portion of the upper surface of the foundation and installing a PC module on the upper surface of the foundation; d) repeating the steps of pouring concrete on the upper surface of the already installed PC module and installing the PC module of the upper layer, thereby installing the PC module up to the uppermost layer; e) installing a roof module on the upper surface of the PC module of the uppermost layer; A method for constructing a load-bearing expandable modular building is provided, characterized in that the PC module is composed of a module corner portion installed vertically at a corner of a hexahedron, an upper module face portion and a lower module face portion installed horizontally above and below the module corner portion, respectively, and an upper slab and a lower slab installed between the upper module face portions and the lower module face portions that are horizontally opposed to each other, and the foundation has a cross-sectional structure of a strip foundation, and is composed of a foundation corner portion at a position where the module corner portion is placed in step c) and a foundation face portion installed between adjacent foundation corner portions.

[0012] At this time, each of the above-mentioned base corner portion and module corner portion may be made to protrude upwards compared to each of the base surface portion and the upper module surface portion, and in this case, the height of each protrusion must be such that a supporting structure of the desired specification can be formed.

[0013] A guide pin protruding upwards may be installed in the base corner portion and the module corner portion, and the installation of the guide pin must be performed in advance before the module corner portion is installed thereon. In this case, a guide groove into which the guide pin is inserted is provided on the bottom surface of each module corner portion.

[0014] The above guide pins are installed with a number of guide pins spaced apart from each other in proportion to the number of module corners placed on top thereof, and the spacing between these guide pins is such that after the installation of the PC modules, the spacing between the module corners of each PC module is a size set for forming a load-bearing body of the desired specification.

[0015] The step b) above may include a process of installing a shear connector protruding upwards on the foundation surface, and an externally protruding shear connector may also be installed on the outer surface of the module edge portion located in the direction of connection between the upper and lower module surfaces of the PC module and the adjacent PC module, and the installation of such shear connectors is performed before each installation step of the PC module. At this time, among the shear connectors installed on the PC module, a hook may be formed at the end of at least the shear connector installed on the module edge portion, and a process of inserting and installing vertical reinforcing bars into the hooks of the shear connectors installed on the module edge portion in the steps c) and d) above may be included.

[0016] In addition, a fastening hole may be provided at the center of each cross-section of the base edge portion and the module edge portion, and a process of integrating the base and each PC module by inserting a tension member into the fastening hole may be included in step d) or step e).

[0017] In addition, the step d) above may include a process of installing insulation on the upper surface of the upper slab before pouring concrete.

[0018] Since the present invention assembles hexahedral PC modules with space by simply stacking them, the number of joints is significantly smaller than in typical prefabricated buildings, thereby minimizing the possibility of defects occurring. In addition, since the load-bearing body such as a column or a braced structure can be expanded during the process of joining each PC module, the specifications of the column and braced structure formed in the PC module itself can be minimized when manufacturing the PC module, thereby promoting weight reduction of the PC module and maximizing the usable space within it.

[0019] Figure 1 is a perspective view of a modular structure of a conventional building and a cross-sectional view of its laminated structure.

[0020] Figure 2 is a cross-sectional view of the expanded internal strength body of the present invention.

[0021] Figure 3 is a perspective view of one embodiment of a PC module of the present invention.

[0022] Figure 4 is a diagram showing the state in which the foundation of the present invention is installed.

[0023] Figures 5 to 8 are perspective views of the process of installing a PC module on the base surface.

[0024] Figures 9 to 11 are perspective views of each process of installing an upper PC module on the upper surface of an already installed PC module.

[0025] Figures 12 and 13 are perspective views of each process of installing a roof module on top of the top PC module.

[0026] Figure 14 is an explanatory drawing of an example in which the assembled modular structure of the present invention is additionally reinforced.

[0027] The best method for constructing a building for carrying out the present invention comprises the steps of: a) preparing the ground; b) installing a foundation; c) pouring concrete on a portion of the upper surface of the foundation and installing PC modules on the upper surface of the foundation; d) repeating the steps of pouring concrete on the upper surfaces of the already installed PC modules and installing the PC modules of the upper layers, thereby installing PC modules up to the uppermost floor; e) installing a roof module on the upper surface of the PC module of the uppermost floor; wherein the PC modules are composed of module corner portions installed vertically at corners of a hexahedron, upper module face portions and lower module face portions installed horizontally above and below the module edge portions, respectively, and upper slabs and lower slabs installed between the upper module face portions and the lower module face portions that are horizontally opposed to each other, and the foundation has a cross-sectional structure of a strip foundation, and is composed of a foundation edge portion at a position where the module edge portion is placed in step c) and a foundation face portion installed between adjacent foundation edge portions.

[0028] Hereinafter, the present invention will be described in detail with reference to the attached drawings based on the most preferred embodiments. However, in explaining the present invention, if a detailed description of a known structure would obscure or make unclear the technical idea of ​​the present invention, a description of the structure of the known structure will be omitted.

[0029]

[0030] FIG. 2 is a drawing for explaining the expansion of the internal structure, which is one of the core technical ideas of the present invention, and is an example of constructing a frame structure building with two PC modules (200) having a module corner portion (210) of a column structure.

[0031] The present invention manufactures PC modules (200) by minimizing the cross-sectional dimensions of module corners (210), etc., and then adjusts the spacing between each PC module (200) on site, and makes the concrete (C) poured between these PC modules (200) become integral with the PC modules (200) through shear connectors (511), etc., so that the planned column (610) cross-section can be formed.

[0032] That is, the present invention enables the specification of load-bearing bodies such as columns (610), load-bearing walls, and reinforcement structures (620) to be set through the spacing between the hexahedral PC modules (200), thereby preventing the cross-section of columns or reinforcement structures independently provided in the PC module (200) from becoming excessive, and also increases the bearing capacity, thereby enabling the scale or number of floors of a building to be constructed to be large.

[0033] Figure 3 illustrates an embodiment of a PC module (200) of the present invention for this purpose.

[0034] As shown in FIG. 3, the PC module (200) of the present invention is composed of a module corner portion (210), an upper module surface portion (220A), a lower module surface portion (220B), an upper slab (230A), and a lower slab (230B), and has a hexahedral shape, and a wall portion may be further formed thereon.

[0035]

[0036] The module corner part (210) is a part installed vertically at the corner of a hexahedron. In a frame structure, this corresponds to a column within a PC module (200), and in a wall structure, this corresponds to a side edge part of the wall structure.

[0037] When two PC modules (200) are connected, they are spaced apart by a set amount, and the two module corner parts (210) facing each other are integrated by the concrete (C) poured between them to form a single column (610) load-bearing body. As described above, a shear connector (511) protruding outward must be installed on the outer surface of the module corner part (210) located in the direction in which the two PC modules (200) are connected to each other.

[0038] The above-mentioned shear connecting material (511) may be installed together with the manufacturing of the PC module (200), but it is preferable to install it during the construction process of the building in the future to facilitate the manufacturing of the PC module (200).

[0039] A protruding mounting portion (211) that protrudes further upward than the upper module surface portion (220A) can be formed on the module edge portion (210). This upper protruding structure of the module edge portion (210) facilitates the construction of an extended support structure (620) as described below. Therefore, the height of the protruding mounting portion (211) that protrudes further upward than the upper module surface portion (220A) of the module edge portion (210) must be a size set for the formation of a support structure (620) of a specification to be constructed by structural design, including the thickness of the upper module surface portion (220A) and the thickness of the lower module surface portion (220B) of the PC module (200) stacked thereon.

[0040] A guide pin (501) protruding upwards may be installed on the upper surface of the module edge portion (210). In this case, a guide groove (502) into which the guide pin (501) is inserted must also be provided on the lower surface of the module edge portion (210). The guide pin (501) and the guide groove (502) enable the stacking operation of the PC module (200) to be performed accurately and efficiently.

[0041] Additionally, a fastening hole (503) may be further provided at the module corner (210).

[0042] The above-mentioned fastening hole (503) is preferably positioned at the center of the cross-section of the module edge portion (210), and by inserting the tension member (504), the entire portion from the foundation (100) to the roof module (300) or between the PC modules (200) is structurally integrated. This fastening hole (503) may have a structure that penetrates from the top surface to the bottom surface of the module edge portion (210), or may be formed only in a portion of the top and bottom surfaces.

[0043]

[0044] The upper module surface (220A) is a part installed horizontally on the upper side of the module edge part (210). In the frame structure, this corresponds to the upper supporting structure within the PC module (200), and in the wall structure, this corresponds to the side edge part of the upper slab structure.

[0045] The lower module surface (220B) is a part installed horizontally at the bottom of the module edge (210). In a frame structure, this corresponds to the lower supporting structure within the PC module (200), and in a wall structure, this corresponds to the side edge of the lower slab structure.

[0046] Accordingly, the upper module surface (220A) and the lower module surface (220B) are positioned at the upper and lower portions between two adjacent module corner portions (210) to have a ramen structure.

[0047] A shear connector (511) may be installed on each of the upper module face (220A) and the lower module face (220B). The shear connector (511) installed here may also be installed together with the manufacturing of the PC module (200), but it is preferable to install it during the construction process of the building in the future.

[0048]

[0049] The upper slab (230A) and the lower slab (230B) are located on the inner side of the upper module face (220A) and the lower module face (220B), respectively. That is, the upper slab (230A) is installed between the horizontally opposed upper module faces (220A), and the lower slab (230B) is also installed between the horizontally opposed lower module faces (220B). The upper surface of the upper slab (230A) and the lower surface of the lower slab (230B) can have a waffle structure.

[0050]

[0051] Next, the above-described technical idea will be specifically explained through the most desirable example of the process of constructing a building by stacking PC modules (200). In addition, for convenience of explanation, the construction will be based on a frame structure.

[0052] In the present invention, a method for constructing a building by stacking hexahedral PC modules (200) includes a) a step of preparing the ground, b) a step of installing a foundation (100), c) a step of installing a PC module (200) on the upper surface of the foundation (100), d) a step of repeatedly installing an upper-layer PC module (200) on the upper surface of the installed PC module (200) to install the PC module (200) up to the top floor, and e) a step of installing a roof module (300), which are sequentially performed, and each of these steps is described in detail as follows.

[0053]

[0054] a) Ground preparation stage;

[0055] Level the ground of the site where you want to build a building.

[0056] This stage may include excavation, and depending on the ground conditions, it may also include further ground strengthening processes such as driving support piles.

[0057]

[0058] b) Step of installing the foundation (100);

[0059] Figure 4 illustrates a state in which a foundation (100) on which a PC module (200) is to be placed is installed.

[0060] It is preferable that the foundation (100) has a cross-sectional structure of a stem foundation so that the entire module corner portion (210) and lower module surface portion (220B) of the PC module (200) are placed on the upper surface of the foundation (100).

[0061] The above-described foundation (100) is composed of a foundation corner portion (110) and a foundation surface portion (120) corresponding to the above-described PC module (200). Accordingly, the module corner portion (210) of the PC module (200) is placed on the upper surface of the foundation corner portion (110), and the foundation surface portion (120) is positioned between the foundation corner portions (110) so that the lower module surface portion (220B) of the PC module (200) can be placed on the upper surface thereof.

[0062] The base corner portion (110) may be provided with a protruding mounting portion (111) that protrudes upward from the base surface portion (120), as in the module corner portion (210).

[0063] The base corner portion (110) is also provided with the above-described guide pin (501) and fastening hole (503), and when the fastening hole (503) is a through hole, a fixing groove (112) is further provided on the bottom surface as shown in Fig. 14. In addition, a shear connecting member (511) is installed on the base surface portion (120).

[0064] The foundation (100) at this stage can be manufactured in advance on a PC and installed on site, or can be built directly on site.

[0065] The above guide pin (501) and shear connector (511) must be installed before the next step of installing the PC module (200). Therefore, if the foundation (100) is made of PC, this step includes the installation process of the shear connector (511) protruding upwards from the foundation surface (120).

[0066] Meanwhile, the foundation edge part (110) is positioned where the module edge part (210) of the PC module (200) is positioned, and the foundation edge part (110) is also positioned inside the foundation (100) where two PC modules (200) are placed horizontally adjacent to each other. A plurality of module edge parts (210) are installed together in the foundation edge part (110) inside the foundation (100), and guide pins (501) in a number proportional to the number of module edge parts (210) must be installed so as to be spaced apart from each other.

[0067] For example, in a structure where one guide pin (501) is inserted into each module corner part (210), when two module corner parts (210) are positioned as shown in FIG. 3, the two guide pins (501) installed in the foundation corner part (110) must be installed spaced apart from each other so as to correspond to the set spacing of the PC modules (200). That is, the spacing of the guide pins (501) must be set to a size so that the column (610) load-bearing body can be expanded and formed to the desired specifications after the PC modules (200) are installed. This also applies to a case where another PC module (200) is stacked on the upper surface of a PC module (200) in a future step.

[0068] In addition, reinforcing bars for future connection with vertical reinforcing bars (521) can be installed in advance at the inner corner of the foundation (110) of the above-mentioned foundation (100).

[0069]

[0070] c) Step of installing a PC module (200) on the upper surface of the base (100);

[0071] Figures 5 to 8 each illustrate the process of installing a PC module (200) on the upper surface of a base (100).

[0072] First, concrete (C) is poured on a portion of the upper surface of the foundation (100) (specifically, the upper surface of the foundation surface (120)), as illustrated in Fig. 5. The pouring height of the concrete (C) is set to coincide with the upper surface of the protruding support member (111).

[0073] Next, as shown in Fig. 6, one of the PC modules (200) is installed on the upper surface of the base (100).

[0074] The installation of the PC module (200) is performed by inserting a guide pin (501) that is installed to protrude in advance from the base corner portion (110) into the guide groove (502) of the PC module (200). As a result, the PC module (200) can be naturally placed in the set position.

[0075] The point at which the PC module (200) is placed on the upper surface of the foundation (100) must be done while the concrete (C) is still in a raw concrete state. Accordingly, the shear connector (511) installed on the base surface (120) of the foundation (100) and the shear connector (511) installed on the lower module surface (220B) of the PC module (200) are embedded within the concrete (C), thereby securing structural integrity between the foundation (100) and the PC module (200).

[0076] As illustrated in Fig. 7, when the installation of one PC module (200) on the base (100) is completed, another PC module (200) to be connected thereto is installed on the upper surface of the base (100) in the same manner as described above. Accordingly, the adjacent PC modules (200) are also naturally spaced apart by the amount that each module corner portion (210) is set to.

[0077] When the installation of PC modules (200) on the upper surface of the foundation (100) is completed, vertical reinforcing bars (521) are placed inside the gaps between each module corner portion (210), and also, after blocking the inner end of each module corner portion, concrete (C) is poured to construct a column (610) of an expanded load-bearing body. Fig. 8 shows a state in which concrete (C) is poured inside the gaps between each module corner portion (210) to form an expanded column (610).

[0078] At this time, the vertical reinforcing bar (521) may be connected to a reinforcing bar installed in advance at the foundation corner portion (110) as described above.

[0079] In addition, before the PC module (200) is installed on the foundation (100), the shear connectors (511) installed on the foundation (100) and the PC module (200) can form hooks (511a) at the ends to increase the composite force, and it is preferable to form hooks (511a) at the ends of the shear connectors (511) installed at least on the module corners (210) so that buckling of the vertical reinforcing bars (521) is prevented by the hooks (511a). For this purpose, the direction of the hook (511a) must be inside the space formed by the gap between the module corners (210), and when the vertical reinforcing bar (521) is inserted into the hook (511a) of the shear connector (511) installed in the module corners (210) at this stage, as shown in FIG. 2, the vertical reinforcing bar (521) is wrapped by the hook (511a) portion, thereby preventing buckling due to axial force.

[0080]

[0081] d) A step of repeatedly installing the upper PC module (200) on the upper surface of the already installed PC module (200) to install the PC module (200) up to the top layer;

[0082] Figures 9 to 11 illustrate each process of installing an upper PC module (200) on the upper surface of a PC module (200) installed on a base (100).

[0083] This step may further include a process of installing interlayer materials for insulation or soundproofing between the upper and lower layers. For example, as illustrated in FIG. 9, by installing a plate-shaped insulation material (531) between the upper slab (230A) of the lower layer and the lower slab (230B) of the upper layer, it can have the function of the interlayer material described above as well as the function of an inner formwork for constructing the expanded reinforcement structure (620) described later, thereby further improving constructability.

[0084] When the above-mentioned insulation (531) installation work is completed, concrete (C) is poured on the upper surface of the upper module surface (220A) of the already installed PC module (200) in the same way as concrete (C) was poured on the foundation surface (120) previously, so as to align the surface with the upper surface of the protruding mounting portion (111, 211) of the module corner portion (210). Fig. 10 shows a state in which concrete (C) is poured on the upper surface of the upper module surface (220A) for the construction of an extended support structure (620).

[0085] When the pouring of concrete (C) on the upper surface of the upper module face (220A) of the previously installed lower PC module (200) is completed, the upper PC module (200) is installed on top of the lower PC module (200) in the same manner as in the preceding step c). That is, the guide pin (501) previously installed in the module edge (210) of the lower PC module (200) should be inserted into the guide groove (502) provided on the bottom surface of the module edge (210) of the newly installed upper PC module (200), so that it can be spaced apart from another adjacent upper PC module (200) by a set amount. The method of installing the vertical reinforcing bars (521) is also not different from that described in step c).

[0086] Of course, the PC modules (200) installed at this stage must be installed when the concrete (C) poured on the upper surface of the PC modules (200) of the lower layer that has already been installed is unhardened raw concrete, and at this time, the shear connector (511) must be installed before the PC modules (200) are installed so that it is embedded in the raw concrete, which is the same as when constructing an extended column (610).

[0087] After pouring concrete (C) on the upper surface of the installed PC module (200), the process of installing the PC module (200) on the upper floor is repeated to install the PC module (200) up to the top floor. Fig. 11 shows the state in which the PC module (200) is installed up to the planned top floor.

[0088]

[0089] e) Step of installing the roof module (300)

[0090] Figures 12 and 13 illustrate each step of the process of installing a roof module (300) on top of the top PC module (200).

[0091] As shown in Fig. 12, insulation (531) is installed on the upper slab (230A) of the top PC module (200), and concrete (C) is poured on the upper surface of the upper module face (220A) where a concrete (C) pouring space is formed, and then the roof module (300) is installed while the concrete (C) is still raw concrete before it hardens, thereby integrating them.

[0092] In addition, concrete (C) is poured into the space between adjacent roof modules (300) so that the extended column (610) becomes structurally integrated with the roof module (300). Fig. 13 shows a state in which the roof module (300) is installed through the above-described process.

[0093] During the above process, insertion of the guide pin (501) into the guide home (502) and installation of the vertical reinforcing bar (521) are no different from the lamination process of the PC module (200).

[0094] By completing the installation work of the roof module (300) only by pouring the above-mentioned concrete (C), the work on the structural part of the modular building can be completed. However, in addition, additional reinforcing means can be provided for stronger integration from the foundation (100) to the roof module (300).

[0095] For the above additional reinforcement means, the corners of the foundation corner (110), the module corner (210), and the roof module (300) must be provided with the above-described fastening holes (503).

[0096] That is, the above-mentioned additional reinforcing means enables the connection between the foundation (100) and the PC module (200), between each PC module (200), and between the PC module (200) and the roof module (300) to be integrated by tensile connection through the connection hole (503).

[0097] As described above, the above-mentioned tensile bond structurally integrates the entire structure from the foundation (100) to the roof module (300) or between the PC modules (200).

[0098] For example, the fastening hole (503) from the foundation corner part (110) to the support module can be made into a penetrating structure, and one end of a tensile body (504) such as a steel bar or a steel wire can be fixed to the roof module (300) and the other end can be anchored to the foundation corner part (110). In the case of a high-rise building, the entire building can be divided and the two ends of the tensile body (504) can be fixed to the two ends of each section as described above. However, in the case of the former, when it is desired to fasten the entire building with a single tensile body (504), this must be performed after the installation up to the roof module (300) is completed, but in the latter, when it is desired to fasten each section, the work of additional reinforcing means must be performed for each section during the installation process of the PC module (200).

[0099] Alternatively, a non-penetrating fastening hole (503) is provided on the upper surface of the foundation edge portion (110), the upper and lower surfaces of the module edge portion (210), and the lower surface of the corner of the roof module (300), and a sleeve having a female thread is installed in the fastening hole (503), and then a tension member (504) having male threads on both sides can be used to integrate the base (100) and the PC module (200), each PC module (200), and the PC module (200) and the roof module (300).

[0100] Fig. 14 illustrates an example of a building being secured with a single tension member (504). In this case, as described above, a fixing groove (112) must be provided in advance on the bottom surface of the foundation corner portion (110) so that the end of the tension member (504) can be fixed even after the foundation (100) is installed.

[0101]

[0102] While the present invention has been described in detail above with reference to specific embodiments, these embodiments are merely illustrative examples intended to facilitate understanding of the present invention. Therefore, it is apparent that those skilled in the art will be able to implement the present invention in various ways, within the scope of its technical spirit. Accordingly, such modifications are deemed to fall within the scope of the present invention as set forth in the claims.

[0103] The present invention relates to a method for constructing a modular building that can expand the specifications of a load-bearing body during the process of constructing a building by stacking hexahedral PC modules manufactured in a factory, and thus has industrial applicability.

Claims

1. In a method for constructing a building by stacking hexahedral PC modules (200), a) Ground preparation stage; b) Step of installing the foundation (100); c) A step of pouring concrete (C) on a portion of the upper surface of the foundation (100) and installing a PC module (200) on the upper surface of the foundation (100); d) A step of pouring concrete (C) on the upper surface of the installed PC module (200) and repeating the process of installing the PC module (200) of the upper layer to install the PC module (200) up to the top layer; e) a step of installing a roof module (300) on the upper surface of the uppermost PC module (200); which is comprised of, The above PC module (200) is It is composed of a module corner portion (210) installed vertically at the corner of the hexahedron, an upper module surface portion (220A) and a lower module surface portion (220B) installed horizontally at the upper and lower portions of the module corner portion (210), and an upper slab (230A) and a lower slab (230B) installed between the upper module surfaces (220A) and the lower module surfaces (220B) that are horizontally opposed to each other. The above foundation (100) is, It has a cross-sectional structure of a stem foundation, and is composed of a foundation edge portion (110) at a position where the module edge portion (210) is placed in step c) above, and a foundation surface portion (120) installed between adjacent foundation edge portions (110). The above step b) includes a process of installing a shear connector (511) protruding upwardly on the base surface (120), and an externally protruding shear connector (511) is installed on the outer surface of the module edge portion (210) located in the direction of connection between the upper and lower module surfaces (220B) of the PC module (200) and the adjacent PC module (200), but the installation of the shear connector (511) is performed before each installation step of the PC module (200). A method for constructing a modular building with an expandable internal structure, characterized in that among the shear connectors (511) installed in the PC module (200), at least the shear connectors (511) installed in the module corner portion (210) have a hook (511a) formed at the end.

2. In paragraph 1, The above-mentioned base corner portion (110) protrudes upwards from the base surface portion (120), A method for constructing a modular building with an internal expansion structure, characterized in that the above module corner portion (210) protrudes upwards more than the upper module surface portion (220A).

3. In paragraph 2, A method for constructing a modular building with an expandable load-bearing body, characterized in that the height at which the module corner portion (210) protrudes above the upper module face portion (220A) is a size set for forming a structural member (620) of a desired specification, including the thickness of the upper and lower module faces (220B).

4. In paragraph 1, The above step b) includes a process of installing a guide pin (501) protruding upwards on the base corner portion (110), A method for constructing a modular building with an internal expansion structure, characterized in that the PC module (200) is provided with a guide groove (502) into which a guide pin (501) is inserted on the bottom surface of the module corner portion (210).

5. In paragraph 4, In the inner side of the foundation (100) configured so that a plurality of module edge parts (210) among the above-mentioned foundation edge parts (110) are installed together, guide pins (501) in a number proportional to the number of module edge parts (210) are installed spaced apart from each other. A method for constructing a modular building with expandable load-bearing body, characterized in that the spacing of the guide pins (501) above is such that the spacing between the module corners (210) of each PC module (200) after installation of the PC modules (200) is set to a size for forming a load-bearing body of the desired specification.

6. In paragraph 1, A method for constructing a modular building with an expandable load-bearing body, characterized in that steps c) and d) above include a process of inserting and installing a vertical reinforcing bar (521) into a hook (511a) of a shear connector (511) installed in a module corner (210).

7. In paragraph 1, A method for constructing a load-bearing expandable modular building, characterized in that the installation of the PC module (200) in the above steps c) and d) is performed when the concrete (C) poured on the upper surface of the foundation (100) or the upper surface of the PC module (200) of the lower layer is unhardened raw concrete.

8. In paragraph 1, A fastening hole (503) is provided at the center of each cross-section of the above-mentioned base corner portion (110) and module corner portion (210). A method for constructing a modular building with an expandable load-bearing body, characterized in that the step d) or step e) includes a process of integrating the foundation (100) and each PC module (200) by inserting a tension member (504) into the fastening hole (503).

9. In paragraph 1, A method for constructing a load-bearing expandable modular building, characterized in that the step d) above includes a process of installing insulation (531) on the upper surface of an upper slab (230A) before pouring concrete (C).

Citation Information

Patent Citations

  • Apartment house

    JP1996184204A

  • Foundation of unit building

    JP1996232274A

  • Unit construction method

    JP2003082770A

  • Skin diary for personal skin and skin care routine improvement

    KR1020240077868A

  • Construction method of expandable load-bearing structure for modular building

    KR102620765B1