A system and method for improving coalbed methane extraction volume in surface drilling and extraction of old gobs
A surface drilling and coalbed methane technology, which is applied in the direction of earthwork drilling, mining fluid, wellbore/well components, etc., can solve the problems of high accident rate, difficult construction, low porosity rate, etc., so as to save economic cost, Improve rock breaking efficiency and fast crushing speed
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2018-01-02
Smart Images

Figure 1
Abstract
Description
technical field
[0001] The invention relates to a system and a method for improving the coalbed methane extraction volume in the old goaf area of ground drilling and drainage, and belongs to the technical field of coalbed methane extraction. Background technique
[0002] At present, my country mainly adopts surface drilling to extract residual coalbed methane in the old empty area, and the extraction effect is not ideal. When the production of coalbed methane decreases, surface drilling is often abandoned directly. A large amount of underground coalbed methane is fully extracted and utilized, and a large amount of available coalbed methane is still adsorbed in a large amount of unmined coal in the underground. It will take a certain time for this part of coalbed methane to desorb from the adsorption state to the free state. At this time, if the ground drilling is abandoned, a large amount of coalbed methane will be abandoned. The utilization of ground still requires ground...
Examples
Embodiment
[0029] Such as figure 1 As shown, the present invention provides a system for improving the extraction volume of coalbed methane in the old goaf area of ground drilling, including extraction drilling 1, surface extraction station 11, valve II 7, extraction pipe 4, injection pipe 5, pressure Table 23, valve Ⅰ 8, tee pipe Ⅰ 20, heating device 22, liquid booster pump 17, liquid CO 2 Storage tank 16, refrigeration device 15, valve III 14, gas booster pump 9, valve IV 13, tee pipe II 21, CO 2 The gas storage tank 10, the extraction well 1 leads to the bottom of the coal pillar 3, the extraction pipe 4 and the injection pipe 5 are sent to the bottom of the coal pillar 3 through the extraction well 1; the sealing section I (6) is flush with the ground, The sealing section II (19) is located 0.5~2m above the coal pillar; the injection pipe 5 above the ground is connected to the pressure gauge 23, the valve I8, and the tee pipe I20, and the other end of the tee pipe I20 is connected...