A method for installing super high and super large floating cranes in dock
A floating crane, ultra-large technology, applied in the direction of cranes, etc., can solve the problem of hoisting and carrying herringbone frame, the lifting capacity of the gantry crane cannot meet the requirements of the herringbone frame, the overall hoisting of the main arm frame of the boom bracket, and the construction of no floating crane, etc. problems, to achieve the effect of reducing cost and construction cycle
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2017-08-08
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to a method for installing a super-high and super-large floating crane in a shipyard. Background technique
[0002] Research on super-high floating cranes for offshore installation and construction of marine engineering, such as deep-sea semi-submersible platforms, towering legs of jack-up drilling platforms, drilling derricks and other offshore marine engineering equipment maintenance, dismantling and installation, overall hoisting of offshore wind power, etc. This project is proposed and researched under such a background, super-lifting height, large lifting capacity, large working range, four-hook large-plane multi-hanging points, special main and auxiliary jib frames, used for offshore engineering manufacturing, installation and maintenance Technical research, design and manufacture of special crane vessels; research and development, design and manufacture of a new generation of ultra-large floating cranes with stronger capabi...
Examples
Embodiment Construction
[0032] like Figure 1-8 As shown, a method for installing super high and super large floating cranes in a dock includes the following steps:
[0033] Step 1: After the hull is closed in the dock, adjust the level of the hull, draw the hull deck centerline 1 on the deck surface, and use this as a reference to draw the centerline 2 of the gable frame tie rod and the center line 3 of the gable frame pressure rod , centerline of the rear outrigger of the jib bracket 4, centerline of the front outrigger of the jib bracket 5 and centerline of the luffing mechanism 6, centerline of the main hook lifting mechanism 9, centerline of the auxiliary hook lifting mechanism 10, main hook rigging The centerline 8 of the hook mechanism, the centerline 7 of the hook mechanism of the auxiliary hook rigging, recheck after marking;
[0034] Step 2: Install and weld the guide plate at the installation position of the jib bracket on the hull deck, use a 900T gantry crane to hoist the rear outrigger...