Technology for filling of gob under well with adhesive filling materials
A technology of cemented filling and filling slurry, which is applied to filling materials, mining equipment, earth square drilling and mining, etc. It can solve the problems of discontinuous preparation of filling slurry, increased mixing time, and insufficient mixing, so as to save pressure filtration and Effects of tailings stockpiling cost, material transport reduction, and filling cost reduction
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2017-06-23
- Estimated Expiration
- Not applicable · inactive patent
Smart Images

Figure 1
Abstract
Description
technical field
[0001] The invention relates to the technical field of mine filling slurry, in particular to a process for filling underground mined-out areas with cemented filling slurry. Background technique
[0002] When the tailings produced by the gravity separation process are used as mine filling materials, it is necessary to carry out crushing and other treatment processes on the mineral processing waste slag produced in the dressing plant, and then process them below a certain particle size, and then mix them with cementing materials to prepare filling slurry and fill them to the goaf Area. However, the content of fine particles in the crushed material of waste residue is very low, and the fluidity of the slurry made from the crushed material is poor, and it is often necessary to add a large amount of cement or use a booster pump to transport it. In order to reduce cement consumption and improve the fluidity of filling slurry in China, multi-stage technological pro...
Examples
Embodiment Construction
[0031] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without creative efforts fall within the protection scope of the present invention.
[0032] The invention discloses a process for filling underground mined-out area with cemented filling slurry, the steps are as follows:
[0033] 1) Release the tailings waste slag produced by the dressing plant from the waste slag bin through the ore-drawing valve, and transport it to the screening vibrating screen through the belt conveyor for the first stage of screening;
[0034] 2) The fine material under the screen is sent to the finished sand and gravel silo through the ...