A prestressed anchor cable combined with a drainage board preloading device and a foundation treatment method
Through the prestressed anchor cable combined with the drainage plate preloading device, the jack is used to provide reaction force and hydraulic control load, which solves the problems of long construction period, large soil consumption and difficult load control in the existing foundation treatment technology, and achieves an efficient and stable foundation. processing effect.
Patent Information
- Application Number
- CN201810468507.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-05-16
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2038-05-16
AI Technical Summary
Among the existing foundation treatment technologies, the pile-load preloading method has a long construction period, requires a large amount of soil, and has a limited treatment depth. The vacuum preloading method has high technical requirements and limited effects, and the manual tightening nut control efficiency is low, especially in soft soil layers. When it is deep, it is difficult for the anchor rod to reach the bearing layer, and the preload load cannot be effectively controlled.
Prestressed anchor cables combined with drainage plate preloading devices are used, including prestressed anchor cables, reaction frames and plastic drainage plates. The reaction force is provided through jacks. The anchor cables pass through the soft soil layer to the bearing layer, combined with the concrete panel and hydraulic pump. Control the load to achieve uniform preloading and rapid drainage.
It reduces the stacking load, shortens the construction period, improves the load control accuracy, avoids foundation instability, has low equipment requirements, and has good engineering adaptability and economic benefits.
Smart Images

Figure CN108442357B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of foundation treatment, and in particular relates to a prestressed anchor cable structure. Background Art
[0002] At present, the preloading method in foundation treatment technology is widely used in actual engineering, but there are still some practical application problems: the preloading method requires a relatively long construction period, requires a large amount of piled soil, the treatment depth is controlled by the piled load size and the length of the drainage board, and may cause foundation instability; the vacuum preloading method has high technical requirements, the treatment effect is limited by the vacuum level, and the treatment depth is generally shallow;
[0003] Wang Kuihua's method of treating soft foundation with ground anchor and reaction loading preloading compresses the spring by manually tightening the nut, and uses the reaction force of the spring to apply upward pulling force to the ground anchor rod to preload the steel plate on the foundation. It does not require a loading soil source and is not restricted by site conditions. However, when the soft soil layer is deep, it is difficult for the anchor rod to reach the bearing layer. Moreover, the preloading load cannot be well controlled by manual pressure, and when the preloading pressure to be loaded is large, the force-receiving component of the ground anchor needs to be reinstalled with a jack to reach the preloading pressure value, which is relatively inefficient. Summary of the invention
[0004] The purpose of the present invention is to overcome the deficiencies in the prior art and to provide a prestressed anchor cable combined with a drainage board preloading device and a foundation treatment method.
[0005] This prestressed anchor cable combined with a drainage board preloading device comprises a prestressed anchor cable and a reaction frame, wherein the prestressed anchor cable comprises an anti-pullout anchor head, a steel strand and a fixed end head, wherein the anti-pullout anchor head penetrates into the foundation bearing layer, the upper end of the anti-pullout anchor head is connected to the lower end of the steel strand, a plastic drainage board is sleeved on the outer side of the steel strand, and a sand cushion layer is provided above the plastic drainage board; the upper end of the steel strand is connected to the fixed end head, and the fixed end head is fixed to the central reserved hole of the reaction frame; the reaction frame comprises a concrete panel, a reaction frame base, a crossbeam and a jack, wherein the concrete panel is located above the sand cushion layer, the reaction frame base is located above the concrete panel, the jack constitutes a column of the reaction frame, and the bottom of the crossbeam is connected to the jack.
[0006] Preferably, the pull-out anchor head is located in the bearing layer, and two rows of side rods are arranged outside the pull-out anchor head.
[0007] Preferably, the concrete panel is prefabricated with reserved holes and is assembled from multiple pieces.
[0008] The foundation treatment method of the prestressed anchor cable combined with the drainage board preloading device comprises the following steps:
[0009] Step 1): Level the site and lay the lower sand cushion layer;
[0010] Step 2): Install plastic drainage board;
[0011] Step 3): Lay an upper sand cushion layer, and place a concrete panel with reserved holes on the sand cushion layer;
[0012] Step 4): Driving prestressed anchor cables, passing the prestressed anchor cables through the reserved holes of the concrete panel and drilling down, so that the pull-out anchor head at the bottom of the anchor cables passes through the soft soil layer in the treatment area to the bearing layer;
[0013] Step 5): Install the reaction frame above the concrete panel. The reaction frame is directly placed on the concrete panel to evenly transmit the reaction force to the concrete panel, the sand cushion layer and the soft soil layer;
[0014] Step 6): Tension the steel strand and fix the fixed end to the central reserved hole of the reaction frame.
[0015] Step 7): Operate the jack, the crossbeam of the reaction frame bears the lifting force of the jack and the tension provided by the anchor cable through the fixed end, the base of the reaction frame bears the downward reaction force of the jack and transmits it to the concrete panel, and the concrete panel evenly spreads the load to the foundation surface as a preload;
[0016] Step 8): The pore water is discharged to the ground through the plastic drainage board;
[0017] Step 9): The load is applied in stages, and the preload of each stage is controlled to remain stable by setting the oil pressure of the hydraulic pump; the development of foundation settlement is monitored by measuring the lifting stroke of the jack; when the change in settlement value per unit time is less than the set value, it indicates that the settlement of this stage of loading has reached stability, and the next level of loading is carried out until the preload value reaches the final requirement and the settlement reaches stability, then the preloading process is ended.
[0018] As a preferred embodiment, when the foundation treatment area is large, the number of plastic drainage boards and anchor cables is appropriately increased in step 2) and step 4) to speed up drainage.
[0019] As a preferred embodiment: in step 9), the control device of the jack controls the graded pressurization of the jack by an oil distribution valve and a hydraulic pump.
[0020] Preferably, after step 9), the jack and its control equipment, reaction frame, concrete panel and anchor cable are all recovered for recycling.
[0021] The beneficial effects of the present invention are:
[0022] 1. The present invention provides upward pulling force by lifting the reaction frame with a jack, thereby reducing the loading process, or can be used in conjunction with the loading preloading, thereby greatly reducing the required loading amount for the design; and combined with the drainage board to treat the foundation, the construction period is accelerated.
[0023] 2. The jack can achieve relatively fast and accurate graded loading. The size of the preload and the loading speed are easy to control, which can avoid the problem of foundation instability caused by excessive loading speed during the loading process.
[0024] 3. The present invention has low requirements on equipment, does not require high-strength, high-precision and expensive instruments, and is highly economical.
[0025] 4. Loading equipment such as jacks and reaction frames can be reused, are easy to transport, and have good economic benefits.
[0026] 5. The loading equipment such as anchor cables, jacks, reaction frames, etc. can be flexibly arranged on site, can effectively handle a variety of working conditions, and have good engineering adaptability. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a partial cross-sectional schematic diagram of the present invention;
[0028] Figure 2 It is a top view of the prestressed anchor cable combined with the drainage board preloading device;
[0029] Figure 3 It is a top view of the reaction frame base;
[0030] Figure 4 is a top view of the beam;
[0031] Figure 5 This is a schematic diagram of the assembly of concrete panels;
[0032] Figure 6 This is a diagram of the control device for the jack;
[0033] Explanation of the reference numerals in the accompanying drawings: pull-out anchor head 1, steel strand 2, plastic drainage board 3, sand cushion layer 4, concrete panel 5, reaction frame base 6, cross beam 7, jack 8, fixed end 9, center reserved hole 10, oil distribution valve 11, hydraulic pump 12. DETAILED DESCRIPTION
[0034] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for those of ordinary skill in the art, without departing from the principles of the present invention, several improvements and modifications may be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
[0035] The prestressed anchor cable combined with drainage board preloading device improves the existing pile load preloading method, and uses prestressed anchor cables and reaction frames to preload and drain the foundation. The prestressed anchor cable combined with drainage board preloading device comprises: a prestressed anchor cable and a reaction frame, the prestressed anchor cable comprises an anti-pulling anchor head 1, a steel strand 2, and a fixed end head 9, the anti-pulling anchor head 1 is a reinforced anchor head, which is easy for the anchor cable to be driven into the bearing layer and difficult to be pulled out, and its upper end is connected to the lower end of the steel strand 2, the outer side of the steel strand 2 is covered with a plastic drainage board 3, and the upper part of the plastic drainage board 3 is a sand cushion layer 4, and the water in the soft soil layer can flow into the drainage board under the action of preloading and finally be discharged from the sand cushion layer 4. The upper end of the steel strand 2 is connected to the fixed end head 9, and the fixed end head 9 is fixed on the central reserved hole 10 of the reaction frame, and the reaction frame comprises a concrete panel 5, a reaction frame base 6, a crossbeam 7, and a jack 8. The concrete panel 5 is located above the sand cushion layer 4 , the reaction frame base 6 is located above the concrete panel 5 , the jacks 8 constitute columns of the reaction frame, and the bottom of the crossbeam 7 is connected to the jacks 8 .
[0036] The pull-out anchor head 1 is in the bearing layer, and two rows of side rods are arranged outside the pull-out anchor head 1, which can provide sufficient pull-out resistance for the anchor cable and evenly transmit the reaction force of the pull-out resistance to the concrete panel 5 through the reaction frame structure.
[0037] The plastic drainage board 3 material has good strength, ductility and water conductivity, and can adapt to the deformation capacity of the foundation without affecting the drainage performance.
[0038] The concrete panel 5 is prefabricated with reserved holes, so that multiple pieces can be assembled and used.
[0039] The jack 8 is an electric synchronous hydraulic jack, which can provide sufficient lifting force and long-term load work, and support multiple jacks to lift at the same time. The control device of the jack 8 controls the graded pressurization of the jack 8 by an oil distribution valve 11 and a hydraulic pump 12.
[0040] In the reaction frame, the deadweight of the concrete panel 5, the reaction frame base 6, the crossbeam 7 and the jack 8 can be considered as the vertical load at the same time.
[0041] First, a sand cushion layer 4 is laid on the soft soil layer and a plastic drain board 3 is installed. Then, a concrete panel 5 is placed, and prestressed anchor cables are installed at the reserved holes of the concrete panel 5 to the bearing layer. A reaction frame with jacks 8 replacing columns is set on the ground. The crossbeam 7 of the reaction frame is lifted by the jack 8, and the prestressed anchor cables are tensioned, and a uniform and controllable preload is applied to the foundation surface through the reaction frame structure. The pore water is discharged by the plastic drain board 3, and the foundation is consolidated.
[0042] The foundation treatment method of the prestressed anchor cable combined with the drainage board preloading device has the following specific steps:
[0043] Step 1: Level the site and lay the lower sand cushion layer 4.
[0044] Step 2: Install plastic drainage board 3.
[0045] Step 3: Lay the upper sand cushion layer 4 , and place the concrete panel 5 with reserved holes on the sand cushion layer 4 .
[0046] Step 4: Install the prestressed anchor cable, and drill the prestressed anchor cable through the reserved hole of the concrete panel 5, so that the pull-out anchor head 1 at the bottom of the anchor cable passes through the soft soil layer in the treatment area to the bearing layer.
[0047] Step 5: Install the reaction frame above the concrete panel 5. The reaction frame is placed directly on the concrete panel 5 to facilitate uniform transmission of the reaction force to the concrete panel 5, the sand cushion layer 4 and the soft soil layer.
[0048] Step 6: Tension the steel strand 2 and fix the fixed end 9 to the central reserved hole 10 of the reaction frame.
[0049] Step 7: Operate the jack 8. The crossbeam 7 of the reaction frame bears the lifting force of the jack 8 and the tension provided by the anchor cable through the fixed end 9. The reaction frame base 6 bears the downward reaction force of the jack 8 and transmits it to the concrete panel 5. The concrete panel 5 evenly spreads the load to the foundation surface as a preload.
[0050] Step 8: The pore water is discharged to the ground through the plastic drainage board 3.
[0051] Step 9: Plan the size of the graded load in advance, and control the preload of each level to remain stable by setting the oil pressure of the hydraulic pump 12. Monitor the development of foundation settlement by measuring the lifting stroke of the jack 8. When the change in the settlement value per unit time is less than the set value, it indicates that the settlement of this level of loading has reached stability, and the next level of loading can be carried out until the preload value reaches the final requirement and the settlement reaches stability, then the preload process ends.
[0052] When the foundation treatment area is large, the number of plastic drainage boards 3 and anchor cables is appropriately increased in step 2 and step 4 to speed up drainage.
[0053] The control device of the jack 8 controls the graded pressurization of the jack 8 by means of an oil distribution valve 11 and a hydraulic pump 12 .
[0054] After the preloading process is completed, the jack 8 and its control equipment, the reaction frame, the concrete panel 3 and the anchor cable are all recovered for recycling.
[0055] The reaction frame is a prefabricated structure made of steel sections, and the plane layout of the jack 8 and the reaction frame can be designed according to actual engineering requirements.
Claims
1. A prestressed anchor cable combined with a drainage board preloading device, characterized in that: The invention comprises a prestressed anchor cable and a reaction frame, wherein the prestressed anchor cable comprises an anti-pullout anchor head (1), a steel strand (2) and a fixed end head (9), wherein the anti-pullout anchor head (1) penetrates into the foundation bearing layer, the upper end of the anti-pullout anchor head (1) is connected to the lower end of the steel strand (2), the outer side of the steel strand (2) is covered with a plastic drainage board (3), and the upper part of the plastic drainage board (3) is a sand cushion layer (4); the upper end of the steel strand (2) is connected to the fixed end head (9), and the fixed end head (9) is fixed to the central reserved hole (10) of the reaction frame; The frame comprises a concrete panel (5), a reaction frame base (6), a crossbeam (7) and a jack (8); the concrete panel (5) is located above the sand cushion layer (4); the reaction frame base (6) is located above the concrete panel (5); the jack (8) constitutes a column of the reaction frame; the bottom of the crossbeam (7) is connected to the jack (8); the pull-out anchor head (1) is located in the bearing layer, and two rows of side rods are arranged outside the pull-out anchor head (1); the concrete panel (5) is prefabricated with reserved holes and is composed of multiple pieces.
2. A foundation treatment method for the prestressed anchor cable combined with the drainage board preloading device according to claim 1, characterized in that: The following steps are involved: Step 1): Level the site and lay the lower sand cushion layer (4); Step 2): Install plastic drainage board (3); Step 3): Laying an upper sand cushion layer (4), and placing a concrete panel (5) with reserved holes on the sand cushion layer (4); Step 4): installing prestressed anchor cables, passing the prestressed anchor cables through the reserved holes of the concrete panel (5) and drilling down, so that the pull-out anchor head (1) at the bottom of the anchor cables passes through the soft soil layer in the treatment area until reaching the bearing layer; Step 5): Install a reaction frame above the concrete panel (5), the reaction frame is directly placed on the concrete panel (5), and the reaction force is evenly transmitted to the concrete panel (5), the sand cushion layer (4) and the soft soil layer; Step 6): tension the steel strand (2) and fix the fixed end (9) to the central reserved hole (10) of the reaction frame. Step 7): operate the jack (8), the crossbeam (7) of the reaction frame bears the lifting force of the jack (8) and the tension provided by the anchor cable through the fixed end (9), the reaction frame base (6) bears the downward reaction force of the jack (8) and transmits it to the concrete panel (5), and the concrete panel (5) evenly spreads the load to the foundation surface as a preload; Step 8): The pore water is discharged to the ground through the plastic drainage board (3); Step 9): The magnitude of the load applied is graded, and the preload of each stage is controlled to remain stable by setting the oil pressure of the hydraulic pump (12); the development of the foundation settlement is monitored by measuring the lifting stroke of the jack (8); when the change in the settlement value per unit time is less than the set value, it indicates that the settlement of this stage of loading has reached stability, and the next stage of loading is carried out until the preload value reaches the final requirement and the settlement reaches stability, and the preload loading process is terminated.
3. The foundation treatment method of the prestressed anchor cable combined with the drainage board preloading device according to claim 2 is characterized in that: When the foundation treatment area is large, the number of plastic drainage boards (3) and anchor cables is appropriately increased in step 2) and step 4) to speed up drainage.
4. The foundation treatment method of the prestressed anchor cable combined with the drainage board preloading device according to claim 2 is characterized in that: In step 9), the control device of the jack (8) controls the graded pressurization of the jack (8) by means of the oil distribution valve (11) and the hydraulic pump (12).
5. The foundation treatment method of the prestressed anchor cable combined with the drainage board preloading device according to claim 2 is characterized in that: After step 9) is completed, the jack (8) and its control equipment, reaction frame, concrete panel (3) and anchor cables are all recovered for recycling.
Citation Information
Patent Citations
Method and device for regulating and controlling deformation of foundation by utilizing pullout resistance of reinforcing elements
CN102242546A
Ground anchor and counter-force loading type soft foundation prepressing treatment method
CN106087945A
Joint drain bar pre -compaction device of prestressed anchorage cable
CN208668396U