Simulation device and simulation method for shield construction

By designing a simulation device including a test soil bin, a shield cutterhead assembly and a measuring segment assembly, the problems of insufficient diameter and high cost of the existing shield simulation device are solved, and simple and accurate shield construction simulation and earth pressure are achieved Measure and visually observe the grouting effect.

CN110242315BActive Publication Date: 2024-10-11CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910512064.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-06-13
Publication Date
2024-10-11
Estimated Expiration
2039-06-13

AI Technical Summary

Technical Problem

The diameter of the existing shield simulation device is too small to accurately simulate the actual scene. The diameter is large, the cost is high, and the attitude control is difficult, making it difficult to simulate the shield construction process simply and accurately.

Method used

A simulation device is designed that includes a test soil bin, a shield cutterhead assembly and a measuring segment assembly. The transparent front wall allows for visual observation of formation movement. The measuring segment assembly is used to accurately measure earth pressure, and is used to accurately measure earth pressure through the driving spindle and traction mechanism. Realize the movement of the cutterhead and shield shell and simulate the shield excavation process.

Benefits of technology

It achieves a simple and accurate simulation of the shield construction process. It can visually observe the movement and collapse of the ground, accurately measure the earth pressure, and at the end of the simulation, the measuring segment assembly can be disassembled to observe the grouting effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110242315B_ABST
    Figure CN110242315B_ABST
Patent Text Reader

Abstract

The present invention is applicable to the field of underground engineering tests, and provides a simulation device and method for shield construction. The simulation device for shield construction provided by the present invention includes: a test soil bin, a receiving cavity for receiving sample soil is formed inside the test soil bin, and the test soil bin includes two transparent front walls arranged at intervals, and an opening connecting the receiving cavity is formed between the two transparent front walls; a shield cutterhead assembly, at least partially arranged in the receiving cavity, and capable of moving along the extension direction of the opening to excavate the sample soil; a measuring segment assembly, which can be arranged in the receiving cavity adjacent to the shield cutterhead assembly, and the measuring segment assembly includes a segment with a grouting hole and an earth pressure measuring device fixed on the segment. The simulation device and method for shield construction of the present invention can simply, intuitively and accurately simulate the actual scene of shield construction and measure the stress conditions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of underground engineering experiments, and in particular relates to a simulation device and a simulation method for shield construction. Background Art

[0002] With the acceleration of urbanization and the increasing advancement of tunnel design and construction technology, earth pressure balance shield technology has been widely used in underground tunnel construction. Since the geological conditions of shield construction are complex and the construction environment varies greatly, experimental simulation of shield construction has become an effective means to study shield construction technology. Some of the related shield simulation devices have too small diameters, making it difficult to assemble the segments and grouting reinforcement, and thus cannot accurately simulate the actual scene of shield construction; while shield simulation devices with large diameters have high simulation costs and difficulty in controlling the posture during the excavation process. Summary of the invention

[0003] In view of this, the present invention provides a simulation device and a simulation method for shield construction to solve the technical problem of how to simulate shield construction simply and accurately.

[0004] In order to solve the above problems, the present invention provides a simulation device for shield construction, comprising: a test soil bin, a accommodating cavity for accommodating sample soil is formed inside the test soil bin, the test soil bin comprises two transparent front walls arranged at intervals, and an opening connected to the accommodating cavity is formed between the two transparent front walls; a shield cutterhead assembly, at least partially arranged in the accommodating cavity, and capable of moving along the extension direction of the opening to excavate the sample soil; a measuring segment assembly, which can be arranged in the accommodating cavity adjacent to the shield cutterhead assembly, and the measuring segment assembly comprises a segment with grouting holes and an earth pressure measuring device fixed on the segment.

[0005] Preferably, the shield cutterhead assembly includes: a cutterhead, including a protrusion with a through hole and a connecting portion arranged around the protrusion; a tool protruding and fixed to the outer surface of the protrusion; a shield shell, one end of which is rotatably connected to the connecting portion and the other end of which is adjacent to the measuring segment assembly; and a driving spindle fixedly connected to the protrusion to drive the cutterhead to rotate and move in the direction in which the opening extends.

[0006] Preferably, the simulation device further comprises a cutter disc rotation driving mechanism, which comprises a main gear fixed on the driving main shaft, a driving gear meshing with the main gear for transmission, and a driving device connected to the driving gear.

[0007] Preferably, the simulation device also includes a cutter disc traction mechanism, which includes: a fixed plate to keep the position fixed; a traction jack having a first end fixedly connected to the fixed plate and a second end opposite to the first end; a traction plate fixedly connected to the second end of the traction jack; wherein the drive spindle passes through the fixed plate and the traction plate and engages with the traction plate.

[0008] Preferably, the traction plate is provided with a groove, one end of the driving spindle is fixedly connected to the protruding portion of the cutter disc, and the other end of the driving spindle is provided with a sphere, which is inserted into the groove.

[0009] Preferably, a shield tail brush is provided at the other end of the shield shell, and the shield tail brush can contact the pipe segment.

[0010] Preferably, there are multiple segments, and the measuring segment assembly further comprises: a waterproof pad, which is arranged between adjacent segments; and a connector, which fixedly connects the adjacent segments and the corresponding waterproof pads.

[0011] Preferably, the pipe segment is semi-cylindrical, and a plurality of earth pressure measuring devices arranged at intervals along the circumferential direction are fixed to the outer wall surface of each pipe segment.

[0012] Preferably, the simulation device further comprises: a retaining plate movable along the extension direction of the opening; and a retaining plate limiter detachably fixed to the transparent front wall to limit the retaining plate to be located in the opening and to conflict with the two transparent front walls.

[0013] Preferably, the simulation device further comprises: a tube segment stopper, fixed to the transparent front wall, to prevent the tube segment from moving out of the accommodating cavity.

[0014] Preferably, the simulation device also includes: a segment reaction force applying device, which is fixed to the test soil bin, can be detachably connected to the segment and exerts a force in the opposite direction to the movement of the shield cutter head assembly.

[0015] Preferably, the segment reaction force applying device includes: a reaction jack, one end of which is fixed to the test soil bin and the other end is fixed to the first plate; a pull rod, one end of which is fixed to the first plate and the other end is fixed to the second plate; a reaction rod, one end of which is fixed to the second plate and the other end is detachably connected to the segment.

[0016] The present invention also provides a simulation method for shield construction, comprising: setting a test soil bin, wherein a holding cavity for holding sample soil is formed inside the test soil bin, wherein the test soil bin comprises two transparent front walls arranged at intervals, and an opening communicating with the holding cavity is formed between the two transparent front walls; the sample soil is filled into the test soil bin to the lower edge of the opening; a shield cutterhead assembly is installed in the opening, so that the shield cutterhead assembly is at least partially arranged in the holding cavity; the shield cutterhead assembly comprises: a cutterhead, comprising a protruding portion with a through hole and a connecting portion arranged around the protruding portion; a cutter protruding and fixed to the outer surface of the protruding portion; surface; a shield shell, one end of which is rotatably connected to the connecting portion; a driving spindle, fixedly connected to the protrusion, to drive the cutter disc to rotate and move along the direction in which the opening extends; a retaining plate is installed in the opening adjacent to the cutter disc to close part of the opening; the sample soil is filled in the test soil bin to a preset height, wherein the preset height is higher than the upper edge of the opening; a first pipe segment is installed in the test soil bin adjacent to the shield shell; the driving spindle is driven to rotate and move to drive the cutter disc and the shield shell to move; a second pipe segment is installed between the first pipe segment and the moved shield shell.

[0017] Preferably, after the shield cutterhead assembly is installed in the opening, the method further includes: installing a cutterhead rotation drive mechanism and a cutterhead traction mechanism, wherein the cutterhead rotation drive mechanism and the cutterhead traction mechanism are connected to the driving spindle to respectively drive the driving spindle to rotate and move.

[0018] Preferably, the cutter disc and the shield shell move while pulling the earth retaining plate to move at the same speed.

[0019] Preferably, the adjacent shield shell applies a reaction force to the first segment while installing the first segment in the test soil bin, and cancels the reaction force applied to the first segment and applies a reaction force to the second segment while installing the second segment between the first segment and the moved shield shell.

[0020] Preferably, grouting is performed after the first pipe segment and / or the second pipe segment are installed, and the soil pressure borne by the first pipe segment and / or the second pipe segment is measured before and after the grouting.

[0021] Preferably, the simulation method further comprises: removing the first pipe segment and / or the second pipe segment after grouting.

[0022] The simulation device for shield construction provided by the present invention comprises a test soil bin, a shield cutterhead assembly and a measuring segment assembly. The test soil bin has two transparent front walls with an opening in the middle. The shield cutterhead assembly can move along the extension direction of the opening. The measuring segment assembly is arranged adjacent to the shield cutterhead assembly, and comprises a segment with a grouting hole and a soil pressure measuring member arranged on the segment. The front wall of the test soil bin of the present invention is transparent, so that the movement and collapse of the strata under different stratum conditions can be observed intuitively during the movement of the shield cutterhead assembly to simulate the shield construction process; by installing the measuring segment assembly, the soil pressure and grouting pressure on the segment can be accurately measured; and at the end of the simulation process of the shield construction, the measuring segment assembly can be removed to intuitively observe the grouting effect. Therefore, the simulation device and simulation method for shield construction of the present invention can simply, intuitively and accurately simulate the actual scene of shield construction and measure the stress conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 It is a structural schematic diagram of a simulation device for shield construction provided by an embodiment of the present invention;

[0025] Figure 2 It is a schematic diagram of the structure of the test soil bin provided by an embodiment of the present invention;

[0026] Figure 3A is a schematic structural diagram of a shield cutterhead assembly provided in an embodiment of the present invention;

[0027] Figure 3B is a side view of a shield cutterhead assembly provided by an embodiment of the present invention;

[0028] Figure 4A is a structural schematic diagram of a cutter disc rotation drive mechanism provided by an embodiment of the present invention;

[0029] Figure 4B is a side view of a cutter disc rotation drive mechanism provided by an embodiment of the present invention;

[0030] Figure 5A is a structural schematic diagram of a cutter disc traction mechanism provided by an embodiment of the present invention;

[0031] Figure 5B is a side view of a cutter head traction mechanism provided by an embodiment of the present invention;

[0032] Fig. 6Ais a structural schematic diagram of a measuring segment assembly provided by an embodiment of the present invention;

[0033] Figure 6B is a side view of a measuring segment assembly provided by an embodiment of the present invention;

[0034] Fig. 7A It is a schematic structural diagram of a retaining plate and a retaining plate stopper provided in an embodiment of the present invention;

[0035] Figure 7B is a side view of a retaining plate and a retaining plate stopper provided by an embodiment of the present invention;

[0036] Figure 8 is a schematic structural diagram of a segment stopper provided in an embodiment of the present invention;

[0037] Fig.9A is a schematic structural diagram of a segment reaction force applying device provided in an embodiment of the present invention;

[0038] Fig. 9B is a front view of a reaction rod provided by an embodiment of the present invention;

[0039] Fig. 9C It is a side view of a reaction rod provided in an embodiment of the present invention.

[0040] Description of reference numerals:

[0041] 1. Test soil bin; 11. Transparent front wall; 12. Opening; 2. Shield cutterhead assembly; 21. Cutterhead; 211. Protrusion; 212. Connecting part; 22. Cutting tool; 23. Shield shell; 24. Driving spindle; 25. Shield tail brush; 3. Measuring segment assembly; 31. Segment; 32. Soil pressure measuring piece; 33. Waterproof pad; 34. Connecting piece; 4. Cutterhead rotation drive mechanism; 41. Main gear; 42. Driving gear; 43 , driving device; 44, speed reducer; 5, cutter disc traction mechanism; 51, fixing plate; 52, traction jack; 53, traction plate; 54, controller; 61, earth retaining plate; 62, earth retaining plate limiter; 71, segment limiter; 72, rubber pad; 8, segment reaction force applying device; 81, reaction jack; 82, pull rod; 83, reaction rod; 84, first plate; 85, second plate; 831, threaded rod; 832, fan-shaped plate. DETAILED DESCRIPTION

[0042] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0043] It should be noted that the terms “setting” and “connection” should be understood in a broad sense. For example, it can be directly setting or connecting, or it can be indirectly setting or connecting through a central component or a central structure.

[0044] The various specific technical features and embodiments described in the specific implementation methods can be combined in any suitable manner unless there is any contradiction. For example, different implementation methods can be formed by combining different specific technical features / embodiments. In order to avoid unnecessary repetition, the various possible combinations of the specific technical features / embodiments in the present invention will not be described separately.

[0045] like Figure 1 As shown, the simulation device for shield construction provided by the embodiment of the present invention includes a test soil bin 1, a shield cutterhead assembly 2 and a measuring segment assembly 3.

[0046] like Figure 2 As shown, the test soil bin 1 includes two transparent front walls 11 spaced apart, as well as a bottom wall, two side walls and a rear wall. The bottom wall is connected to the two side walls and the rear wall as a whole. The two transparent front walls 11 are connected to the two side walls and coated with waterproof material on the contact surface, thereby enclosing a receiving cavity for receiving sample soil inside the test soil bin 1. The upper end of the test soil bin 1 is open for filling the sample soil into the receiving cavity. It should be noted that the surface of the transparent front wall 11 facing the observer is parallel to the direction in which the shield cutterhead assembly 2 advances. The "front" of the transparent front wall refers to facing the observer rather than the direction in which the shield cutterhead assembly 2 advances. Optionally, the two side walls and the rear wall of the bottom wall are made of steel plates, and reinforcing ribs are arranged on the steel plates. The two transparent front walls 11 are made of tempered glass plates. An opening 12 connected to the receiving cavity is formed between the two transparent front walls 11 spaced apart, and the height range in the receiving cavity corresponding to the opening 12 is used as the range of the tunneling tunnel of the shield cutterhead assembly 2 for simulating shield construction. For example, the lower transparent front wall extends upward from the bottom wall to 0.5m, and the upper transparent front wall extends from a height of 0.7m to 2m, and the height of 0.5-0.7m is the area of ​​the opening 12. The shield cutterhead assembly 2 is used to excavate within the height range corresponding to the opening 12, and the transparent front walls 11 above and below the opening 12 block the sample soil, so that the movement of the shield cutterhead assembly 2 simulates the shield construction process, and the movement and collapse of the strata under different stratum conditions can be directly observed, and the influence of the shield construction on the strata under the construction environment can be simply and effectively simulated.

[0047] like Figure 1 As shown, the shield cutterhead assembly 2 is at least partially disposed in the accommodating cavity inside the test soil bin 1, and can extend along the extension direction of the opening 12 ( Figure 1The shield cutterhead assembly 2 is moved horizontally to the right (in the horizontal direction shown) to dig the sample soil in the test soil bin 1. Optionally, the shield cutterhead assembly 2 is partially located outside the accommodating cavity and protrudes from the opening 12 to the front of the accommodating cavity; the shield cutterhead assembly 2 can also be completely located in the accommodating cavity, but should be close to the opening 12, so that the movement and collapse of the sample soil in the test soil bin 1 during the movement of the shield cutterhead assembly 2 can be observed from the transparent front wall 11.

[0048] like Figure 1 As shown, the measuring segment assembly 3 is arranged in the accommodating cavity adjacent to the shield cutterhead assembly 2. Specifically, the measuring segment assembly 3 is arranged in the opposite direction of the moving direction of the shield cutterhead assembly 2 ( Figure 1 The measuring segment assembly 3 and the shield cutter assembly 2 are adjacent to or in contact with each other, and there may be a certain space between them, as long as there are no other physical components. The measuring segment is used to simulate the segment forming the tunnel during shield construction. In the actual shield construction process, the shield cutter head advances a certain distance forward, and then the assembled segments are installed on the wall of the hole dug during the excavation to form a tunnel pipe. In order to stabilize the tunnel pipe, the segments are provided with grouting holes so as to stabilize the soil layer adjacent to the tunnel pipe by grouting. In this embodiment, the actual segments are simulated, and the measuring segment assembly 3 includes a segment with a grouting hole and an earth pressure measuring device fixed on the segment, so that the earth pressure and grouting pressure on the segment can be accurately measured; and at the end of the simulation process of the shield construction, the measuring segment assembly can also be removed to visually observe the grouting effect. The simulation device for shield construction of the present invention can simply, intuitively and accurately simulate the actual scene of shield construction and measure the stress conditions.

[0049] like Figure 3A and Figure 3B As shown, in some embodiments, the shield cutterhead assembly 2 includes a cutterhead 21, a cutter 22, a shield shell 23 and a drive spindle 24. The cutterhead 21 is a hollow, axisymmetric, hemispherical structure, including a protrusion 211 with a through hole and a connecting portion 212 arranged around the protrusion 211. The cutter 22 is fixed to the outer surface of the protrusion 211, and the cutter 22 protrudes relative to the protrusion 211 in the moving direction of the shield cutterhead assembly 2. Figure 3B As shown, the area of ​​the through hole on the protrusion 211 accounts for 25%-35% of the area of ​​the entire protrusion 211. The connection portion 212 of the cutter head 21 is rotatably connected to one end of the shield shell 23. During the movement of the shield cutter head assembly 2, the cutter head 21 rotates while the shield shell 23 does not rotate; the specific rotatable connection method can be connected through roller bearings, so that the transition area between the shield shell 23 and the connection portion 212 does not change in height difference.

[0050] The shield shell 23 is an axisymmetric device. The portion close to the connection portion 212 is a cylindrical structure with the same thickness, and the portion away from the connection portion 212 is a cylindrical structure with a gradually decreasing thickness. Figure 3A The left end shown in the figure) can be adjacent to the measuring segment assembly 3. As the shield cutterhead assembly 2 moves forward, the shield shell 23 also moves forward, forming a hole in the test soil bin 1, and at the same time, segments are installed on the wall of the hole to form a tunnel pipe. Every time the shield shell 23 moves forward a section, a segment is installed, so that the shield shell 23 is always kept adjacent to the segment. Furthermore, a shield tail brush 25 is provided at the tail end of the shield shell 23, and the shield tail brush 25 can contact the segment of the measuring segment assembly 3 to complete the installation of the segment. Specifically, the shield tail brush 25 is a plurality of small steel sheets, such as a steel sheet with a thickness of 2 mm, which are distributed at the tail end of the shield shell 23 in the circumferential direction. There are gaps between adjacent brush sheets to absorb the deformation of the brush sheets, and there is a certain overlap between the brush sheets, which can prevent water and stop soil during the shield excavation process. The shield tail brush 25 is bent, with one end fixedly connected to the shield shell 23 and the other end being a free end that shrinks inward. When installing the pipe segment, the pipe segment can be assembled in the cylindrical cavity formed inside the shield shell 23 first, and then pushed out to the test soil bin 1 through the shield tail brush 25. Since the free end of the shield tail brush 25 shrinks inward, it can contact the pipe segment and apply a certain pressure when pushing out the pipe segment, so that manual force is required to push the pipe segment out to complete the installation of the pipe segment, thereby preventing the pipe segment from sliding out of the shield shell 23 uncontrollably when not installed.

[0051] like Figure 3A As shown, the driving spindle 24 is arranged in front of the shield cutterhead assembly 2 in the moving direction, extending to the outside of the test soil bin 1, and the driving spindle 24 is fixedly connected to the protruding portion 211; specifically, the driving spindle 24 and the protruding portion 211 can be connected by setting a flange. The rotation of the driving spindle 24 drives the cutterhead 21 and the cutter 22 fixed on the cutterhead to rotate, and the movement of the driving spindle 24 drives the cutterhead 21, the cutter 22 and the shield shell 23 to move in the direction in which the opening extends.

[0052] like Figure 4A and Figure 4BAs shown, the simulation device of some embodiments of the present invention further includes a cutter disc rotation drive mechanism 4, which includes a main gear 41 fixed on the driving spindle 24, a driving gear 42 meshing with the main gear 41 for transmission, and a driving device 43 connected to the driving gear 42. Optionally, the main gear 41 can be nested and fixed on the outside of the driving spindle 24 by a key connection. Two identical driving gears 42 can be provided, respectively located above and below the main gear; each driving gear can be connected to a driving device 43, such as a motor, for driving; a reducer 44 can also be connected between the driving device 43 and the corresponding driving gear 42 to adjust the rotation speed of the driving gear 42, thereby adjusting the rotation speed of the main gear 41, the rotation speed of the driving spindle 24, and finally adjusting the rotation speed of the cutter disc 21.

[0053] like Figure 5A and Figure 5B As shown, the simulation device of some embodiments of the present invention further includes a cutter disc traction mechanism 5. The cutter disc traction mechanism 5 includes a fixed plate 51, a traction jack 52 and a traction plate 53. Among them, the fixed plate 51 is used to keep the position fixed, and its lower end can be fixed to the ground. The traction jack 52 has a first end fixedly connected to the fixed plate 51 and a second end opposite to the first end. The traction plate 53 is fixedly connected to the second end of the traction jack 52, that is, the traction jack 52 is fixedly connected to the fixed plate 51 and the traction plate 53. The driving spindle 24 passes through the fixed plate 51 and the traction plate 53 and is engaged with the traction plate 53. The engagement means that the driving spindle 24 forms a matching relationship with the traction plate 53, and the driving spindle 24 is clamped by the traction plate 53 so that it cannot produce horizontal and vertical displacement relative to the traction plate 53.

[0054] There are many ways to form the engagement, such as Figure 5A As shown, a groove is provided on the front surface side of the traction plate 53 along the moving direction of the shield cutter head assembly 2, one end of the drive spindle 24 is fixedly connected to the protrusion 211 of the cutter head 21, and a sphere is provided at the other end, which is inserted into the groove. The corresponding groove may be a hemispherical shape matching the shape of the sphere. By providing a sphere at the end of the drive spindle 24 and engaging it in the groove provided in the traction plate 53, the traction plate 53 moves under the action of the traction jack 52, thereby causing the drive spindle 24 to move; and the sphere is engaged in the groove so that the traction movement does not affect the rotation of the drive spindle 24 driven by the cutter head rotation drive mechanism 4. Optionally, as Figure 5B As shown, four traction jacks 52 may be provided and arranged along a square. The cutter head traction mechanism 5 may also include a controller 54 fixed on the fixing plate 51, and the speed of the traction jacks 52 is controlled by the controller 54, thereby controlling the speed of the cutter head 21 moving and advancing.

[0055] like Fig. 6A and Figure 6BAs shown, the measuring segment assembly 3 includes not only a segment 31 and a soil pressure measuring member 32 fixed on the segment 31, but also a waterproof pad 33 and a connecting member 34. The segment 31 has multiple pieces, each of which is semi-cylindrical. Compared with the length and width, the thickness of the segment 31 is small. The semi-cylindrical outer wall of the segment 31 protrudes toward the inside of the test soil bin 1. The segment 31 is installed in the excavated hole to form a tunnel pipe. Figure 6B As shown, the side view of the segment 31 is a semicircular ring formed by two concentric semicircles, and multiple earth pressure measuring devices 32 arranged at intervals along the circumferential direction are fixed on the outer wall surface of each segment 31, for example, three earth pressure sensors 32 are fixed; thus, the earth pressure on the segment 31 during the simulated shield tunneling process can be accurately and comprehensively measured at various positions on the outer wall surface of the segment 31. The earth pressure sensor 32 can be similarly regarded as a sheet-like two-dimensional structure, which is curved and fits the outer wall surface of the segment 31 to measure the pressure. Multiple segments 31 have the same structure, shape and size, and are arranged adjacently along the moving direction of the shield cutterhead assembly 2. For each certain distance of tunneling, one more segment 31 can be installed. The waterproof pad 33 is arranged between adjacent segments 17 to ensure that there will be no gap leakage when multiple segments 31 form a tunnel pipe. Multiple connectors 34 can be provided to fixedly connect adjacent segments and corresponding waterproof pads between adjacent segments. For example, three connecting bolts can be distributed along the height direction as connectors.

[0056] like Fig. 7A and 7BAs shown, the simulation device for shield construction in some embodiments of the present invention may also include a retaining plate 61 and a retaining plate stopper 62. The retaining plate 61 is arranged between the two glass front walls 11 and in front of the shield cutterhead assembly 2 along the excavation direction. The height of the retaining plate 61 is the same as the height of the opening 12, so that the opening portion in front of the shield cutterhead assembly 2 along the excavation direction can be closed, thereby preventing the sample soil in the test soil bin 1 from falling out of the test soil bin 1 from the opening. Specifically, the retaining plate 61 is a long strip of plate, the thickness of which is the same as the thickness of the glass front wall 11, and one end close to the shield cutterhead assembly 2 is processed into an arc shape, which matches the hemispherical shape of the cutterhead 21; while the cutterhead 21 is excavating, the retaining plate can be moved out at a constant speed under the action of manual labor, so that it does not block the movement of the cutterhead 21 and can prevent the sample soil from falling out of the test soil bin 1. A plurality of retaining plate stoppers 62 can be provided to limit the retaining plate 61 to be located in the opening 12 and to conflict with the two transparent front walls 11. Specifically, the retaining plate stopper 62 includes an iron sheet and a bolt passing through the iron sheet. The bolt passes through the lower edge of the upper transparent front wall 11 or the upper edge of the lower transparent front wall 11 and is fixed to the corresponding transparent front wall 11. Since the iron sheet extends from the edge of the transparent front wall 11 in the height direction, the retaining plate 62 stuck in the opening 12 contacts the upper and lower transparent front walls 11 respectively and is abutted in the upper and lower directions, and the side of the retaining plate 62 is supported by the outer iron sheet, so that it will not fall out of the opening 12. The retaining plate stopper 62 can be removed from the fixed transparent front wall 11. When the retaining plate 61 has been moved out of the position of the corresponding retaining plate stopper 62, the retaining plate stopper 62 is removed. Optionally, the outer wall of the retaining plate 61 protrudes outward near the center to form a groove for accommodating the driving spindle 24, so as to support the driving spindle 24 so that it does not deviate.

[0057] like Figure 8As shown, the simulation device for shield construction of some embodiments of the present invention may further include a segment stopper 71. The segment stopper 71 is disposed at the rear of the shield cutterhead assembly 2 along the excavation direction, and is used to limit the segment 31 from moving from the opening 12 to the outside of the accommodating cavity. Specifically, a plurality of segment stoppers 71 may be provided, and each segment stopper 71 is fixedly connected to a transparent front wall 11. The segment stopper 71 is similar to the retaining plate stopper 62, and includes an iron sheet and bolts passing through the iron sheet. The bolts pass through the lower edge of the upper transparent front wall 11 or the upper edge of the lower transparent front wall 11, and are fixed to the corresponding transparent front wall 11. Since the iron sheet extends from the edge of the transparent front wall 11 in the height direction, the edge of the segment 31 is blocked by the iron sheet and cannot move from the opening 12 to the outside of the accommodating cavity, thereby ensuring that the structure and position of the tunnel tube formed by the segment 31 are stable. In addition, a rubber pad 72 can be arranged between the iron sheet and the edge of the tube sheet 31 blocked by the iron sheet. The thickness of the rubber pad 72 is the same as the thickness of the transparent front wall 11, so that the axis of the tube sheet 31 is the same as the axis of the shield shell 23 and the driving spindle 24, and it also has a waterproof effect.

[0058] like Fig.9A As shown, the shield construction simulation device of some embodiments of the present invention may also include a segment reaction force applying device 8. The segment reaction force applying device 8 and the test soil bin 1 (refer to Figure 1 ) is fixed, for example, fixed on the side wall of the test soil bin 1 at the rear relative to the direction of cutterhead excavation. The segment reaction force applying device 8 is used to simulate the reaction force of the traction jack on the segment during actual shield excavation. Therefore, the specific segment 31 acted by the segment reaction force applying device 8 varies according to the simulated excavation process. When a certain segment 31 is simulated to be subjected to a reaction force, the segment reaction force applying device 8 is connected to it. As the excavation continues, the segment is no longer subjected to a reaction force, and the connection between the segment reaction force applying device 8 and it is removed. The segment reaction force applying device 8 can be detachably connected to the segment 31 and act in a direction opposite to the movement of the shield cutterhead assembly 2.

[0059] Specifically, Fig.9A As shown, the segment reaction force applying device 8 includes a reaction force jack 81, a pull rod 82 and a reaction force rod 83. One end of the reaction force jack 8 is fixed to the test chamber 1, for example, Figure 1The left end side wall of the test soil bin 1 shown in the figure, and the other end is fixed to the first plate 84. One end of the pull rod 82 is fixed to the first plate 84, and the other end is fixed to the second plate 85; wherein, the pull rod 82 can be provided with a plurality of parallel pull rods, and the extension direction of the first plate 84, the second plate 85 and the left end side wall of the test soil bin 1 is the same, and they all extend vertically. One end of the reaction rod 83 is fixed to the second plate 85, and the other end is detachably connected to the pipe segment 31. Then, when the reaction jack 81 is working, the pull rod 82 is driven to act in the opposite direction of the shield excavation on the second plate 85 and the reaction rod 83, and the reaction rod 83 thereby acts a reaction force on the pipe segment 31 to which it is connected. Specifically, the detachable connection between the reaction rod 83 and the pipe segment 31 can be achieved as follows, such as Fig. 9B and Fig. 9C As shown, the reaction rod 83 includes a threaded rod 831 and a sector piece 832. One end of the threaded rod 831 is fixedly connected to the second plate 85, and the other end is fixedly connected to the sector piece 832. In the process of simulating shield construction, the threaded rod 831 passes through the cavity inside the segment 31, and extends from the sector piece 832 to the front end face of the segment 31 along the forward direction of the shield, thereby hooking the segment 31. When the reaction jack acts, the reaction force applied to the segment 31 can be simulated. When assembling the next segment 31, the sector piece 832 is rotated to withdraw the reaction force, and the next segment 31 is installed and used, and then the sector piece 832 is used to hook the next segment 31 to apply a reaction force to it.

[0060] In other embodiments of the present invention, a simulation method for shield construction is also provided, which can adopt the simulation device for shield construction in the above embodiments. The simulation method includes:

[0061] S1. Set up a test soil bin, which has a holding cavity for holding the sample soil. The test soil bin includes two transparent front walls spaced apart, and an opening connecting the holding cavity is formed between the two transparent front walls. Optionally, the test soil bin is an open-top structure for filling the sample soil. The test soil bin can be set in a hole actually constructed, and there is still space outside the test soil bin to place the test simulation equipment.

[0062] S2. Fill the test soil bin with sample soil to the lower edge of the opening to simulate the underground construction soil layer environment of shield construction. During the filling process, sampling and density measurement can be carried out to get the soil structure as close to the actual soil layer as possible.

[0063] S3. Install the shield cutterhead assembly in the opening so that the shield cutterhead assembly is at least partially disposed in the accommodating cavity. Specifically, the shield cutterhead assembly is installed on the top of the soil sample that has been filled. The shield cutterhead assembly can protrude outside the opening, or it can be completely located in the accommodating cavity but close to the opening. The shield cutterhead assembly includes: a cutterhead, including a protruding portion with a through hole and a connecting portion disposed around the protruding portion; a tool protruding and fixed to the outer surface of the protruding portion; a shield shell, one end of which is rotatably connected to the connecting portion; and a driving spindle fixedly connected to the protruding portion to drive the cutterhead to rotate and move along the direction in which the opening extends.

[0064] S4, installing a retaining plate in the opening adjacent to the cutterhead to close part of the opening. Installing a retaining plate in the opening in front of the cutterhead along the advancing direction of the cutterhead shield to prevent the sample soil in the accommodating cavity from falling out of the opening.

[0065] Optionally, in order to ensure that the retaining plate can be stably inserted into the opening, a retaining plate stopper may be installed on the transparent front wall before step S4 and after step S3.

[0066] S5. Continue to fill the test soil bin with sample soil to a preset height, wherein the preset height is higher than the upper edge of the opening. This simulates the height area where the soil of the stratum is pressed on the shield device and covered by the soil of the stratum during the shield construction process. During the filling process, sampling and density measurement can be implemented to be as close as possible to the soil structure of the actual soil layer.

[0067] S6. The adjacent shield shell is installed with the first segment in the test soil bin. The first segment refers to the segment installed behind the shield shell along the moving direction when the shield cutter assembly has not yet moved; since the segment is provided with a soil pressure measuring device, the soil pressure on the segment is measured before the shield is simulated.

[0068] S7, driving the driving main shaft to rotate and move, so as to drive the cutter head and the shield shell to move, thereby simulating the shield tunneling process of the shield device. After tunneling for a certain distance, the soil pressure on the first segment is measured again, so as to obtain the overburden load on the segment during the shield tunneling process.

[0069] S8. After the shield shell moves a certain distance, when the distance between the first segment and the shield shell is sufficient to install other segments, install the second segment between the first segment and the moved shield shell. It should be noted that the second segment can be one segment or multiple segments; the second segment can be formed by one-time installation or multiple installations. The second segment refers to the segment installed behind the shield shell along the moving direction after the shield cutter assembly has started to move; for example, the shield cutter assembly may move a certain distance, and a second segment may be added, and these segments installed after the shield cutter assembly starts to move are collectively referred to as the second segment. A soil pressure measuring device is provided on each segment, so the upper pressure load on each segment during the shield excavation process can be obtained in real time and accurately.

[0070] The front wall of the test soil bin of the embodiment of the present invention is transparent, so that the movement and collapse of the strata under different stratum conditions can be observed intuitively during the movement of the shield cutter assembly to simulate the shield construction process; by installing the measuring segment assembly, the soil pressure on the segment can be accurately measured. Therefore, the simulation method of the shield construction of the embodiment of the present invention can simply, intuitively and accurately simulate the actual scene of the shield construction and measure the stress conditions.

[0071] Optionally, after step S3 and before step S4, after the shield cutterhead assembly is installed in the opening, the method further includes:

[0072] S31, installing a cutterhead rotation drive mechanism and a cutterhead traction mechanism, which are connected to the driving spindle to drive the driving spindle to rotate and move respectively. The cutterhead rotation drive mechanism and the cutterhead traction mechanism are arranged in front of the shield cutterhead assembly along the moving direction of the shield cutterhead assembly, and are both arranged outside the test soil bin.

[0073] Optionally, step S7 also includes pulling the retaining plate to move at the same speed as the cutter disc and the shield shell move, so that during the excavation process of the cutter disc and the shield shell moving, the retaining plate will not be hindered and the sample soil in front of the cutter disc in the excavation direction will not fall out of the accommodating cavity from the opening.

[0074] Optionally, step S6 also includes: applying a reaction force to the first segment while installing the first segment in the test soil bin adjacent to the shield shell. Step S8 also includes: installing the second segment between the first segment and the moved shield shell while canceling the reaction force applied to the first segment and applying a reaction force to the second segment. Thus, in the process of simulating shield tunneling, the reaction force opposite to the tunneling direction is simulated for the segment closest to the tail of the shield shell.

[0075] Optionally, grouting is performed after the first segment is installed in step S6 and / or the second segment is installed in step S8, and the soil pressure on the first segment and / or the second segment is measured before and after the grouting. Grouting holes are provided on each segment, so that grouting can be performed after the segment is installed to simulate the grouting in the actual shield construction process, and the pressure change on the segment before and after the grouting is measured to evaluate the grouting effect.

[0076] Optionally, the simulation method further comprises: removing the first pipe segment and / or the second pipe segment after grouting, so as to visually observe the grouting reinforcement effect and measure the reinforcement range, thus providing a basis for evaluating the grouting reinforcement effect.

[0077] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A shield construction simulation device, characterized in that: include: A test soil bin, wherein a holding cavity for holding the sample soil is formed inside the test soil bin, the test soil bin comprising two transparent front walls spaced apart, an opening communicating with the holding cavity is formed between the two transparent front walls; A shield cutterhead assembly, at least partially disposed in the accommodating cavity, capable of moving along an extending direction of the opening to excavate the sample soil; A measuring segment assembly can be arranged in the accommodating cavity adjacent to the shield cutterhead assembly, the measuring segment assembly is arranged in the opposite direction of the moving direction of the shield cutterhead assembly, the measuring segment assembly comprises a segment with a grouting hole and an earth pressure measuring member fixed on the segment; the segment has a plurality of pieces, the outer wall of the segment protrudes toward the inside of the test soil bin, the segment is semi-cylindrical, and a plurality of earth pressure measuring members spaced along the circumferential direction are fixed on the outer wall surface of each segment; A segment reaction force applying device is fixed to the test soil bin, can be detachably connected to the segment and exerts a force in the opposite direction to the movement of the shield cutterhead assembly; A retaining plate movable along the extension direction of the opening; A retaining plate stopper is detachably fixed to the transparent front wall to limit the retaining plate to be located in the opening and to abut against the two transparent front walls; The shield cutterhead assembly comprises: The cutter disc comprises a protruding portion with a through hole and a connecting portion arranged around the protruding portion; a cutter protruding and fixed to the outer surface of the protruding portion; A shield shell, one end of which is rotatably connected to the connecting portion, and the other end of which is adjacent to the measuring tube segment assembly; a shield tail brush is provided at the other end of the shield shell, and the shield tail brush can contact the tube segment; the shield tail brush is bent, one end of the shield tail brush is fixedly connected to the shield shell, and the other end of the shield tail brush is a free end that shrinks inward; A driving spindle is arranged in front of the shield cutter head assembly in the moving direction and is fixedly connected to the protruding portion to drive the cutter head to rotate and move along the extending direction of the opening.

2. The simulation device according to claim 1, characterized in that Also includes: The cutter disc rotation driving mechanism comprises a main gear fixed on the driving main shaft, a driving gear meshing with the main gear for transmission, and a driving device connected with the driving gear.

3. The simulation device according to claim 1, characterized in that It also includes a cutter disc traction mechanism, the cutter disc traction mechanism comprising: Fixing plate to keep the position fixed; a traction jack having a first end fixedly connected to the fixing plate and a second end opposite to the first end; a traction plate, fixedly connected to the second end of the traction jack; Wherein, the driving main shaft passes through the fixing plate and the traction plate and is engaged with the traction plate.

4. The simulation device according to claim 3, characterized in that The traction plate is provided with a groove, one end of the driving spindle is fixedly connected to the protruding portion of the cutter disc, and the other end of the driving spindle is provided with a sphere, which is stuck in the groove.

5. The simulation device according to any one of claims 1 to 4, characterized in that: The measuring segment assembly further comprises: A waterproof pad is provided between adjacent pipe segments; Connectors are used to fix adjacent pipe segments and corresponding waterproof pads.

6. The simulation device according to claim 1, characterized in that Also includes: The pipe segment stopper is fixed to the transparent front wall to prevent the pipe segment from moving out of the accommodating cavity.

7. The simulation device according to claim 1, characterized in that The segment reaction force applying device comprises: A reaction jack, one end of which is fixed to the test soil bin, and the other end of which is fixed to the first plate; A pull rod, one end of which is fixed to the first plate, and the other end of which is fixed to the second plate; A reaction rod has one end fixed to the second plate and the other end detachably connected to the pipe segment.

8. A method for simulating shield construction, characterized in that: include: A test soil bin is provided, wherein a holding cavity for holding the sample soil is formed inside the test soil bin, wherein the test soil bin comprises two transparent front walls spaced apart from each other, and an opening communicating with the holding cavity is formed between the two transparent front walls; Filling the sample soil into the test soil bin to the lower edge of the opening; A shield cutterhead assembly is installed in the opening so that the shield cutterhead assembly is at least partially arranged in the accommodating cavity; the shield cutterhead assembly comprises: a cutterhead, comprising a protruding portion with a through hole and a connecting portion arranged around the protruding portion; a tool protruding and fixed to the outer surface of the protruding portion; a shield shell, one end of which is rotatably connected to the connecting portion, and the other end of the shield shell is provided with a shield tail brush, which can contact the pipe segment; the shield tail brush is bent, one end of the shield tail brush is fixedly connected to the shield shell, and the other end of the shield tail brush is a free end that shrinks inwardly; a driving spindle is fixedly connected to the protruding portion to drive the cutterhead to rotate and move along the direction in which the opening extends; A retaining plate is installed in the opening adjacent to the cutterhead to close a portion of the opening; Filling the sample soil into the test soil bin to a preset height, wherein the preset height is higher than the upper edge of the opening; A first pipe segment is installed adjacent to the shield shell in the test soil bin; Driving the driving spindle to rotate and move, so as to drive the cutter disc and the shield to move; Installing a second pipe segment between the first pipe segment and the moved shield shell; Among them, the adjacent shield shell applies a reaction force to the first pipe segment while installing the first pipe segment in the test soil bin, and the reaction force applied to the first pipe segment is cancelled and a reaction force is applied to the second pipe segment while installing the second pipe segment between the first pipe segment and the moved shield shell.

9. The simulation method according to claim 8, characterized in that: After the shield cutterhead assembly is installed in the opening, the method further comprises: A cutter disc rotation drive mechanism and a cutter disc traction mechanism are installed, and the cutter disc rotation drive mechanism and the cutter disc traction mechanism are connected to the driving spindle to respectively drive the driving spindle to rotate and move.

10. The simulation method according to claim 8, characterized in that: The cutter head and the shield shell move while pulling the retaining plate to move at the same speed.

11. The simulation method according to claim 8, characterized in that: Grouting is performed after the first pipe segment and / or the second pipe segment are installed, and the soil pressure borne by the first pipe segment and / or the second pipe segment is measured before and after the grouting.

12. The simulation method according to claim 11, characterized in that: The simulation method further comprises: The first segment and / or the second segment are removed after grouting.