A machine head structure and construction method for empty pushing through a dark excavated primary lining tunnel

By designing the head structure and propulsion device for air pushing through the tunnel with primary lining of underground excavation, the problems of difficult excavation of pipe jacking machine in hard rock section and long period of secondary lining of underground excavation are solved, and the air pushing construction of pipe jacking pipes is realized. , shorten the construction period and reduce costs.

CN111441776BActive Publication Date: 2024-10-18WUHAN MUNICIPAL CONSTR GROUP
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202010003856.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-01-03
Publication Date
2024-10-18
Estimated Expiration
2040-01-03

AI Technical Summary

Technical Problem

The existing pipe jacking machine cannot tunnel normally in the hard rock section, and the construction period of the secondary lining of the underground excavation is long, resulting in slow construction speed and high cost.

Method used

Design a machine head structure for empty pushing through underground excavation and primary lining tunnels, including a cylindrical nose body and a tapered extension section, equipped with a sliding shoe plate to match the guide groove, combined with a power mechanism and pipe jacking pipes, through The jacking pipe pushes the machine head structure forward to realize empty pushing construction.

Benefits of technology

The pipe jacking pipe can be air-pushed through the underground excavation section in the hard rock section, shortening the construction period, reducing the project cost, and improving the construction efficiency. The machine head structure is simple and recyclable, reducing the construction cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111441776B_ABST
    Figure CN111441776B_ABST
Patent Text Reader

Abstract

The present invention discloses a machine head structure for empty pushing through a dark excavation primary lining tunnel, comprising a cylindrical machine head body and an extension section arranged at the end of the machine head body; the extension section is a conical structure coaxially arranged with the machine head body, the large end of the extension section has the same diameter as the machine head body and is connected to the end of the machine head body; the outer wall lower edge of the machine head body and the extension section is symmetrically installed with a sliding shoe plate on both sides, and the sliding shoe plate is adapted to a guide groove; the guide groove is arranged on a guide groove plate pre-buried in the cushion layer of the dark excavation tunnel. The present invention also discloses a construction method for empty pushing through a dark excavation primary lining tunnel. The beneficial effects of the present invention are as follows: the machine head structure is not equipped with a cutterhead, a sliding shoe plate is installed, and a jacking pipe is used to empty push through the dark excavation primary lining, and dark excavation is combined with the jacking pipe, so as to solve the problems that the existing jacking machine cannot be normally excavated in the hard rock section and the dark excavation secondary lining construction period is long, and the jacking pipe is empty pushed through the dark excavation section to construct an underground tunnel, and at the same time, the construction period is greatly shortened, the project cost is reduced, and the investment in manpower, materials and machines is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of underground tunnel construction, and in particular to a machine head structure and a construction method for air-pushing through a dark-excavated primary lining tunnel. Background Art

[0002] With the rapid development of urban construction in my country, the construction of supporting urban municipal pipe networks has become more and more common. Pipe jacking construction has been widely used due to its many advantages such as small impact on the environment and ground traffic, fast construction speed, short construction period, small working surface, and low construction cost. However, during underground tunnel construction, if there are unfavorable conditions such as moderately weathered hard rock sections or isolated rock formations, and sharp curves on the tunnel axis, the pipe jacking machine cannot jack normally.

[0003] At present, underground tunnel construction adopts different construction methods according to the different strata it passes through. For hard rock sections, the dark excavation method is mostly used for construction. However, if the dark excavation method is used for the primary lining construction of the hard rock section, the lining construction adopts the traditional cast-in-place secondary lining construction method, which is constructed in sections, poured in sections, and maintained in sections. Especially for tunnels with longer lines, the construction speed is slow and the construction cost is high. When the shield machine is directly used to push through the dark excavation section, the equipment investment is large, the construction efficiency is low, the shield machine installation and commissioning are complicated, and the assembly of the pipe segments takes a long time. Summary of the invention

[0004] The purpose of the present invention is to provide a head structure and construction method for pushing a pipe jacking machine through a dark excavated primary lining tunnel in view of the deficiencies in the prior art, so as to solve the problems that the existing pipe jacking machine cannot normally excavate in the hard rock section and the dark excavated secondary lining construction period is long.

[0005] The technical solution adopted by the present invention is: a machine head structure for empty pushing through a dark-excavated primary lining tunnel, characterized in that it includes a cylindrical machine head body and an extension section arranged at the end of the machine head body; the extension section is a conical structure coaxially configured with the machine head body, and the large-mouth end of the extension section has the same diameter as the machine head body and is connected to the end of the machine head body; sliding shoe plates are symmetrically installed on both sides of the lower edge of the outer wall of the machine head body and the extension section, and the sliding shoe plates are adapted to the guide groove; the guide groove is arranged on a guide groove plate pre-buried in the cushion layer of the dark-excavated tunnel.

[0006] According to the above scheme, the diameter of the small end of the extension section is five-sixths of the diameter of the large end.

[0007] The present invention also provides a propulsion device for empty pushing through a dark-excavated primary lining tunnel, comprising a power mechanism and the machine head structure as described above, wherein the power mechanism is arranged in a working shaft, and the pushing end of the power mechanism, a plurality of jacking pipes and the machine head structure can contact each other in sequence, and the power mechanism pushes the machine head structure forward through the jacking pipes.

[0008] The present invention also provides a construction method for empty pushing through a dark excavated primary lining tunnel, comprising the following steps:

[0009] Step 1: Preliminary construction preparation;

[0010] Step 2: providing the components of the propulsion device as described above, and assembling the nose structure;

[0011] Step 3: Construction of tunnel primary lining, guide channel plate and cushion layer: Construct the primary lining by dark excavation in the tunnel section, clean the bottom surface of the dark excavation primary lining and lay the cushion layer, and embed the guide channel plate before the cushion layer construction;

[0012] Step 4: Drilling holes on the ground and burying grouting pipes;

[0013] Step 5: The propulsion device is installed and pushed in the well: the power mechanism, the first section of the jacking pipe and the machine head body are installed, and the sliding shoe plate at the bottom of the machine head body is matched with the guide groove on the cushion layer; after the installation, the jacking pipe is pushed in the tunnel primary lining until all the jacking pipes in the tunnel are installed;

[0014] Step 6: Seal the tunnel portal interface to prevent the slurry from overflowing into the working pit;

[0015] Step 7: The gap between the inner wall of the tunnel's initial lining and the outer wall of the top pipe is a slurry filling area, and cement mortar is injected into the slurry filling area for filling;

[0016] Step 8. Secondary grouting of the tunnel: After surface grouting of the air push section, secondary grouting of the tunnel is carried out through the lifting holes of the jacking pipe every 3 to 5 rings at the place where the slurry shrinks.

[0017] According to the above scheme, in step four, holes are drilled from the ground surface to the central axis of the tunnel, and the grouting holes are arranged at intervals along the axis of the tunnel; a grouting pipe is arranged in each grouting hole, and the length of the grouting pipe is designed according to the actual construction situation, with its end located in the gap between the outer wall of the top pipe after the air push and the inner wall of the dark excavation lining.

[0018] According to the above scheme, in step six, a pressure relief hole is pre-buried above the tunnel door.

[0019] According to the above scheme, in step seven, the grouting pressure is 0.2-0.4 MPa.

[0020] According to the above scheme, in step eight, the grouting pressure is 0.2-0.6 MPa.

[0021] According to the above scheme, in step three, the cushion layer is cast by concrete.

[0022] The beneficial effects of the present invention are:

[0023] 1. The machine head structure of the present invention is not equipped with a cutter disc, but is equipped with a sliding shoe plate. The jacking pipe is pushed through the dark excavation primary lining. The dark excavation and jacking pipe are combined to solve the problems that the existing jacking machine cannot normally excavate in the hard rock section and the dark excavation secondary lining construction period is long. The jacking pipe is pushed through the dark excavation section to construct the underground tunnel, which greatly shortens the construction period, reduces the project cost, and reduces the investment in manpower, materials and machines. 2. The jacking pipe is pushed through the dark excavation primary lining, so that the tunnel can be formed in one time. 3. The machine head structure is simple and the construction cost is low. 4. The installation of the sliding shoe plate on the machine head body can effectively reduce the friction resistance of the push and improve the construction efficiency. 5. The machine head body modification and the installation of the sliding shoe plate can be prefabricated separately in advance according to the size of the hole diameter, which can shorten the construction period. 6. The machine head structure can be recycled and reused, effectively reducing the cost of tunnel construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of the head structure in the present invention.

[0025] Figure 2 It is a schematic diagram of the machine head structure and the jacking pipe being pushed in the primary lining of the dark excavation in this embodiment.

[0026] Figure 3 for Figure 2 AA section view in.

[0027] Figure 4 Schematic diagram of the grouting pipe in this embodiment.

[0028] Among them: 1. Slurry filling area; 2. Jacking pipe; 3. Blind excavation primary lining; 4. Head structure; 4.1. Head body; 4.2. Extension section; 4.3. Sliding shoe plate; 5. Grouting pipe; 6. Cushion layer. DETAILED DESCRIPTION

[0029] In order to better understand the present invention, the present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0030] like Figure 1 The head structure 4 shown is used for empty pushing through the tunnel of the primary lining 3 of the dark excavation, comprising a cylindrical head body 4.1, and an extension section 4.2 arranged at the end of the head body 4.1; the extension section 4.2 is a conical structure coaxially arranged with the head body 4.1, and the large end of the extension section 4.2 has the same diameter as the head body 4.1 and is connected to the end of the head body 4.1. In the present invention, the head structure 4 is not provided with a cutter disc; the head structure 4 can be directly used in the power system of the existing pipe jacking machine.

[0031] Preferably, the diameter of the small end of the extension section 4.2 is five-sixths of the diameter of the large end, so as to avoid affecting the initial lining 3 of the dark excavation during the empty pushing process and prevent debris in the tunnel from entering the head structure 4 and the jacking pipe 2, so as to ensure smooth empty pushing of the jacking pipe 2.

[0032] Preferably, the lower edges of the outer walls of the machine head body 4.1 and the extension section 4.2 are symmetrically provided with sliding shoe plates 4.3, which are adapted to the guide grooves; the guide grooves are provided on the guide groove plates pre-buried in the dark tunnel cushion 6. The sliding shoe plates 4.3 can reduce the friction resistance during the empty push and prevent the machine head structure 4 from rolling sideways during the empty push.

[0033] In this embodiment, the sliding shoe plate 4.3 at the lower part of the head body 4.1 is horizontal; due to the different diameters of the extension section 4.2 and the head body 4.1, there is a certain angle between the sliding shoe plate 4.3 located at the lower part of the extension section 4.2 and the sliding shoe plate 4.3 located at the lower part of the head body 4.1; the sliding shoe plate 4.3 is made of I-beam, and the lower part of the sliding shoe plate 4.3 is located in the guide groove; the guide groove plate is made of 10 cm thick steel plate. In order to reduce the empty push resistance of the jacking pipe 2 and ensure that the jacking posture of the propulsion device is within a controllable range, the two sides of the guide groove plate exceed the sliding shoe plate 4.3 by 50mm.

[0034] A propulsion device for empty pushing through a dark excavated primary lining 3 tunnel comprises a power mechanism and a head structure 4 as described above. The power mechanism is arranged in a working well. The pushing end of the power mechanism, a plurality of jacking pipes 2 and the head structure 4 can contact each other in sequence. The power mechanism pushes the head structure 4 forward through the jacking pipes 2. The focus of the propulsion device described in the present invention is the improvement of the head structure 4, which does not have a cutter disc; the power mechanism can adopt the power mechanism of an existing shield machine or a jacking machine, which can be a hydraulic jack. The power mechanism is a prior art, which is not shown in the drawings and will not be described here.

[0035] A construction method for empty pushing through a dark excavation primary lining 3 tunnel, after laying a cushion layer 6 in the dark excavation primary lining 3 tunnel, the propulsion device is used to perform jacking empty pushing construction in the dark excavation primary lining 3 tunnel (such as Figure 2 and Figure 3 After the empty push is completed, the gap between the outer wall of the top pipe 2 and the inner wall of the dark excavation primary lining 3 is filled with surface drilling and grouting (as shown in FIG. Figure 4 As shown), the underground tunnel construction is completed; in this embodiment, the power mechanism is a hydraulic jack. The method specifically includes the following steps:

[0036] Step 1: Preliminary construction preparation: Install construction electricity, water, access, drainage, lighting and other equipment according to conventional pipe jacking construction to ensure smooth access for construction machinery and materials.

[0037] Step 2: Provide the components of the propulsion device as described above: In this embodiment, the power mechanism of the propulsion device is arranged in the shaft, and the pushing end of the propulsion device contacts the rear end of the head body 4.1 through the top pipe 2 to achieve propulsion; the head body 4.1 and the extension section 4.2 are respectively made of 20mm thick steel plates welded; a pair of 14# I-beams are welded to the lower part of the head structure 4. Sliding shoe plates 4.3. In this embodiment, the diameter of the head body 4.1 is 3.6m, and the diameter of the small end of the extension section 4.2 is 3m.

[0038] Step three, construct the primary lining, guide channel plate and cushion layer 6 of the tunnel, and embed the guide channel on the cushion layer 6, the axial direction of the guide channel is consistent with the propulsion direction of the propulsion device: construct the primary lining by dark excavation in the tunnel section, and lay the cushion layer 6 after cleaning the bottom surface of the dark excavation primary lining 3, and embed the guide channel plate configured with the sliding shoe plate 4.3 before the construction of the cushion layer 6: first, position the embedded guide channel plate according to the designed axis of the tunnel, and to prevent the embedded guide channel from floating up when the cushion layer 6 is poured, before pouring, while measuring and releasing the preset guide channel center axis, use 100mm diameter C20 threaded steel as an anchor type embedded part for vertical positioning and welding on the dark excavation steel arch frame, after the anchor type embedded part is positioned and welded, locate the guide channel axis position according to the measuring point, and then weld and fix the guide channel plate, and the anchor type embedded part is set at an interval of 2m; in this embodiment, the cushion layer 6 is cast with C20 concrete and has a thickness of 15mm.

[0039] Step 4, surface drilling and burying of grouting pipe 5: drilling from the surface to the central axis of the tunnel, arranging a grouting hole every 10 meters along the axis of the tunnel, arranging a grouting pipe 5 in each grouting hole, and the length of the grouting pipe 5 is designed according to the actual construction situation, with its end located in the gap between the outer wall of the top pipe 2 after air pushing and the inner wall of the dark excavation lining.

[0040] Step 5, empty pushing down the well: refer to the traditional jacking construction method to install the power mechanism, the first section of the jacking pipe 2 and the head body 4.1, the sliding shoe plate 4.3 at the bottom of the head body 4.1 is matched with the guide groove on the cushion layer 6; after the installation, the jacking pipe 2 is pushed into the tunnel primary lining.

[0041] 1. The propulsion device enters the dark tunnel

[0042] Before the machine head body 4.1 is lowered into the well, the starting base is installed (the machine head body 4.1 and the jacking pipe 2 are both cylindrical structures, easy to roll, and the starting base is equivalent to a positioning device). After the machine head body 4.1 is lowered into the well, it falls on the starting base. The power mechanism pushes the machine head body 4.1 forward and then retracts. At this time, the starting base is empty, and the first section of the jacking pipe 2 is lowered into the well and falls on the starting base. The power mechanism then pushes the first section of the jacking pipe 2 forward, and the subsequent jacking pipes 2 fall on the starting base in turn and are then pushed forward by the power mechanism. Before the jacking pipe 2 is pushed forward, the power mechanism is adjusted, and the posture of the machine head structure 4 is determined by measurement. During jacking, the pushing speed cannot be too fast and should be controlled within the range of 15 to 25 mm / min. The axis must be measured for each section of the jacking pipe 2 pushed forward. If necessary, measurements should be taken every 0.5 sections so that the jacking pipe 2 can enter the dark excavation primary lining 3 in a good posture. In terms of thrust, considering the friction resistance between the pipe and the soil, the cylinder jacking pressure is controlled within the range of 5 to 15 MPa.

[0043] 2. Push the pipe through the curved section

[0044] The stroke difference of the jack is calculated according to the design radius of the axis. Through the stroke difference of the jack, it is ensured that the head structure 4 moves along the axis of the dark excavation tunnel. At the same time, before each section of the jacking pipe 2 is pushed in, the axis error between the dark excavation primary lining 3 and the jacking pipe 2 is measured. The stroke difference of the propulsion jack is adjusted according to the error, and the gap between the jacking pipe 2 and the dark excavation primary lining 3 is ensured.

[0045] 3. The propulsion device is in the dark excavation hollow propulsion section

[0046] During the jacking process at this stage, special attention should be paid to the jacking pressure of the jack. When the oil pressure of the jacking cylinder suddenly increases, stop the jacking construction immediately and check whether there is any debris in front of the head structure 4 that needs to be cleaned up to prevent damage to the primary lining of the dark excavation section.

[0047] In the present invention, the working process of the propulsion device is basically the same as the propulsion process of the existing shield machine or jacking machine, both of which use the power mechanism in the working well to push the last section of the jacking pipe 2, and the last section of the jacking pipe 2 then pushes the head body 4.1 and the extension section 4.2 forward through the middle several jacking pipes 2; after the pushing end of the power mechanism retracts, an installation gap is left between it and the last section of the jacking pipe 2, and the jacking pipe 2 is installed in the gap, and so on.

[0048] Step 6: Tunnel portal interface plugging: After the head structure 4 passes through the dark excavation tunnel, the gap between the outer wall of the top pipe 2 and the dark excavation primary lining 3 needs to be filled with grouting. In order to prevent the slurry from overflowing into the working well, the portal interface must be closed. The gap between the portal and the top pipe 2 is closed by a grout stop plate, and a pressure relief hole is pre-buried above the portal to check whether the slurry is densely filled later.

[0049] Step 7: The gap between the inner wall of the tunnel's initial lining 3 and the outer wall of the top pipe 2 is the slurry filling area 1. Cement mortar is injected into the slurry filling area 1: Cement mortar is injected through the grouting pipe 5. The cement mortar is prepared by mixing water: cement: sand: fly ash: bentonite in a mass ratio of 4:1:6.5:4:1. The grouting pressure is controlled between 0.2 and 0.4 MPa to ensure the quality of the formed tunnel construction. When the grouting orifice pressure is maintained at about 0.5 to 0.8 MPa, the slurry absorption is no more than 40 L / min, and this state is maintained for 30 minutes, the grouting of the hole can be ended.

[0050] Step 8, secondary grouting: After surface grouting of the air push section, perform secondary grouting on the slurry filling area 1 through the lifting holes on the top pipe 2 every 3 to 5 rings at the slurry contraction point. The grouting pressure is controlled between 0.2 and 0.6 MPa (preferably 0.3 to 0.5 MPa) to ensure the quality of the formed tunnel construction. The grouting material uses double liquid slurry, the slurry ratio is a cement slurry water-cement ratio of 0.8:0.9, and the water glass and water are diluted at a ratio of 1:1.5. The volume ratio of slurry to water glass during injection is cement slurry: water glass = 4:1.

[0051] Before grouting, add a one-way check valve to the grouting hole, drill through the 3cm protective layer behind the hole with an electric hammer, and connect the tee, cement slurry pipe and water glass pipe. When grouting, first inject pure cement slurry for 1 minute, open the water glass valve for mixed injection, and increase the concentration of water glass when the hole is completed. After the grouting of each hole is completed, wait for 5 to 10 minutes, open the sulfur pass of the grouting head to check the injection effect. If there is a lot of water, inject again. When less water flows out, the hole can be completed, the grouting head is removed, and the grouting hole is blocked with double-fast cement mortar, and the plastic screw plug is put on to grout the next hole.

[0052] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the embodiments, it is still possible for those skilled in the art to modify the technical solutions and parameters described in the aforementioned embodiments, or to perform equivalent substitutions on some of the technical features therein. However, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A construction method for empty pushing through a dark excavated primary lining tunnel, characterized in that: The following steps are involved: Step 1: Preliminary construction preparation; Step 2: Provide the components of the propulsion device and assemble the nose structure; Step 3: Construction of tunnel primary lining, guide channel plate and cushion layer: Construct the primary lining by dark excavation in the tunnel section, clean the bottom surface of the dark excavation primary lining and lay the cushion layer, and embed the guide channel plate before the cushion layer construction; Step 4: Drilling holes on the ground and burying grouting pipes; Step 5: The propulsion device is installed and pushed in the well: the power mechanism, the first section of the jacking pipe and the machine head body are installed, and the sliding shoe plate at the bottom of the machine head body is matched with the guide groove on the cushion layer; after the installation, the jacking pipe is pushed in the tunnel primary lining until all the jacking pipes in the tunnel are installed; Step 6: Seal the tunnel portal interface to prevent the slurry from overflowing into the working pit; Step 7: The gap between the inner wall of the tunnel's initial lining and the outer wall of the top pipe is a slurry filling area, and cement mortar is injected into the slurry filling area for filling; Step 8: Secondary grouting of the tunnel: After surface grouting of the air-pushing section, secondary grouting of the tunnel is carried out through the hoisting holes of the jacking pipe every 3 to 5 rings at the slurry contraction point; The propulsion device comprises a power mechanism and a machine head structure, wherein the power mechanism is arranged in the working well, and the pushing end of the power mechanism, a plurality of jacking pipes and the machine head structure can contact each other in sequence, and the power mechanism pushes the mechanism structure forward through the jacking pipes; The machine head structure includes a cylindrical machine head body and an extension section arranged at the end of the machine head body; the extension section is a conical structure coaxially configured with the machine head body, the large mouth end of the extension section has the same diameter as the machine head body and is connected to the end of the machine head body; sliding shoe plates are symmetrically installed on both sides of the lower edge of the outer wall of the machine head body and the extension section, and the sliding shoe plates are adapted to the guide groove; the guide groove is arranged on a guide groove plate embedded in the cushion layer of the dark excavated tunnel.

2. The construction method of empty pushing through the dark excavation primary lining tunnel as claimed in claim 1 is characterized in that: In step four, holes are drilled from the ground surface toward the central axis of the tunnel, and the grouting holes are arranged at intervals along the tunnel axis. A grouting pipe is arranged in each grouting hole, and the length of the grouting pipe is designed according to the actual construction situation, with its end located in the gap between the outer wall of the top pipe after air pushing and the inner wall of the dark excavation lining.

3. The construction method of empty pushing through the dark excavation primary lining tunnel as claimed in claim 1 is characterized in that: In step six, a pressure relief hole is pre-buried above the tunnel door.

4. The construction method of empty pushing through the dark excavation primary lining tunnel as claimed in claim 1 is characterized in that: In step seven, the grouting pressure is 0.2~0.4MPa.

5. The construction method of empty pushing through the dark excavation primary lining tunnel as claimed in claim 1 is characterized in that: In step eight, the grouting pressure is 0.2-0.6 MPa.

6. The construction method of empty pushing through the dark excavation primary lining tunnel as claimed in claim 1 is characterized in that: In step three, the cushion layer is cast by concrete.

7. The construction method of empty pushing through the dark excavation primary lining tunnel as claimed in claim 1 is characterized in that: The diameter of the small-diameter end of the extension section is five-sixths of the diameter of the large-diameter end.

Citation Information

Patent Citations

  • Circumferential variable-cross-section expanding excavation method of tunnel

    CN109026035A

  • Machine head structure for empty-pushing over-underground-excavation primary lining tunnel and pushing device

    CN212508308U

  • Propulsion unit head that is used in shield method

    KR101237749B1