A telecontrol verification method based on SCD and RCD files

By using a remote verification method based on SCD and RCD files, the virtual IED device is reconstructed and the signal consistency is verified, which solves the problem of difficult signal fault location in substation acceptance, realizes a fast and automated acceptance process, and improves the efficiency of substation commissioning.

CN111478818BActive Publication Date: 2024-11-05QINZHOU POWER SUPPLY BUREAU OF GUANGXI POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010392205.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-05-11
Publication Date
2024-11-05
Estimated Expiration
2040-05-11

AI Technical Summary

Technical Problem

During the substation acceptance process, existing technologies cannot effectively monitor and locate signal faults, resulting in slow acceptance progress, frequent instances of multiple manufacturers shirking responsibility, and a lack of reliable means to troubleshoot equipment wiring errors and signal mismatch issues.

Method used

By using a remote control verification method based on SCD and RCD files, the entire station's virtual IED intelligent devices are reconstructed, action and reset signals are sent, and the consistency of signals is verified through the virtual master station to generate a verification report, automatically locating remote control configuration and equipment wiring faults.

Benefits of technology

Quickly locate remote control configuration and equipment wiring issues, shorten the acceptance cycle, improve acceptance efficiency, ensure signal transmission link connectivity, reduce manual operation, and enhance automation level.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111478818B_ABST
    Figure CN111478818B_ABST
Patent Text Reader

Abstract

The present invention relates to a telecontrol verification method based on SCD files and RCD files, and its main technical features are: obtaining substation information; importing substation design point table, SCD file and RCD file, dynamically parsing configuration information of each IED intelligent device; configuring substation network parameters; constructing virtual IED intelligent devices, obtaining telecontrol signal forwarding relationship information, virtual IED intelligent devices sending action and reset signals, and verifying whether the signal received by the virtual master station is consistent with the signal state sent by the virtual IED intelligent device; automatically generating a verification report, and intuitively displaying the verification pass signal and fail signal results. The present invention is reasonably designed, and can centrally discover and eliminate faults including telecontrol configuration, equipment configuration and connection, and point table signal and point number correspondence during the acceptance process, which can greatly shorten the substation commissioning cycle, improve the efficiency and automation level of substation telecontrol information acceptance, and shorten the substation commissioning acceptance cycle.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of transformer substations, in particular to a telecontrol verification method based on an SCD file and an RCD file. Background Art

[0002] Before the substation is officially put into use, the substation system needs to be accepted. In the existing substation acceptance scheme, each station cannot monitor the 104 message sent when the dispatching master station is accepting it. When encountering a fault signal, it is impossible to locate the fault point in the master station or the substation, resulting in a time-consuming and laborious problem of fault elimination.

[0003] Since the correct triggering of the monitoring signal requires the cooperation of the merging unit, measurement and control equipment, remote motor, encryption machine, front-end machine, and monitoring system to be transmitted to the on-duty personnel, any problem in any link will lead to signal failure. At the same time, on-site acceptance personnel cannot directly diagnose and send or simulate instructions, cannot troubleshoot message problems, and multiple hardware interface channels cannot be compared and diagnosed. Acceptance will also be interrupted on site due to graphics, models, and parameter errors. When the acceptance encounters an error signal that needs to be eliminated, there is a lack of reliable means to find the fault point. Therefore, multiple manufacturers often blame each other, resulting in slow acceptance progress. Summary of the invention

[0004] The purpose of the present invention is to overcome the shortcomings of the prior art and propose a telecontrol verification method based on SCD files and RCD files. By checking the fault points of the telecontrol host configuration and verifying whether the design point table signal is consistent with the point number, equipment wiring errors can be discovered in advance and factors that lead to stagnation of substation acceptance or excessively long acceptance cycles can be eliminated, thereby improving the efficiency of substation commissioning and acceptance.

[0005] The present invention solves the technical problem by adopting the following technical solutions:

[0006] A telecontrol verification method based on SCD files and RCD files includes the following steps:

[0007] Step 1: Obtain the following substation information: substation design point table, SCD file, RCD file, master station network configuration information and telecontrol network configuration information;

[0008] Step 2: Import the substation design point table, SCD file and RCD file, and dynamically parse the configuration information of each IED intelligent device;

[0009] Step 3: Configure the following substation network parameters: network IP, mask, gateway, and protocol type;

[0010] Step 4: construct a virtual IED intelligent device, obtain telecontrol signal forwarding relationship information, send action and reset signals to the virtual IED intelligent device, and check whether the signal received by the virtual master station is consistent with the signal state sent by the virtual IED intelligent device;

[0011] Step 5: After the verification is completed, a verification report is automatically generated, which intuitively displays the verification pass and fail signal results.

[0012] The specific implementation method of step 2 is: import the substation design point table, SCD file and RCD file through the file import module, generate the corresponding signal list to be verified, generate the corresponding virtual IED intelligent device and the corresponding configuration information inside the device, and generate a virtual master station according to the configured port and network information.

[0013] The list of signals to be checked includes point numbers, signal names and alarm level information.

[0014] In the step 2, during the import process, the format of the imported SCD file and RCD file is checked, and an error message is given if the format of the imported file is inconsistent with the standard specification format.

[0015] The specific implementation method of step 4 includes the following steps:

[0016] ⑴ Parse the access points, logical devices, logical nodes, data objects, data attributes and interconnection relationship information in the SCD file to build a virtual IED intelligent device; build a virtual master station model by parsing the master station network information and protocol type information;

[0017] (2) Parse the RCD file and obtain the telecontrol signal forwarding relationship information by matching the des field corresponding to the signal description with the reference field of the IEC61850 path name corresponding to the telecontrol host;

[0018] ⑶ The virtual IED intelligent device sends the action-reset signal of the corresponding device in sequence at fixed intervals and sends it to the telecontrol host. The telecontrol host receives the corresponding signal and uploads the signal to the virtual master station through the forwarding relationship table and checks whether the received signal corresponds to the action and reset signal status sent by the virtual IED intelligent device; records the time when the virtual IED intelligent device sends the action and reset signal and the time when the virtual master station receives the action and reset signal;

[0019] ⑷ If the signal, point number and corresponding signal status received by the virtual master station are exactly the same as the signal sent by the virtual IED intelligent device, the signal passes the verification; if the signal status received by the virtual master station is inconsistent or the signal cannot be received, the station-side maintenance personnel will intervene to check whether the telecontrol configuration and telecontrol wiring diagram are correct, and check whether the point number of the signal in the design point table corresponds to the actual device signal point number, and check whether the station-side device configuration and the internal connection of the equipment are correct.

[0020] The virtual IED intelligent device includes a secondary device table, IED instance configuration, communication configuration information, GOOSE / SV configuration and IED virtual terminal connection relationship; the virtual master station model includes a master station IP, a master station and telecontrol communication port and a data transmission protocol type.

[0021] The verification signals in step 4 include types such as ordinary telesignaling, communication interruption telesignaling and telemetering signals, and the verification contents include telesignaling action signals, telesignaling reset signals, telemetering transmission values ​​and telemetering reception values.

[0022] In step 4, the telemetry value sent by the virtual IED device to the virtual master station needs to be verified by reverse calculation whether the telemetry value sent by the virtual IED intelligent device is correct and checked.

[0023] In step 4, the action signal of the virtual IED intelligent device and the action signal received by the virtual master station are marked by red squares, the reset action sent by the virtual IED intelligent device and the reset signal received by the virtual master station are marked by green squares, the signal that passes the verification is marked with a "√" symbol, and the signal that fails the verification is marked with an "×" symbol.

[0024] In step 5, the signals that have passed the calibration and the signals that have not passed the calibration are automatically grouped and displayed, and the number of the signals that have passed the calibration and the number of the signals that have not passed the calibration are given.

[0025] The advantages and positive effects of the present invention are:

[0026] 1. The present invention reconstructs the virtual IED intelligent devices of the entire station, sends action and reset signals in sequence, and verifies the correctness of the telecontrol configuration through the telecontrol forwarding signals received by the virtual master station. It can quickly locate the fault points in the telecontrol configuration and the problems such as incorrect equipment wiring. It can also quickly locate the problem of incorrect matching between the signal and the point number in the design point table, and eliminate the situation of signal acceptance failure due to the telecontrol itself in advance, greatly shorten the substation commissioning cycle, improve the efficiency and automation level of the substation telecontrol information acceptance, and reduce the number of times the substation maintenance personnel operate the equipment, shortening the substation commissioning acceptance cycle.

[0027] 2. The present invention can centrally discover and eliminate faults including remote control configuration, equipment configuration and wiring, and correspondence between point table signals and point numbers during the acceptance process, thereby improving the efficiency of acceptance work.

[0028] 3. The present invention can ensure the link connectivity of the signal transmission from the station end to the dispatching main station in advance, so as to avoid the situation that the dispatching main station cannot normally receive the station end signal and the acceptance is interrupted, resulting in delayed acceptance progress. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a process flow chart of the present invention. DETAILED DESCRIPTION

[0030] The present invention is further described in detail below with reference to the accompanying drawings.

[0031] The present invention is implemented based on the following processing modules:

[0032] Parameter configuration module: configures substation, telecontrol network, protocols and other related information, and simulates the actual master station receiving the telecontrol uplink signal.

[0033] Import file module: import substation design point table, SCD (substation configuration description) file and RCD (telecontrol configuration description) file, dynamically parse the instance configuration, communication configuration, virtual terminal connection and telecontrol forwarding relationship of IED devices in the file, and reconstruct the virtual IED intelligent devices of the whole station.

[0034] Telecontrol test module: The virtual IED intelligent device sends intermittent action and reset signals, and verifies the internal signal correspondence of the telecontrol host and whether the signal is consistent with the point number by checking the signal received by the virtual master station.

[0035] Verification report module: automatically records the actions and reset states sent by the virtual IED intelligent device, as well as the time of signal sending and receiving, and automatically generates a telecontrol verification report.

[0036] Based on the above processing modules, the present invention proposes a telecontrol verification method based on SCD files and RCD files, such as Figure 1 As shown, the following steps are included:

[0037] Step 1: Obtain substation information, including substation design point table, SCD file, RCD file, master station network configuration, telecontrol network configuration and other information.

[0038] Step 2: Import the substation design point table, SCD file and RCD file, and dynamically parse the configuration information of each IED intelligent device.

[0039] The specific implementation method of this step is: import the substation design point table, substation configuration SCD file and telecontrol configuration RCD file through the import file module, generate the corresponding signal list to be verified, including point number, signal name, alarm level and other information, generate the corresponding virtual IED intelligent device and the corresponding internal configuration of the device and other information, and generate a virtual master station according to the configured port and network information.

[0040] This step implements the format verification function for the imported SCD file and RCD file. If the imported file format is inconsistent with the standard specification format, an error message will be given.

[0041] Step 3: Configure network parameters, including network IP, mask, gateway, protocol type and other parameters.

[0042] In this step, the substation, telecontrol network, protocol and other related information are configured through the parameter configuration module to simulate the actual master station receiving the telecontrol uplink signal.

[0043] Step 4: construct a virtual IED intelligent device, obtain telecontrol signal forwarding relationship information, send action and reset signals to the virtual IED intelligent device, and check whether the signal received by the virtual master station is consistent with the signal status sent by the virtual IED intelligent device.

[0044] This step is implemented by a telecontrol test module, and the specific method includes the following steps:

[0045] (1) By parsing the access points, logical devices, logical nodes, data objects, data attributes, interconnection relationships and other information in the SCD file, a virtual IED intelligent device is constructed, including secondary device table, IED instance configuration, communication configuration information, GOOSE / SV configuration, IED virtual terminal connection relationship, etc.; by parsing the master station network information, protocol type and other information, a virtual master station model is constructed, including the master station IP, master station and telecontrol communication port, data transmission protocol type and other contents;

[0046] (2) Parse the RCD file and obtain the telecontrol signal forwarding relationship information by matching the des field corresponding to the signal description with the reference field of the IEC61850 path name corresponding to the telecontrol host;

[0047] (3) The virtual IED intelligent device sends the action-reset signal of the corresponding device in sequence at a fixed interval (which can be manually configured) and sends it to the telecontrol host. The telecontrol host receives the corresponding signal and uploads it to the virtual master station through the forwarding relationship table and checks whether the received signal corresponds to the action and reset signal status sent by the virtual IED intelligent device. At the same time, it records the time when the virtual IED intelligent device sends the action and reset signal and the time when the virtual master station receives the action and reset signal.

[0048] (4) If the signal, point number and corresponding signal status received by the virtual master station are completely consistent with the signal sent by the virtual IED intelligent device, that is, the signal status is: the virtual IED intelligent device sends an action signal - the virtual master station receives the corresponding action signal - the virtual IED intelligent device sends a reset signal - the virtual master station receives the corresponding reset signal, then the signal passes the verification; if the signal status received by the virtual master station is inconsistent or fails to receive the signal, the station-side maintenance personnel will intervene to check whether the telecontrol configuration and telecontrol wiring diagram are correct, and at the same time check whether the point number of the signal in the design point table corresponds to the actual device signal point number, and at the same time check whether the station-side device configuration and the internal connection of the device are correct;

[0049] In this step, the verification signal includes types including ordinary telesignaling, communication interruption telesignaling and telemetering signal, and the verification content includes telesignaling action signal, telesignaling reset signal, telemetering sending value and telemetering receiving value.

[0050] In this step, the telemetry signal acceptance rule must meet the requirement of point number plus deviation multiplied by the specified coefficient. Therefore, the telemetry value sent by the virtual IED device to the virtual master station needs to be verified by reverse calculation whether the telemetry value sent by the virtual IED intelligent device is correct and checked.

[0051] In this step, the action signal of the virtual IED intelligent device and the action signal received by the virtual master station are marked with red squares, the reset action sent by the virtual IED intelligent device and the reset signal received by the virtual master station are marked with green squares, the signal that passes the verification is marked with a "√" symbol, and the signal that fails the verification is marked with an "×" symbol.

[0052] Step 5: After the verification is completed, a verification report is automatically generated, which intuitively displays the verification pass and fail signal results.

[0053] In this step, the verification report module automatically records the action and reset status sent by the virtual IED intelligent device, as well as the time of signal sending and receiving, and automatically generates a remote verification report. It also groups and displays the signals that pass the verification and the signals that fail the verification, and gives the number of signals that pass the verification and the number of signals that fail the verification.

[0054] Through the automatically generated telecontrol verification report, you can intuitively view the number of signals that failed the verification and the specific point number signals. By locating the configuration of the corresponding signal in the telecontrol machine and the connection diagram, you can find out the reason why the signal failed the verification.

[0055] It should be emphasized that the embodiments described in the present invention are illustrative rather than restrictive, and therefore the present invention is not limited to the embodiments described in the specific implementation manners. Any other implementation manners derived by those skilled in the art based on the technical solutions of the present invention also fall within the scope of protection of the present invention.

Claims

1. A telecontrol verification method based on SCD files and RCD files, characterized in that The following steps are involved: Step 1: Obtain the following substation information: substation design point table, SCD file, RCD file, master station network configuration information and telecontrol network configuration information; Step 2: Import the substation design point table, SCD file and RCD file through the import file module, generate the corresponding signal list to be verified, generate the corresponding virtual IED intelligent device and the corresponding configuration information inside the device, and generate the virtual master station according to the configured port and network information; Step 3: Configure the following substation network parameters: network IP, mask, gateway, and protocol type; Step 4: construct a virtual IED intelligent device, obtain telecontrol signal forwarding relationship information, send action and reset signals to the virtual IED intelligent device, and check whether the signal received by the virtual master station is consistent with the signal state sent by the virtual IED intelligent device; The specific implementation method of step 4 includes the following steps: ⑴ Parse the access points, logical devices, logical nodes, data objects, data attributes and interconnection relationship information in the SCD file to build a virtual IED intelligent device; build a virtual master station model by parsing the master station network information and protocol type information; (2) Parse the RCD file and obtain the telecontrol signal forwarding relationship information by matching the des field corresponding to the signal description with the reference field of the IEC61850 path name corresponding to the telecontrol host; ⑶ The virtual IED intelligent device sends the action-reset signal of the corresponding device in sequence at fixed intervals and sends it to the telecontrol host. The telecontrol host receives the corresponding signal and uploads the signal to the virtual master station through the forwarding relationship table and checks whether the received signal corresponds to the action and reset signal status sent by the virtual IED intelligent device; records the time when the virtual IED intelligent device sends the action and reset signal and the time when the virtual master station receives the action and reset signal; (4) If the signal, point number and corresponding signal status received by the virtual master station are completely consistent with the signal sent by the virtual IED intelligent device, the signal passes the verification; if the signal status received by the virtual master station is inconsistent or the signal is not received, the station-side maintenance personnel will intervene to check whether the telecontrol configuration and telecontrol wiring diagram are correct, and check whether the point number of the signal in the design point table corresponds to the actual device signal point number, and check whether the station-side device configuration and the internal connection of the device are correct; The virtual IED intelligent device includes a secondary device table, IED instance configuration, communication configuration information, GOOSE / SV configuration and IED virtual terminal connection relationship; the virtual master station model includes the master station IP, the master station and telecontrol communication port and the data transmission protocol type; Step 5: After the verification is completed, a verification report is automatically generated, which intuitively displays the verification pass and fail signal results.

2. A telecontrol verification method based on SCD files and RCD files according to claim 1, characterized in that: The list of signals to be checked includes point numbers, signal names and alarm level information.

3. The telecontrol verification method based on SCD file and RCD file according to claim 1, characterized in that: In the step 2, during the import process, the format of the imported SCD file and RCD file is checked, and an error message is given if the format of the imported file is inconsistent with the standard specification format.

4. The telecontrol verification method based on SCD file and RCD file according to claim 1, characterized in that: The verification signals in step 4 include types such as ordinary telesignaling, communication interruption telesignaling and telemetering signals, and the verification contents include telesignaling action signals, telesignaling reset signals, telemetering transmission values ​​and telemetering reception values.

5. The telecontrol verification method based on SCD file and RCD file according to claim 1, characterized in that: In step 4, the telemetry value sent by the virtual IED device to the virtual master station needs to be verified by reverse calculation whether the telemetry value sent by the virtual IED intelligent device is correct and checked.

6. The telecontrol verification method based on SCD file and RCD file according to claim 1, characterized in that: In step 4, the action signal of the virtual IED intelligent device and the action signal received by the virtual master station are marked by red squares, the reset action sent by the virtual IED intelligent device and the reset signal received by the virtual master station are marked by green squares, the signal that passes the verification is marked with a "√" symbol, and the signal that fails the verification is marked with a "√" symbol. Symbols are used to mark the 7. The telecontrol verification method based on SCD file and RCD file according to claim 1, characterized in that: In step 5, the signals that have passed the calibration and the signals that have not passed the calibration are automatically grouped and displayed, and the number of the signals that have passed the calibration and the number of the signals that have not passed the calibration are given.