Intelligent flexible assembly execution system, method, computer device and storage medium
Through the intelligent flexible assembly execution system, combined with the intelligent assembly execution system, station system and logistics system, the problem of poor flexibility of assembly systems in the existing technology is solved, and the intelligent production of complex electromechanical products is realized, and the production efficiency is improved.
Patent Information
- Application Number
- CN202010611736.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-06-30
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2040-06-30
AI Technical Summary
The existing intelligent assembly system has poor flexibility and cannot automatically realize the full process production of complex electromechanical products when production products and production processes change, resulting in low efficiency.
An intelligent flexible assembly execution system was designed, including an intelligent assembly execution system, station system and logistics system. By obtaining production tasks, process information and logistics information, the assembly station and the production process are dispatched to realize automatic assembly and human-machine collaboration. Assembly and manual assembly, combined with in-line handling system, achieve standardized and modular design, and adapt to the production of different types of products.
It improves the flexibility and efficiency of the assembly system, is compatible with products of different weights and sizes, realizes intelligent assembly of complex electromechanical products, and improves the efficiency of production of multiple products.
Smart Images

Figure CN111784153B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of intelligent manufacturing technology, and in particular to an intelligent flexible assembly execution system, method, computer device and storage medium. Background Art
[0002] With the development of intelligent manufacturing technology, more and more production lines are equipped with electromechanical equipment with the help of industrial robots and other equipment. However, the assembly system in the relevant technology has fixed functions and produces single products. It cannot meet the production needs of general products in intelligent production lines for complex electromechanical products, and cannot automatically realize the full production process of complex electromechanical products when the products and production processes change.
[0003] With regard to the problems of poor flexibility and low efficiency of intelligent assembly systems in related technologies, no effective solution has been proposed so far. Summary of the invention
[0004] Based on this, it is necessary to provide an intelligent flexible assembly execution system, method, computer device and storage medium to address the above technical problems.
[0005] According to one aspect of the present invention, an intelligent flexible assembly execution system is provided, the system comprising an intelligent assembly execution system FIL, a workstation system and a logistics system.
[0006] The intelligent assembly execution system is used to obtain production tasks and send the production tasks to the workstation system, obtain process information and send the process information to the workstation system, obtain logistics information and send the logistics information to the logistics system;
[0007] The workstation system is used to schedule assembly stations according to the production tasks and the process information and execute the production process, and feed back the production quality information generated by executing the production process to the intelligent assembly execution system, wherein the assembly stations include at least one of the following: automatic assembly stations, human-machine collaborative assembly stations and manual assembly stations;
[0008] The logistics system is used to execute the logistics process according to the logistics information and feed back the logistics execution information generated by executing the logistics process to the intelligent assembly execution system, wherein the logistics system includes an in-line handling system.
[0009] In one embodiment, the automatic assembly station is used to receive the raw materials delivered by the logistics system according to the logistics information, and assemble the raw materials into task semi-finished products;
[0010] The human-machine collaborative assembly station is used to receive the task semi-finished products delivered by the logistics system, and assemble the task semi-finished products to obtain the task finished products;
[0011] The manual assembly station is used to receive the semi-finished task product or the finished task product delivered by the logistics system, and to perform installation operations and electrical testing on the semi-finished task product or the finished task product.
[0012] In one of the embodiments, the intelligent assembly execution system is further used to receive the detection result of the manual assembly station;
[0013] When the detection result is unqualified, the intelligent assembly execution system instructs the logistics system to transport the task semi-finished product or the task finished product to a preset area according to a preset unqualified processing process.
[0014] In one embodiment, the intelligent flexible assembly execution system also includes a manufacturing operations management system MOM,
[0015] The manufacturing operation management system MOM is used to issue the production task and the process information to the intelligent assembly execution system, and receive the production quality information and the logistics execution information.
[0016] In one embodiment, the manufacturing operation management system is further used to issue a plurality of the production tasks, and when the assembly tools of the assembly station meet the requirements of each of the production tasks, instruct the intelligent assembly execution system to complete the production tasks in sequence;
[0017] When the assembly tools at the assembly station do not meet the requirements of each of the production tasks, the intelligent assembly execution system instructs the in-line transport system to obtain additional tools and transport the additional tools to the corresponding assembly station, instructing the intelligent assembly execution system to complete the production tasks in sequence.
[0018] In one of the embodiments, the workstation system is also used to compile, modulate and test the initialization process plan, and upload the initialization process plan to the intelligent assembly execution system, the intelligent assembly execution system generates work step operation standards based on the process initialization plan, and transmits the work step operation standards to the manufacturing operation management system. When the manufacturing operation management system approves the work step operation standards, a formal process plan is generated and issued.
[0019] In one embodiment, the system further comprises a line side warehouse,
[0020] The line side warehouse is used to store raw materials, semi-finished products and finished products.
[0021] In one embodiment, the station system includes a sensor,
[0022] The sensor is used to obtain abnormal information during the assembly process and feed the abnormal information back to the intelligent assembly execution system, and the intelligent assembly execution system performs abnormal processing according to the abnormal information.
[0023] In one embodiment, the workstation system further includes a visual inspection system.
[0024] The visual inspection system is used to perform material scanning on the assembly materials on the assembly station;
[0025] When the material scanning result indicates that the material is out of stock, the intelligent assembly execution system instructs the logistics system to return the assembly material and re-arrange the material.
[0026] According to another aspect of the present invention, there is also provided an intelligent flexible assembly execution method, the method comprising:
[0027] Obtain production tasks, process information and logistics information;
[0028] The assembly stations are scheduled and the production process is executed according to the production tasks and the process information, and the logistics process is executed according to the logistics information, wherein the assembly stations include at least one of the following: automatic assembly stations, human-machine collaborative assembly stations and manual assembly stations, and the logistics system includes an in-line handling system.
[0029] In one embodiment, after obtaining the production task, process information and logistics information, the method includes:
[0030] When receiving a plurality of the production tasks issued, and when the jig and fixture meet the requirements of each of the production tasks, issuing the production tasks in sequence;
[0031] In the case that the jigs and fixtures do not satisfy all the production tasks, a task of acquiring additional jigs and fixtures is issued, and the production tasks are issued in sequence.
[0032] In one embodiment, after scheduling assembly stations and executing production processes according to the production tasks and process information, and executing logistics processes according to the logistics information, the method includes:
[0033] Acquire production quality information corresponding to the production task and logistics execution information corresponding to the logistics information.
[0034] According to another aspect of the present invention, a computer device is also provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the above-mentioned intelligent flexible assembly execution method when executing the computer program.
[0035] According to another aspect of the present invention, there is also provided a computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor, the above-mentioned intelligent flexible assembly execution method is implemented.
[0036] The above-mentioned intelligent flexible assembly execution system, method, computer equipment and storage medium obtain production tasks, process information and logistics information; schedule assembly stations and execute production processes according to production tasks and process information, and execute logistics processes according to logistics information, wherein the assembly stations include at least one of the following: automatic assembly stations, human-machine collaborative assembly stations and manual assembly stations, and the logistics system includes an in-line handling system, thereby realizing standardized and modular design, being compatible with the assembly production of the same type of products with different weights and sizes, and improving the flexibility and efficiency of the assembly system. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0038] Figure 1 is a schematic diagram of the hardware structure of an intelligent flexible assembly execution system according to one embodiment of the present invention;
[0039] Figure 2 FIG. 1 is a schematic diagram of the software architecture of an intelligent flexible assembly execution system in an embodiment. Figure 2 As shown;
[0040] Figure 3 is a flowchart of the production execution of an instrument cabin of an intelligent flexible assembly execution system according to one embodiment of the present invention;
[0041] Figure 4 is an architecture diagram of an intelligent flexible assembly execution system including a MOM system according to one embodiment of the present invention;
[0042] Figure 5 is a flow chart of a production business of a human-machine collaborative assembly station according to one embodiment of the present invention;
[0043] Figure 6 is a flow chart of production changeover of an intelligent flexible assembly execution system according to one embodiment of the present invention;
[0044] Figure 7 is a flow chart of mixed-line production of an intelligent flexible assembly execution system according to one embodiment of the present invention;
[0045] Figure 8 is a flow chart of process management in an intelligent flexible assembly execution system according to one embodiment of the present invention;
[0046] Fig. 9 According to one embodiment of the present invention, an intelligent flexible assembly execution method is also provided;
[0047] Fig.10 is a structural diagram of a FIL system according to one embodiment of the present invention;
[0048] Fig.11 It is a structural diagram of an intelligent flexible assembly execution computer device according to one embodiment of the present invention. DETAILED DESCRIPTION
[0049] In order to make the purpose, technical solutions and advantages of the present application clearer, the present application is described and illustrated below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not intended to limit the present application. Based on the embodiments provided in the present application, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the present application.
[0050] Obviously, the drawings described below are only some examples or embodiments of the present application. For ordinary technicians in this field, the present application can also be applied to other similar scenarios based on these drawings without creative work. In addition, it can also be understood that although the efforts made in this development process may be complicated and lengthy, for ordinary technicians in this field related to the content disclosed in this application, some changes in design, manufacturing or production based on the technical content disclosed in this application are just conventional technical means, and should not be understood as insufficient content disclosed in this application.
[0051] Reference to "embodiments" in this application means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those of ordinary skill in the art that the embodiments described in this application may be combined with other embodiments without conflict.
[0052] Unless otherwise defined, the technical terms or scientific terms involved in this application should be understood by people with ordinary skills in the technical field to which this application belongs. The words "one", "a", "a", "the" and the like involved in this application do not indicate a quantitative limitation, and may represent the singular or plural. The terms "include", "comprise", "have" and any of their variations involved in this application are intended to cover non-exclusive inclusions; for example, a process, method, system, product or device that includes a series of steps or modules (units) is not limited to the listed steps or units, but may also include steps or units that are not listed, or may also include other steps or units inherent to these processes, methods, products or devices. The words "connect", "connected", "coupled" and the like involved in this application are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. The "multiple" involved in this application refers to two or more. "And / or" describes the association relationship of associated objects, indicating that there may be three relationships, for example, "A and / or B" can represent: A exists alone, A and B exist at the same time, and B exists alone. The character " / " generally indicates that the objects before and after are in an "or" relationship. The terms "first", "second", "third", etc. involved in this application are only used to distinguish similar objects and do not represent a specific ordering of the objects.
[0053] This application provides an intelligent flexible assembly execution system. Figure 1 FIG. 1 is a schematic diagram of the hardware structure of an intelligent flexible assembly execution system according to an embodiment of the present invention. Figure 1As shown, the intelligent flexible assembly execution system includes automatic assembly stations, human-machine collaborative assembly stations, manual assembly stations, in-line handling systems, etc. Optionally, the intelligent assembly execution system also includes reserved stations, which can flexibly increase assembly stations. In some embodiments, the intelligent flexible assembly execution system also includes a line-side warehouse, which is used to store raw materials, task semi-finished products and task finished products, etc. It is a temporary storage area for various raw materials and products, located at the edge of the production line, so that the in-line handling system does not need to go to a distant stereoscopic warehouse to pick up and place raw materials and products, thereby improving the work efficiency of the logistics system. The in-line handling system uses a multi-axis articulated industrial robot for loading and unloading, and is equipped with multiple end effectors. While realizing the handling between in-line stations and stations, and between stations and line-side warehouses, it can assist related assembly stations in product assembly. The carriers in the in-line handling system are standardized to meet the unified use of logistics and production, realize the transfer of materials within the system, and complete the entire assembly process of the product through the cooperation of multiple stations. The storage warehouse, the loading and unloading station of the station, and the handling station in the process are all designed in an integrated manner, which can fully meet the diverse production needs in the future. Among them, the automatic assembly station includes industrial robots. For example, the automatic assembly station includes two industrial robots, a 10KG robot and a 16KG robot, which automatically complete the assembly actions such as the stringer frame combination, and use high-precision cameras, force sensors, torque sensors, displacement sensors, etc. to realize the quality inspection and control of the assembly process. The human-machine collaborative assembly station uses human-machine collaborative robots, such as 35KG human-machine collaborative robots, to complete the assembly of the stringer frame combination into the cabin together with the operator. The manual assembly station mainly performs steps that cannot be automated, such as electrical performance testing of the stringer frame combination and the instrument cabin. There are two automated electrical performance testing equipment in the station. The operator connects the cables of the stringer frame combination and the instrument cabin at the station. After completion, the test cable is connected, the electrical performance test starts, and the start time, end time and test results of the test are recorded. The in-line handling system can use a handling robot, such as a 60KG robot and the seventh axis, which is responsible for the coordination of the loading position and the workstation logistics of the three-dimensional warehouse, the coordination of the unloading position and the workstation logistics of the three-dimensional warehouse, the coordination of the logistics of the three-dimensional warehouse and the line-side warehouse, the coordination of the logistics of the line-side warehouse to the workstation, and the logistics of the workstation to the unloading area. Among them, the three-dimensional warehouse is the storage space used by this system to store raw materials, semi-finished products and finished products. Optionally, in this system, the in-line handling system also participates in some assembly actions at the automatic intelligent assembly station and the human-machine collaborative intelligent assembly station to enhance the assembly capacity of this system and reduce investment. The line-side warehouse is mainly used to store the complete pallets of products transported from the three-dimensional warehouse, as well as the semi-finished pallets and finished product pallets generated during the in-line assembly process. The above hardware system can perform three types of assembly, namely automatic intelligent assembly, human-machine collaborative intelligent assembly, and manual assembly, and the three types of assembly can be freely combined according to assembly requirements. It can realize the intelligent assembly of complex electromechanical products such as instrument cabins and realize rapid assembly during the assembly process.
[0054] Figure 2 FIG. 1 is a schematic diagram of the software architecture of an intelligent flexible assembly execution system in an embodiment. Figure 2 As shown in the figure, the software architecture of the intelligent flexible assembly execution system includes an intelligent assembly execution system, a workstation system and a logistics system. Among them, the intelligent assembly execution system (FIL) is responsible for receiving production task information, logistics information, and process file information, managing the production, process, resources, and quality in the system, and directing, scheduling, and monitoring the components of this system to collaboratively complete the assembly work. The workstation system is responsible for executing production tasks based on this workstation, directing and monitoring the operation of sensors and actuator resources in the workstation, and uploading the operation status and abnormal data of the production and assembly process to the FIL system. Under the instruction of the FIL system, the logistics system completes the transfer of materials between workstation systems, and uploads the operation status and abnormal data of the logistics transportation process to the FIL system.
[0055] When the FIL system receives the production task and the bill of material (BOM) process route and procedure related to the task, the FIL system sends the above task, process route and procedure to the workstation system for execution. Optionally, when modifying the production task, the production task modification information is transmitted to the FIL system, and the FIL system determines whether it involves process modification. If it involves process modification, after completing the production of the currently started product or the operator stops the production of the product that has started, the current scheduling task order is closed and a new scheduling task order is generated according to the new process; if it does not involve process modification, the information of the current scheduling task order is updated. After receiving the production task and sending it to the workstation system, the FIL system starts to execute the production task, and after each process is completed, it will provide feedback on the production situation of the process, such as the personnel who execute it, the equipment, tooling information, material information, production process information, etc., production process information such as product code, pallet number, production equipment code, assembly and inspection action time, assembly and inspection tooling and end effector number, operator code, assembly in place information including pictures and picture processing results, assembly and inspection results, fastener tightening torque curve and results, assembly process assembly force, air source pressure, performance index measured value, quality qualified information, etc. The FIL system can record the above-mentioned various key assembly information in real time, and record the feedback in the product full traceability record. Optionally, the record is stored in the intelligent integrated assembly information system server in the form of a file and bound to the product code, which is used to determine whether the product assembly is in place and whether the assembly process is reliable through data analysis.
[0056] The above-mentioned intelligent flexible assembly execution system can accurately receive instructions from the main control information system, and independently complete the main assembly procedures in the process flow with the help of industrial robots, flexible tooling, end effectors, sensors, etc., and analyze and judge the execution status in real time; at the same time, it can realize data interconnection and integration with electrical performance testing equipment and intelligent warehousing and logistics systems, and collaboratively complete automatic loading and unloading, completeness inspection, intermediate state quality inspection and other tasks. The intelligent flexible assembly execution system can realize the flexible assembly of electromechanical products. An important source of its flexibility lies in decoupling, and then reassembling these decoupled elements. In this system, the achievable decoupling methods are mainly in three areas: structural system, management system and control system. The flexibility of the structural system is realized by the fact that the core execution resource robots of the production stations in the in-line handling system in the logistics system and the station system have a large redundant design. For example, the main handling robot of the in-line handling system has a load of 60KG and a maximum range of motion of 2.03 meters, which can meet the production and handling requirements of various possible products; the robot configured in the automatic assembly station uses a linkage 16KG robot and a 10KG robot, which can meet the assembly requirements of different product parts; the 35KG human-machine collaborative robot selected in the human-machine collaborative assembly station has a maximum range of motion of 1.813 meters, which can also meet the different human-machine collaborative assembly needs. The robots can run in parallel to improve assembly efficiency, and can also avoid the risk of robot collision when running in parallel. The combination of the above different assembly stations can meet various different assembly needs. The flexible implementation of the management system is fully decoupled from the station system and logistics system through the FIL system, which is convenient for the addition or reduction of subsequent stations; and the software system is based on the microservice architecture, and can configure personalized services according to customer needs through the assembly of benchmark services. The flexible implementation of the control system is fully decoupled according to the three objects of control scheme-control process-action behavior through the control architecture, which is conducive to reassembling new control flows and control schemes. The same action behavior can be compiled into different control flows, and the control scheme can combine different control flows according to different products. Control schemes and control processes can be programmed through configuration. Standardized and modular design is adopted, which is compatible with the assembly production of the same type of products with different weights and sizes, thus greatly improving the flexibility of the intelligent assembly system, and is compatible with the final assembly production of multiple models of complex electromechanical products. At the same time, it has the mixed production capacity of multiple models of instrument cabins, which improves the efficiency of multi-product production of the intelligent assembly system.
[0057] In one embodiment, the automatic assembly station is used to receive the raw materials delivered by the logistics system according to the logistics information, and assemble the raw materials into task semi-finished products. Optionally, the automatic intelligent assembly station includes a multi-axis articulated industrial robot, a flexible tooling, an end effector, a gluing device, a control system, and necessary auxiliary systems, etc., wherein the number of multi-axis articulated industrial robots is not less than 2. The FIL system receives the process management files under the process version number corresponding to the production task and the production task, including the process route, BOM, management procedures, etc., controls the in-line handling system to distribute materials, and cooperates with the station system to execute the station production assembly task to complete the production task. The specific process is as follows: the FIL system receives production tasks, which include production task order number, version number, material code, material name, quantity, work station, etc., and synchronizes relevant information to the work station system; the in-line handling system places the complete set of material pallets from the three-dimensional warehouse loading position to the line side warehouse; the in-line handling system sends the complete set of material pallets to the automatic assembly station or the line side warehouse for temporary storage according to the FIL system instructions; the in-line handling system takes the material pallet from the three-dimensional warehouse loading position or the line side warehouse to the station loading position according to the system instructions. After the loading is completed, the automatic intelligent assembly station performs the production assembly task according to the instructions of the station system. The automatic assembly station puts the completed semi-finished products into the station unloading position, and the in-line handling system automatically puts them into the line side warehouse.
[0058] The human-machine collaborative assembly station is used to receive the semi-finished products delivered by the logistics system and assemble the semi-finished products to obtain the finished products. The human-machine collaborative intelligent assembly station includes a multi-axis articulated human-machine collaborative robot, flexible tooling, end effector, gluing equipment, control system, auxiliary system, etc. The FIL system receives the production task and the process management files under the process version number corresponding to the production task, including process route, BOM, management procedure, etc., controls the in-line handling system for material distribution, and coordinates the station system to execute the station production assembly task to complete the production task. The specific process is as follows: the FIL system receives production tasks, such as production task number, version number, material code, material name, quantity, work station, etc., and synchronizes relevant information to the work station system; the in-line handling system sends the complete set of material pallets to the assembly station or the line-side warehouse for temporary storage according to the system instructions; the in-line handling system takes the material pallet from the line-side warehouse to the work station loading position according to the system instructions; after the loading is completed, the human-machine collaborative intelligent assembly station performs the production assembly task according to the instructions of the work station system; the human-machine collaborative assembly station places the finished product into the work station unloading position, and the in-line handling system automatically places it into the line-side warehouse.
[0059] The manual assembly station is used to receive the task semi-finished products or the task finished products delivered by the logistics system, and to perform installation operations and electrical testing on the task semi-finished products or the task finished products. The manual assembly station includes an operating table, tooling and tools, etc., which are used to realize the cable connection and electrical performance testing of the frame assembly. The manual assembly station management business process is mainly the process of electrical performance testing of the frame assembly and the instrument cabin, and entering the test results into the FIL system. The process is described as follows: Before executing each new task of the electrical performance test, it is necessary to judge the current equipment status. If the equipment status is normal, start executing new related task instructions; the in-line delivery robot puts the frame assembly or instrument cabin pallet into the loading position of the manual assembly station according to the FIL system instructions, and installs the cable assembly; after the cable is installed, the operator manually scans the pallet material, starts the electrical performance detection switch, and performs the inspection according to the material inspection items.
[0060] In this embodiment, the functions and workflow definitions of an automatic assembly station, a human-machine collaborative assembly station, and a manual assembly station are provided. Through the above definitions, each assembly station can have its own assembly process and assembly function, avoiding functional duplication of assembly stations. This function not only meets the equipment characteristics set for each assembly station, but also can cover the final assembly production of various models of complex electromechanical products after combination, which is convenient for the design of process flow, further improves the flexibility of the intelligent assembly system, and improves the efficiency of multi-product production of the intelligent assembly system.
[0061] In a preferred embodiment, Figure 3 FIG. 1 is a flowchart of the production execution of the instrument cabin of the intelligent flexible assembly execution system according to one embodiment of the present invention. Figure 3 As shown in the figure, the main business processes of instrument cabin production are as follows:
[0062] Step S302, raw material loading. The FIL system generates logistics tasks based on production tasks and controls the in-line handling system to transport the raw materials to the automatic assembly station for processing;
[0063] Step S304, assembling the frame assembly. The frame assembly assembly is assembled at the automatic assembly station;
[0064] Step S306: Cable installation and electrical performance testing. The in-line handling system transports the completed frame assembly to the manual assembly station for cable installation and electrical performance testing of the frame assembly;
[0065] Step S308, cabin entry and parts assembly. The in-line handling system transports the inspected frame assembly to the human-machine collaborative intelligent assembly station for pre-cabin assembly of the frame assembly, cabin entry of the frame assembly, and installation of the remaining parts;
[0066] Step S310, electrical performance test of the instrument cabin. The in-line handling system transports the assembled instrument cabin to the manual workstation for electrical performance test of the instrument cabin;
[0067] Step S312, finished product unloading. The in-line handling system transports the instrument cabin that has completed the electrical performance test to the unloading position of the workstation and returns it to the stereoscopic warehouse for storage.
[0068] In some embodiments, the workstation system also includes a sensor, which is used to obtain abnormal information during the assembly process and feed the abnormal information back to the intelligent assembly execution system, which performs abnormal processing based on the abnormal information. During the assembly execution process, the feedback information from various sensors is used to detect whether there is production abnormality information in the work step. For example: when tightening the screws, the torque feedback tightening force is not within the set value range, the laser displacement sensor, the plug-in board is not in place, etc. The workstation system feeds back the above abnormal information to the FIL system, and the FIL system will issue a processing plan according to the preset abnormal processing process, thereby improving the accuracy of the assembly station work and improving the work efficiency of the intelligent assembly execution system.
[0069] In some embodiments, the station system also includes a visual inspection system, which is used to scan the assembly materials on the assembly station; when the material scanning result is a shortage of material, the intelligent assembly execution system instructs the logistics system to return the assembly materials and re-provision. During the handling process, the shortage detection visual system performs a complete set detection by taking photos and comparing. If there is a shortage, the in-line handling system places the material tray at the unloading position and returns it to the raw material warehouse for re-provisioning. In this embodiment, the visual inspection system, for example, installs a high-precision camera to take photos and record the assembly results according to the assembly process requirements, and uses image recognition and processing technology to compensate for the accuracy of the assembly process with high assembly accuracy requirements and high assembly difficulty. The visual inspection function can also prevent the loss of materials during transportation. The real-time storage of visual inspection process data and results can improve the work accuracy of the assembly station in the intelligent assembly execution system, improve work efficiency, reduce rework rate, and the processing process and results can be traced, which is convenient for process improvement.
[0070] In some embodiments, FIL is also used to receive the test results of the manual assembly station. The inspector at the manual assembly station fills the test results into the FIL system, and the FIL system records the test results and performs subsequent scheduling according to the preset test result processing rules. Optionally, the electrical performance test results are divided into two situations: one situation is that the test result is qualified. If the material is an instrument cabin, it is placed in the lower material position of the stereoscopic warehouse through the in-line handling system for warehousing. If the material is a frame combination, it is placed in the line side warehouse for temporary storage through the in-line handling system for subsequent assembly; the other situation is that the test result is unqualified. Optionally, in the case of unqualified test results, the FIL system instructs the logistics system to transport the task semi-finished product or the task finished product to a preset area according to the preset unqualified processing process. Preferably, there are five ways to deal with unqualified products: total scrapping, single-piece scrapping, rework, out-of-tolerance concession and repair. The unqualified product processing process is as follows: the operator marks the material tray corresponding to the unqualified product as unqualified in the workstation system, and puts the unqualified product into the unloading position of the workstation; the in-line handling system puts the unqualified material tray from the unloading position of the workstation into the unloading position of the stereoscopic warehouse, and feeds back information such as task order number, tray serial number, status, etc.; the unqualified products are sent to the round-trip repair area by the automated guided vehicle (AGV) for unqualified product determination. If there are unassembled material trays in this process, they need to be sent to the round-trip repair area together, and the unqualified products are determined according to quality standards; there are two main ways to deal with unqualified products. In the first case, assembly continues from the process specified by the system, and the FIL system performs assembly production according to the processing results; in the second case, the production task of the unqualified product is cancelled, and the unqualified product is broken up. The broken parts can be scrapped or reused for new product assembly. This embodiment provides a process for processing defective products, thereby further improving the flexibility of the intelligent assembly system and the comprehensiveness and integrity of the assembly process.
[0071] In some embodiments, the intelligent flexible assembly execution system also includes a manufacturing operations management system MOM, which is used to issue production tasks and process information to the intelligent assembly execution system, and receive production quality information and logistics execution information. After consultation with the FIL system, the interface adopts POST request and uniformly uses the json data format for transmission. Figure 4 is an architecture diagram of an intelligent flexible assembly execution system including a MOM system according to one embodiment of the present invention, such as Figure 4As shown in the figure, the MOM system includes production task information, material information, process route information, execution file information, warehouse information, shelf information, carrier information, equipment information, tooling information and user information. The MOM system sends production tasks, process information and logistics distribution to the FIL system, and also receives production quality related information, abnormal alarm information and logistics distribution information fed back by FIL. It transforms raw materials or parts into products by coordinating and managing the company's personnel, equipment, materials and energy resources. It includes managing behaviors performed by physical equipment, people and information systems, and covers activities related to scheduling, production capacity, product definition, historical information, production device information, and related resource status information. It transmits and records the relevant information of the equipment, equipment status, component status, production process information, product quality information, etc. to the intelligent integrated assembly information system for subsequent data tracing and analysis, and can further accurately monitor the status of each equipment and adjust the process according to the status, thereby further improving the flexibility and work efficiency of the intelligent flexible assembly execution system.
[0072] Preferably, Figure 5 is a flow chart of a production business of a human-machine collaborative assembly station according to an embodiment of the present invention. Figure 5 As shown, the human-machine collaborative assembly station production business includes the following steps:
[0073] Step S502, receiving production tasks. The FIL system receives the production tasks issued by the MOM system and synchronizes the relevant information to the workstation system;
[0074] Step S504, material delivery. The in-line handling system delivers the complete set of material pallets to the assembly station or the line warehouse for temporary storage according to the system instructions. When the production line production task starts production, the material pallets are delivered directly to the station at the first delivery of the human-machine collaborative intelligent assembly station;
[0075] Step S506, check whether there is a shortage of materials. The in-line handling system takes the material tray from the line side warehouse to the loading position of the workstation according to the system instruction. During the handling process, the shortage detection visual system performs detection step S508 by taking pictures and comparing. In the case of shortage of materials, the in-line handling system places the material tray at the unloading position;
[0076] Step S510, sending information to the MOM system, returning the raw material warehouse for re-mixing;
[0077] Step S512, after the loading is completed, the human-machine collaborative intelligent assembly station performs the production assembly task according to the instructions of the station system;
[0078] Step S514, detecting whether there is production abnormality. During the assembly execution process, the feedback information of various sensors is used to detect whether there is production abnormality information in the process step. Optionally, human intervention is performed to carry out the production abnormality handling process in the event of an abnormality.
[0079] Step S516: The human-machine collaborative intelligent assembly station places the completed frame assembly semi-finished product into the station unloading position, and the in-line handling system automatically places it into the line-side warehouse.
[0080] In step S502 to step S516, the FIL system receives the production tasks and the process management files under the process version number corresponding to the production tasks, controls the in-line handling system to distribute materials, and coordinates the workstation system to execute the workstation production assembly tasks to complete the production tasks issued by the MOM system. It can dynamically and real-time perceive and record the assembly process information, determine the assembly status, including products, equipment, etc., through data analysis, and guide the next operation of the system.
[0081] In one embodiment, the manufacturing operation management system is also used to issue multiple production tasks. When the assembly tools at the assembly station meet the requirements of each production task, the intelligent assembly execution system is instructed to complete the production tasks in sequence. When the assembly tools at the assembly station do not meet the requirements of each production task, the intelligent assembly execution system instructs the in-line handling system to obtain additional tools, and transports the additional tools to the corresponding assembly station, instructing the intelligent assembly execution system to complete the production tasks in sequence. In the intelligent flexible assembly execution system, the connection parts between the tooling and the robot use a quick-change system. During the production process, different tooling fixtures can be automatically changed according to the different requirements of the products and processes produced. The above-mentioned multiple production tasks include production change tasks and mixed line production tasks. Production change refers to the process of switching a production line from producing one product to producing another. Figure 6 FIG. 1 is a flow chart of production changeover of an intelligent flexible assembly execution system according to an embodiment of the present invention. Figure 6 As shown in the figure, the specific operation process of production change is as follows:
[0082] Step S602: before production change, the MOM system provides a tooling fixture replacement list and tooling fixture replacement tasks according to the production tasks;
[0083] Step S604, the FIL system confirms the receipt and executes the tooling fixture replacement according to the production situation;
[0084] Step S606, the FIL system checks the fixtures according to the received tasks, and confirms the fixture delivery tasks from the three-dimensional warehouse to the assembly station;
[0085] Step S608, the FIL system checks the fixtures according to the received task, confirms the fixtures that need to be replaced at the assembly station, and establishes a task for delivering the fixtures from the assembly station to the stereoscopic warehouse;
[0086] Step S610, transport the fixture to be replaced from the assembly station to the three-dimensional warehouse, place it at the loading position of the three-dimensional warehouse, and push the information to the MOM system in sequence after delivery;
[0087] Step S612: After all the fixtures that need to be replaced at the workstation are sent to the three-dimensional warehouse, the MOM system will sequentially place the fixtures that need to be transported to the assembly workstation from the three-dimensional warehouse into the loading position of the three-dimensional warehouse according to the fixture tasks, and push the information to the FIL system after completion;
[0088] Step S614: The FIL system transports the new fixture from the loading position of the stereoscopic warehouse to the corresponding assembly station through the in-line handling system. After the fixture arrives at the station, it is manually installed;
[0089] Step S616, after the fixture preparation is completed, the fixture switching completion check is performed;
[0090] Step S618, execute the new production task after checking and confirming.
[0091] Mixed line production refers to the production process of producing multiple products simultaneously on the same production line. Figure 7 FIG. 1 is a flow chart of mixed-line production of an intelligent flexible assembly execution system according to an embodiment of the present invention. Figure 7 As shown, the specific operation process of mixed line production is as follows:
[0092] Step S702, the MOM system simultaneously issues two or more production tasks;
[0093] Step S704, the MOM system detects whether the fixtures in the current production line meet the requirements of completing all production tasks according to the generated tasks. If they meet the requirements, the process goes to step S608;
[0094] Step S706: If the fixtures in the current production line do not meet the requirements for completing all production tasks, a fixture replacement task is issued. After the fixture replacement is completed, the process goes to step S608;
[0095] Step S708, executing the production task;
[0096] Step S710, switching production tasks in the workstation system according to the tasks currently to be executed. In the mixed-line production mode, switching tasks is done by clicking the task switching button in the workstation system;
[0097] Step S712, the workstation system completes tooling switching according to the switched task and executes the new task. After completing the production and assembly of the current product, the workstation system automatically replaces the corresponding tooling from the tooling library of the workstation according to the switched task and starts executing the new task.
[0098] The above-mentioned production changeover and mixed-line production can realize rapid switching of assembly product production, have the ability to produce mixed flows of different products, and improve the efficiency of assembly execution of multiple products.
[0099] In one embodiment, the workstation system is also used to compile, modulate and test the initialization process plan, and upload the initialization process plan to the intelligent assembly execution system. The intelligent assembly execution system generates the work step operation standard according to the process initialization plan, and transmits the work step operation standard to the manufacturing operation management system. When the manufacturing operation management system approves the work step operation standard, it generates a formal process plan and issues the formal process plan. The process management process refers to the process of process control plan maintenance and version control. Each process control plan file consists of the following four parts: plan version, execution frame (operation step), action frame (action step) and change items. Among them, the plan version can set the initial version to version 1.0, and any subsequent addition, modification or deletion of the content in the plan will result in a version upgrade, for example: from V1.0 to V1.1; the execution frame is used to distinguish the operation steps of the entire process control plan; the action frame is used to distinguish the action behavior of each operation step in a more detailed manner; the change items are used to record the changes in the process control file when it changes. Figure 8 FIG. 1 is a flowchart of process management in an intelligent flexible assembly execution system according to an embodiment of the present invention. Figure 8 As shown, the process management process provided in this embodiment includes the following steps:
[0100] Step S802, compiling a process control plan for each process step in the workstation system, and generating a test version of the process control plan after debugging and verification;
[0101] Step S804: The workstation system uploads the test version of the process control plan to the FIL system, and the FIL system generates a new work step operation standard based on the process control plan. The process control plan in the work step operation standard is not allowed to be modified;
[0102] Step S806, the FIL system uploads the work step operation standard to the MOM system for approval;
[0103] Step S808: The approved work step standard is upgraded to the official version. During production, MOM sends the production task information and the work step standard version number to the FIL system.
[0104] Step S810, the FIL system calls the corresponding process control plan according to the process file version number issued by the MOM and sends it to the workstation system, and the workstation system executes production and assembly according to the process control plan.
[0105] Through steps S802 to S810, a convenient method for debugging the production process and equipment of a new product is provided, and the use rights are opened to users for users to conduct production debugging and formal production of new products. During the debugging and production of new products, the underlying code of the operating system is avoided, the code writing work is reduced, and the production efficiency of the system is improved.
[0106] According to another aspect of the present invention, Fig. 9 According to an embodiment of the present invention, an intelligent flexible assembly execution method is also provided. Fig. 9 As shown, the method includes:
[0107] Step S910, obtaining production tasks, process information and logistics information;
[0108] Step S920, scheduling assembly stations and executing production processes according to production tasks and process information, and executing logistics processes according to logistics information. The assembly stations include at least one of the following: automatic assembly stations, human-machine collaborative assembly stations, and manual assembly stations, and the logistics system includes an in-line handling system.
[0109] In step S910 to step S920, the above method can be implemented by the intelligent execution assembly execution system FIL. The FIL system is responsible for receiving production task information, logistics information, and process file information, managing the production, process, resources, and quality in the system, and directing, scheduling, and monitoring the system components to collaboratively complete the assembly work. The FIL system schedules assembly stations according to production tasks and process information. The assembly stations include automatic assembly stations, human-machine collaborative assembly stations, manual assembly stations, etc. Each assembly station has a preset responsible assembly task. In each process flow, the corresponding assembly station flow can be selected according to the processing steps, thereby decoupling the FIL system from the assembly station, so that the FIL system can be applied to the assembly process flow of more different types of products. Optionally, the assembly station is not limited to the above three types of assembly stations. If an assembly station needs to be added later, it only needs to increase the corresponding station management information to introduce a new assembly station in the process flow. Through the above method, automatic intelligent assembly, human-machine collaborative intelligent assembly, and manual assembly division of labor and cooperation can balance the process beat, avoid bottleneck processes, greatly improve the flexibility of the intelligent assembly execution system, and improve assembly efficiency.
[0110] In some embodiments, after obtaining the production tasks, process information and logistics information, the method includes: when receiving multiple production tasks, if the tooling and fixtures meet each production task, the production tasks are issued in sequence; if the tooling and fixtures do not meet each production task, the task of obtaining additional tooling and fixtures is issued, and the production tasks are issued in sequence. In this embodiment, the FIL system can also be used to receive and issue multiple production tasks, and check whether the assembly tooling on the assembly station meets the various production tasks to be issued according to the production tasks. If they meet, multiple production tasks can be executed in sequence. If they do not meet, logistics tasks are generated according to the tooling required for the production tasks, and the logistics system is instructed to transport the tooling and fixtures. It has the function of managing assembly process routes, managing different process route versions, and ensuring that instructions are checkable and traceable; the above-mentioned production change and mixed line production can realize rapid assembly product production switching, have mixed flow production capabilities for different products, and improve the efficiency of assembly execution of multiple products.
[0111] In some embodiments, after scheduling assembly stations and executing production processes according to production tasks and process information, and executing logistics processes according to logistics information, the FIL system will also obtain production quality information corresponding to the production tasks, as well as logistics execution information corresponding to the logistics information. Optionally, the above-mentioned production quality information includes the production status of each process after completion, including the personnel who execute it, the equipment, tooling information, material information, production process information, etc. The production process information includes product code, pallet number, production equipment code, assembly and inspection action time, assembly and inspection tooling and end effector number, operator code, assembly in place information, assembly and inspection results, fastener tightening torque curve and results, assembly process assembly force, air source pressure, performance index measured value, quality qualified information, etc. The above-mentioned logistics execution information includes material scheduling execution status, execution resource information, etc. Therefore, the FIL system can accurately monitor the status and operation of each device, and should be able to alarm in time when it is different from the set value, and independently decide the next action according to the type of alarm.
[0112] Preferably, Fig.10 is a structural diagram of a FIL system according to an embodiment of the present invention, such as Fig.10 As shown, the FIL system includes a process management module 1002 , a production management module 1004 , a quality management module 1006 , a logistics management module 1008 , an abnormal alarm module 1010 , an equipment management module 1012 and an interface management module 1014 .
[0113] Among them, the process management module 1002 is used to manage the definition of basic process data such as work centers, work units, and work steps, as well as to configure the work routes, work step material BOM, and work step operation standards. The above functions are used to effectively manage the process in the entire assembly process. In the work center management, the work center is the unit of production operations that directly changes the form or properties of the material. This module is used to maintain the master data of the work center. In the work station management module, the work station is the most basic production unit in the production process. This module is used to maintain the master data of the work station. The work step management module is used to maintain the master data of the work step. The work route management module is used to configure the work steps and the order of the work steps that need to be performed during the assembly process. The work step material BOM module manages the bill of materials required for the work step. The work step operation standard management module manages the work step's work instructions, process control plans and other process documents, and realizes the control of process versions.
[0114] The production management module 1004 is used to receive the scheduling task list and send the scheduling task list to each workstation. At the same time, it receives the production data uploaded by each workstation and uploads the production data to the upper management system.
[0115] The quality management module 1006 implements the maintenance of the inspection standards for product quality inspection and the recording of the inspection results. Among them, the inspection standard management module is used for inspection standards, mainly for the maintenance of the inspection standards for materials, and guides the execution of the inspection process. The inspection business management module is mainly used to record the inspection results, and record the pallet code, material information, scheduling task information, inspection items, and inspection results during the inspection process.
[0116] The logistics management module 1008 realizes the automation of the material scheduling process. The module configures the execution resources, connection channels, execution plans, carriers and other related data required for the material scheduling process, and manages and tracks the scheduling tasks and related scheduling instructions. Among them, the execution resource management module manages all the execution resource information in the in-line handling system. The execution resource treasure includes robots, racks, sensors, cylinders, electric cylinders, etc. The execution resource type module manages the types of all execution resources in the in-line handling system. The channel management module manages the configuration information of each execution resource connected to the in-line handling system. The execution plan configuration module is used to configure the action flow that the execution resource needs to execute in each material scheduling process. The execution resource class action module manages the execution actions of the execution resources and the interface functions corresponding to the execution actions in the execution resources. The action management module manages the actions of all execution resources and the interface functions corresponding to the actions. The parameter management module manages all variables and constants used in the execution plan configuration. The function management module manages all function programs used in the execution plan configuration. The end effector management module manages the end effector on the robot and the execution head on the actuator. The execution head specification module manages the parameter information of the execution head, including the materials and carrier information that can be clamped. The carrier object management module manages all the carriers used in the intelligent assembly execution system and compiles unique numbers. The carrier specification management module manages the parameters of the carrier classification in the intelligent assembly execution system, including length, width, height, user automation production parameters, etc. The physical location management module manages all work points in the intelligent assembly execution system. The scheduling instruction module is used to track and query the execution of material scheduling instructions. The execution instruction status module is used to query the execution status of each action in the scheduling instruction.
[0117] The abnormal alarm module 1010 is divided into two situations: manual alarm and system automatic alarm. The manual alarm is mainly an abnormal alarm at the workstation terminal of the FIL system after the equipment fails. The system automatic alarm is mainly after the execution resource fails, the system automatically sends the fault code information to the FIL system, and the FIL system automatically forms an identifiable fault cause and fault handling strategy based on the maintained fault code information. Among them, the object fault configuration module manages the possible fault content and processing priority information of all execution resources in the intelligent assembly execution system, as well as the handling plan. The fault project module manages all possible fault projects for master data reference. The fault level module manages the priority of fault handling. The fault handling configuration module configures the fault handling strategy corresponding to the fault event, and the fault handling strategy mainly includes fault code, execution resource category number, execution resource type name, fault project number, fault project name, etc. The fault and processing module is mainly used to handle fault events generated by manual alarms and fault events generated by automatic alarms. For example, when the execution resource program runs abnormally, the system automatically detects the abnormal situation of the current program, suspends the action of the abnormal execution resource, waits for manual intervention, receives the signal to resume production, and then resumes the production task.
[0118] The equipment management module 1012 mainly manages the maintenance of equipment ledger information and equipment repair business during the production and assembly process. Among them, the equipment specification module is used to manage various specifications and models of equipment. The equipment ledger module manages the information of newly purchased equipment and attaches a unique code to the equipment throughout the entire life cycle of the equipment, while also controlling the equipment status.
[0119] The interface management module 1014 is used to interact with the upper management system such as the manufacturing operation management system (MOM) or the manufacturing execution system (MES). After negotiation with the FIL system, the interface can use POST request and uniformly use the json data format for transmission.
[0120] The above modules may be embedded in or independent of a processor in a computer device in the form of hardware, or may be stored in a memory in a computer device in the form of software, so that the processor can call and execute operations corresponding to the above modules.
[0121] The above-mentioned FIL system adopts a standardized and modular design, which is compatible with the assembly production of the same type of products with different weights and sizes. It can dynamically and real-time perceive and record assembly process information, judge the assembly status through data analysis, including products, equipment, etc., guide the next operation of the system, realize the transfer of materials within the system, and complete the entire assembly process of the product through the cooperation of multiple workstations.
[0122] It should be understood that although Figures 1 to 9 The steps in the flowchart are shown in sequence as indicated by the arrows, but these steps are not necessarily executed in the order indicated by the arrows. Unless otherwise specified in this document, there is no strict order restriction for the execution of these steps, and these steps can be executed in other orders. Moreover, Figures 1 to 9 At least part of the steps may include multiple sub-steps or multiple stages. These sub-steps or stages are not necessarily executed at the same time, but can be executed at different times. The execution order of these sub-steps or stages is not necessarily sequential, but can be executed in turn or alternately with other steps or at least part of the sub-steps or stages of other steps.
[0123] In one embodiment, Fig.11 is a structural diagram of an intelligent flexible assembly execution computer device according to an embodiment of the present invention, such as Fig.11 As shown, a computer device is provided, which may be a terminal, and its internal structure diagram may be as shown in Fig.11 As shown. The computer device includes a processor, a memory, a network interface, a display screen and an input device connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The network interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, an intelligent flexible assembly execution method is implemented. The display screen of the computer device can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device can be a touch layer covering the display screen, or a button, trackball or touchpad set on the computer device housing, or an external keyboard, touchpad or mouse, etc.
[0124] Those skilled in the art will understand that Fig.10The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.
[0125] In one embodiment, a computer device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the above-mentioned intelligent flexible assembly execution method when executing the computer program.
[0126] The above-mentioned intelligent flexible assembly execution computer equipment obtains production tasks, process information and logistics information; schedules assembly stations and executes production processes according to production tasks and the process information, and executes logistics processes according to logistics information, wherein the assembly stations include at least one of the following: automatic assembly stations, human-machine collaborative assembly stations and manual assembly stations, and the logistics system includes an in-line handling system, thereby realizing standardized and modular design, which is compatible with the assembly production of the same type of products with different weights and sizes, and improves the flexibility and efficiency of the assembly system.
[0127] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the above-mentioned intelligent flexible assembly execution method is implemented.
[0128] The above-mentioned intelligent flexible assembly executes computer-readable storage media by acquiring production tasks, process information and logistics information; scheduling assembly stations and executing production processes according to the production tasks and the process information, and executing logistics processes according to the logistics information, wherein the assembly stations include at least one of the following: automatic assembly stations, human-machine collaborative assembly stations and manual assembly stations, and the logistics system includes an in-line handling system, thereby realizing standardized and modular design, which is compatible with the assembly production of the same type of products with different weights and sizes, and improves the flexibility and efficiency of the assembly system.
[0129] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application can include non-volatile and / or volatile memory. Non-volatile memory can include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory can include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).
[0130] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0131] The above-mentioned embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent of the present application shall be subject to the attached claims.
Claims
1. An intelligent flexible assembly execution system, It is characterized in that The system includes an intelligent assembly execution system FIL, a workstation system and a logistics system. The intelligent assembly execution system is used to obtain production tasks and send the production tasks to the workstation system, obtain process information and send the process information to the workstation system, obtain logistics information and send the logistics information to the logistics system; The workstation system is used to schedule assembly stations according to the production tasks and the process information and execute the production process, and feed back the production quality information generated by executing the production process to the intelligent assembly execution system, wherein the assembly stations include at least one of the following: automatic assembly stations, human-machine collaborative assembly stations and manual assembly stations; The logistics system is used to execute the logistics process according to the logistics information and feed back the logistics execution information generated by executing the logistics process to the intelligent assembly execution system, wherein the logistics system includes an in-line handling system; the in-line handling system adopts a multi-axis articulated industrial robot for loading and unloading, and is equipped with multiple end effectors; the in-line handling system also participates in the assembly actions at the automatic intelligent assembly station and the human-machine collaborative intelligent assembly station; The intelligent flexible assembly execution system also includes a manufacturing operation management system, which is used to issue the production task and the process information to the intelligent assembly execution system, and receive the production quality information and the logistics execution information; The workstation system is also used to compile, modulate and test the initialization process plan, and upload the initialization process plan to the intelligent assembly execution system. The intelligent assembly execution system generates work step operation standards based on the initialization process plan, and transmits the work step operation standards to the manufacturing operation management system. When the manufacturing operation management system approves the work step operation standards, a formal process plan is generated and issued.
2. The system according to claim 1, It is characterized in that The automatic assembly station is used to receive the raw materials delivered by the logistics system according to the logistics information, and assemble the raw materials into task semi-finished products; The human-machine collaborative assembly station is used to receive the task semi-finished products delivered by the logistics system, and assemble the task semi-finished products to obtain the task finished products; The manual assembly station is used to receive the semi-finished task product or the finished task product delivered by the logistics system, and to perform installation operations and electrical testing on the semi-finished task product or the finished task product.
3. The system according to claim 2, It is characterized in that The intelligent assembly execution system is also used to receive the detection results of the manual assembly station; When the detection result is unqualified, the intelligent assembly execution system instructs the logistics system to transport the task semi-finished product or the task finished product to a preset area according to a preset unqualified processing process.
4. The system according to claim 1, It is characterized in that The manufacturing operation management system is further used to issue a plurality of the production tasks, and when the assembly tools at the assembly stations meet the requirements of each of the production tasks, instruct the intelligent assembly execution system to complete the production tasks in sequence; When the assembly tools at the assembly station do not meet the requirements of each of the production tasks, the intelligent assembly execution system instructs the in-line transport system to obtain additional tools and transport the additional tools to the corresponding assembly station, instructing the intelligent assembly execution system to complete the production tasks in sequence.
5. The system according to claim 1, It is characterized in that The system also includes a line side warehouse, The line side warehouse is used to store raw materials, semi-finished products and finished products.
6. The system according to claim 1, It is characterized in that The station system includes a sensor, The sensor is used to obtain abnormal information during the assembly process and feed the abnormal information back to the intelligent assembly execution system, and the intelligent assembly execution system performs abnormal processing according to the abnormal information.
7. The system according to claim 1, It is characterized in that The workstation system also includes a visual inspection system, The visual inspection system is used to perform material scanning on the assembly materials on the assembly station; When the material scanning result indicates that the material is out of stock, the intelligent assembly execution system instructs the logistics system to return the assembly material and re-arrange the material.
8. An intelligent flexible assembly execution method, It is characterized in that The method comprises: Obtain production tasks, process information and logistics information; The assembly station is scheduled according to the production task and the process information and the production process is executed, and the logistics process is executed according to the logistics information, wherein the assembly station includes at least one of the following: an automatic assembly station, a human-machine collaborative assembly station and a manual assembly station, and the logistics system includes an in-line handling system; the in-line handling system adopts a multi-axis articulated industrial robot for loading and unloading, and is equipped with multiple end effectors; the in-line handling system also participates in the assembly actions at the automatic intelligent assembly station and the human-machine collaborative intelligent assembly station; The intelligent flexible assembly execution system further includes a manufacturing operation management system, which is used to issue the production tasks and process information to the intelligent assembly execution system, and receive production quality information and logistics execution information; Among them, the work station system is also used to compile, modulate and test the initialization process plan, and upload the initialization process plan to the intelligent assembly execution system, the intelligent assembly execution system generates work step operation standards according to the process initialization plan, and transmits the work step operation standards to the manufacturing operation management system. When the manufacturing operation management system approves the work step operation standards, a formal process plan is generated and issued.
9. The method according to claim 8, It is characterized in that After obtaining the production tasks, process information and logistics information, the method includes: When receiving a plurality of the production tasks issued, and when the jig and fixture meet the requirements of each of the production tasks, issuing the production tasks in sequence; In the case that the jigs and fixtures do not satisfy all the production tasks, a task of acquiring additional jigs and fixtures is issued, and the production tasks are issued in sequence.
10. The method according to claim 9, It is characterized in that After scheduling assembly stations and executing production processes according to the production tasks and process information, and executing logistics processes according to the logistics information, the method includes: Acquire production quality information corresponding to the production task and logistics execution information corresponding to the logistics information.
11. A computer device comprising a memory, a processor and a computer program stored in the memory and executable on the processor, It is characterized in that When the processor executes the computer program, the steps of the method according to any one of claims 8 to 10 are implemented.
12. A computer-readable storage medium having a computer program stored thereon, It is characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 8 to 10 are implemented.