A dry hanging structure, a finishing system and an installation method of the finishing system

Through the combination of dry-hanging structure and adhesive, the problems of low adhesion firmness and complex construction in the existing cement wet patch and copper wire binding processes are solved, and the fast and stable installation of the decorative panels is achieved and the construction process is simplified, which is reduced. Maintenance cost.

CN111962790BInactive Publication Date: 2024-12-20SHENZHEN ZHONGZHUANG CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010872989.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-08-26
Publication Date
2024-12-20
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing cement wet sticking operations and copper wire tie tileing process have problems such as low sticking firmness, complex construction processes and long cycles, which leads to hollowing and falling off of the decorative panels, and the later maintenance costs are high.

Method used

Adopt a dry hanging structure, including the first and second hanging parts, which are detachably connected to the wall base layer through fasteners, and are fixed with adhesive when installing the decorative panel to realize direct dry hanging of the decorative panel on the wall. Construction, avoid cement adhesive layer technology and simplify the construction process.

Benefits of technology

It realizes rapid installation of decorative panels, improves durability and firmness after installation, shortens construction cycle, saves the cost of cement mortar materials, and is convenient for later maintenance, and can replace part decorative panels separately.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111962790B_ABST
    Figure CN111962790B_ABST
Patent Text Reader

Abstract

The present application provides a dry hanging structure, a finishing system and an installation method of the finishing system, which relate to the field of construction; wherein the dry hanging structure includes at least one group of first hangers and at least one second hanger; the first hanger and the second hanger both have a first side for connecting to a wall base and a second side for connecting to a decorative panel; the first side is detachably connected to the wall base by a fastener; the first hanger is provided with a first bracket in the direction of the second side, and the second hanger is provided with a second bracket in the direction of the second side; the installation method includes arranging the first hanger and the second hanger on the wall base as required and fixing them; the back of the decorative panel contacts the first hanger and the second hanger and is fixed by adhesive. The present application enables the wall construction of the decorative panel to be assembled and achieve dry installation, with simple construction, high safety factor, and convenient disassembly and disassembly for later maintenance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building technology, and in particular to a dry hanging structure, a finishing system and an installation method of the finishing system. Background Art

[0002] At present, during wall decoration construction, the finishing effect is processed through decorative materials such as tiles, wallpaper, hard packing, and wood veneer.

[0003] The existing construction methods of decorative panels are usually cement wet pasting, copper wire binding and tile laying.

[0004] Cement wet pasting is a pasting material prepared by mixing a certain proportion of cement, sand and water to make the wall base and tiles bonded and fixed. Due to the change of ambient temperature and temperature, the pasting material and the decorative surface base undergo different physical changes, and the adhesion between the two gradually peels off, which is prone to hollowing problems. The pasting firmness is low, and there is a safety hazard of the decorative panel falling off, and the later maintenance cost is relatively high.

[0005] Copper wire binding tile tiling is to add copper wire binding technology on the basis of wet pasting operation. First, cement nails are pre-fixed on the wall base, and then grooves for binding copper wires are cut on the back of the decorative panel. The binding position of copper wire and decorative panel is fixed with marble glue, and the other end of steel wire is fixed with pre-fixed cement nails. It is a combination of wet pasting and binding technology. The construction process is complicated, the construction period is long, and the construction environment is poor, which is not conducive to improving construction efficiency. Summary of the invention

[0006] The purpose of this application is to provide a dry hanging structure, a finishing system and an installation method of the finishing system in view of the deficiencies in the above-mentioned prior art, so as to solve the problems of low adhesion firmness, complex construction procedures and long cycles in the existing cement wet pasting operation and copper wire binding tile laying process.

[0007] To achieve the above purpose, the technical solution adopted in the embodiment of the present application is as follows:

[0008] In a first aspect, an embodiment of the present application provides a dry hanging structure, comprising at least one set of first hanging members and at least one second hanging member;

[0009] The first hanging member and the second hanging member each have a first side for connecting to a wall base layer and a second side for connecting to a decorative panel;

[0010] The first side is detachably connected to the wall base layer by fasteners;

[0011] The first hanging member is provided with a first hanging bracket in the second side direction, and the second hanging member is provided with a second hanging bracket in the second side direction;

[0012] When the decorative panel is installed on the wall, the decorative panel is attached to the second side surface; one end of the decorative panel located at the two ends abuts against the first hanging bracket, and the other end abuts against the second hanging bracket adjacent to the first hanging bracket; the two ends of the decorative panel located in the middle abut against the two adjacent second hanging brackets respectively.

[0013] Optionally, the first hanger and the second hanger both include a first strip plate and a second strip plate that are integrally formed, and the cross-sections of the first strip plate and the second strip plate are both hollow rectangles with one side open, the open side of the first strip plate faces the first side, and the open side of the second strip plate faces the second side.

[0014] Optionally, ribs are provided on the opening sides of the first strip-shaped plate body and the second strip-shaped plate body.

[0015] Optionally, the closed side of the second strip plate facing the first side is a second closed side surface, the second closed side surface is detachably connected to the wall base layer by screws, and the second closed side surface is also provided with positioning grooves along its length direction, and the screws are distributed in the positioning grooves.

[0016] Optionally, the closed side of the first strip plate body facing the second side is a first closed side surface; the first bracket and the second bracket are both extended plates arranged on the first closed side surface and extending in the thickness direction of the decorative panel; a reinforcement groove is arranged at the junction of the first closed side surface and the extended plate.

[0017] Optionally, the first hanging member includes a first strip plate body and a second strip plate body distributed up and down, and the extension plate is located at an end position of the first closed side surface;

[0018] Optionally, the second hanger includes one first strip plate body and two second strip plate bodies, the first strip plate body is located between two upper and lower second strip plate bodies, and the extension plate is located in the middle of the first closed side surface.

[0019] In a second aspect, an embodiment of the present application further provides a finishing system, comprising the dry hanging structure and a finishing panel described in the first aspect, wherein the finishing panel is connected to the second side.

[0020] In a third aspect, the embodiment of the present application further provides a method for installing the facing system according to the second aspect, comprising the following steps:

[0021] Arrange the positions of the first hanging component and the second hanging component on the wall base layer according to the design requirements, and mark the positions;

[0022] Fixing the first hanging member and the second hanging member on the wall base according to the layout;

[0023] Adhesive glue is applied in advance to the joint between the second side and the first bracket, and to the joint between the second side and the second bracket.

[0024] Paste the decorative panel on the second side surface, and ensure that one end of the decorative panel located at both ends abuts against the first hanging bracket, and the other end abuts against the second hanging bracket adjacent to the first hanging bracket; the two ends of the decorative panel located in the middle abut against the two adjacent second hanging brackets respectively.

[0025] Optionally, when the decorative panel is installed on the wall, it is pasted and installed in a sequence from bottom to top.

[0026] The beneficial effects of this application are:

[0027] This application can realize the direct dry hanging installation of the decorative panel on the wall. The cement bonding layer process is optimized on the back of the decorative panel, and there is no need to use water, cement, or wet pasting on site. The dry construction on site is green and environmentally friendly. In addition, the dry hanging method has better controllability on the construction site, which can shorten the construction period. There is no need to wait for the cement mortar to solidify before the next process can be carried out, saving the cost of cement mortar materials.

[0028] At the same time, the veneer is fixedly installed by combining a hanger with a specific structure with adhesive, avoiding the hidden danger of hollowing of the veneer and improving the durability and firmness of the veneer after installation;

[0029] Finally, the pendant with this specific structure can be installed in an assembled manner, and is easy to disassemble and assemble during later maintenance. For example, if the decorative panels in a local area need to be replaced, they can be removed individually for protective purposes without affecting the decorative panels on the entire wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0031] Figure 1 A schematic diagram of the connection state of the dry hanging structure, decorative panels and wall base provided in one embodiment of the present application;

[0032] Figure 2 A vertical cross-sectional view of the connection state of the dry hanging structure, decorative panels and wall base provided in one embodiment of the present application;

[0033] Figure 3 A schematic structural diagram of a first hanging member located at an upper end portion of a dry hanging structure provided in an embodiment of the present application;

[0034] Figure 4 A schematic diagram of the structure of a second hanging member located in the middle of a dry hanging structure provided in an embodiment of the present application;

[0035] Figure 5 A schematic structural diagram of a first hanging member located at the lower end of a dry hanging structure provided in an embodiment of the present application;

[0036] Figure 6 A flow chart of an installation method of a finishing system provided in one embodiment of the present application.

[0037] Icons: 100-dry hanging structure; 101-first side; 102-second side; 103-first strip plate; 104-second strip plate; 105-edge; 106-second closed side; 107-positioning groove; 108-first closed side; 109-reinforcement groove; 110-first hanger; 111-first bracket; 120-second hanger; 121-second bracket; 200-wall base; 400-adhesive; 300-decorative panel; 500-screws. DETAILED DESCRIPTION

[0038] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.

[0039] Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the present application for which protection is sought, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.

[0040] It should be noted that similar reference numerals denote similar items in the following drawings, and therefore, once an item is defined in one drawing, it does not require further definition and explanation in the subsequent drawings.

[0041] In the description of this application, it should be noted that the terms "upper", "lower", "inner", "outer", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the application is usually placed when in use. They are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this application. In addition, the terms "first", "second", etc. are only used to distinguish descriptions and cannot be understood as indicating or implying relative importance.

[0042] In addition, the terms "horizontal", "vertical" and the like do not mean that the components are required to be absolutely horizontal or suspended, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0043] In the description of this application, it should also be noted that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0044] Example 1

[0045] Figure 1 This is a schematic diagram of the connection state of the dry hanging structure 100, the decorative panel 300 and the wall base 200 provided in one embodiment of the present application. Figure 2 A vertical cross-sectional view of the connection state of the dry hanging structure 100, the decorative panel 300 and the wall base 200 provided in an embodiment of the present application, referring to Figure 1 and Figure 1 The dry hanging structure 100 includes: at least one set of first hangers 110 and at least one second hanger 120; the first hanger 110 and the second hanger 120 each have a first side 101 for connecting to a wall base 200 and a second side 102 for connecting to a decorative panel 300;

[0046] The first side 101 is detachably connected to the wall base layer 200 via fasteners;

[0047] The first hanging member 110 is provided with a first hanging bracket 111 in the direction of the second side 102, and the second hanging member 120 is provided with a second hanging bracket 121 in the direction of the second side 102;

[0048] When the decorative panel 300 is installed on the wall, the decorative panel 300 is attached to the side of the second side 102; one end of the decorative panel 300 located at the two ends abuts against the first bracket 111, and the other end abuts against the second bracket 121 adjacent to the first bracket 111; the two ends of the decorative panel 300 located in the middle abut against two adjacent second brackets 121 respectively.

[0049] In this embodiment, by providing a dry hanging structure 100 composed of a first hanging member 110 and a second hanging member 120, the decorative panel 300 can be installed by dry method, thereby realizing the rapid installation of the decorative panel 300, effectively shortening the installation construction time of the decorative panel 300, improving the efficiency of the decoration project, and avoiding the hollowing and falling problems caused by the traditional wet method.

[0050] Among them, by providing the hanging support structure on both the first hanging member 110 and the second hanging member 120, it can be ensured that the decorative panel 300 has sufficient supporting force after installation, so that the gravity of the decorative panel 300 mainly acts on the hanging support structure, reducing the load force of the bonding between the decorative panel 300 and the side surface of the second side 102, so that the decorative panel 300 is fixed more firmly and reliably, and the risk of falling off is fully reduced;

[0051] In addition, the first side 101 of the dry hanging structure 100 can be detachably connected to the wall base 200 by fasteners, so as to facilitate the separate disassembly and installation of the dry hanging structure 100, and facilitate the independent replacement of the first hanger 110 or the second hanger 120 at a certain position when the decorative panel 300 at that position is damaged or needs to be replaced, thereby realizing the assembly installation of the hangers, which can be individually protectively disassembled without affecting the decorative panel of the entire wall, and the fasteners can be detachable fasteners such as screws;

[0052] The first hanging member 110 and the second hanging member 120 may be made of metal hanging members with good strength, or other non-metallic materials that can meet the use strength, such as polymer materials, etc., and the specific materials are not limited here;

[0053] The decorative panel 300 is a hard decorative panel with a fixed shape, for example, it can be a decorative tile with certain texture characteristics.

[0054] Figure 3 This is a structural schematic diagram of a first hanging member 110 located at the upper end of a dry hanging structure 100 provided in an embodiment of the present application. Figure 4 This is a structural schematic diagram of a second hanging member 120 located in the middle of a dry hanging structure 100 provided in an embodiment of the present application. Figure 5 A schematic diagram of the structure of the first hanging member 110 located at the lower end of the dry hanging structure 100 provided in an embodiment of the present application; in one implementation, refer to Figure 3-5 The first hanging member 110 and the second hanging member 120 both include an integrally formed first strip plate 103 and a second strip plate 104. The cross-sections of the first strip plate 103 and the second strip plate 104 are both hollow and rectangular with one side open. The open side of the first strip plate 103 faces the first side 101, and the open side of the second strip plate 104 faces the second side 102.

[0055] Among them, the hanging member is designed as a structural form of the first strip plate 103 and the second strip plate 104 formed in one piece, which can separate the two connecting side stress points of the connecting side of the dry hanging structure 100 and the decorative panel 300 and the connecting side of the dry hanging structure 100 and the wall base 200, thereby effectively increasing the stress area of ​​the dry hanging structure 100, making it difficult for the dry hanging structure 100 and the decorative panel 300 to separate, and further extending the service life of the dry hanging structure 100;

[0056] Designing the first strip plate 103 and the second strip plate 104 to be a rectangular shape with a hollow cross-section and an open one side can effectively reduce the weight of the first strip plate 103 and the second strip plate 104 while meeting their strength for use; specifically, the first hanger 110 and the second hanger 120 can be made of metal profiles with a specific cross-sectional structure, thereby forming the cross-sectional structure of the first strip plate 103 and the second strip plate 104.

[0057] Furthermore, the opening sides of the first strip plate 103 and the second strip plate 104 are both provided with a retaining edge 105; the retaining edge 105 can be set as a retaining edge structure parallel to the closed side surface opposite to the opening side of the above-mentioned strip plate body. At this time, the opening side just forms a partially closed state. The setting of the retaining edge 105 can increase the contact force area between the first strip plate body 103 and the wall base layer 200, and increase the contact force area between the second strip plate body 104 and the decorative panel 300, thereby maintaining the stable structure of the first strip plate body 103 and the second strip plate body 104.

[0058] Furthermore, the closed side of the second strip plate 104 facing the first side 101 is a second closed side surface 106, and the second closed side surface 106 is detachably connected to the wall base layer 200 by screws 500; the design of the second closed side surface 106 effectively increases the contact force area between the second strip plate 104 and the wall base layer 200, and also facilitates the installation and fixing of the screws 500;

[0059] The second closed side surface 106 is also provided with a positioning groove 107 along its length direction, and the screws 500 are distributed in the positioning groove 107; the design of the positioning groove 107 can facilitate the positioning and fixing of the screws 500, so that adjacent screws 500 are fixed in a horizontal line, so that the screws 500 are evenly stressed when being fixed to the wall base layer 200;

[0060] Of course, the screw 500 here is only a fastener that can achieve a detachable connection, and other forms of fasteners can also be used to achieve fixed installation here, and the design of the positioning groove 107 is also applicable to the positioning of other types of fasteners;

[0061] In addition, the cross-sectional structure of the positioning groove 107 can be set to be V-shaped. This V-shaped structure can facilitate the screw 500 to slide smoothly into the center position of the positioning groove 107, further improving the positioning accuracy of the screw 500.

[0062] Furthermore, the closed side of the first strip plate 103 facing the second side 102 is the first closed side surface 108. The design of the first closed side surface 108 effectively increases the contact force area between the second strip plate 104 and the decorative panel 300, and also facilitates the bonding and fixing of the decorative panel 300.

[0063] In one implementation, the first bracket 111 and the second bracket 121 are both extended plates arranged on the first closed side surface 108 and extending in the thickness direction of the decorative panel 300; a reinforcing groove 109 is arranged at the junction of the first closed side surface 108 and the extended plate;

[0064] The outer plate and the first closed side surface 108 may be an integrally formed structure. When installing the decorative panel 300, adhesive 400 may be applied in advance to the junction of the first closed side surface 108 and the outer plate. When the decorative panel 300 is attached to the dry hanging structure, the adhesive 400 can serve to adhere the decorative panel 300. The setting of the reinforcing groove 109 can increase the friction between the adhesive 400 and the first closed side surface 108 during pasting, thereby effectively strengthening the bonding strength and ensuring the stability of the dry installation of the decorative panel 300.

[0065] Further, see Figure 3 and Figure 5 The first hanging member 110 includes a first strip plate body 103 and a second strip plate body 104 distributed up and down, and the extension plate is located at the end position of the first closed side surface 108;

[0066] The first hanger 110 designed in this way can meet the operating conditions for installing the decorative panels 300 at the upper and lower ends. This is because the decorative panels 300 at the upper and lower ends only need to abut against one end surface of the first bracket 111 when installing, so the extension plate at this location is set at the end position of the first closed side surface 108; specifically, the first hanger 110 of this design can adopt a metal profile with a cross-section consisting of two opposite open rectangles arranged up and down.

[0067] Further, see Figure 4 The second hanging member 120 includes one first strip plate 103 and two second strip plates 104, the first strip plate 103 is located between the upper and lower second strip plates 104, and the extension plate is located in the middle of the first closed side surface 108;

[0068] The second hanger 120 designed in this way can meet the working conditions for installing the decorative panel 300 in the middle position. This is because the decorative panel 300 in the middle position needs to be abutted against the upper and lower end faces of the second bracket 121 when being installed to complete the installation. Therefore, the extension plate at this location is set in the middle position of the first closed side surface 108. Correspondingly, the extension plate is set in the middle position of the first closed side surface 108. At the same time, a group of first strip plate bodies 103 are symmetrically arranged at the upper and lower ends of the first strip plate body 103, which can ensure the overall force balance of the second hanger 120 and ensure the stable structure of the second hanger 120. Specifically, the second hanger 120 of this design can adopt a metal profile with a cross-section composed of three open rectangles, and ensure that the middle open rectangle is opposite to the open rectangles at the upper and lower ends.

[0069] Example 2

[0070] Figure 1 This is a schematic diagram of the connection state of the dry hanging structure 100, the decorative panel 300 and the wall base 200 provided in an embodiment of the present application, referring to Figure 1 The finishing system includes: the dry hanging structure 100 and the finishing panel 300 described in Example 1, and the finishing panel 300 is connected to the second side 102.

[0071] The dry hanging structure 100 in the finishing system realizes the dry assembly method between the decorative panel 300 and the wall base 200. Therefore, the application of the finishing system can effectively reduce the noise and air pollution caused by on-site construction of plasterers; at the same time, it can also avoid the quality and safety hazards of falling off caused by hollowing of the decorative panel 300, and improve the installation firmness of the decorative panel 300.

[0072] Example 3

[0073] Figure 6 This is a flow chart of the installation method of the veneer system provided in one embodiment of the present application, referring to Figure 6 The facing system is the facing system in Example 2, and the installation method of the facing system comprises the following steps:

[0074] Step 1: Arrange the positions of the first hanging part and the second hanging part on the wall base according to the design requirements and mark the positions;

[0075] Step 2: fixing the first hanging member and the second hanging member on the wall base according to the layout;

[0076] Step 3: Apply adhesive to the joint between the second side and the first bracket, and the joint between the second side and the second bracket.

[0077] Step 4: Paste the decorative panel on the side of the second side 102, and ensure that one end of the decorative panel located at both ends abuts against the first hanging bracket, and the other end abuts against the second hanging bracket adjacent to the first hanging bracket; the two ends of the decorative panel located in the middle abut against the two adjacent second hanging brackets respectively.

[0078] The positioning mark in step 1 may be positioned by laying out the lines, and the first hanging component and the second hanging component are laid out by the corresponding laying out lines;

[0079] When the first hanging member and the second hanging member in step 2 are fixed to the wall base, the first hanging member and the second hanging member can be fixed to the wall base manually or electrically with screws;

[0080] In addition, when the decorative panels are installed on the wall, it is preferred to paste and install them in a bottom-up order. Specifically, first, the lower end of the first row of decorative panels is pressed onto the first bracket of the first hanger at the lowest end, so that the second side surface of the first hanger and the reinforcing groove at the junction of the first bracket are firmly bonded to the lower end of the first row of decorative panels through the adhesive. At this time, the upper end of the first row of decorative panels is just tightly pressed on the reinforcing groove at the junction of the second side surface of the adjacent second hanger and the second bracket; then, the second to nth rows of decorative panels located in the middle position are successively pressed between the second brackets of the upper and lower adjacent second hangers to complete the installation of the decorative panels in the middle position; finally, the upper end of the last row of decorative panels is pressed onto the first bracket of the first hanger at the upper end, so that the second side surface of the first hanger and the reinforcing groove at the junction of the first bracket are firmly bonded to the upper end of the last row of decorative panels through the adhesive. At this time, the lower end of the last row of decorative panels is just tightly pressed on the reinforcing groove at the junction of the second side surface of the adjacent second hanger and the second bracket.

[0081] The installation method of this finishing system is different from the traditional cement wet pasting operation and copper wire clasp tiling. The hangers can be directly and detachably fixed to the structural wall. The fixing method can be manual or electric with internal screws, and the requirements for tools and materials are simple. At the same time, the construction site is directly dry-hanging on the wall for construction and installation. The cement pasting layer process is optimized on the back of the decorative panel, and there is no need to use water, cement, and sand wet operations on site. The dry construction on site is green and environmentally friendly. In addition, the dry hanging method makes the construction site more controllable, shortens the construction period, and does not need to wait for the cement sand to set, while saving the cost of cement mortar materials.

[0082] In addition, the veneer is installed by bonding with a special structure of hangers combined with adhesive, avoiding the risk of hollowing of the veneer and improving the durability and firmness of the veneer after installation.

[0083] Finally, the pendants are installed in an assembled manner, which makes them easy to disassemble and assemble during later maintenance. For example, if the decorative panels in a local area need to be replaced, they can be removed individually for protective purposes without affecting the decorative panels on the entire wall.

[0084] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A method for installing a veneer system, characterized in that: The finishing system includes a dry hanging structure and a finishing panel. The dry hanging structure includes at least one set of first hangers and at least one second hanger; the first hanger and the second hanger each have a first side for connecting to a wall base layer and a second side for connecting to a decorative panel; the decorative panel is connected to the second side; The first side is detachably connected to the wall base layer by fasteners; The first hanging member is provided with a first hanging bracket in the second side direction, and the second hanging member is provided with a second hanging bracket in the second side direction; When the decorative panel is mounted on the wall, the decorative panel is attached to the second side surface; one end of the decorative panel located at both ends abuts against the first hanging bracket, and the other end abuts against the second hanging bracket adjacent to the first hanging bracket; the two ends of the decorative panel located in the middle abut against two adjacent second hanging brackets respectively; The first hanging member and the second hanging member each include an integrally formed first strip plate and a second strip plate, the first strip plate and the second strip plate both being hollow and rectangular in cross section with one side open, the open side of the first strip plate facing the first side, and the open side of the second strip plate facing the second side; The opening sides of the first strip-shaped plate body and the second strip-shaped plate body are both provided with retaining edges; The closed side of the second strip-shaped plate body facing the first side is a second closed side surface, the second closed side surface is detachably connected to the wall base layer by screws, and the second closed side surface is also provided with positioning grooves along its length direction, and the screws are distributed in the positioning grooves; The closed side of the first strip-shaped plate body facing the second side is the first closed side surface; the first bracket and the second bracket are both extended plates arranged on the first closed side surface and extending in the thickness direction of the decorative panel; a reinforcing groove is arranged at the junction of the first closed side surface and the extended plate; The first hanging member includes a first strip plate body and a second strip plate body distributed up and down, and the extension plate is located at the end position of the first closed side surface; The second hanging member includes one first strip plate and two second strip plates, the first strip plate is located between the upper and lower second strip plates, and the extension plate is located in the middle of the first closed side surface; The installation method comprises the following steps: Arrange the positions of the first hanging component and the second hanging component on the wall base layer according to the design requirements, and mark the positions; Fixing the first hanging member and the second hanging member on the wall base according to the layout; Adhesive glue is applied in advance to the joint between the second side and the first bracket, and to the joint between the second side and the second bracket. Paste the decorative panel on the second side surface, and ensure that one end of the decorative panel located at both ends abuts against the first hanging bracket, and the other end abuts against the second hanging bracket adjacent to the first hanging bracket; the two ends of the decorative panel located in the middle abut against the two adjacent second hanging brackets respectively.

2. The method for installing a veneer system according to claim 1, characterized in that: When the decorative panel is installed on the wall, it is pasted and installed in a sequence from bottom to top.