A two-stage selection method for power system operation mode data characteristics

By combining information theory and a two-stage feature selection method with an improved SVM algorithm, the key features of the power system are screened out, solving the problems of data redundancy and low computational efficiency in large-scale AC and DC hybrid systems, and achieving efficient power grid stability assessment. , Accurate feature automatic search and scheduling support.

CN112396113BActive Publication Date: 2024-10-15STATE GRID CORP NORTHEAST DIVISION +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202011318226.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-11-23
Publication Date
2024-10-15
Estimated Expiration
2040-11-23

AI Technical Summary

Technical Problem

There are many data variables in large-scale AC and DC hybrid systems, which results in low computational efficiency and poor classification effect in power system stability assessment, and redundant features affect online applications. It is necessary to screen the initial input features to improve the observability and reliability of the power grid. control.

Method used

A two-stage selection method for power system operating mode data features is proposed. Key features are screened out through the Filter stage feature selection based on information theory and the Wrapper stage feature selection of the improved SVM algorithm, combined with the IG-RFE algorithm of standardized mutual information and interactive information gain. , to achieve efficient and accurate automatic search of characteristics of the power system.

Benefits of technology

It achieves efficient and accurate automatic search of key features of the power system, reduces the impact of redundant features, improves the calculation efficiency and classification accuracy of power grid transient stability assessment, and provides better power flow information to support dispatch operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure BDA0002791959330000021
    Figure BDA0002791959330000021
  • Figure BDA0002791959330000022
    Figure BDA0002791959330000022
  • Figure BDA0002791959330000023
    Figure BDA0002791959330000023
Patent Text Reader

Abstract

The present invention belongs to the technical field of power system operation and control, and relates to a two-stage selection method for power system operation mode data features. First, through the IG-RFE feature selection Filter stage algorithm based on standardized mutual information and mutual information gain, the prior parameters in the relevant algorithm are removed and the complex dependencies between the features are correctly judged, thereby realizing the automatic search and extraction of key features of the power system operation mode data; then, the improved hybrid kernel function SVM algorithm is used in conjunction with the recursive feature elimination RFE search method to remove bad features until a feature set with a result quantity of a preset value is obtained, thereby realizing efficient and accurate automatic search of key features of the power system. This method improves the efficiency and accuracy of the selection of power system operation mode data features, and provides a technical basis and practical method for the selection of power grid operation mode data features.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of power system operation and control, and relates to a two-stage selection method for power system operation mode data characteristics. Background Art

[0002] The scale of my country's ultra-high voltage AC / DC hybrid power grid continues to expand, the widespread access to new energy sources and the increasing degree of two-way interaction between flexible loads and power grids have increased the uncertainty of both sides of the source and load, and the increasingly complex characteristics of the power grid, which poses a huge challenge to the dispatching and operation personnel in monitoring and regulating the safe and stable operation of the power grid. Therefore, it is of great significance to study the potential safety and stability issues of the power grid, improve the observability and controllability of the power system, and realize efficient and rapid evaluation of the transient stability of large power grids to maintain the safe and stable operation of the power system. With the maturity of wide-area measurement technology and the development of big data theory, online TSA based on artificial intelligence methods provides a new idea for the intelligent control of large power grids.

[0003] Since actual large-scale AC / DC hybrid systems contain many variables, their data scale is large and the dimension is high. Only a few feature quantities will affect the stability level of the system, and most of the features are redundant. If they are used as inputs to transient assessment models, they will inevitably affect the computational efficiency, classification effect and online application requirements. Therefore, it is necessary to screen the initial input features in the power system to find the features that play a key role in the safety and stability issues being studied. Summary of the invention

[0004] The purpose of the present invention is to propose a two-stage selection method for power system operation mode data features, including a Filter stage feature selection process based on information theory and a Wrapper stage feature selection process based on an improved SVM algorithm, in which the power grid operation mode data features that have been proven in practice are incorporated into the initial candidate features, and features that can provide supplementary information are screened, so as to provide as much power flow information as possible with as few features as possible, so as to facilitate the dispatching and operation personnel to implement monitoring.

[0005] The present invention proposes a two-stage selection method for power system operation mode data characteristics, which comprises the following steps:

[0006] (1) The filter stage feature selection based on normalized mutual information and mutual information gain is performed on the power system operation mode data, which includes the following steps:

[0007] (1-1) Obtain the power system operation mode data from the synchronous vector measurement unit of the power system, supplement the missing data in the data, delete the duplicate data, obtain valid data, construct a sample and sample characteristics for each set of operation data, and label the sample with 0 or 1 according to whether it is transient stable or not, which is recorded as the category attribute C of the sample;

[0008] (1-2) Construct a selected feature subset S, and initialize S to an empty set; construct an alternative feature set US, and initialize it to an empty set; construct the classification accuracy index of set S and set US respectively, denoted as Acc(S) and Acc(US), and set Acc(S) and Acc(US) to 0 respectively during initialization;

[0009] The above Acc(US) and Acc(S) represent the classification accuracy of the target optimal feature subset S and the candidate feature set US respectively. The calculation formula of the classification accuracy is as follows:

[0010]

[0011] Where TP, FN, FP and TN represent the number of samples correctly classified as positive examples, the number of samples incorrectly classified as negative examples, the number of samples incorrectly classified as positive examples and the number of samples correctly classified as negative examples in a given machine learning algorithm.

[0012] (1-3) constructing an initial feature set of power system operation mode data based on the valid data in step (1-1), and updating the candidate feature set US to the initial feature set;

[0013] (1-4) The Parzen window method is used to perform discrete estimation and probability density estimation on each feature in the current candidate feature set US, and the probability distribution of the power system operation mode data feature is obtained, that is, the feature f i The probability distribution p(f i ), feature f j ,f i The joint probability distribution p(f i ,f j ), the probability distribution p(c) of the feature category attribute C and the feature f j The conditional probability distribution p(f j ,c);

[0014] (1-5) Using the following formula, calculate the normalized mutual information NMI(f; C) of all features f and category attributes C in the candidate feature set US of step (1-4) respectively:

[0015]

[0016] Among them, MI(f;C) represents the mutual information between feature f and feature category attribute C, that is:

[0017]

[0018]

[0019] H(f) represents the information entropy of feature f, and H(C) represents the information entropy of feature category attribute C. For a single continuous variable X, the calculation formula for information entropy is as follows:

[0020] H(X)=-∫p(x)log2(p(x))

[0021] Where p(x) is the probability distribution of variable X;

[0022] Eliminate the corresponding features whose value in NMI(f;C) is zero from the candidate feature set US;

[0023] (1-6) Calculate the NIG index and Score index between any two features in the candidate feature set US of step (1-4), and use the following formula to form the IG-RFE evaluation standard result of each feature, that is, calculate each feature of the candidate feature set US to obtain the weight score w(f i ):

[0024]

[0025] Where N is the number of features in the candidate feature set US;

[0026] Score index Score(f i ,f j ) is as follows:

[0027]

[0028] (1-7) The weight score w(f) of all features in step (1-6) i ) are arranged in descending order, and the feature corresponding to the minimum weight score in the max(1,r*N) sortings is removed from the candidate feature set US, where r is the minimum elimination ratio of a single iteration of the backward search, and N is the total number of features in the candidate feature set US;

[0029] (1-8) judging the total number of features in the candidate feature set US of step (1-7); if US is an empty set, outputting the currently selected feature subset S as the optimal feature subset to achieve the two-stage selection of the power system operation mode data features; if US is not an empty set, taking the current candidate feature set US as the input of step (2) to perform the second stage of screening;

[0030] (2) Using the candidate feature set US obtained in step (1) as the input of the improved hybrid kernel function SVM, the second stage Wrapper feature selection is performed, which includes the following steps:

[0031] (2-1) Using the improved hybrid kernel function support vector machine algorithm, taking the candidate feature set US as input, the candidate feature set US is classified and trained according to the 10-fold cross-validation method, and the classification accuracy Acc(US) of the current candidate feature set US is output;

[0032] (2-2) Compare the classification accuracy Acc(S) of the selected feature subset S with the classification accuracy of the alternative subset US calculated in step (2-1). If Acc(US) is greater than Acc(S), update S to US and update Acc(S) to Acc(US), and return to step (1-4). If Acc(US) is less than or equal to Acc(S), return directly to step (1-4).

[0033] In step (1-1) of the above-mentioned feature extraction method, the initial feature set is the steady-state operation data information in the power system before the fault, including component feature data and system feature data. The component feature data includes the active power and reactive power of each generator set in the system before the fault, the active power and reactive power of each node load in the system before the fault, the active power and reactive power of the transmission line, and the voltage and phase angle of each bus in the system before the fault; the system feature data is the total active output and total reactive output of the generator in the system before the fault, all active loads and all reactive loads in the system before the fault, the total mechanical input power in the system before the fault, the total reactive reserve capacity in the system before the fault, and the network topology indicators of the power system before the fault.

[0034] In step (1-4) of the above feature extraction method, the Parzen window method shown is a non-parametric estimation method, which performs spatial division on the power system operation mode data characteristics after data cleaning in step (1-1), uses the frequency as the probability corresponding to the coordinates of the spatial center point, and obtains the density distribution of the operation mode data characteristics.

[0035] In the steps (1-6) of the above feature extraction method, the NIG index is the standardized information gain index NIG (f i ;f j ; C), the expression is as follows:

[0036]

[0037] Among them, IG(f i ;f j ; C) represents the feature f i 、f j and the mutual information gain index IG(f i ;f j ; C) = MI(f i ;f j ; C) = MI(fi ;C)-MI(f j ; C), H(f i ) represents the feature f i Information entropy.

[0038] In the steps (1-6) of the feature extraction method, the IG-RFE evaluation standard of a single feature is obtained by weighting the correlation degree NMI measured by the normalized mutual information index and the synergy degree NIG calculated by the mutual information gain between the features. The IG-RFE evaluation standard expression for a single feature is as follows:

[0039]

[0040] Where N is the total number of set US features calculated in steps (1-6).

[0041] In step (2) of the feature extraction method, the improved hybrid kernel function support vector machine algorithm uses the selected mapping function transformation as the hybrid function to map the data samples into a high-dimensional space, and distinguishes the two types of data samples through a linear hyperplane in the high-dimensional space, wherein the specific expression of the improved hybrid function is as follows:

[0042] K mix =λK local +(1-λ)K global

[0043] In the formula, K local Represents the local kernel function, and the local kernel function selects the RBF kernel function K global Represents the global kernel function, which is selected as the polynomial kernel function k(x,x′)=(x*x'+c) d .

[0044] The two-stage selection method for power system operation mode data characteristics proposed in the present invention has the following advantages:

[0045] 1. The two-stage selection method for the data features of the power system operation mode of the present invention first uses the IG-RFE (Interaction Gain-Recursive Feature elimination) feature selection Filter stage algorithm based on standardized mutual information and interactive information gain to remove the prior parameters in the relevant algorithm and correctly judge the complex dependencies between the features, thereby realizing the automatic search and extraction of the key features of the power system operation mode data; then, the improved hybrid kernel function SVM algorithm is used in conjunction with the recursive feature elimination RFE search method to remove bad features until a feature set with a preset number of results is obtained, thereby realizing efficient and accurate automatic search of the key features of the power system.

[0046] 2. The method of the present invention is easy to implement. The method introduces a data-driven method in the field of artificial intelligence to realize automatic search for key features of the power system by designing a classifier based on the two most critical parts, namely, a feature selection algorithm based on standardized mutual information and interactive information gain and a search method based on an improved hybrid kernel function SVM algorithm and a collaborative recursive feature elimination (RFE). Therefore, the method is easy to implement. DETAILED DESCRIPTION

[0047] The two-stage selection method of power system operation mode data characteristics proposed by the present invention comprises the following steps:

[0048] (1) The filter stage feature selection based on normalized mutual information and mutual information gain is performed on the power system operation mode data, which includes the following steps:

[0049] (1-1) Obtain the power system operation mode data from the synchronous vector measurement unit of the power system, supplement the missing data in the data, delete the duplicate data, obtain valid data, construct a sample and sample characteristics for each set of operation data, and label the sample with 0 or 1 according to whether it is transient stable or not, which is recorded as the category attribute C of the sample;

[0050] (1-2) Construct a selected feature subset S, and initialize S to an empty set; construct an alternative feature set US, and initialize it to an empty set; construct the classification accuracy index of set S and set US respectively, denoted as Acc(S) and Acc(US), and set Acc(S) and Acc(US) to 0 respectively during initialization;

[0051] The above Acc(US) and Acc(S) represent the classification accuracy of the target optimal feature subset S and the candidate feature set US respectively. The calculation formula of the classification accuracy is as follows:

[0052]

[0053] In the formula, TP, FN, FP and TN respectively represent the number of samples correctly classified as positive examples, the number of samples incorrectly classified as negative examples, the number of samples incorrectly classified as positive examples and the number of samples correctly classified as negative examples in a given machine learning algorithm; please refer to the following table:

[0054] Sample category attributes Prediction is 0 Prediction is 1 The actual value is 0 TN FP The actual value is 1 FN TP

[0055] (1-3) constructing an initial feature set of power system operation mode data based on the valid data in step (1-1), and updating the candidate feature set US to the initial feature set;

[0056] (1-4) The Parzen window method is used to perform discrete estimation and probability density estimation on each feature in the current candidate feature set US, and the probability distribution of the power system operation mode data feature is obtained, that is, the feature f i The probability distribution p(f i ), feature f j ,f i The joint probability distribution p(f i ,f j ), the probability distribution p(c) of the feature category attribute C and the feature f j The conditional probability distribution p(f j ,c);

[0057] (1-5) Using the following formula, calculate the normalized mutual information NMI(f; C) of all features f and category attributes C in the candidate feature set US of step (1-4) respectively:

[0058]

[0059] Among them, MI(f;C) represents the mutual information between feature f and feature category attribute C, that is:

[0060]

[0061]

[0062] H(f) represents the information entropy of feature f, and H(C) represents the information entropy of feature category attribute C. For a single continuous variable X, the calculation formula for information entropy is as follows:

[0063] H(X)=-∫p(x)log2(p(x))

[0064] Where p(x) is the probability distribution of variable X;

[0065] Eliminate the corresponding features whose value in NMI(f;C) is zero from the candidate feature set US;

[0066] (1-6) Calculate the NIG index and Score index between any two features in the candidate feature set US of step (1-4), and use the following formula to form the IG-RFE evaluation standard result of each feature, that is, calculate each feature of the candidate feature set US to obtain the weight score w(f i ):

[0067]

[0068] Wherein, N is the number of features in the candidate feature set US.

[0069] Score index Score(f i ,f j ) is as follows:

[0070]

[0071] (1-7) The weight score w(f) of all features in step (1-6) i ) are arranged in descending order, and the feature corresponding to the minimum weight score in the max(1,r*N) sortings is removed from the candidate feature set US, where r is the minimum elimination ratio of a single iteration of the backward search, and N is the total number of features in the candidate feature set US;

[0072] (1-8) The total number of features in the candidate feature set US of step (1-7) is judged. If US is an empty set, it means that the feature subset selection process of backward elimination has ended, and the current selected feature subset S is output as the optimal feature subset to achieve the two-stage selection of the power system operation mode data features; if US is not an empty set, the current candidate feature set US is used as the input of step (2) to perform the second stage of screening;

[0073] (2) Using the candidate feature set US obtained in step (1) as the input of the improved hybrid kernel function SVM, the second stage Wrapper feature selection is performed, which includes the following steps:

[0074] (2-1) Using the improved hybrid kernel function support vector machine algorithm, taking the candidate feature set US as input, the candidate feature set US is classified and trained according to the 10-fold cross-validation method, and the classification accuracy Acc(US) of the current candidate feature set US is output;

[0075] (2-2) Compare the classification accuracy Acc(S) of the selected feature subset S with the classification accuracy of the alternative subset US calculated in step (2-1). If Acc(US) is greater than Acc(S), it means that the performance of the current feature subset US is better than that of the selected feature subset S. Update S to US and update Acc(S) to Acc(US). Return to step (1-4). If Acc(US) is less than or equal to Acc(S), it means that the classification performance of US at this time is not as good as that of the selected feature set S. Therefore, no update is made and return to step (1-4).

[0076] In step (1-1) of the above-mentioned feature extraction method, the initial feature set is the steady-state operation data information in the power system before the fault, including component feature data and system feature data. The component feature data includes the active power and reactive power of each generator set in the system before the fault, the active power and reactive power of each node load in the system before the fault, the active power and reactive power of the transmission line, and the voltage and phase angle of each bus in the system before the fault; the system feature data is the total active output and total reactive output of the generator in the system before the fault, all active loads and all reactive loads in the system before the fault, the total mechanical input power in the system before the fault, the total reactive reserve capacity in the system before the fault, and the network topology indicators of the power system before the fault.

[0077] In step (1-4) of the above-mentioned feature extraction method, the Parzen window method is a non-parametric estimation method, which performs spatial division on the power system operation mode data characteristics after data cleaning in step (1-1), uses the frequency as the probability corresponding to the coordinates of the spatial center point, and obtains the density distribution of the operation mode data characteristics.

[0078] In the steps (1-6) of the above feature extraction method, the NIG index is the standardized information gain index NIG (f i ;f j ; C), the expression is as follows:

[0079]

[0080] Among them, IG(f i ;f j ; C) represents the feature f i 、f j and the mutual information gain index IG(f i ;f j ; C) = MI(f i ;f j ; C) = MI(f i ;C)-MI(f j ; C), H(f i ) represents the feature f i Information entropy.

[0081] In the steps (1-6) of the feature extraction method, the IG-RFE evaluation standard of a single feature is obtained by weighting the correlation degree NMI measured by the normalized mutual information index and the synergy degree NIG calculated by the mutual information gain between the features. The IG-RFE evaluation standard expression for a single feature is as follows:

[0082]

[0083] Where N is the total number of set US features calculated in steps (1-6).

[0084] In step (2) of the feature extraction method, the improved hybrid kernel function support vector machine algorithm uses the selected mapping function transformation as the hybrid function to map the data samples into a high-dimensional space, and distinguishes the two types of data samples through a linear hyperplane in the high-dimensional space, wherein the specific expression of the improved hybrid function is as follows:

[0085] K mix =λK local +(1-λ)K global

[0086] In the formula, K local Represents the local kernel function, and the local kernel function selects the RBF kernel function K global Represents the global kernel function, which is selected as a polynomial kernel function k (x,x′)=(x*x'+c) d In one embodiment of the present invention, the accuracy requirements of the data, the classification performance of the algorithm and the actual running time requirements are comprehensively considered, four parameters are tested, and the typical values ​​given in the following table are finally selected as the actual values.

[0087] parameter σ C d λ Value 2.5 1 3 0.783

[0088] The two-stage selection method of the power system operation mode data feature of the present invention firstly uses the Filter stage feature selection process based on information theory, and uses the IG-RFE feature selection Filter stage algorithm based on standardized mutual information and mutual information gain proposed in this part to remove the prior parameters in the relevant algorithm and correctly judge the complex dependencies between the features, including correlation, redundancy and complementarity, so as to realize the automatic search and extraction of the key features of the power system. Then, based on the Wrapper stage feature selection process of the improved SVM algorithm, the improved hybrid kernel function SVM algorithm and the recursive feature elimination RFE search method are used to continuously remove bad features from the current feature set to be processed to realize the selection process, until a feature set with a preset value of the number of results is obtained, and the power grid operation mode data features that have been proven in practice are included in the initial candidate features, and the features that can provide supplementary information are screened, so as to provide as much flow information as possible with as few features as possible, so as to facilitate the dispatching and operation personnel to implement monitoring.

[0089] The method of the present invention targets power system operation mode data with large data scale and high dimension, and adopts a two-stage feature selection method combining a Filter stage feature selection method based on information theory and a Wrapper stage feature selection method based on an improved SVM algorithm for different training tasks, which can effectively improve the efficiency and accuracy of automatic search for key features of the power system.

[0090] The method of the present invention is mainly divided into two stages: first, the feature selection process of the Filter stage based on information theory, in which the definition and basic indicators of the relevant concepts of information theory are introduced, and the corresponding IG-RFE evaluation standard is proposed. This evaluation standard, as the evaluation indicator of the Filter stage algorithm, has a good characterization effect on the correlation between features and the combined synergistic effect, and largely avoids the correlation errors that may be caused by the artificial prior parameter setting of the traditional method. This is one of the inventive points of the method of the present invention. Then, the Wrapper stage feature selection process based on the improved SVM algorithm is carried out, and the selection process is realized by continuously removing bad features from the current feature set to be processed through the improved hybrid kernel function SVM algorithm and the recursive feature elimination RFE search method, until a feature set with a preset value of the number of results is obtained. This is another essential difference between the method of the present invention and other methods, and it is also the second inventive point of the present invention.

Claims

1. A two-stage selection method for power system operation mode data features, the method comprising the following steps: (1) The filter stage feature selection based on normalized mutual information and mutual information gain is performed on the power system operation mode data, which includes the following steps: (1-1) Obtain the power system operation mode data from the synchronous vector measurement unit of the power system, supplement the missing data in the data, delete the duplicate data, obtain valid data, construct a sample and sample characteristics for each set of operation data, and label the sample with 0 or 1 according to whether it is transient stable or not, which is recorded as the category attribute C of the sample; (1-2) Construct a selected feature subset S, and initialize S to an empty set; construct an alternative feature set US, and initialize it to an empty set; construct the classification accuracy indicators of set S and set US respectively, denoted as Acc(S) and Acc(US), and set Acc(S) and Acc(US) to 0 respectively during initialization; The above Acc(US) and Acc(S) represent the classification accuracy of the target optimal feature subset S and the candidate feature set US respectively. The calculation formula of the classification accuracy is as follows: Where TP, FN, FP and TN represent the number of samples correctly classified as positive examples, the number of samples incorrectly classified as negative examples, the number of samples incorrectly classified as positive examples and the number of samples correctly classified as negative examples in a given machine learning algorithm. (1-3) Based on the valid data in step (1-1), an initial feature set of power system operation mode data is constructed, and the candidate feature set US is updated to the initial feature set; (1-4) The Parzen window method is used to perform discrete estimation and probability density estimation on each feature in the current candidate feature set US, and the probability distribution of the power system operation mode data characteristics is obtained, that is, the characteristic The probability distribution of ,feature The joint probability distribution of , the probability distribution of feature category attribute C and Features Conditional probability distribution under feature category attribute C ; (1-5) Use the following formula to calculate the normalized mutual information of all features f and category attributes C in the candidate feature set US in step (1-4). : in, Representation characteristics f And the mutual information between the feature category attribute C, that is: Representation characteristics f The information entropy of Represents the information entropy of the feature category attribute C. For a single continuous variable X, the calculation formula for information entropy is as follows: Where p(x) is the probability distribution of variable X; Will The corresponding features with a value of zero are removed from the candidate feature set US; (1-6) Calculate the NIG index and Score index between any two features in the candidate feature set US in step (1-4), and use the following formula to form the IG-RFE evaluation standard result of each feature, that is, calculate each feature in the candidate feature set US to obtain the weight score of all features in the candidate feature set US : Where N is the number of features in the candidate feature set US; Score indicator The expression is as follows: (1-7) Weight scores for all features in step (1-6) Arrange in descending order, and remove the feature corresponding to the minimum weight score in the max(1,r*N) sorting from the candidate feature set US, where r is the minimum elimination ratio of a single iteration of the backward search, and N is the total number of features in the candidate feature set US; (1-8) Determine the total number of features in the candidate feature set US of step (1-7). If US is an empty set, output the currently selected feature subset S as the optimal feature subset to achieve two-stage selection of power system operation mode data features. If US is not an empty set, use the current candidate feature set US as the input of step (2) to perform the second stage of screening. (2) Using the candidate feature set US obtained in step (1) as the input of the improved hybrid kernel function SVM, the second stage Wrapper feature selection is performed, which includes the following steps: (2-1) Using the improved hybrid kernel function support vector machine algorithm, taking the candidate feature set US as input, the candidate feature set US is classified and trained according to the 10-fold cross-validation method, and the classification accuracy Acc(US) of the current candidate feature set US is output; (2-2) Compare the classification accuracy Acc(S) of the selected feature subset S with the classification accuracy of the candidate subset US calculated in step (2-1). If Acc(US) is greater than Acc(S), update S to US and Acc(S) to Acc(US), and return to step (1-4). If Acc(US) is less than or equal to Acc(S), return directly to step (1-4). The initial feature set in the step (1-1) is the steady-state operation data information of the power system before the fault, including component feature data and system feature data. The component feature data includes the active power and reactive power of each generator set in the system before the fault, the active power and reactive power of each node load in the system before the fault, the active power and reactive power of the transmission line, and the voltage and phase angle of each bus in the system before the fault; the system feature data includes the total active output and total reactive output of the generator in the system before the fault, all active loads and all reactive loads in the system before the fault, the total mechanical input power in the system before the fault, the total reactive reserve capacity in the system before the fault, and the network topology index of the power system before the fault; The Parzen window method in step (1-4) is a non-parametric estimation method, which performs spatial division on the power system operation mode data characteristics after data cleaning in step (1-1), uses the frequency as the probability corresponding to the coordinates of the spatial center point, and obtains the density distribution of the operation mode data characteristics; The NIG index in the steps (1-6) is the standardized information gain index , the expression is as follows: in, Representation characteristics f i , f j and the mutual information gain index between the category attributes C , Representation characteristics Information entropy.

2. The two-stage selection method for power system operation mode data characteristics according to claim 1, characterized in that: The IG-RFE evaluation standard of a single feature in the steps (1-6) is obtained by weighting the correlation degree NMI measured by the standardized mutual information index and the synergy degree NIG calculated by the mutual information gain between the features. The expression of the IG-RFE evaluation standard for a single feature is as follows: Where N is the total number of set US features calculated in steps (1-6).

3. The two-stage selection method for power system operation mode data characteristics according to claim 1, characterized in that: The improved hybrid kernel function support vector machine algorithm in step (2) uses the selected mapping function transformation as the hybrid function to map the data samples into a high-dimensional space, and distinguishes the two types of data samples through a linear hyperplane in the high-dimensional space, wherein the specific expression of the improved hybrid function is as follows: In the formula, Represents the local kernel function, and the local kernel function selects the RBF kernel function , Represents the global kernel function, which is selected as a polynomial kernel function .