A construction device based on synchronous drilling and prefabricated pile splicing
Through the construction equipment of synchronous drilling and splicing of prefabricated piles, the problems of too much equipment, large land occupation and low construction efficiency caused by the separation of drilling and pile planting in the existing technology are solved, achieving the effect of less equipment, small land occupation and high construction efficiency. , ensuring construction quality and progress.
Patent Information
- Application Number
- CN202110641709.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-06-09
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2041-06-09
AI Technical Summary
In the existing pile foundation construction technology, drilling and pile planting are carried out separately, which requires a lot of equipment, a large area, and low construction efficiency. The splicing and dismantling of drill pipes is complicated, resulting in low construction efficiency and equipment utilization.
Design a construction equipment based on simultaneous drilling and prefabricated pile splicing. It adopts a 360-degree rotating main mast and track plate system, realizes automatic splicing and disassembly of drill pipes and prefabricated piles through a hydraulically driven pile clamping device, and combines the traveling device and Lifting device enables simultaneous operations of drilling, bottom expansion, grouting and pile planting.
It reduces the number of construction equipment and floor space, improves construction efficiency, reduces the frequency of equipment movement during drilling and pile planting, ensures construction quality and progress, and reduces the solidification time of cement slurry.