By designing a maintainable intelligent drainage system in urban tunnels, and switching of three drainage modes using electronic valves and water pressure sensors, it solves the problem that cannot be switched on demand in the existing technology and does not affect traffic conditions The safety maintenance is carried out, and the electronic and information management of drainage prevention is realized.

CN113339059BInactive Publication Date: 2024-11-12重庆城投基础设施建设有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110375440.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-04-08
Publication Date
2024-11-12
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing urban tunnel drainage system cannot achieve on-demand switching of three drainage modes, and the safety of maintenance personnel is difficult to ensure the safety of maintenance personnel during operation and maintenance, which affects tunnel traffic.

Method used

A maintenance-based intelligent drainage system for tunnels is designed, including longitudinal and circumferential drainage blind pipes, vertical inspection wells, side drainage pipes and central drainage ditches, equipped with electronic valves and water pressure sensors, realizing three drainage modes and safe maintenance through vertical inspection wells.

Benefits of technology

The electronic and information management of urban tunnel drainage prevention and drainage mode is realized, and the drainage prevention and drainage mode can be switched according to actual needs, meet the drainage prevention and drainage requirements during operation, and maintain it without affecting traffic.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113339059B_ABST
    Figure CN113339059B_ABST
Patent Text Reader

Abstract

The present invention discloses a maintainable tunnel intelligent drainage system and method, including a longitudinal drainage blind pipe, an annular drainage blind pipe, a vertical inspection well, a side drainage pipe, a drainage side ditch, a central drainage ditch, an electronic valve, and a computer terminal. The computer terminal is used to receive and analyze the urban tunnel water pressure load data transmitted by the electronic valve, and send instructions to the electronic valve to control the opening and closing of the electronic valve to achieve the balance of water pressure-discharge volume of the tunnel project. Compared with the prior art, the present invention can complete the switching of three urban tunnel drainage modes according to the actual needs of tunnel drainage, and realize the electronic and information management of tunnel drainage; it can meet the drainage needs of the tunnel structure during operation, and also has a maintainable function. When the drainage function is obstructed, the vertical inspection well can be entered for operation and maintenance without affecting the traffic of the urban tunnel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of tunnel drainage, and in particular to a maintainable tunnel intelligent drainage system and method. Background Art

[0002] Urban tunnels can effectively improve urban traffic efficiency and reduce environmental pollution, and are also in line with the current advocacy of low-carbon living. Due to the particularity of urban tunnels themselves, the presence of buildings and vegetation on the ground makes urban tunnels face many challenges during operation and maintenance. Through field investigations of a large number of urban tunnels in my country, it was found that in addition to construction quality problems caused by human factors, water damage problems (groundwater, rainfall, etc.) have the most common impact on tunnel engineering safety, and safety problems caused by groundwater account for 58% of the total number of tunnels. When water damage problems occur in urban tunnels, it usually leads to a drop in groundwater levels, resulting in the depletion of surface water sources, soil erosion, vegetation destruction, and ground collapse. Solving tunnel water problems can effectively extend the service life of urban tunnels and also have a positive effect on the surrounding ecological environment. It has become a key factor affecting the success or failure of tunnel projects.

[0003] In order to reduce the probability of water damage, three types of drainage systems are mainly used in urban tunnels in my country: (1) the drainage type or drainage self-drainage type system mainly based on drainage and drainage, that is, the water pressure load on the support structure of the urban tunnel is reduced by drainage. This method can effectively reduce the groundwater level, but the damage to the ground vegetation caused by it is difficult to recover; (2) the full-cover waterproof system, which isolates the stratum seepage outside the support structure of the urban tunnel and realizes the waterproof function of the urban tunnel by improving the waterproof capacity of the support structure. However, under the long-term action of the water pressure load, the support structure is prone to cracking, resulting in water leakage; (3) the control type waterproof system combined with drainage, which usually adopts a semi-cover waterproof method, allowing partial discharge of groundwater, which can not only ensure the safety of the structure, but also reduce the water pressure behind the lining. However, this method is difficult to achieve a dynamic balance between the relationship between water pressure and drainage, so it is difficult to achieve an ideal state. The above three urban tunnel drainage modes all have certain disadvantages, and the drainage volume is difficult to control. Therefore, an intelligent urban tunnel drainage system is needed.

[0004] In the existing urban tunnel drainage system, it is not possible to switch the three drainage modes on demand. In addition, in the later operation and maintenance of urban tunnels, the inspection wells of the drainage system are usually located in the town center of the urban tunnel road surface. During the inspection and maintenance process, the personal safety of the maintenance personnel is difficult to guarantee, and the passage of vehicles in the tunnel will also be affected. Therefore, it is necessary to build a maintainable urban tunnel intelligent drainage system that can realize the on-demand switching of the urban tunnel drainage system and meet the maintainability requirements. Summary of the invention

[0005] The purpose of the present invention is to solve the shortcomings of the prior art and to provide a maintainable urban tunnel intelligent drainage system, which can switch between three drainage modes: full drainage, full waterproofing and half waterproofing according to the drainage needs of urban tunnels, and provide convenient and safe drainage maintenance for the later operation and maintenance personnel to ensure the healthy state of urban tunnels during the operation stage.

[0006] To achieve the above object, the present invention is implemented according to the following technical solutions:

[0007] A maintainable tunnel intelligent drainage system, comprising a longitudinal drainage blind pipe, an annular drainage blind pipe, a vertical inspection well, a side drainage pipe, a drainage side ditch, and a central drainage ditch; the longitudinal drainage blind pipes are a plurality of pipes and are arranged along the tunnel depth direction between the tunnel initial support structure and the secondary lining structure of the tunnel support structure; the annular drainage blind pipes are a plurality of pipes and are arranged along the tunnel vault between the tunnel initial support structure and the secondary lining structure of the tunnel support structure; the longitudinal drainage blind pipes are connected to the annular drainage blind pipes; the vertical inspection wells are arranged at intervals along the tunnel depth direction. At the bottom of the two arch feet of the tunnel support structure, the vertical inspection well includes a vertical shaft and an inspection door arranged on the vertical shaft; the side drainage pipes are arranged at the two arch feet of the tunnel support structure along the longitudinal direction of the tunnel, and the two ends of the annular drainage blind pipe are connected with the two side drainage pipes and distributed in the vertical inspection well; the central drainage ditch is arranged at the center of the bottom of the tunnel invert structure, and the two sides of the central drainage ditch are connected with the side drainage pipes through the central drainage ditch drainage blind pipe; the drainage side ditches are arranged on both sides of the road in the tunnel, and the drainage side ditches are connected with the side drainage pipes through the side ditch drainage blind pipes.

[0008] Furthermore, an electronic valve is installed at the connection position between the annular drainage blind pipe and the side drainage pipe, and the electronic valve is integrated with a water pressure sensor that can collect and record urban tunnel water pressure data in real time; the electronic valve is connected to a computer terminal via wired or wireless means, and the computer terminal is used to receive and analyze the urban tunnel water pressure load data transmitted by the electronic valve, and send instructions to the electronic valve to control the opening and closing of the electronic valve to achieve a balance between water pressure and drainage volume in the tunnel project.

[0009] Furthermore, a ladder is provided on the inner wall of the vertical shaft.

[0010] Preferably, the vertical inspection wells are arranged at the bottom of two arch feet of the tunnel support structure every 12 m along the longitudinal direction of the tunnel.

[0011] In addition, the present invention also provides an intelligent drainage method of a maintainable urban tunnel intelligent drainage system, comprising the following steps:

[0012] S1. After the construction of the urban tunnel is completed, the electronic valve is connected, the tunnel as a whole is in a fully waterproof state, groundwater cannot enter the tunnel, and the support structure bears the surrounding rock pressure and groundwater pressure load;

[0013] S2. As the tunnel is put into operation, the longitudinal drainage blind pipe, the annular drainage blind pipe, the central drainage ditch and the drainage side ditch begin to collect groundwater infiltrating the urban tunnel, and the water pressure sensor integrated in the electronic valve collects and records the urban tunnel water pressure data in real time, and transmits the data to the computer terminal;

[0014] S3. Based on S2, as the tunnel is in operation, the computer terminal receives the tunnel water pressure data transmitted by the water pressure sensor integrated in the electronic valve, and sends an opening instruction to the electronic valve according to the tunnel drainage requirements, so as to open the electronic valve and put the tunnel in a drainage state;

[0015] S4, based on S3, the tunnel groundwater collected by the annular drainage blind pipe and the longitudinal drainage blind pipe enters the side drainage pipe through the opened electronic valve, the central drainage ditch passes through the central drainage ditch drainage blind pipe, and the drainage side ditch passes through the side ditch drainage blind pipe to collect the groundwater and enter the side drainage pipe through the opened electronic valve;

[0016] S5. Based on S4, the side drainage pipe discharges the collected groundwater from the urban tunnel, and the water pressure sensor integrated in the electronic valve collects and records the urban tunnel water pressure data in the current full drainage state in real time, and transmits the data to the computer terminal;

[0017] S6. Based on S5, the computer terminal receives the tunnel water pressure data transmitted by the water pressure sensor integrated in the electronic valve, and the management personnel issues a closing instruction to the electronic valve through the computer terminal according to the actual needs of tunnel drainage, so as to close part or all of the electronic valves, thereby realizing the transition between the semi-enclosed drainage state and the fully-enclosed drainage state;

[0018] S7. When the electronic valve is damaged during tunnel operation, the electronic valve will feed back fault information to the computer terminal, and maintenance personnel can enter the vertical inspection well through the ladder to repair or manually open the electronic valve according to actual conditions.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] 1) Different from the traditional self-draining system, all-inclusive waterproofing system and controlled waterproofing system, this new intelligent tunnel drainage system can switch between three urban tunnel drainage modes according to the actual needs of tunnel drainage, and realize the electronic and information management of tunnel drainage.

[0021] 2) In addition to meeting the drainage needs of the tunnel structure during operation, this new maintainable tunnel drainage system also has a maintainable function. When the drainage function is obstructed, it is possible to enter the vertical inspection well for operation and maintenance without affecting the urban tunnel traffic. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the structure of the present invention. DETAILED DESCRIPTION

[0023] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments. The specific embodiments described herein are only used to explain the present invention and are not used to limit the invention.

[0024] like Figure 1The embodiment shown provides a maintainable tunnel intelligent drainage system, characterized in that it includes a longitudinal drainage blind pipe 2, an annular drainage blind pipe 3, a vertical inspection well 4, a side drainage pipe 402, a drainage side ditch 6, and a central drainage ditch 5; the longitudinal drainage blind pipes 2 are a plurality of and are arranged along the tunnel depth direction between the initial tunnel support structure and the secondary lining structure of the tunnel support structure 1, the annular drainage blind pipes 3 are a plurality of and are arranged along the tunnel vault between the initial tunnel support structure and the secondary lining structure of the tunnel support structure, the longitudinal drainage blind pipes 2 are a plurality of and are arranged along the tunnel vault between the initial tunnel support structure and the secondary lining structure of the tunnel support structure, The pipe 2 is connected with the annular drainage blind pipe 3; the vertical inspection well 4 is arranged at the bottom of the two arch feet of the tunnel support structure every 12m along the longitudinal direction of the tunnel. The vertical inspection well 4 includes a vertical shaft 405 and an inspection door 404 arranged on the vertical shaft 405. A ladder 403 is arranged on the inner wall of the vertical shaft 405. The size of the vertical inspection well 4 can be set according to geological conditions and design data to ensure that the side drainage pipe 402 is located at the lowest elevation of the urban tunnel. In order to facilitate the entry and exit of later operation and maintenance personnel, the vertical inspection well 4 is longitudinally The length can be set to more than 3m; the operation and maintenance personnel enter the vertical inspection well 4 through the inspection door 404 and enter the vertical shaft 405 through the ladder 403 to repair the equipment and perform related operations on the later waterproofing and drainage of urban tunnels; the side drainage pipe 402 is arranged at the two arch feet of the tunnel support structure along the depth direction of the tunnel, and is located at the lowest point of the entire urban tunnel; the two ends of the annular drainage blind pipe 3 are connected to the two side drainage pipes 402 and are distributed in the vertical inspection well 4, which is used to collect the annular drainage blind pipe 3. The central drainage ditch drainage blind pipe 501 and the side ditch drainage blind pipe 601 discharge groundwater, and discharge the groundwater out of the urban tunnel; the central drainage ditch 5 is arranged at the bottom center of the tunnel invert structure, and the two sides of the central drainage ditch 5 are connected with the side drainage pipe 402 through the central drainage ditch drainage blind pipe 501; the drainage side ditch 6 is arranged on both sides of the road in the tunnel, and the drainage side ditch 6 is connected with the side drainage pipe 402 through the side ditch drainage blind pipe 601; the above-mentioned pipelines are connected to form a complete drainage system to collect groundwater in the side drainage pipe 402.

[0025] An electronic valve 401 is installed at the connection portion between the annular drainage blind pipe 2 and the side drainage pipe 402. The electronic valve 401 is integrated with a water pressure sensor that can collect and record urban tunnel water pressure data in real time. Of course, a manual device is also provided on the electronic valve 401, so that maintenance personnel can manually control the opening and closing of the electronic valve 401 when there is a lack of power support or the electronic valve 401 cannot work normally; the electronic valve 401 is connected to a computer terminal (not shown in the figure) via a wired or wireless method. The computer terminal is used to receive and analyze the urban tunnel water pressure load data transmitted by the electronic valve 401, and send instructions to the electronic valve 401 to control the opening and closing of the electronic valve 401 to achieve a balance between the water pressure and the drainage volume of the tunnel project.

[0026] It should be noted that the tunnel support structure 1, the longitudinal drainage blind pipe 2, the annular drainage blind pipe 3, the central drainage ditch 5, the drainage side ditch 6, the central drainage ditch drainage blind pipe 501 and the side ditch drainage blind pipe 601 in the embodiment of the present invention are all basic components in the tunnel engineering. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0027] The above-mentioned maintainable urban tunnel intelligent drainage system can realize intelligent drainage, and the specific implementation process is as follows:

[0028] S1. After the construction of the urban tunnel is completed, the electronic valve 401 is connected, the tunnel as a whole is in a fully waterproof state, groundwater cannot enter the tunnel, and the support structure 1 bears the surrounding rock pressure and groundwater pressure load;

[0029] S2. As the tunnel is in operation, the longitudinal drainage blind pipe 1, the annular drainage blind pipe 2, the central drainage ditch 5 and the drainage side ditch 6 begin to collect groundwater infiltrating the urban tunnel, and the water pressure sensor integrated in the electronic valve 401 collects and records the urban tunnel water pressure data in real time, and transmits the data to the computer terminal;

[0030] S3, based on S2, as the tunnel is in operation, the computer terminal receives the tunnel water pressure data transmitted by the water pressure sensor integrated in the electronic valve 401, and sends an opening instruction to the electronic valve 401 according to the tunnel drainage requirements, so as to open the electronic valve 401 and put the tunnel in a drainage state;

[0031] S4, based on S3, the tunnel groundwater collected by the annular drainage blind pipe and the longitudinal drainage blind pipe 2 enters the side drainage pipe 402 through the opened electronic valve 401, the central drainage ditch 5 passes through the central drainage ditch drainage blind pipe 501, and the drainage side ditch 6 passes through the side ditch drainage blind pipe 601 to collect the groundwater into the side drainage pipe 402 through the opened electronic valve 401;

[0032] S5. Based on S4, the side drainage pipe discharges the collected groundwater out of the urban tunnel, and the water pressure sensor integrated in the electronic valve 401 collects and records the urban tunnel water pressure data in the current full drainage state in real time, and transmits the data to the computer terminal;

[0033] S6. Based on S5, the computer terminal receives the tunnel water pressure data transmitted by the water pressure sensor integrated in the electronic valve 401. The manager issues a closing instruction to the electronic valve 401 through the computer terminal according to the actual demand for tunnel drainage, and closes part or all of the electronic valve 401, thereby realizing the transition between the semi-enclosed drainage state and the fully-enclosed drainage state.

[0034] S7. When the electronic valve 401 is damaged during tunnel operation, the electronic valve system 401 will feed back fault information to the computer terminal, and maintenance personnel can enter the vertical inspection shaft 4 through the ladder 403 to repair or manually open the electronic valve 401 according to actual conditions.

[0035] Through the implementation of the above scheme, the present invention can complete the switching of three urban tunnel drainage modes according to the actual needs of tunnel drainage, and realize the electronic and information management of tunnel drainage; in addition to meeting the drainage needs during the operation of the tunnel structure, it also has a maintainable function. When the drainage function is obstructed, it is possible to enter the vertical inspection well for operation and maintenance without affecting the urban tunnel traffic.

[0036] The technical solution of the present invention is not limited to the above-mentioned specific embodiments. All technical variations made according to the technical solution of the present invention fall within the protection scope of the present invention.

Claims

1. An intelligent drainage method for a maintainable tunnel intelligent drainage system, wherein: The maintainable tunnel intelligent drainage system includes longitudinal drainage blind pipes, annular drainage blind pipes, vertical inspection wells, side drainage pipes, drainage side ditches, and central drainage ditches; the longitudinal drainage blind pipes are multiple and are arranged along the tunnel depth direction between the tunnel initial support structure and the secondary lining structure of the tunnel support structure; the annular drainage blind pipes are multiple and are arranged along the tunnel vault between the tunnel initial support structure and the secondary lining structure of the tunnel support structure; the longitudinal drainage blind pipes are connected to the annular drainage blind pipes; the vertical inspection wells are arranged at intervals along the tunnel depth direction between the tunnel support structure and the secondary lining structure; At the bottom of the two arch feet, the vertical inspection well includes a vertical shaft and an inspection door arranged on the vertical shaft; the side drainage pipes are arranged at the two arch feet of the tunnel support structure along the tunnel depth direction, and the two ends of the annular drainage blind pipe are connected with the two side drainage pipes and distributed in the vertical inspection well; the central drainage ditch is arranged at the center of the bottom of the tunnel inverted arch structure, and the two sides of the central drainage ditch are connected with the side drainage pipes through the central drainage ditch drainage blind pipe; the drainage side ditch is arranged on both sides of the road in the tunnel, and the drainage side ditch is connected with the side drainage pipe through the side ditch drainage blind pipe; it is characterized in that it includes the following steps: S1. After the construction of the urban tunnel is completed, the electronic valve is closed, and the tunnel is fully waterproof. Groundwater cannot enter the tunnel, and the tunnel support structure bears the surrounding rock pressure and groundwater pressure load; S2. As the tunnel is put into operation, the longitudinal drainage blind pipe, the annular drainage blind pipe, the central drainage ditch and the drainage side ditch begin to collect groundwater infiltrating the urban tunnel, and the water pressure sensor integrated in the electronic valve collects and records the water pressure data of the urban tunnel in real time, and transmits the data to the computer terminal; S3. Based on S2, as the tunnel is in operation, the computer terminal receives the tunnel water pressure data transmitted by the water pressure sensor integrated in the electronic valve, and sends an opening instruction to the electronic valve according to the tunnel drainage demand, so as to open the electronic valve and put the tunnel in a drainage state; S4, based on S3, the tunnel groundwater collected by the annular drainage blind pipe and the longitudinal drainage blind pipe enters the side drainage pipe through the opened electronic valve, the central drainage ditch passes through the central drainage ditch drainage blind pipe, and the drainage side ditch passes through the side ditch drainage blind pipe to collect the groundwater and enter the side drainage pipe through the opened electronic valve; S5. Based on S4, the side drainage pipe discharges the collected groundwater into the urban tunnel, and the water pressure sensor integrated in the electronic valve collects and records the urban tunnel water pressure data in the current full drainage state in real time, and transmits the data to the computer terminal; S6. Based on S5, the computer terminal receives the tunnel water pressure data transmitted by the water pressure sensor integrated in the electronic valve. The manager issues a closing command to the electronic valve through the computer terminal according to the actual needs of tunnel drainage, closes part or all of the electronic valves, and realizes the transition between the semi-enclosed drainage state and the fully-enclosed drainage state; S7. When the electronic valve is damaged during tunnel operation, the electronic valve will feed back the fault information to the computer terminal, and the maintenance personnel can enter the vertical inspection well by climbing a ladder to repair or manually open the electronic valve according to the actual situation.

2. The intelligent drainage method of the maintainable tunnel intelligent drainage system according to claim 1, characterized in that: An electronic valve is installed at the connection position between the annular drainage blind pipe and the side drainage pipe, and the electronic valve is integrated with a water pressure sensor that can collect and record urban tunnel water pressure data in real time; the electronic valve is connected to a computer terminal via a wired or wireless method, and the computer terminal is used to receive and analyze the urban tunnel water pressure load data transmitted by the electronic valve, and send instructions to the electronic valve to control the opening and closing of the electronic valve to achieve a balance between the water pressure and the drainage volume of the tunnel project.

3. The intelligent drainage method of the maintainable tunnel intelligent drainage system according to claim 1, characterized in that: A ladder is provided on the inner wall of the vertical shaft.

4. The intelligent drainage method of the maintainable tunnel intelligent drainage system according to claim 1, characterized in that: The vertical inspection wells are arranged at the bottom of the two arch feet of the tunnel support structure every 12m along the longitudinal direction of the tunnel.