Centralized control system and method for distributed load equipment using existing power grid
Through the centralized control system of distributed load equipment, the load of power grid lines is dynamically dispatched, which solves the problem of waste of power grid line resources and the cost of new equipment, achieves efficient utilization of grid capacity and preferential electricity prices for users, and improves grid security and utilization.
Patent Information
- Application Number
- CN202110958555.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-08-20
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2041-08-20
AI Technical Summary
Existing power grid lines have a large amount of idle capacity due to the concentration of power load during the day and low periods, resulting in a waste of resources. New high-power equipment requires dedicated line access and increases installation costs, making it difficult to effectively utilize the existing power grid capacity.
Adopting a distributed load equipment centralized control system, through a combination of distributed load equipment, user-side controllers, data management servers, centralized control servers and database servers, it collects and processes information about power grid lines and user equipment, and generates dispatch plans and real-time dispatch. instructions, dynamically adjust load input and withdrawal, and optimize power grid line capacity utilization.
It achieves efficient utilization of grid line capacity, reduces electricity costs, avoids investment in new dedicated lines and switching stations, improves grid security and utilization, allows users to enjoy preferential electricity prices, and has grid peak shaving capabilities.
Smart Images

Figure CN113608486B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of solid electric energy storage, and in particular to a distributed load equipment centralized control system and method utilizing an existing power grid. Background Art
[0002] In my country, in order to achieve the goal of carbon peak before 2030, the comprehensive use of wind and light electricity to replace coal and gas heat is an effective way to reduce carbon emissions. Since 2010, the applicant has installed solid electric heat storage equipment for nearly 600 users in provinces, municipalities and autonomous regions north of the Yangtze River with a total power of 3000MW, which is far from meeting the needs of heat users. The main bottleneck restricting the demand for heat storage of electricity by the majority of users lies in the difficulty of electricity prices and the site selection of grid access lines and the cost of laying lines, which often exceeds the affordability of users. Analysis of the actual situation on the electricity side found that the actual electricity load of each user under the grid line is still partially surplus compared to the applied capacity. This part of the surplus is accumulated, and the actual idle capacity of the line generated is very huge. At the same time, most of the electricity load is concentrated in daytime work, and a large amount of idle capacity will be released during the off-peak period, which will cause a great waste of the capacity resources of the grid line. In the past, if new high-power equipment such as power replacement and electric energy storage were added in the area where the line was laid, it was necessary to calculate whether there was enough capacity after the line capacity was applied for by each user. If it was fully occupied, even if there was still a surplus in the actual utilization rate of the line capacity, it would not be able to be used to ensure the safety of the line. Therefore, such new high-power equipment often requires additional application for dedicated line access, which increases a lot of installation costs and the cost of building new switch stations. Summary of the invention
[0003] In view of the deficiencies in the prior art, an object of the present invention is to provide a centralized control system for distributed load equipment utilizing the existing power grid.
[0004] The technical solution adopted by the invention is: a centralized control system for distributed load equipment using the existing power grid, the technical points of which are as follows:
[0005] Distributed load equipment is installed at the user end of each node of the existing power grid line to collect and store information on the geographical location of each user, the power grid line, the rated power of the equipment, the current remaining thermal storage capacity of the equipment, and the thermal load;
[0006] A user-side controller, whose input end is connected to the output end of the distributed load device, is used to receive the collected data of the distributed load device, set and store the device operation parameters and device protection parameters, execute the downloaded scheduling plan, and execute the real-time scheduling instructions;
[0007] The data management server, whose input end is connected to the output end of the user-side controller through the communication access layer, the tunnel network and the firewall, is used to decrypt and verify the data signal output by the user-side controller and encrypted and protected by the communication access layer, the tunnel network and the firewall, and establish a private communication connection with the user-side controller;
[0008] A centralized control server, whose input terminal is connected to the output terminal of the data management server, is used to determine the control authority;
[0009] The user application server, whose input end is connected to the output end of the data management server, is used to publish the operating status and control authority of the equipment to the outside world;
[0010] The database server, whose input end is connected to the output end of the data management server, is used to store all operating data and scheduling data.
[0011] A control method for centrally controlling electric energy using distributed load equipment of an existing power grid, the technical key points of which are suitable for execution in a centralized control server, specifically including:
[0012] Receive the 96-point load indicators of each user area and line and the remaining capacity information of each grid line issued by the grid dispatching automation system, and calculate the capacity gap and expected power consumption time required by the equipment based on the stored geographical location of each user, the grid line, the equipment rated power, the current equipment heat storage remaining capacity, and the heat load information;
[0013] Summarize all user information under the line, combine 96 load points, grid line remaining capacity information, and capacity gap required by each user to calculate and generate a dispatch plan for each user;
[0014] At the same time, the downloaded dispatch plan is dynamically adjusted and supplemented according to the real-time information of the power grid line capacity for real-time dispatching, so as to realize the accurate input and output of each user's load and match the safe capacity and idle capacity utilization requirements of the power grid line.
[0015] In the above scheme, the formulas for calculating the capacity gap and estimated power consumption time required by the equipment are:
[0016]
[0017] In the formula, Q s is the capacity gap, kw / H; t' is the current heat storage temperature; T is the rated heat storage temperature; Q is the rated capacity of the equipment;
[0018]
[0019] In the formula, S is the expected electricity consumption time; Q is the expected electricity consumption time; s Capacity gap; W is the rated power of the equipment.
[0020] The beneficial effects of the present invention are: a centralized control system for distributed load equipment that utilizes the existing power grid, solves the capacity waste of existing power grid lines, breaks down single high-power equipment into parts, and eliminates the need to invest in new dedicated lines and switch stations. For distributed load equipment, two modes, local control and centralized control, can be adopted. In the centralized control mode, the full automatic operation of the load equipment is achieved through downloading the dispatch plan and real-time dispatch instructions. At present, the time-of-use electricity price policy has gradually begun to face residential users. At the same time, the use of the technology of the present invention can enable each independent user to have the power grid peak-shaving capability. Therefore, the use of this control mode will be dispatched in real time according to the power grid situation, so that users can enjoy preferential electricity prices and reduce electricity costs. As the scale of distributed load equipment increases, the power grid will also save investment in new lines, improve utilization, and have peak-shaving capabilities under the premise of power grid safety. The main body of distributed load equipment installed on the existing transmission or distribution network can convert the heat energy from electric energy into hot water for heating, drinking, bathing and other domestic purposes, saturated or superheated steam, hot air and other heat sources to users; the main body of distributed load equipment installed in the existing wind farm or solar photovoltaic power field can convert the heat energy from electric energy into 10Mpa high-temperature steam, drive 0.5MW to 5MW small steam turbines to generate electricity, and its economy and stability are better than battery energy storage. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0022] Figure 1 It is a structural block diagram of a centralized control system for distributed load equipment using an existing power grid in an embodiment of the present invention. DETAILED DESCRIPTION
[0023] To make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the following is a brief description of the present invention in conjunction with the attached Figure 1 The present invention is further described in detail with reference to the accompanying drawings and specific embodiments.
[0024] This embodiment takes the current "peak, flat and valley" time periods and electricity price divisions in Liaoning Province as an example (there will be differences in various regions and with policy adjustments, for reference only):
[0025]
[0026] From the above data, it can be seen that compared with the "peak" period, the "valley" period has a more favorable electricity price, which constitutes a simple "dispatching plan download" information. From the actual situation, although the "peak, flat and valley" period division is a common method, this method can only roughly divide the line capacity situation, and because the time is fixed and cannot be adjusted dynamically, it cannot reflect the dynamic situation of the capacity of a certain power grid line. Therefore, it is not conducive to precise adjustment. Therefore, a more sophisticated "96-point load" or other types of dynamic indicator information are used to generate the user-side dispatch plan, and even through a dedicated network set up with the power grid dispatch to dynamically receive the capacity information of the power grid line, to complete a more accurate "real-time dispatch" function so that each user has the ability to participate in the peak regulation of the power grid and enjoy the preferential electricity price policy, that is, at the "peak" moment when the remaining capacity of the power grid line is small and the unit price of electricity is high, the dispatch plan and real-time dispatch function are used to make the user equipment exit (stop) operation, and at the "valley" or "peak regulation" moment when the remaining capacity of the power grid line is large and the unit price of electricity is low, the equipment is put into (started) operation.
[0027] Figure 1 As shown, the distributed load devices 1 to distributed load devices N dispersed at various nodes of the existing power grid line are constituted by the distributed load device 1 and the user-side controller 2. In this embodiment, the electric energy storage equipment and intermittent working equipment dispersed at various nodes of the existing power grid line are used as the distributed load devices.
[0028] The user-side controller 2 is an electronic control component used to set storage device operating parameters, device protection parameters, execute local control strategies, execute downloaded scheduling plans, and execute real-time scheduling instructions. The user-side controller 2 collects the operating data of the distributed load device 1. The operating data is encrypted and decrypted at the communication access layer 3 and then accessed to the tunnel network 4, and then enters the data management server 6 after passing through the firewall 5. The process of encrypting and decrypting the operating data in this embodiment is as follows:
[0029] The data encryption and decryption layer refers to the use of multi-layer encryption and decryption verification methods to two-way bind the user-side controller hardware information, handshake key and data management server information, and encrypt and transmit them to provide security for data communication. The specific implementation is: before the device-side controller leaves the factory, the hardware information such as the device ID, the unique identity ID and MAC address of the extraction processor are stored in the data management server and the user-side controller, and the data management server uses the national secret SM2 or RSA and other asymmetric encryption algorithms to generate a pair of universal keys according to actual needs, where the public key is saved to the user-side controller and the private key is saved to the data management server. Generate a random device identity code and a random data management server identity code. Write to the user-side controller and the data management server at the same time. During the initial communication, the user-side controller encrypts the "handshake instruction + time parameter + processor ID + MAC address and other hardware information + device identification code" with the public key and sends it to the data management server. After receiving the data, the data management server decrypts the data with the private key, extracts the "time parameter" in the message to determine the validity and real-time of the communication frame, extracts the "processor ID and MAC address and other hardware information" to determine whether it is an original device bound to the data management server, and verifies that the "device identification code" is compared with the saved information to determine the legitimacy of the device. After the verified legitimate original device successfully shakes hands with the data management server, a pair of private connection keys (using asymmetric encryption such as SM2 and RSA) is regenerated, and the "change public key instruction + time parameter + newly generated public key + data management server identification code" is sent to the user-side controller through the original encryption path. After receiving the data, the device-side controller extracts the "time parameter" to determine the validity and real-time of the communication frame, verifies that the "data management server identification code" is compared with the information saved in the memory, and determines the legitimacy of the data management server connection. After verifying that the connection to the data management server is legal, the encryption public key is replaced to encrypt and transmit the subsequent "control information", and the data management server uses the new private key to decrypt. At the same time, in order to ensure the legality and uniqueness of each communication frame, during the transmission process, the data management server adds "previous frame GUID + current frame GUID" to each communication frame, and the user-side controller verifies whether the "previous frame GUID" is consistent, and adds the received "current frame GUID" to the returned data for the data management server to verify and use. At the same time, during the communication process, the user-side controller and the data management server monitor the communication behavior and extract the characteristics of each frame of communication behavior, including handshake time, number of handshakes, number of legal frames, number of illegal frames, key exchange frequency, IP address range, network delay and other information. When abnormal communication occurs, alarm information such as network abnormality and device intrusion will be given respectively, and the device will stop running according to the alarm level and enter the standby state. The data management server will add the device to the blacklist.
[0030] After the data arrives at the data management server 6, the data management server 6 decrypts the data and verifies whether the data is legal and whether it is the original and legal device that has been bound. After the verification is successful, the data management server handshakes successfully and sends the private communication key and control information to the user-side controller 2. The user-side controller 2 verifies the validity and legality of the data sent by the data management server 6. After the verification is successful, a private communication connection is established. At the same time, the data management server 6 provides this private communication connection data to the centralized control server 7, the user application server 8 and the database 9 in the lower network for use. The centralized control server 7 determines the control right. If it is under local control authority, the centralized control server 7 will not schedule the distributed load equipment, but only perform basic functions such as network accurate time synchronization, data analysis, early warning, alarm, and database 9 data recording. All control operation logics are executed by the user-side controller 2 according to the upper and lower limits of the heat storage temperature set by the user, the local peak and valley heat storage time period, the heating time period and the supply and return water temperature, the atmospheric compensation correction value, the frequency of the circulating pump in each time period and other parameters; if it is under centralized control authority, the centralized control system will uniformly operate the distributed load equipment according to the scheduling plan download and real-time scheduling instructions, such as: Figure 1 The distributed load devices 1 and 2 shown in the figure belong to the same power grid line for power supply. This attribute information will be entered into the centralized control server 7. The time rules for the investment and withdrawal of these two distributed load devices are relatively strong. After entering December, the capacity of the power grid line is tight from 9:00 to 13:00 and it is strictly forbidden to invest in equipment. From 18:00 to 19:00, the capacity of the line is largely idle and equipment needs to be invested and preferential electricity prices need to be enjoyed. A new scheduling plan can be generated for these two distributed load devices to disable the time from 9:00 to 13:00 and give priority to the time from 18:00 to 19:00. Other idle capacity and preferential electricity price periods are allocated according to the results of big data analysis. Among them, distributed load device 1 requires more electricity usage time due to the increase in load demand, and preferential electricity prices with less abundant power grid line capacity can be allocated preferentially in the scheduling plan. During the peak-shaving period, at a certain moment, the centralized control system receives an instruction from the power grid dispatching to participate in the peak-shaving and the power grid lines where the two distributed load devices are located are within the peak-shaving range. The real-time dispatching instruction will be used to put the distributed load devices 1 and 2 into operation. After the peak-shaving is completed, they will operate according to their respective dispatching plans. Under special circumstances, the power grid line needs to release part of its capacity to ensure the safety of the line. The centralized control system will dispatch the distributed load devices 1 and 2 to exit operation in real time according to the released capacity requirements, so as to provide protection for the safety of the power grid lines. All operating data and dispatching data will be saved by the database 9 for data analysis and query. The operating status and control authority of the equipment will be published to the public through the user application server 8 in the form of app, web, etc., and provided to users.
[0031] The network precise timing involved in this embodiment refers to the use of a centralized control system to issue a timing instruction containing time parameters to a user-side controller. After receiving the timing instruction, the user-side controller starts an internal timer. The centralized control system issues a timing instruction containing time parameters again. The user-side controller extracts the current time parameters and corrects them with the time parameters in the first timing instruction and the internal timer value, calculates the delay, and thus achieves precise network timing.
[0032] The downloading of the dispatching plan described in this embodiment refers to calculating the capacity gap and expected power consumption time required by the equipment based on the dynamic indicator information such as "96-point load" of the power grid dispatching and the remaining capacity information of each power grid line, using the geographical location of each user, the power grid line, the rated power of the equipment, the current equipment thermal storage remaining capacity, the heat load information, etc. stored in the centralized control system. All user information under the line is summarized and decomposed into the dispatching plan for each user, and the dispatching plan information is issued to the user-side controller in advance, so that the controller performs work according to the predetermined plan.
[0033] The capacity gap calculation formula is:
[0034]
[0035] In the formula, Q s Capacity gap, unit: kw / H; t'current heat storage temperature; Trated heat storage temperature; Qrated capacity of equipment;
[0036] The formula for calculating the expected electricity consumption time is:
[0037]
[0038] Where S is the estimated electricity consumption time, unit: minutes; Q is the estimated electricity consumption time, unit: minutes; s Capacity gap; W equipment rated power;
[0039] The real-time dispatching instruction described in this embodiment is to adjust and supplement the downloaded dispatching plan according to the real-time information of the power grid line capacity, and issue the dispatching instruction to the user-side controller in real time so that the controller performs real-time work.
[0040] The big data analysis described in this embodiment refers to a comprehensive analysis of the user's location weather, air temperature, residual heat storage temperature in each time period, heating fan output frequency in each time period, heating water supply, heating return water, daily heat storage electricity consumption time, heat load parameters in the design stage and other information. First, according to the local climate conditions over the years, the temperature change process from "warm-cold-warm" is finely divided into multiple alternating time ranges, the "periodic heat storage temperature rise coefficient" is increased in "warm weather" and the "periodic heat storage temperature rise coefficient" is reduced in "cold weather", and the "heat storage temperature rise coefficient of the day" is adjusted according to the weather forecast. The "corrected heat storage temperature rise coefficient" is adjusted according to the residual heat storage temperature in each time period in the past historical data, the fan output frequency, the supply and return water data, and the daily heat storage electricity consumption time. Each value is multiplied by its own weight and then added. The lower the result, the longer the total heat storage time in the allocated scheduling plan and the higher the upper limit of the heat storage temperature. The "heating compliance rate for each period" is calculated based on the residual heat storage temperature, supply and return water temperature, fan frequency, and set water supply temperature in each period in the historical data. The more periods that fail to meet the standards, the lower the compliance rate, the denser the start intervals allocated in the scheduling plan download, and the smaller the upper and lower temperature difference of the heat storage temperature. Coordinate with the scheduling plan download and real-time scheduling instructions to ensure the optimal working state of distributed load equipment.
[0041] The ability to participate in the peak-shaving of the power grid described in this embodiment means that each independent user, through the large-scale distributed load equipment centralized control system constructed by the present invention, forms a safe, controlled, high-capacity, and power-adjustable entity through scheduling plan downloads and real-time scheduling instructions. The centralized control system receives the peak-shaving information of the power grid dispatch through a dedicated network, and generates scheduling plans and real-time scheduling instructions for each user according to the capacity of the peak-shaving information. The centralized control system is used as a unified peak-shaving settlement interface to solve the problem of low individual capacity and no settlement channels for individual users. Each user after integrated control has the ability to participate in the peak-shaving of the power grid.
[0042] The early warning prompt described in this embodiment refers to extracting the key feature points of the operation data of each user at each time point in the previous database and the key feature points of similar user data through the centralized control system, and comparing them with the key feature points at the current moment, so as to timely discover the hidden dangers of equipment operation and notify the user and the on-duty personnel of the centralized control system. The implementation method is divided into three early warning parts: heat storage, heat output, and water system. In the heat storage early warning, a dynamic heat storage temperature rise curve is generated according to the heat storage temperature record, current record, heating output load and other records, and compared with the current actual heat storage temperature rise curve and the temperature rise curve of similar users. If the heat storage deviation is too large, it proves that there is a hidden danger of failure in a certain link in the operation of the equipment, which should be investigated in detail. The heating output early warning and water system early warning use the supply and return water temperature difference record, air temperature record, heat storage temperature record and heating period compliance rate record to issue early warning prompts for gas trapped in the pipeline, water loss, and blocked circulating water.
[0043] The alarm prompt described in this embodiment refers to two independent and parallel detection systems in the user-side controller and the centralized control system, which are used to detect in real time whether the equipment operation data is within the protection parameter setting range. When a fault occurs, the user-side controller activates the sound and light alarm to issue a local alarm, and the centralized control system pops up an alarm information window on the platform and pushes app information to the user. It plays the role of redundant alarm.
[0044] The user-side controller protection strategy described in this embodiment refers to a general protection strategy that is solidified in the controller. The strategy detects the operating status of the equipment in real time according to the specific parameters input by the user, and executes relevant protection actions when a fault occurs. It mainly includes three types of protection: heat storage, heat supply, and circulating water. It operates independently and does not rely on the network or centralized control system.
[0045] The system of this embodiment can be mounted on a distributed load device and used together with the device, or can be mounted on an existing load device for technical transformation.
[0046] The system and method in this embodiment will greatly improve the safety and utilization rate of the power grid lines. At the same time, through the summary of the "dispatching plan download" information of each user, it can reflect the future increase in the capacity of the power grid lines, and provide a basis for the power grid dispatch to predict the load changes. In this way, under the existing power grid lines, the capacity safety of the lines is guaranteed, the utilization rate of the lines is fully improved, and the electricity cost is reduced. The shortcomings and limitations brought about by the independent construction of high-power equipment are solved. At the same time, the technical background of this system will be able to support more cooperative operation models. In addition to users independently installing equipment to enjoy the dividends of the low electricity price time window, for some users who have difficulty in making a one-time investment, the inventor can also invest in the installation of solid electric heat storage equipment, and users only need to bear the lower electricity use cost. The inventor gradually recovers the construction and installation costs through service fees, and thoroughly solves the various bottlenecks in the construction and installation of solid electric heat storage equipment through a variety of cooperative operation models.
[0047] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.
Claims
1. A centralized control system for distributed load equipment using an existing power grid, characterized in that: include, Distributed load equipment (1) is dispersedly installed at the user end of each node of the existing power grid line, and is used to collect and store information on the geographical location of each user, the power grid line where it is located, the rated power of the equipment, the current remaining heat storage capacity of the equipment, and the heat load; A user-side controller (2), whose input end is connected to the output end of the distributed load device (1), is used to receive collected data from the distributed load device (1), set and store device operating parameters and device protection parameters, execute a downloaded scheduling plan, and execute real-time scheduling instructions; A data management server (6), whose input end is communicatively connected to the output end of the user-side controller (2) via the communication access layer (3), the tunnel network (4) and the firewall (5), for decrypting and verifying the data signal output by the user-side controller (2) and encrypted and protected by the communication access layer (3), the tunnel network (4) and the firewall (5), and establishing a private communication connection with the user-side controller (2); The input end of the centralized control server (7) is connected to the output end of the data management server (6) for determining the control authority. When the centralized control server (7) determines the control authority and the centralized control server (7) is in the local control authority, the centralized control server (7) does not dispatch the distributed load equipment, but only performs the basic functions of network accurate time synchronization, data analysis, early warning, alarm, and database (9) data recording. All control operation logics are executed by the user-side controller (2) according to the upper and lower limits of the heat storage temperature set by the user, the local peak, flat and valley heat storage time period, the heating time period and the supply and return water temperature, the atmospheric compensation correction value, and the circulation pump frequency of each time period. When the centralized control authority is in the centralized control authority, the centralized control system uniformly operates the distributed load equipment in accordance with the dispatch plan download and the real-time dispatch instruction. A user application server (8), whose input end is connected to the output end of the data management server (6) and is used to publish the operating status and control authority of the device to the outside; A database server (9), whose input end is connected to the output end of the data management server (6) and is used to store all operating data and scheduling data; Suitable for execution in a centralized control server, specifically including: Receive the 96-point load indicators of each user area and line and the remaining capacity information of each grid line issued by the grid dispatching automation system, and calculate the capacity gap and expected power consumption time required by the equipment based on the stored geographical location of each user, the grid line, the equipment rated power, the current equipment heat storage remaining capacity, and the heat load information; Summarize all user information under the line, combine 96 load points, remaining capacity information of power grid lines, and capacity gap required by each user to calculate and generate a dispatch plan for each user; At the same time, the downloaded dispatch plan is dynamically adjusted and supplemented according to the real-time information of the power grid line capacity to carry out real-time dispatching, so as to achieve accurate input and output of each user's load and match the safe capacity and idle capacity utilization requirements of the power grid line; Big data analysis conducts a comprehensive analysis of the user's location weather, temperature, residual heat storage temperature in each time period, heating fan output frequency in each time period, heating water supply, heating return water, daily heat storage electricity consumption, and heat load parameter information in the design stage. First, according to the local climate conditions over the years, the temperature change process from "warm-cold-warm" is finely divided into multiple alternating time ranges, and the "warm weather" increases the "periodic heat storage temperature rise coefficient", and the "cold weather" reduces the "periodic heat storage temperature rise coefficient". Then, according to the weather forecast, the "day's heat storage temperature rise coefficient" is adjusted. According to the residual heat storage temperature in each time period in the previous historical data, The "corrected heat storage temperature rise coefficient" is adjusted based on the fan output frequency, water supply and return data, and daily heat storage electricity consumption. Each value is multiplied by its own weight and then added together. The lower the result, the longer the total heat storage time in the allocated scheduling plan and the higher the upper limit of the heat storage temperature. The "heating compliance rate in each period" is calculated based on the residual heat storage temperature, water supply and return temperature, fan frequency, and set water supply temperature in each period in the historical data. The more periods that do not meet the standards and the lower the compliance rate, the denser the start intervals allocated in the scheduling plan download and the smaller the upper and lower temperature difference of the heat storage temperature. Cooperate with the scheduling plan download and real-time scheduling instructions to ensure the optimal working state of distributed load equipment. The formulas for calculating the capacity gap and expected power consumption time required by the equipment are: ; In the formula, Q s is the capacity gap, kw / H; t' is the current heat storage temperature; T is the rated heat storage temperature; Q is the rated capacity of the equipment; ; In the formula, S is the expected electricity consumption time; Q is the expected electricity consumption time; s Capacity gap; W is the rated power of the equipment.