A rapid construction process for cable troughs in double-track railway tunnels
By designing a device that can simultaneously chisel the tunnel side wall and the trench base, the problem of long construction process in the existing technology is solved, the rapid construction of the ditch cable trough of the double-track railway tunnel is realized, and the construction efficiency is improved. And reduce the space occupied by the device.
Patent Information
- Application Number
- CN202111356470.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-11-16
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2041-11-16
AI Technical Summary
In the existing tunnel ditch cable trough construction process, the tunnel side walls and base need to be chiseled separately, resulting in a long construction process and inability to achieve rapid construction.
A deburring device is designed that can deburr the tunnel side wall and the trench base at the same time. It achieves synchronous operation by setting up pulleys, screws and driving mechanisms, and increases ground friction through reinforcement mechanisms to prevent device separation.
It realizes the rapid construction of ditch cable trough, shortens the construction time, improves the construction efficiency, and reduces the space occupied by the device through the storage tank, making it easy to store.
Smart Images

Figure HDA0003357742530000011 
Figure HDA0003357742530000021 
Figure HDA0003357742530000031
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel ditch cable trough construction, in particular to a rapid construction process for a railway double-track tunnel ditch cable trough. Background Art
[0002] The existing tunnels are generally provided with side ditches, power cable troughs, communication and signal cable troughs on both sides, and a central drainage ditch is provided in the middle of the tunnel. The side ditches are connected to the central ditch through transverse water pipes, and steel bars are arranged in the ditch wall near the line side to strengthen the strength of the ditch body. In order to strengthen the adhesion between the cable trough and the tunnel, it is usually necessary to roughen the side wall and the base of the tunnel. However, the existing method can only roughen the bottom or side wall of the tunnel separately. The roughening process is long, resulting in a long construction process. Therefore, a rapid construction process for the cable trough of the railway double-track tunnel is needed. Summary of the invention
[0003] The invention provides a rapid construction process for a water ditch cable trough in a railway double-track tunnel, which solves the problems existing in the prior art.
[0004] In order to achieve the above object, the present invention adopts the following technical solutions:
[0005] A rapid construction process for a ditch cable duct in a double-track railway tunnel comprises the following steps: S1: surveying and laying out, laying out a group of positioning points every 10m on one side, wherein one point is laid out on the second lining side wall as the elevation point of the top surface of the ditch cable duct; and another point is laid out on the invert filling surface as the horizontal position point of the outermost side wall of the ditch cable duct.
[0006] S2: roughening, using the roughening device to roughen the tunnel side wall and the groove base at the same time.
[0007] S3: After cleaning and flushing the base and roughening the joint surface, clean up the loose slag, debris and silt on the base of the ditch and cable trough, and wash it with high-pressure water to remove the accumulated water.
[0008] S4: Steel bar binding.
[0009] S5: Drain holes on the secondary lining side wall are led out and drainage pipes are pre-buried.
[0010] S6: Setting of grounding terminal and connection of reserved grounding steel bars in the secondary lining.
[0011] S7: Setting of rail-crossing steel pipe.
[0012] S8: Set up formwork and pour concrete.
[0013] S9: demoulding.
[0014] A rapid construction process for a cable trough in a double-track railway tunnel. The chiseling device comprises a shell with an opening and pulleys installed at the four corners of the bottom of the shell. A chiseling assembly is provided inside the opening, and a reinforcement mechanism is provided outside the shell.
[0015] First installation grooves are provided on both sides of the interior of the opening, and lead screws are rotatably sleeved inside the two first installation grooves, and sliders are threadedly sleeved on the outer rings of the two lead screws.
[0016] The haircutting assembly includes a first mounting plate fixed between two sliders, and the first mounting plate is vertically slidably sleeved inside the opening, a first rotating shaft is rotatably sleeved on one side of the top of the first mounting plate, a second mounting plate is fixedly connected to the outer ring of the first rotating shaft, and a haircutting machine is installed on the side away from the first mounting plate and the second mounting plate.
[0017] A first driving mechanism is provided at the end of the first rotating shaft to drive the first rotating shaft to rotate.
[0018] Preferably, the reinforcement mechanism includes storage grooves opened on both sides of the outside of the shell, a second rotating shaft rotatably connected to the storage grooves, a U-shaped rod fixed to the outer ring of the second rotating shaft, a plurality of annular reinforcement plates rotatably connected to the outer ring of the U-shaped rod, and a second driving mechanism is provided on the outside of the second rotating shaft to drive the second rotating shaft to rotate.
[0019] Preferably, the first driving mechanism comprises a first gear fixed to the end of the first rotating shaft, a first rack is meshedly connected to the outer side of the first gear, and the first rack is fixedly connected to the housing.
[0020] Preferably, the second driving mechanism comprises a second gear fixed to the outer ring of the second rotating shaft, and a third gear meshingly connected to the second gear, the outer side of the third gear meshingly connected to a second rack, and the second rack is fixedly connected to the slider.
[0021] Preferably, a support rod is rotatably sleeved on the outer side of the second mounting plate, and a fastening bolt is movably sleeved on one end of the support rod away from the second mounting plate.
[0022] Preferably, a side plate is fixed to the outer side of the shell, and threaded holes for fitting with fastening bolts are provided inside the second mounting plate and inside the side plate.
[0023] Preferably, a driving motor is installed at the top end of the lead screw.
[0024] The present invention provides two groups of chiseling machines to chisel the tunnel bottom and side walls simultaneously, thereby accelerating the construction efficiency of the ditch cable trough. At the same time, the reinforcement mechanism is provided to reduce the friction between the device and the ground during the chiseling process, thereby preventing the chiseling machine on the second mounting plate from being separated from the side wall during the chiseling process. The reinforcement plate and the U-shaped rod can be retracted into the storage groove when not in use, and the second mounting plate and the chiseling machine thereon can be retracted into the opening when not in use, thereby reducing the space occupied by the device and facilitating storage. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the overall structure of the present invention in a non-working state;
[0026] Figure 2 It is a schematic diagram of the overall structure of the present invention in working state;
[0027] Figure 3 It is a schematic diagram of the installation structure of the second driving mechanism of the present invention;
[0028] Figure 4 It is an enlarged schematic diagram of the structure at A of the present invention;
[0029] Figure 5 It is a schematic diagram of the installation structure of the first driving mechanism of the present invention;
[0030] Figure 6 It is an enlarged schematic diagram of the structure at B of the present invention.
[0031] In the figure: 1. housing; 2. pulley; 3. chiseling assembly; 31. first mounting plate; 32. first rotating shaft; 33. second mounting plate; 34. chiseling machine; 4. reinforcement mechanism; 41. storage slot; 42. second rotating shaft; 43. U-shaped rod; 44. reinforcement plate; 5. first mounting slot; 6. first gear; 7. first rack; 8. second gear; 9. second rack; 10. support rod; 11. lead screw; 12. slider; 13. third gear. DETAILED DESCRIPTION
[0032] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0033] A rapid construction process for a ditch cable duct in a double-track railway tunnel comprises the following steps: S1: surveying and laying out, laying out a group of positioning points every 10m on one side, wherein one point is laid out on the second lining side wall as the elevation point of the top surface of the ditch cable duct; and another point is laid out on the invert filling surface as the horizontal position point of the outermost side wall of the ditch cable duct.
[0034] S2: roughening, using the roughening device to roughen the tunnel side wall and the groove base at the same time.
[0035] S3: After cleaning and flushing the base and roughening the joint surface, clean up the loose slag, debris and silt on the base of the ditch and cable trough, and wash it with high-pressure water to remove the accumulated water.
[0036] S4: Steel bar binding.
[0037] S5: Drain holes on the secondary lining side wall are led out and drainage pipes are pre-buried.
[0038] S6: Setting of grounding terminal and connection of reserved grounding steel bars in the secondary lining.
[0039] S7: Setting of rail-crossing steel pipe.
[0040] S8: Set up formwork and pour concrete.
[0041] S9: demoulding.
[0042] Reference Figure 1-6 A rapid construction process for a cable trough in a double-track railway tunnel. The roughening device includes a shell 1 with an opening and pulleys 2 installed at the four corners of the bottom of the shell 1. The invention is characterized in that a roughening assembly 3 is provided inside the opening and a reinforcement mechanism 4 is provided outside the shell 1.
[0043] First installation grooves 5 are provided on both sides of the opening, and lead screws 11 are rotatably sleeved inside the two first installation grooves 5 , and sliders 12 are threadedly sleeved on the outer rings of the two lead screws 11 .
[0044] The chiseling assembly 3 includes a first mounting plate 31 fixed between two sliders 12, and the first mounting plate 31 is vertically slidably sleeved inside the opening, a first rotating shaft 32 is rotatably sleeved on one side of the top of the first mounting plate 31, and a second mounting plate 33 is fixedly connected to the outer ring of the first rotating shaft 32, and a chiseling machine 34 is installed on the side away from the first mounting plate 31 and the second mounting plate 33, and the device is moved to the position where chiseling is required by the pulley 2, and the driving motor drives the screw 11 to rotate. When the screw 11 rotates, the slider 12 drives the first mounting plate 31 to move downward, so that the chiseling machine 34 located at the bottom of the first mounting plate 31 contacts the ground and chisels the ground.
[0045] A first driving mechanism is disposed at the end of the first rotating shaft 32 to drive the first rotating shaft 32 to rotate.
[0046] Furthermore, the reinforcement mechanism 4 includes a storage groove 41 opened on both sides of the outside of the shell 1, a second rotating shaft 42 rotatably sleeved with the storage groove 41, a U-shaped rod 43 is fixed to the outer ring of the second rotating shaft 42, and a plurality of annular reinforcement plates 44 are rotatably sleeved on the outer ring of the U-shaped rod 43. A second driving mechanism is provided on the outside of the second rotating shaft 42 to drive the second rotating shaft 42 to rotate. The U-shaped rod 43 drives the reinforcement plate 44 to rotate so that it can fit with the ground. Without affecting the movement of the device, the lateral friction between the device and the ground is increased to prevent the haircutting machine 34 on the second mounting plate 33 from separating from the side wall during the haircutting process.
[0047] Furthermore, the first driving mechanism includes a first gear 6 fixed to the end of the first rotating shaft 32, the first gear 6 is meshedly connected with a first rack 7 on the outer side, and the first rack 7 is fixedly connected to the outer shell 1, and when the slider 12 drives the first mounting plate 31 to move downward, the first gear 6 is meshedly connected with the first rack 7, and when the first gear 6 moves downward, it drives the first rotating shaft 32 to rotate, and the first rotating shaft 32 drives the second mounting plate 33 to rotate, and finally the second mounting plate 33 contacts the side wall of the tunnel, and the side wall of the tunnel is roughened.
[0048] Furthermore, the second driving mechanism includes a second gear 8 fixed to the outer ring of the second rotating shaft 42, and a third gear 13 meshingly connected to the second gear 8. The third gear 13 is rotatably sleeved with the inner wall of the storage groove 41. The outer side of the third gear 13 is meshingly connected with the second rack 9, and the second rack 9 is fixedly connected to the slider 12. The slider 12 drives the first mounting plate 31 to move downward and also drives the second rack 7 to move downward. When the second rack 7 moves downward, the second gear 8 is driven to rotate through the third gear 13.
[0049] Furthermore, a support rod 10 is rotatably sleeved on the outer side of the second mounting plate 33 , and a fastening bolt is movably sleeved on one end of the support rod 10 away from the second mounting plate 33 .
[0050] Furthermore, a side panel is fixed to the outer side of the shell 1, and threaded holes for fastening bolts are provided inside the second mounting plate 33 and the inside of the side panel. After the second mounting plate 33 is unfolded, the second mounting plate 33 is supported by screwing and sleeved with the threaded holes inside the side panel, so that the second mounting plate 33 can be installed more firmly when the chiseling machine 34 on the second mounting plate 33 is working.
[0051] Furthermore, a driving motor is installed at the top of the lead screw 11, and the driving motor drives the lead screw 11 to rotate.
[0052] Working principle: when in use, the device is moved to the position where roughening is required through the pulley 2, and the driving motor drives the lead screw 11 to rotate. When the lead screw 11 rotates, the slider 12 drives the first mounting plate 31 to move downward, so that the roughening machine 34 located at the bottom of the first mounting plate 31 contacts the ground. In the process of the slider 12 driving the first mounting plate 31 to move downward, the first gear 6 is meshed and connected with the first rack 7. In the process of the first gear 6 moving downward, the first rotating shaft 32 is driven to rotate, and the first rotating shaft 32 drives the second mounting plate 33 to rotate, and finally the second mounting plate 33 contacts the side wall of the tunnel. The slider 12 drives the first mounting plate 31 to move downward and also drives the second rack 7 to move downward. When the second rack 7 moves downward, the third gear 13 is used to drive the second rack 7 to move downward. The second gear 8 is driven to rotate, thereby driving the U-shaped rod 43 to rotate. When the roughening machine 34 at the bottom of the first mounting plate 31 contacts the ground, the bottom of the reinforcement plate 44 fits with the ground. During the movement of the device, the two groups of roughening machines 34 are used to roughen the bottom and side walls of the tunnel at the same time, thereby accelerating the construction efficiency. At the same time, the reinforcement mechanism 4 is set to make the friction between the device and the ground during the roughening process to prevent the roughening machine 34 on the second mounting plate 33 from separating from the side wall during the roughening process. The reinforcement plate 44 and the U-shaped rod 43 can be retracted into the storage groove 41 when not in use. The second mounting plate 33 and the roughening machine 34 thereon can be retracted into the opening when not in use, thereby reducing the space occupied by the device and facilitating storage.
[0053] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0054] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0055] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A rapid construction process for a cable trough in a double-track railway tunnel, characterized in that: The steps include: S1. Survey and lay out. Set out a group of positioning points every 10m on one side. One point is set out on the second lining side wall, which is the elevation point of the top surface of the ditch cable trough; the other point is set out on the invert filling surface, which is the horizontal position point of the outermost side wall of the ditch cable trough; S2, roughening, using a roughening device to roughen the tunnel sidewall and the groove base at the same time; S3. Clean and rinse the base, roughen the joint surface, clean the loose slag, debris and silt on the base of the ditch and cable trough, and wash it with high-pressure water to remove the accumulated water; S4, steel bar binding; S5. Drain holes on the secondary lining side wall and pre-buried drainage pipes; S6. Setting of grounding terminal and connection of reserved grounding steel bars in the secondary lining; S7, installation of rail-crossing steel pipes; S8, support formwork and pour concrete; S9, demoulding; The construction process adopts a chiseling device, which comprises a shell (1) provided with an opening, pulleys (2) installed at the four corners of the bottom of the shell (1), a chiseling assembly (3) is provided inside the opening, and a reinforcement mechanism (4) is provided on the outside of the shell (1); First installation grooves (5) are provided on both sides of the opening, and screws (11) are rotatably sleeved inside the two first installation grooves (5), and sliders (12) are threadedly sleeved on the outer rings of the two screws (11); The chiseling assembly (3) comprises a first mounting plate (31) fixed between two sliders (12), and the first mounting plate (31) is slidably sleeved inside the opening in the vertical direction, a first rotating shaft (32) is rotatably sleeved on one side of the top of the first mounting plate (31), a second mounting plate (33) is fixedly connected to the outer ring of the first rotating shaft (32), and a chiseling machine (34) is installed on the side away from the first mounting plate (31) and the second mounting plate (33); A first driving mechanism is provided at the end of the first rotating shaft (32) to drive the first rotating shaft (32) to rotate; The reinforcement mechanism (4) comprises a receiving groove (41) provided on both sides of the outer shell (1), a second rotating shaft (42) rotatably sleeved with the receiving groove (41), a U-shaped rod (43) fixed to the outer ring of the second rotating shaft (42), and a plurality of annular reinforcement plates (44) rotatably sleeved on the outer ring of the U-shaped rod (43); A second driving mechanism is provided outside the second rotating shaft (42) to drive the second rotating shaft (42) to rotate.
2. A rapid construction process for a double-track railway tunnel ditch cable trough according to claim 1, characterized in that: The first driving mechanism comprises a first gear (6) fixed to the end of the first rotating shaft (32); a first rack (7) is meshedly connected to the outer side of the first gear (6); and the first rack (7) is fixedly connected to the housing (1).
3. The rapid construction process for a double-track railway tunnel ditch cable trough according to claim 1 is characterized in that: The second driving mechanism comprises a second gear (8) fixed to the outer ring of the second rotating shaft (42), and a third gear (13) meshingly connected to the second gear (8); the outer side of the third gear (13) is meshingly connected to a second rack (9), and the second rack (9) is fixedly connected to the slider (12).
4. The rapid construction process for a double-track railway tunnel ditch cable trough according to claim 1 is characterized in that: A support rod (10) is rotatably sleeved on the outer side of the second mounting plate (33), and a fastening bolt is movably sleeved on one end of the support rod (10) away from the second mounting plate (33).
5. The rapid construction process for a double-track railway tunnel ditch cable trough according to claim 1 is characterized in that: A side plate is fixed to the outer side of the housing (1), and threads for matching with fastening bolts are provided inside the second mounting plate (33) and inside the side plate.
6. According to the rapid construction process for a double-track railway tunnel ditch cable trough as described in claim 1, a driving motor is installed at the top end of the lead screw (11).