Method, device and storage medium for pushing construction plan based on geological early warning

By obtaining construction logs and conducting advanced geological testing, and finding and pushing the optimal construction plan in the database according to geological conditions, the problems of uneven quality of existing construction plans and slow formulation efficiency are solved, and the rapid matching and pushing of construction plans are achieved, and the quality, efficiency and safety of construction are improved.

CN114066053BActive Publication Date: 2025-04-18JIJIANTONG (SANYA) INT TECH CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202111350265.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-15
Publication Date
2025-04-18
Estimated Expiration
2041-11-15

AI Technical Summary

Technical Problem

The quality of the existing construction plans is uneven, the formulation efficiency is slow, and it is impossible to quickly match the construction plans formulated according to geological conditions, which poses construction safety hazards and inefficiency problems.

Method used

By obtaining the construction log of the construction project, determining the next construction area and conducting advance geological testing, finding a matching construction technical plan in the construction plan database based on the geological inspection results and construction type, and sending it to the construction terminal for construction personnel to use.

Benefits of technology

It realizes the rapid matching and pushing of the optimal construction plan according to geological conditions, improves the quality and efficiency of the construction plan, reduces errors and safety hazards during the construction process, and ensures the rapid, efficient and safe construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114066053B_ABST
    Figure CN114066053B_ABST
Patent Text Reader

Abstract

The present invention discloses a method, device and storage medium for pushing a construction plan based on geological early warning. On the one hand, the present invention can perform advanced geological detection on the construction area, and can use the geological detection results and the construction type as keywords to optimally match the construction plan in the construction plan database, thereby ensuring the quality of the construction plan and improving the efficiency of formulating the construction plan. At the same time, it also avoids erroneous construction during the construction process, and can complete the project construction at the fastest speed and with the greatest benefit; on the other hand, when carrying out each process construction, the process construction plan can be optimally matched, thereby ensuring that the optimal construction technology plan is pushed to the site, making the plan more in line with the actual construction situation on site, more practical and convenient, and directly hitting the construction pain points; in addition, construction risk early warning prompt information can also be sent to the construction personnel, thereby realizing timely early warning prompts of construction risks, thereby avoiding accident losses and ensuring construction safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of construction plan push, and specifically relates to a method, device and storage medium for pushing a construction plan based on geological early warning. Background Art

[0002] In recent years, my country's infrastructure construction has entered a period of rapid development. Countless roads, bridges and tunnels have been built, and China has become a major infrastructure country. In the process of constructing basic projects such as tunnels, bridges and roads, due to the complexity and changeability of geological bodies, adverse geological conditions such as faults, caves, broken zones, underground rivers and high ground stress are often encountered. If the geological conditions ahead cannot be grasped in time, during the construction process, it is very likely to cause geological disasters such as landslides, water gushing, rock bursts and even mudslides. Therefore, the formulation of engineering construction plans has become a top priority.

[0003] At present, most of the construction plans are prepared by technicians with different experiences. The reference is generally the templates left by predecessors, the experience passed down orally and the search for similar plans on the Internet. Then they are modified and improved on this basis, and finally submitted to the approval department for review. The above-mentioned construction plan formulation method has the following shortcomings: due to the different abilities of technical personnel, the quality of the formulated construction plans is uneven, which not only affects the construction progress of the project, but also has certain construction safety hazards. At the same time, the efficiency is low, and it is impossible to quickly match the construction plan according to the geological conditions. Therefore, it is urgent to provide a method for quickly pushing construction plans based on geological conditions. Summary of the invention

[0004] The purpose of the present invention is to provide a method, device and storage medium for pushing a construction plan based on geological early warning, so as to solve the problems of uneven quality and low formulation efficiency of existing construction plans.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] The present invention provides a method for pushing a construction plan based on geological early warning, comprising:

[0007] Obtain construction logs for construction projects;

[0008] According to the construction log, the next construction area of ​​the construction project and the construction type corresponding to the next construction area are obtained;

[0009] Sending the next construction area to a construction terminal so that construction personnel can conduct advance geological detection on the next construction area to obtain geological detection results of the next construction area;

[0010] Obtaining geological detection results of the next construction area;

[0011] Using the geological detection result and the construction type as the first screening index, searching for a construction technical scheme matching the first screening index in a construction scheme database as the first construction scheme;

[0012] The first construction plan is sent to a construction terminal so that construction personnel can perform construction work on the next construction area according to the first construction plan.

[0013] Based on the above disclosed content, the present invention constructs a database storing a variety of construction plans, and then, during the construction process, the next construction area can be obtained according to the construction log, and the next construction area can be subjected to advanced geological detection, so as to obtain the geological detection results of the next construction area (for example, the tunnel is subjected to advanced geological prediction, and the surrounding rock grade in a certain section of the tunnel is obtained, whether there is geological conditions such as water gushing), then, the construction type of the next construction area and the geological detection results are used as keywords, and keyword search and matching are performed in the construction plan database, so as to obtain a construction plan matching the aforementioned keywords, and finally, the construction personnel can carry out construction work in the construction area according to the construction plan; through the above design, the present invention can quickly obtain the optimal construction plan for different construction areas according to the geological conditions and construction types of the construction area, thereby not only ensuring the quality of the construction plan, but also improving the efficiency of the formulation of the construction plan, and at the same time, it can also avoid detours in the construction process, so as to complete the project construction at the fastest speed and with the greatest benefit.

[0014] In a possible design, after obtaining the geological detection results of the next construction area, the method further includes:

[0015] According to the geological detection results, determine whether there is a construction risk in the next construction area;

[0016] If yes, then generate construction risk warning information for the next construction area;

[0017] The construction risk warning prompt information is sent to the construction terminal to provide risk warning to the construction personnel.

[0018] Based on the above disclosed content, after obtaining the geological detection results of the next construction area, the present invention will determine whether there is a construction risk based on the detection results. If so, a construction risk early warning prompt information can be sent to the construction personnel; thereby, the problem of cumbersome steps for manual information transmission can be avoided, the efficiency of information transmission is improved, and timely early warning prompts of construction risks are achieved, thereby avoiding accident losses and ensuring construction safety.

[0019] In a possible design, after obtaining the geological detection results of the next construction area, the method further includes:

[0020] Generating geological update information of the next construction area according to the geological detection results;

[0021] The geological update information is used to replace the original geological information of the next construction area in the geological information database to complete the update of the geological information of the next construction area.

[0022] Based on the above disclosed content, the present invention can realize the real-time update of the geological information of the construction area, thereby ensuring the timeliness of the geological information of the construction area.

[0023] In a possible design, after sending the first construction plan to the construction terminal, the method further includes:

[0024] Obtaining the current construction process of the next construction area and geological emergency information during the construction process;

[0025] Taking the construction type of the next construction area, the current construction process and the geological emergency information as the second screening index, searching the construction technical scheme matching the second screening index in the construction scheme database as the emergency construction scheme;

[0026] The emergency construction plan is sent to the construction terminal so that construction personnel can perform emergency construction work on the next construction area according to the emergency construction plan.

[0027] Based on the above disclosed content, the present invention can obtain in real time the geological emergency information during the construction process and the current construction process (such as sudden geological emergencies such as water gushing during tunnel construction spraying). Therefore, according to the acquired geological emergency situation and the current process, the process and the emergency construction plan under the geological emergency situation can be quickly matched, so that emergency construction can be carried out when a geological emergency occurs; through the above design, the emergency response speed during the construction process is improved, and the safety of the construction is further improved.

[0028] In a possible design, after obtaining the construction log of the construction project, the method further includes:

[0029] According to the construction log, obtain the construction type, geological information and next construction process of the construction area corresponding to the construction log;

[0030] Taking the construction type, geological information and next construction process of the construction area corresponding to the construction log as the third screening index, searching the construction technical scheme matching the third screening index from the construction scheme database as the second construction scheme;

[0031] The second construction plan is sent to the construction terminal, so that the construction personnel can perform construction work on the construction area corresponding to the construction log according to the second construction plan.

[0032] Based on the above disclosed content, the present invention can derive the current construction area and the next construction process according to the construction log, and use the above information as keywords to match the construction plan of the next construction process. Therefore, when carrying out each construction process, it can ensure that the optimal construction technology plan is pushed to the site, making the plan more in line with the actual construction situation on site, more practical and convenient, and directly addressing the construction pain points, thereby shortening the construction period and improving the construction quality.

[0033] In a possible design, before obtaining the construction log of the construction project, the method further includes:

[0034] Acquire the construction type, geological information and engineering restriction information of the construction project, wherein the engineering restriction information includes personnel ratio information, construction period information and material consumption quota information;

[0035] Taking the construction type, geological information and engineering restriction information of the construction project as fourth screening indicators, screening out a construction technical solution matching the fourth screening indicator in the construction solution database as a comprehensive construction solution for the construction project;

[0036] The comprehensive construction plan is sent to the construction terminal so that construction personnel can perform construction work on the construction project according to the comprehensive construction plan.

[0037] Based on the above disclosed content, the present invention can use the construction type (such as tunnel excavation), geological information (such as surrounding rock grade) and engineering restriction information of the construction project as keywords to quickly match the optimal construction plan for the construction project, thereby ensuring that the construction plan is more in line with the actual construction conditions on site, more practical and convenient, and directly hits the construction pain points.

[0038] In a second aspect, the present invention provides a pushing device for a construction plan based on geological early warning, comprising:

[0039] An acquisition unit, used for acquiring a construction log of a construction project;

[0040] A construction area determination unit, configured to obtain, according to the construction log, a next construction area of ​​the construction project and a construction type corresponding to the next construction area;

[0041] A sending unit, used for sending the next construction area to a construction terminal, so that construction personnel can conduct advance geological detection on the next construction area to obtain geological detection results of the next construction area;

[0042] The acquisition unit is further used to acquire the geological detection result of the next construction area;

[0043] A search unit, configured to use the geological detection result and the construction type as a first screening index, and search a construction technical scheme matching the first screening index in a construction scheme database as a first construction scheme;

[0044] The sending unit is further used to send the first construction plan to the construction terminal, so that the construction personnel can perform construction work on the next construction area according to the first construction plan.

[0045] In one possible design, the device further includes:

[0046] A judgment unit, used for judging whether there is a construction risk in the next construction area according to the geological detection result;

[0047] An early warning unit, configured to generate a construction risk early warning prompt for the next construction area when the judgment unit determines that the construction risk is yes;

[0048] The sending unit is further used to send the construction risk warning prompt to the construction terminal to provide risk warning to the construction personnel.

[0049] In the third aspect, the present invention provides another device for pushing construction plans based on geological early warning. Taking the device as a computer main device as an example, it includes a memory, a processor and a transceiver that are communicatively connected in sequence, wherein the memory is used to store computer programs, the transceiver is used to send and receive messages, and the processor is used to read the computer program to execute the method for pushing the construction plan based on geological early warning as in the first aspect or any possible design in the first aspect.

[0050] In a fourth aspect, the present invention provides a storage medium having instructions stored thereon, which, when executed on a computer, executes a method for pushing a construction plan based on geological early warning as in the first aspect or any possible design in the first aspect.

[0051] In a fifth aspect, the present invention provides a computer program product comprising instructions, which, when executed on a computer, enables the computer to execute a method for pushing a construction plan based on geological early warning as described in the first aspect or any possible design in the first aspect. BRIEF DESCRIPTION OF THE DRAWINGS

[0052] Figure 1 A schematic diagram of the system architecture of a push system for a construction plan based on geological early warning provided by the present invention;

[0053] Figure 2A schematic diagram of the steps of the method for pushing a construction plan based on geological early warning provided by the present invention;

[0054] Figure 3 A flowchart of the push process of the construction solution provided by the present invention;

[0055] Figure 4 A schematic diagram of the structure of a pushing device for a construction scheme based on geological early warning provided by the present invention;

[0056] Figure 5 This is a structural schematic diagram of a computer main device provided by the present invention. DETAILED DESCRIPTION

[0057] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments. It should be noted that although the description of these embodiments is used to help understand the present invention, it does not constitute a limitation of the present invention. The specific structures and functional details disclosed herein are only used to describe the exemplary embodiments of the present invention. However, the present invention can be embodied in many alternative forms, and it should not be understood that the present invention is limited to the embodiments set forth herein.

[0058] It should be understood that although the terms first, second, etc. may be used herein to describe various units, these units should not be limited by these terms. These terms are only used to distinguish one unit from another unit. For example, a first unit can be referred to as a second unit, and similarly, a second unit can be referred to as a first unit without departing from the scope of the exemplary embodiments of the present invention.

[0059] It should be understood that the term "and / or" that may appear in this article is merely a description of the association relationship between associated objects, indicating that three relationships may exist. For example, A and / or B can represent three situations: A exists alone, B exists alone, and A and B exist at the same time. The term " / and" that may appear in this article describes another type of association object relationship, indicating that two relationships may exist. For example, A / and B can represent two situations: A exists alone, and A and B exist alone. In addition, the character " / " that may appear in this article generally indicates that the previous and next associated objects are in an "or" relationship.

[0060] Example

[0061] like Figure 1As shown, a system architecture is provided for the present application when it is applied, that is, it is applied in the process of infrastructure construction. The system may include but is not limited to: a construction terminal (which may be but is not limited to a mobile phone, a computer and / or a tablet), a server and a management terminal (which may be but is not limited to a mobile phone, a computer and / or a tablet), wherein the construction terminal is configured to each on-site construction personnel and / or department, for example, a team and / or a project department, etc., and the management terminal may be but is not limited to being configured to personnel and / or departments such as senior management of the construction party and senior management of Party A who are not at the construction site. At the same time, a construction plan database is stored in the server, so that when the geological detection results, construction type, construction type and other information uploaded by the construction terminal and / or the management terminal are received, the push method provided in this embodiment is used to optimally match the construction plan to obtain the optimal construction plan, thereby ensuring the quality of the construction plan and improving the efficiency of formulating the construction plan. At the same time, it can also avoid erroneous construction during the construction process, thereby achieving the purpose of completing the project construction at the fastest speed and with the greatest benefit.

[0062] The method for pushing construction plans based on geological early warning provided in the first aspect of this embodiment, on the one hand, can conduct advanced geological detection of the construction area to be constructed, and can use the geological detection results and construction types as keywords to optimally match the construction plans in the construction plan database, thereby ensuring the quality of the construction plan and improving the efficiency of formulating the construction plan. At the same time, it also avoids erroneous construction during the construction process, and can complete the project construction at the fastest speed and with the greatest efficiency; on the other hand, when carrying out each process construction, the optimal matching of the process construction plan can be carried out, thereby ensuring that the optimal construction technology plan is pushed to the site, making the plan more in line with the actual construction situation on site, more practical and convenient, directly hitting the construction pain points, and achieving the purpose of shortening the construction period and improving the construction quality; in addition, according to the results of advanced geological detection, construction risk warning prompt information can be sent to the construction personnel, thereby achieving timely warning prompts of construction risks, thereby avoiding accident losses and ensuring construction safety.

[0063] See also Figure 2 and Figure 3 As shown, the method for pushing construction plans based on geological early warning provided in the first aspect of this embodiment can be applied to, but not limited to, tunnel construction, highway construction, bridge construction, building construction and / or municipal construction, and can include, but not limited to, the following steps S1 to S6; of course, the aforementioned steps S1 to S6 can be executed on the server side, but not limited to.

[0064] S1. Obtain a construction log of a construction project.

[0065] S2. According to the construction log, obtain the next construction area of ​​the construction project and the construction type corresponding to the next construction area.

[0066] In this embodiment, the construction personnel use the construction terminal to upload the construction log, and the example construction log may include but is not limited to: the current construction area, construction plan, construction time, geological information of the construction area, construction progress, construction type, next construction area and the construction type of the next construction area, etc. Therefore, after receiving the construction log, the server can derive the next construction area and the corresponding construction type according to the log; of course, the example server also stores the engineering information corresponding to the entire construction project, such as construction length, divided construction areas, construction party information, etc., so as to query the construction engineering information.

[0067] After the next construction area is obtained, the next construction area can be sent to the construction terminal. After receiving the information, the construction personnel corresponding to the construction terminal can conduct advanced geological detection on the next construction area to obtain the geological information corresponding to the area, providing a data basis for the matching of subsequent construction plans, as shown in the following steps S3 and S4.

[0068] S3. Sending the next construction area to the construction terminal so that construction personnel can conduct advance geological detection on the next construction area to obtain geological detection results of the next construction area.

[0069] S4. Obtaining geological detection results of the next construction area.

[0070] In this embodiment, an example is taken in which the construction personnel conduct geological detection of the next construction area offline, and after obtaining the detection results, upload them to the server through the construction terminal; for example, assuming that the next construction area obtained according to the construction log is: ZH100+13-ZH100+14 section of Tunnel No. 1, then the construction type corresponding to this area is tunnel construction, and the construction personnel use drilling and modern geophysical exploration and other technical means to conduct geological detection of ZH100+13-ZH100+14 section of Tunnel No. 1, and grasp the geological conditions such as rock and soil structure, properties, state, groundwater, gas and ground stress in this area. Therefore, the location, occurrence and integrity of the surrounding rock structure and the possibility of water content of the unfavorable geological body in front of the face can be grasped through the aforementioned geological conditions, thereby providing accurate matching data information for the matching of subsequent construction plans.

[0071] After obtaining the geological detection results and construction type of the next construction area, the optimal construction plan can be matched, as shown in the following step S5.

[0072] S5. Using the geological detection results and the construction type as the first screening index, searching the construction technology scheme matching the first screening index in the construction scheme database as the first construction scheme.

[0073] The principle of step S5 is: using the geological detection results and the construction type as the first screening index, that is, keywords, to match the keywords in the construction plan database, and taking the plan with the highest matching degree as the final output plan, that is, the first construction plan.

[0074] In this embodiment, when performing keyword matching, the specific matching method is: in the matched construction plans, for each keyword that is successfully matched, the matching degree of the construction plan is increased by 1. Finally, the matched construction plans are sorted according to their total matching scores, and the one with the highest total matching score is used as the output result, that is, the first construction plan.

[0075] See also Figure 3 As shown, for example, based on the above example, it is assumed that the geological detection result of the ZH100+13-ZH100+14 section of Tunnel No. 1 is: Grade V surrounding rock, there is water gushing, then the first screening index is: tunnel construction, Grade V surrounding rock and water gushing, that is, according to the above three keywords, search and match are performed in the construction plan database, and the search results include Construction Plan A (the successfully matched keywords are tunnel construction, Grade V surrounding rock and water gushing, and the total matching score is 3 points), Construction Plan B (the successfully matched keywords are tunnel construction and water gushing, and the total matching score is 2 points), and Construction Plan C (the successfully matched keywords are tunnel construction, and the total matching score is 1 point); therefore, according to the above-mentioned rules, Construction Plan A is used as the output result, that is, as the first construction plan.

[0076] In addition, an expert system is also provided in the server of this embodiment so that when multiple construction plans with the same scores are matched, the best one can be selected from the multiple construction plans for output to obtain the best construction plan; in this embodiment, the expert system is an online evaluation system composed of multiple construction experts, and real-time evaluation is performed by experts.

[0077] In this embodiment, the construction plan database is constructed in advance and pre-stored in the server. It can include but is not limited to: different geological conditions in the construction process of various infrastructure (such as bridges, municipal engineering, tunnels, railways and highways, etc.), normal construction of different construction types and construction plans under various emergencies. Its sources can be but are not limited to various journals, documents, papers and construction organization designs, etc., including complete sets of plans and plans divided by process. For example, the tunnel excavation construction process can be divided into: excavation, slag discharge, frame erection and grouting. Therefore, the database contains the overall technical plan for tunnel excavation construction, and the overall construction plan covers the specific construction steps of the above four processes. At the same time, the specific steps of the above four processes are also stored separately as construction plans. Therefore, by constructing a detailed classified construction plan database, the accuracy of plan matching can be guaranteed, and the quality and formulation efficiency of the construction plan can be improved, so that the plan is more in line with the actual construction situation on site, more practical and convenient, and directly hits the pain points of construction.

[0078] After the optimal construction plan for the next construction area is obtained, the matching construction plan can be transmitted to the construction terminal so that construction work can be carried out according to the construction plan, as shown in the following step S6.

[0079] S6. Sending the first construction plan to a construction terminal so that construction personnel can perform construction work on the next construction area according to the first construction plan.

[0080] In this embodiment, after the optimal construction plan for the next construction area is obtained, it can also be sent to the management terminal for retention; thus, through the above design, the present invention can push the optimal construction technology plan for different construction areas according to their corresponding geological conditions, thereby avoiding detours in the construction process, and completing the project construction in the fastest speed, with the greatest benefit, the highest quality and the safest way.

[0081] At the same time, in this embodiment, risk warning and geological update can also be performed on the next construction area, so as to realize the rapid upload of geological detection results, as shown in the following steps S41 to S43 and S44 to S45.

[0082] That is, after obtaining the geological detection results of the next construction area, the server can issue a risk warning, as shown in the following steps:

[0083] S41. Based on the geological detection results, determine whether there is a construction risk in the next construction area.

[0084] S42. If yes, generate a construction risk warning for the next construction area.

[0085] S43. Send the construction risk warning prompt to the construction terminal to provide risk warning to the construction personnel.

[0086] In step S41, judging whether there is a construction risk is to judge whether there are sensitive words in the geological detection results. For example, as long as there are sensitive words, it can be determined that there is a risk. Sensitive words represent geological emergencies that are prone to occur during the construction process. For example, for tunnels, water gushing and mud bursts are both sensitive words. For roads, mountain fragmentation and large longitudinal slope drop are also sensitive words (which can lead to mudslides). Of course, sensitive words are also preset in the server.

[0087] For example, taking a tunnel as an example, assuming that the geological detection result is Grade V surrounding rock, and there is water gushing and mud bursting, then it is judged that there is a construction risk in the construction area; for another example, for highway construction, the geological detection result obtained in the construction area near the mountain is: the mountain is broken and the longitudinal slope is large, then there are sensitive words, and mudslides may occur during the construction process. Therefore, it can be determined that there is a construction risk in the area; of course, the risk judgment of other areas is based on the corresponding sensitive words. The principle is the same as mentioned above and will not be elaborated here.

[0088] In this embodiment, the construction risk warning prompt can be, but is not limited to, a text message, and is sent in the following format: "construction area" + "possible geological hazards" + "warnings and suggestions"; of course, the content of the aforementioned warning prompt is also pre-stored in the server and can be called when used.

[0089] Therefore, through the aforementioned steps S41 to S43, timely risk warning reminders can be given to construction personnel, which not only avoids the cumbersome steps of manual information transmission and improves the efficiency of information transmission, but also avoids accident losses and ensures construction safety.

[0090] Similarly, the updating process of the geological information of the next construction area is as shown in the following steps S44 and S45.

[0091] S44. Generate geological update information of the next construction area based on the geological detection results.

[0092] S45. Use the geological update information to replace the original geological information of the next construction area in the geological information database to complete the update of the geological information of the next construction area.

[0093] See also Figure 3As shown, taking the aforementioned Tunnel No. 1 as an example: the geological detection result of the ZH100+13-ZH100+14 section of Tunnel No. 1 is: Grade V surrounding rock, water gushing exists, then the updating process is: matching the tunnel pile number, that is, finding the ZH100+13-ZH100+14 pile number in the geological information database, and then replacing the geological information corresponding to the pile number, that is, if the original geological information is: Grade IV surrounding rock, water gushing exists, then after replacement it will be: Grade V surrounding rock, water gushing exists.

[0094] Therefore, through the above-mentioned design, the advanced geological detection results can be directly reported to the server, thereby realizing real-time updating of the geological information of the construction area to ensure the timeliness of the geological information of the construction area.

[0095] In addition, in this embodiment, when a geological emergency occurs during the construction process, a corresponding solution can be pushed in time to improve construction safety, as shown in the following steps S20 to S22.

[0096] S20. Obtain the current construction process of the next construction area and geological emergency information during the construction process.

[0097] S21. Using the construction type of the next construction area, the current construction process and the geological emergency information as the second screening index, search the construction plan database for a construction technical plan that matches the second screening index as an emergency construction plan.

[0098] S22. Send the emergency construction plan to the construction terminal, so that the construction personnel can perform emergency construction work on the next construction area according to the emergency construction plan.

[0099] The principle of the above-mentioned steps S20 to S22 is: during the construction process, if a geological emergency occurs, at this time, the construction personnel can use the construction terminal to send the current construction process and the geological emergency information that has occurred to the server, and the server can use the current construction process and the geological emergency information as the second screening index, that is, as keywords for search and matching, and match the construction technical plan corresponding to the above-mentioned information, and return it to the construction terminal as an emergency construction plan, so as to facilitate the construction personnel to carry out emergency processing. Therefore, when a geological emergency occurs, the present invention can timely and accurately match and push the corresponding solution, avoid accident losses, and ensure construction safety.

[0100] Similarly, the server is also equipped with an emergency response plan database. Therefore, when a geological emergency occurs during the construction process, the geological emergency information and the corresponding construction type can be used as keywords to search for solutions in the emergency response plan database and match the emergency plans corresponding to the aforementioned keywords. This can improve the emergency response capability and speed, thereby avoiding accidents and improving the safety of construction.

[0101] The method for pushing the construction plan described in detail in the aforementioned steps S1 to S6 has the following advantages: (1) The results of the advanced geological detection can be directly reported to the server, reducing the tedious steps of manually transmitting information, and the construction personnel, owners, project managers and other management personnel can directly receive early warning prompts, which is convenient for timely follow-up and timely processing, thereby improving the safety of construction; (2) For construction areas with various geological conditions, the server can push the optimal construction technology plan to the construction personnel, avoiding the problem of taking detours in the construction process, and completing the project construction at the fastest speed and with the greatest efficiency; (3) During the construction process, for various emergencies, the corresponding solutions can be matched and pushed in a timely and accurate manner, avoiding accident losses and further improving the safety of construction.

[0102] The second aspect of this embodiment is further optimized on the basis of the first aspect of the embodiment to push the overall construction plan of the construction project and match the optimal plan for the next construction process according to the construction log, as shown in the following steps S30~S32 and S40~S42.

[0103] First, the process of pushing the overall construction plan of the construction project is described, as shown in the following steps S30 to S32.

[0104] S30. Obtain the construction type, geological information and engineering restriction information of the construction project, wherein the engineering restriction information includes personnel ratio information, construction period information and material consumption quota information.

[0105] S31. Using the construction type, geological information and engineering restriction information of the construction project as the fourth screening index, a construction technical scheme matching the fourth screening index is screened out from the construction scheme database as a comprehensive construction scheme for the construction project.

[0106] S32. Send the comprehensive construction plan to the construction terminal so that construction personnel can perform construction work on the construction project according to the comprehensive construction plan.

[0107] The principle of the above steps S30 to S32 is: using construction type, geological information and engineering restriction information as keywords, matching them in the construction plan database, so as to find the construction plan corresponding to the above keywords. The principle is consistent with the above step S5 and will not be elaborated here.

[0108] The following is an example for explanation. It is assumed that the construction type is tunnel excavation construction, the geological information is Grade V surrounding rock, and the engineering restriction information is: personnel ratio information (80 construction personnel, 10 project team members, and 10 material team members), the construction period information is: 1 year, and the material consumption quota is: soft stone 6.88 yuan / meter, hard stone 7.03 yuan / meter, and soil 8.33 yuan / cubic meter; therefore, the server can use the above information as keywords for retrieval, so as to obtain the optimal construction technology plan that meets the above information; at the same time, tunnel excavation construction includes four processes: excavation, slag discharge, frame erection, and grouting. Therefore, the output construction technology plan also includes the detailed construction plans of the above four processes, that is, the detailed construction plans of the above four processes constitute the comprehensive construction plan of the construction project.

[0109] Of course, this embodiment can also perform scheme matching for a certain step. The matching principle is the same as that shown in step S31 and will not be elaborated here. At the same time, each process is marked separately in the form of a subheading. For example, when searching for excavation, the content between the subheadings "excavation" and "slag discharge" can be extracted during matching as the search result.

[0110] In addition, this embodiment can also obtain the next construction process according to the construction log and push the optimal solution, as shown in the following steps S40 to S42.

[0111] S40. According to the construction log, obtain the construction type, geological information and next construction process of the construction area corresponding to the construction log.

[0112] S41. Using the construction type, geological information and next construction process of the construction area corresponding to the construction log as the third screening index, searching the construction technical scheme matching the third screening index from the construction scheme database as the second construction scheme.

[0113] S42. Send the second construction plan to the construction terminal, so that the construction personnel can perform construction work on the construction area corresponding to the construction log according to the second construction plan.

[0114] The following is an example to illustrate the aforementioned steps S40 to S42:

[0115] Assume that the current construction area is ZH100+12-ZH100+13 of Tunnel No. 1, the geological information is: Grade V surrounding rock, the construction type is tunnel construction, and the current construction process is: erection process. Therefore, according to the tunnel construction process, it can be known that the next construction process is shotcrete. Therefore, Grade V surrounding rock, tunnel construction and shotcrete can be used as keywords to match the plans in the construction plan database, so as to obtain the optimal construction plan for the shotcrete process, that is, the second construction plan. In this embodiment, the retrieval principle of step S41 is consistent with the principle of the aforementioned step S5, and no further details will be given here.

[0116] Therefore, through the method of pushing the construction plan described in detail in the aforementioned steps S30~S32 and S40~S42, the present invention can perform the optimal matching of the process construction plan when performing each process construction, thereby ensuring that the optimal construction technology plan is pushed to the site, making the plan more in line with the actual construction conditions on site, more practical and convenient, directly addressing the construction pain points, and achieving the purpose of shortening the construction period and improving the construction quality.

[0117] like Figure 4 As shown, the third aspect of this embodiment provides a hardware device for implementing the method for pushing the construction plan based on geological early warning described in the first aspect or the second aspect of the embodiment, including:

[0118] The acquisition unit is used to acquire the construction log of the construction project.

[0119] The construction area determination unit is used to obtain the next construction area of ​​the construction project and the construction type corresponding to the next construction area according to the construction log.

[0120] The sending unit is used to send the next construction area to the construction terminal so that the construction personnel can conduct advanced geological detection on the next construction area to obtain the geological detection result of the next construction area.

[0121] The acquisition unit is further used to acquire the geological detection result of the next construction area.

[0122] The search unit is used to use the geological detection result and the construction type as the first screening index, and search for a construction technical scheme matching the first screening index in the construction scheme database as the first construction scheme.

[0123] The sending unit is further used to send the first construction plan to the construction terminal, so that the construction personnel can perform construction work on the next construction area according to the first construction plan.

[0124] In one possible design, the device further includes:

[0125] The judgment unit is used to judge whether there is a construction risk in the next construction area according to the geological detection result.

[0126] The early warning unit is used to generate a construction risk early warning prompt for the next construction area when the judgment unit judges that the construction risk is yes.

[0127] The sending unit is further used to send the construction risk warning prompt to the construction terminal to provide risk warning to the construction personnel.

[0128] The working process, working details and technical effects of the hardware device provided in this embodiment can be found in the first aspect or the second aspect of the embodiment, and will not be described in detail here.

[0129] like Figure 5 As shown, the fourth aspect of this embodiment provides another device for pushing construction plans based on geological early warning. Taking the device as a computer main device as an example, it includes: a memory, a processor and a transceiver that are communicatively connected in sequence, wherein the memory is used to store computer programs, the transceiver is used to send and receive messages, and the processor is used to read the computer program to execute the method for pushing construction plans based on geological early warning as described in the first aspect or the second aspect of the embodiment.

[0130] For example, the memory may include, but is not limited to, random access memory (RAM), read-only memory (ROM), flash memory, first-in first-out memory (FIFO) and / or first-in last-out memory (FILO), etc.; the processor may include, but is not limited to, a microprocessor of the STM32F105 series, a reduced instruction set computer (RSIC) microprocessor, an X86 architecture processor, or a processor with an integrated embedded neural network processing unit (NPU); the transceiver may include, but is not limited to, a wireless fidelity (WIFI) wireless transceiver, a Bluetooth wireless transceiver, a general packet radio service technology (GPRS) wireless transceiver, a ZigBee protocol (a low-power local area network protocol based on the IEEE802.15.4 standard, ZigBee) wireless transceiver, a 3G transceiver, a 4G transceiver and / or a 5G transceiver, etc. In addition, the device may also include, but is not limited to, a power module, a display screen, and other necessary components.

[0131] The working process, working details and technical effects of the computer main device provided in this embodiment can be found in the first aspect or the second aspect of the embodiment, and will not be repeated here.

[0132] The fifth aspect of this embodiment provides a storage medium storing instructions for the method for pushing a construction plan based on geological early warning as described in the first aspect or the second aspect of the embodiment, that is, the storage medium stores instructions, and when the instructions are run on a computer, the method for pushing a construction plan based on geological early warning as described in the first aspect or the second aspect is executed.

[0133] The storage medium refers to a carrier for storing data, which may include but is not limited to a floppy disk, a CD, a hard disk, a flash memory, a USB flash drive and / or a memory stick, and the computer may be a general-purpose computer, a special-purpose computer, a computer network, or other programmable devices.

[0134] The working process, working details and technical effects of the storage medium provided in this embodiment can be found in the first aspect or the second aspect of the embodiment, and will not be described in detail here.

[0135] The sixth aspect of this embodiment provides a computer program product comprising instructions, which, when executed on a computer, enables the computer to execute the method for pushing a construction plan based on geological early warning as described in the first aspect or the second aspect of the embodiment, wherein the computer may be a general-purpose computer, a special-purpose computer, a computer network, or other programmable devices.

[0136] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the protection scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for pushing a construction plan based on geological early warning, characterized in that: include: Obtain construction logs for construction projects; According to the construction log, the next construction area of ​​the construction project and the construction type corresponding to the next construction area are obtained; Sending the next construction area to a construction terminal so that construction personnel can conduct advance geological detection on the next construction area to obtain geological detection results of the next construction area; Obtaining geological detection results of the next construction area; Using the geological detection result and the construction type as the first screening index, searching for a construction technical scheme matching the first screening index in a construction scheme database as the first construction scheme; Sending the first construction plan to a construction terminal so that construction personnel can perform construction work on the next construction area according to the first construction plan; After obtaining the construction log of the construction project, the method further includes: According to the construction log, obtain the construction type, geological information and next construction process of the construction area corresponding to the construction log; Taking the construction type, geological information and next construction process of the construction area corresponding to the construction log as the third screening index, searching the construction technical scheme matching the third screening index from the construction scheme database as the second construction scheme; Sending the second construction plan to the construction terminal so that the construction personnel can perform construction work on the construction area corresponding to the construction log according to the second construction plan; Before obtaining the construction log of the construction project, the method further includes: Acquire the construction type, geological information and engineering restriction information of the construction project, wherein the engineering restriction information includes personnel ratio information, construction period information and material consumption quota information; Taking the construction type, geological information and engineering restriction information of the construction project as fourth screening indicators, screening out a construction technical solution matching the fourth screening indicator in the construction solution database as a comprehensive construction solution for the construction project; The comprehensive construction plan is sent to the construction terminal so that construction personnel can perform construction work on the construction project according to the comprehensive construction plan.

2. The method according to claim 1, characterized in that After obtaining the geological detection results of the next construction area, the method further includes: According to the geological detection results, determine whether there is a construction risk in the next construction area; If yes, then generate a construction risk warning prompt for the next construction area; The construction risk warning prompt is sent to the construction terminal to provide risk warning to the construction personnel.

3. The method according to claim 1, characterized in that After obtaining the geological detection results of the next construction area, the method further includes: Generating geological update information of the next construction area according to the geological detection results; The geological update information is used to replace the original geological information of the next construction area in the geological information database to complete the update of the geological information of the next construction area.

4. The method according to claim 1, characterized in that After sending the first construction plan to the construction terminal, the method further includes: Obtaining the current construction process of the next construction area and geological emergency information during the construction process; Taking the construction type of the next construction area, the current construction process and the geological emergency information as the second screening index, searching the construction technical scheme matching the second screening index in the construction scheme database as the emergency construction scheme; The emergency construction plan is sent to the construction terminal so that construction personnel can perform emergency construction work on the next construction area according to the emergency construction plan.

5. A pushing device for a construction plan based on geological early warning, characterized in that: include: An acquisition unit, used for acquiring a construction log of a construction project; A construction area determination unit, configured to obtain, according to the construction log, a next construction area of ​​the construction project and a construction type corresponding to the next construction area; A sending unit, used for sending the next construction area to a construction terminal, so that construction personnel can conduct advance geological detection on the next construction area to obtain geological detection results of the next construction area; The acquisition unit is further used to acquire the geological detection result of the next construction area; A search unit, configured to use the geological detection result and the construction type as a first screening index, and search a construction technical scheme matching the first screening index in a construction scheme database as a first construction scheme; The sending unit is further used to send the first construction plan to the construction terminal, so that the construction personnel can perform construction work on the next construction area according to the first construction plan; After obtaining the construction log for the construction project, also include: According to the construction log, obtain the construction type, geological information and next construction process of the construction area corresponding to the construction log; Taking the construction type, geological information and next construction process of the construction area corresponding to the construction log as the third screening index, searching the construction technical scheme matching the third screening index from the construction scheme database as the second construction scheme; Sending the second construction plan to the construction terminal so that the construction personnel can perform construction work on the construction area corresponding to the construction log according to the second construction plan; Before obtaining the construction log for the construction project, also include: Acquire the construction type, geological information and engineering restriction information of the construction project, wherein the engineering restriction information includes personnel ratio information, construction period information and material consumption quota information; Taking the construction type, geological information and engineering restriction information of the construction project as fourth screening indicators, screening out a construction technical solution matching the fourth screening indicator in the construction solution database as a comprehensive construction solution for the construction project; The comprehensive construction plan is sent to the construction terminal so that construction personnel can perform construction work on the construction project according to the comprehensive construction plan.

6. The device according to claim 5, characterized in that The device also includes: A judgment unit, used for judging whether there is a construction risk in the next construction area according to the geological detection result; An early warning unit, configured to generate a construction risk early warning prompt for the next construction area when the judgment unit determines that the construction risk is yes; The sending unit is further used to send the construction risk warning prompt to the construction terminal to provide risk warning to the construction personnel.

7. A pushing device for a construction plan based on geological early warning, characterized in that: It includes a memory, a processor and a transceiver which are communicatively connected in sequence, wherein the memory is used to store computer programs, the transceiver is used to send and receive messages, and the processor is used to read the computer program to execute the method for pushing a construction plan based on geological early warning as described in any one of claims 1 to 4.

8. A storage medium, characterized in that: The storage medium stores instructions, and when the instructions are executed on a computer, the method for pushing a construction plan based on geological early warning as described in any one of claims 1 to 4 is executed.