Groundwater seepage prediction method for multi-ring structure shafts
By obtaining and analyzing the hydrogeological conditions and permeability coefficients of multi-ring structure shafts, and combining the characteristics of the lining and grouting circles to calculate the water inflow and lining external water pressure, the accuracy of the seepage prediction for multi-ring structure shafts in the existing technology is solved. problem, enabling more precise shaft design.
Patent Information
- Application Number
- CN202111254877.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-10-27
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2041-10-27
AI Technical Summary
It is difficult to effectively predict groundwater seepage in shafts with circular linings and grouting rings using existing technology. Especially when multi-ring structural shafts pass through aquifers with different thicknesses and permeability coefficients, the amount of water inflow and the external water pressure of the lining cannot be predicted. precise.
By obtaining the hydrogeological conditions and the permeability coefficient of each aquifer, determine the permeability coefficient of the lining structure and grouting circle, analyze the seepage influence radius of groundwater, and use specific formulas to iteratively calculate the water inflow and lining external water pressure to provide more accurate seepage predict.
It improves the accuracy of seepage prediction in multi-ring structure shafts, ensures the rationality and economy of lining structure design, avoids the problem of excessive external water pressure or insufficient grouting ring thickness, and provides accurate calculations of water inflow and lining external water pressure. result.
Smart Images

Figure CN114118522B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of vertical shaft groundwater disaster prevention and control, and in particular to a groundwater seepage prediction method suitable for multi-circular ring structure vertical shafts. Background Art
[0002] When a vertical shaft passes through an underground aquifer, it faces the problem of groundwater seepage into the well. If it is a bare well, the Joubi formula can be used to predict the water inflow of the shaft. However, in actual situations, some large wells need to be lined to ensure the stability of the well wall and use the lining structure to bear the external water pressure load. When the water inflow of the shaft is too large, a grouting ring must be set up, that is, grouting is used to reduce the permeability of the aquifer around the shaft to reduce the water inflow; in addition, when the vertical shaft passes through multiple aquifers, the different hydrogeological conditions of each aquifer also bring difficulties to the prediction of seepage.
[0003] At present, regarding vertical shaft seepage, the existing technologies generally target open wells, and there is no effective seepage prediction method for vertical shafts with annular linings and grouting rings. Summary of the invention
[0004] The purpose of the present invention is to provide a groundwater seepage prediction method suitable for a multi-circular-ring structure vertical shaft. Considering that the multi-circular-ring structure vertical shaft passes through aquifers with different thicknesses and permeability coefficients, the method can more accurately predict the water inflow corresponding to each aquifer in the multi-circular-ring structure vertical shaft, the total water inflow, and the external water pressure of the lining structure at different depths of the multi-circular-ring structure vertical shaft.
[0005] To achieve the above object, the present invention has developed a groundwater seepage prediction method suitable for a multi-ring structure shaft, which is characterized by comprising the following steps:
[0006] Step 1), obtaining the hydrogeological conditions of the multi-ring structure shaft and the permeability coefficient of each aquifer outside the multi-ring structure shaft;
[0007] Step 2), respectively determining the permeability coefficient of the lining structure and the permeability coefficient of the grouting ring outside the multi-ring structure shaft;
[0008] Step 3), analyzing the seepage influence radius of groundwater in each aquifer outside the multi-ring structure shaft;
[0009] Step 4), predicting the water inflow of each aquifer in the multi-ring structure shaft, the total water inflow, and the external water pressure of the lining structure at different depths of the multi-ring structure shaft.
[0010] Preferably, in step 1), the hydrogeological conditions include the initial groundwater level, the allowable water level in the well, the well bottom depth, the serial number of each aquifer outside the vertical shaft, and the thickness of each aquifer outside the vertical shaft, wherein the initial groundwater level and the thickness of each aquifer outside the vertical shaft are obtained through drilling exploration; the permeability coefficient of each aquifer is measured by on-site pumping or water pressure test.
[0011] Preferably, the relationship among the initial groundwater level, the allowable well water level and the well bottom depth is well bottom depth ≥ allowable well water level ≥ initial groundwater level.
[0012] Preferably, in step 2), the process of determining the permeability coefficient of the lining structure is: preparing a lining structure of reinforced concrete material, and obtaining the permeability coefficient of the lining structure by measuring through an indoor permeability test;
[0013] The process of determining the permeability coefficient of the grouting ring is as follows: drilling holes into each aquifer outside the multi-ring structure shaft and injecting slurry, sweeping the holes after the slurry solidifies, and measuring the permeability coefficient of the grouting ring through an on-site water pressure test.
[0014] Preferably, in step 3), the seepage influence radius is iteratively calculated by the following formula (1):
[0015]
[0016] in,
[0017] R i is the seepage influence radius of groundwater in aquifer i,
[0018] is the comprehensive permeability coefficient, where K i is the permeability coefficient of aquifer i, K c is the permeability coefficient of the lining structure, K g is the permeability coefficient of the grouting circle,
[0019] r w is the net shaft radius,
[0020] r c is the outer radius of the lining,
[0021] r g is the outer radius of the grouting circle,
[0022] s i is the drawdown of the water level in aquifer i.
[0023] Preferably, the s i Calculated by the following formula (2) or (3):
[0024]
[0025] in,
[0026] s i is the water level drawdown of aquifer i from the initial groundwater level to the allowable well water level,
[0027] i=1~m,
[0028] b i is the thickness of aquifer i,
[0029] b j is the thickness of aquifer j, where j = 1 to i,
[0030] ∑ is the cumulative summation symbol;
[0031]
[0032] in,
[0033] s i is the water level drawdown of aquifer i corresponding to the depth from the allowable well water level to the bottom of the well,
[0034] i=m+1~n,
[0035] b m is the thickness of the aquifer m,
[0036] b j is the thickness of aquifer j, where j = 1~m,
[0037] ∑ is the cumulative summation symbol.
[0038] Preferably, a larger initial value of the seepage influence radius is selected and substituted into the right side of the formula (1), and the result is the second intermediate value of the seepage influence radius. The second intermediate value of the seepage influence radius is substituted into the right side of the formula (1) to obtain the third intermediate value of the seepage influence radius. This cycle is repeated until the difference between the intermediate values of two adjacent seepage influence radii is no more than 1 m, and the calculation is stopped, thus obtaining the final value of the seepage influence radius of the groundwater in the aquifer.
[0039] Preferably, in step 4), the water yield of each aquifer is predicted by the following formula (4):
[0040]
[0041] in,
[0042] Q i is the water yield of aquifer i, i = 1~n,
[0043] b i is the thickness of aquifer i,
[0044] K iis the permeability coefficient of aquifer i,
[0045] K c is the permeability coefficient of the lining structure,
[0046] K g is the permeability coefficient of the grouting circle,
[0047] r w is the net radius of the shaft,
[0048] r c is the outer radius of the lining,
[0049] r g is the outer radius of the grouting circle,
[0050] R i is the groundwater seepage influence radius of aquifer i,
[0051] s i It is the water level drawdown of aquifer i from the initial groundwater level to the allowable well water level, or the water level drawdown of aquifer i from the allowable well water level to the well bottom depth.
[0052] Preferably, the total water inflow is predicted by the following formula (5):
[0053]
[0054] in,
[0055] Q i is the water yield of aquifer i, i = 1~n,
[0056] Q w is the total water inflow of the multi-ring structure shaft,
[0057] ∑ is the cumulative summation symbol.
[0058] Preferably, in step 4), the external water pressure of the lining is predicted by the following formula (6) or (7) or (8):
[0059] P h =0 (6)
[0060] in,
[0061] P h is the external water pressure on the lining corresponding to the distance from the wellhead to the initial groundwater level;
[0062]
[0063] in,
[0064] h is the depth between the initial groundwater level and the allowable well water level,
[0065] h0 is the initial groundwater level,
[0066] h1 is the allowable water level in the well,
[0067] K i is the permeability coefficient of aquifer i,
[0068] K c is the permeability coefficient of the lining structure,
[0069] K g is the permeability coefficient of the grouting circle,
[0070] r w is the net radius of the shaft,
[0071] r c is the outer radius of the lining,
[0072] r g is the outer radius of the grouting circle,
[0073] R i is the groundwater seepage influence radius of aquifer i,
[0074] γ is the weight density of groundwater,
[0075] P h It is the external water pressure of the lining corresponding to the initial groundwater level to the allowable well water level;
[0076]
[0077] in,
[0078] h is the depth between the allowable water level in the well and the bottom depth of the well.
[0079] h1 is the allowable water level in the well,
[0080] K i is the permeability coefficient of aquifer i,
[0081] K c is the permeability coefficient of the lining structure,
[0082] K g is the permeability coefficient of the grouting circle,
[0083] r w is the net radius of the shaft,
[0084] r c is the outer radius of the lining,
[0085] r g is the outer radius of the grouting circle,
[0086] R iis the groundwater seepage influence radius of aquifer i,
[0087] γ is the weight density of groundwater,
[0088] P h It is the external water pressure of the lining corresponding to the initial groundwater level to the allowable water level in the well.
[0089] The advantages of the present invention are:
[0090] 1. This method takes into account the influence of the lining structure and grouting ring outside the shaft, so the seepage prediction is more accurate;
[0091] 2. The present invention takes into account the vertical stratification of aquifers, obtains the thickness and permeability coefficient of each aquifer through drilling exploration, and also takes into account the changes in the water level drop and seepage influence radius of groundwater in each aquifer, further improving the accuracy of vertical shaft seepage prediction;
[0092] 3. The present invention provides a reference for the design of the grouting ring and lining structure outside the shaft by calculating the water gushing amount of each aquifer in the multi-circular ring structure shaft and the external water pressure of the lining structure at different depths outside the multi-circular ring structure shaft, thereby preventing the failure of the lining structure due to excessive external water pressure or excessive water gushing amount due to insufficient thickness of the grouting ring, and also avoiding the design being too conservative and uneconomical.
[0093] The present invention is applicable to the groundwater seepage prediction method of multi-circular ring structure shaft. The analytical solution predicted by the method (the analytical solution refers to: the water gushing volume corresponding to each aquifer in the multi-circular ring structure shaft and the external water pressure of the lining structure at different depths outside the multi-circular ring structure shaft) is compared with the results obtained by computer numerical calculation simulation. The prediction method has better accuracy. BRIEF DESCRIPTION OF THE DRAWINGS
[0094] Figure 1 It is a flow chart of the groundwater seepage prediction method applicable to multi-circular structure shafts of the present invention;
[0095] Figure 2 It is a schematic diagram of a multi-ring structure shaft;
[0096] Figure 3 It is a comparison between the predicted results of water inflow of each aquifer in a multi-ring structure shaft and the results obtained by numerical calculation simulation;
[0097] Figure 4 The paper compares the predicted results of the external water pressure of the lining structure at different depths of a multi-ring structure shaft with the results obtained by numerical simulation.
[0098] In the figure:
[0099] Initial groundwater level h0, allowable well water level h1, well bottom depth h2, sequence number i of each aquifer outside the shaft, thickness b of each aquifer outside the shaft i , the permeability coefficient of each aquifer K i , lining structure permeability coefficient K c , grouting circle permeability coefficient K g , the number of aquifers m within the range from the initial groundwater level h0 to the allowable well water level h1, and the number of aquifers n within the range from the initial groundwater level h0 to the well bottom depth h2. Implementation
[0100] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0101] In the description of the present invention, it is necessary to understand that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the invention.
[0102] like Figure 1 As shown, the groundwater seepage prediction method applicable to multi-circular structure shafts includes the following steps:
[0103] Step 1), obtain the hydrogeological conditions of the multi-ring structure shaft and the permeability coefficient K of each aquifer outside the multi-ring structure shaft i ;
[0104] Step 2), determine the permeability coefficient K of the lining structure outside the multi-ring structure shaft c And the permeability coefficient of the grouting circle K g ;
[0105] Step 3), analyze the seepage influence radius R of groundwater in each aquifer outside the multi-ring structure shaft i ;
[0106] Step 4), predict the water yield Q of each aquifer in the multi-ring structure shaft i 、Total water inflow Q wAnd the lining external water pressure P of the lining structure outside the multi-ring structure shaft at different depths h .
[0107] In the above step 1), if Figure 2 As shown, the hydrogeological conditions include the initial groundwater level h0, the allowable well water level h1, the well bottom depth h2, the sequence number i of each aquifer outside the shaft, the thickness b of each aquifer outside the shaft i , where the initial groundwater level h0 and the thickness of each aquifer outside the shaft b i All of them are obtained through drilling exploration; the permeability coefficient K of each aquifer i The initial groundwater level h0, the allowable well water level h1, and the well bottom depth h2 are measured by on-site pumping or water pressure test.
[0108] Specifically, the hydrogeological conditions of the multi-ring structure shaft and the permeability coefficient K of each aquifer outside the multi-ring structure shaft are taken as i as follows:
[0109] Determine the bottom depth h2 = 200m and the allowable water level in the well h1 = 140m, conduct drilling exploration on each aquifer in the multi-ring structure vertical shaft, and obtain the initial groundwater level h0 = 50m. The serial number i and thickness bi of each aquifer are also obtained through drilling exploration, including b1 = 40m, b2 = 50m, b3 = 20m, b4 = 40m, among which the number of aquifers in the depth range of h = 50m ~ 140m (h = h0 ~ h1) is m = 2, and the number of aquifers in the depth range of h = 140m ~ 200m (h = h1 ~ h2) is nm = 4-2 = 2. The permeability coefficient K of each aquifer is measured by on-site pumping or water pressure test i Including K1=0.6m / d, K2=0.7m / d, K3=0.5m / d, K4=0.4m / d.
[0110] In the above step 2), the permeability coefficient K of the lining structure is c The determination process is as follows: prepare a lining structure of reinforced concrete material, and obtain the permeability coefficient K of the lining structure through indoor permeability test measurement. c =0.02m / d; the permeability coefficient of the grouting circle K g The determination process is as follows: drill holes in each aquifer outside the multi-ring structure shaft and inject slurry, sweep the holes after the slurry solidifies, and measure the permeability coefficient K of the grouting circle through an on-site water pressure test. g =0.1m / d.
[0111] In the above step 3), the seepage influence radius is iteratively calculated by the following formula (1):
[0112]
[0113] in,
[0114] R i is the seepage influence radius of groundwater in aquifer i,
[0115] is the comprehensive permeability coefficient, where K i is the permeability coefficient of aquifer i, K c is the permeability coefficient of the lining structure, K g is the permeability coefficient of the grouting circle,
[0116] r w is the net shaft radius,
[0117] r c is the outer radius of the lining,
[0118] r g is the outer radius of the grouting circle,
[0119] s i is the drawdown of the water level in aquifer i.
[0120] The above i Calculated by the following formula (2) or (3):
[0121]
[0122] in,
[0123] s i is the water level drawdown of aquifer i from the initial groundwater level to the allowable well water level,
[0124] i=1~m,
[0125] b i is the thickness of aquifer i,
[0126] b j is the thickness of aquifer j, where j = 1 to i,
[0127] ∑ is the cumulative summation symbol;
[0128]
[0129] in,
[0130] s i is the water level drawdown of aquifer i corresponding to the depth from the allowable well water level to the bottom of the well,
[0131] i=m+1~n,
[0132] b m is the thickness of the aquifer m,
[0133] b j is the thickness of aquifer j, where j = 1~m,
[0134] ∑ is the cumulative summation symbol.
[0135] Specifically, for m=2, i=1-2, formula (2) yields:
[0136] s1=—1 / 2*40+40=20m, s2=—1 / 2*50+40+50=65m;
[0137] For m=2, i=3-4, we can obtain the following equation (3):
[0138] s3=40+50=90m, s4=40+50=90m.
[0139] For formula (1), a larger initial value of the seepage influence radius is selected and substituted into the right side of the formula (1). The result is the second intermediate value of the seepage influence radius. The second intermediate value of the seepage influence radius is substituted into the right side of the formula (1) to obtain the third intermediate value of the seepage influence radius. This cycle is repeated until the difference between the intermediate values of two adjacent seepage influence radii is no more than 1 m, and the calculation is stopped. This means that the final value of the seepage influence radius of the groundwater in the aquifer is obtained.
[0140] Specifically, when r w =5m,r c =6m,r g =10m, K c =0.02m / d, K g =0.1m / d, K1 of aquifer 1 = 0.6m / d, s1 = 20m, and the process of calculating R1 is as follows:
[0141] In the first iteration, the initial value R1=1000m is taken.
[0142] Calculate K * i =0.6*ln(1000 / 5) / [ln(1000 / 10)+0.6 / 0.1*ln(10 / 6)+0.6 / 0.02*ln(6 / 5)]=0.242m / d, calculate the second intermediate value R1=5+10*20*0.242^0.5=103.4m;
[0143] In the second iteration, R1=103.4m is taken and the third intermediate value R1=86.8m is calculated;
[0144] In the third iteration, R1=86.8m is taken and the fourth intermediate value R1=85.0m is calculated;
[0145] In the fourth iteration, R1=85.0m is taken and the fifth intermediate value R1=84.8m is calculated;
[0146] The difference between 84.8 and 85.0 is 0.2m. The calculation ends when it is less than 1m. The final value of the seepage influence radius of groundwater in aquifer 1 is R1=84.8m.
[0147] Similarly, the seepage influence radius of the groundwater in aquifer 2 is R2 = 306.6 m, the seepage influence radius of the groundwater in aquifer 3 is R3 = 411.2 m, and the seepage influence radius of the groundwater in aquifer 4 is R4 = 393.7 m.
[0148] In the above step 4), the water yield of each aquifer is predicted by the following formula (4):
[0149]
[0150] in,
[0151] Q i is the water yield of aquifer i, i = 1~n,
[0152] b i is the thickness of aquifer i,
[0153] K i is the permeability coefficient of aquifer i,
[0154] K c is the permeability coefficient of the lining structure,
[0155] K g is the permeability coefficient of the grouting circle,
[0156] r w is the net shaft radius,
[0157] r c is the outer radius of the lining,
[0158] r g is the outer radius of the grouting circle,
[0159] R i is the groundwater seepage influence radius of aquifer i,
[0160] s i It is the water level drawdown of aquifer i from the initial groundwater level to the allowable well water level, or the water level drawdown of aquifer i from the allowable well water level to the well bottom depth.
[0161] Specifically, when r w =5m, r c =6m,r g =10m, K c =0.02m / d, Kg =0.1m / d, K1 of aquifer 1 = 0.6m / d, s1 = 20m, b1 = 40m, R1 = 84.8m, then the water yield of aquifer 1 is
[0162] Q1=2*3.14*0.6*20*40 / [ln(84.8 / 10)+0.6 / 0.1*ln(10 / 6)+0.6 / 0.02*ln(6 / 5)]=282.6m 3 / d.
[0163] Similarly, the inflow of aquifer 2 is Q2 = 1068.3 m 3 / d, the water yield of aquifer 3 is Q3 = 522.2m 3 / d, the water yield of aquifer 4 is Q4 = 966.4m 3 / d.
[0164] like Figure 3 As shown, the water inflow of the corresponding aquifer 1, 2, 3 or 4 in the multi-circular structure shaft predicted by the groundwater seepage prediction method applicable to the multi-circular structure shaft is compared with the result obtained by computer numerical calculation simulation, and the results of the two methods are basically consistent.
[0165] The total water inflow mentioned above is predicted by the following formula (5):
[0166]
[0167] in,
[0168] Q i is the water yield of aquifer i, i = 1~n,
[0169] Q w is the total water inflow of the multi-ring structure shaft,
[0170] ∑ is the cumulative summation symbol.
[0171] Specifically, Q w =Q1+Q2+Q3+Q4=2839.5m 3 / d.
[0172] In the above step 4), the external water pressure of the lining is predicted by the following formula (6) or (7) or (8):
[0173] P h =0 (6)
[0174] in,
[0175] P h is the external water pressure on the lining corresponding to the distance from the wellhead to the initial groundwater level;
[0176]
[0177] in,
[0178] h is the depth between the initial groundwater level and the allowable well water level,
[0179] h0 is the initial groundwater level,
[0180] h1 is the allowable water level in the well,
[0181] K i is the permeability coefficient of aquifer i,
[0182] K c is the permeability coefficient of the lining structure,
[0183] K g is the permeability coefficient of the grouting circle,
[0184] r w is the net radius of the shaft,
[0185] r c is the outer radius of the lining,
[0186] r g is the outer radius of the grouting circle,
[0187] R i is the groundwater seepage influence radius of aquifer i,
[0188] γ is the weight density of groundwater,
[0189] P h It is the external water pressure of the lining corresponding to the initial groundwater level to the allowable well water level;
[0190]
[0191] in,
[0192] h is the depth between the allowable water level in the well and the bottom depth of the well.
[0193] h1 is the allowable water level in the well,
[0194] K i is the permeability coefficient of aquifer i,
[0195] K c is the permeability coefficient of the lining structure,
[0196] K g is the permeability coefficient of the grouting circle,
[0197] r w is the net radius of the shaft,
[0198] r cis the outer radius of the lining,
[0199] r g is the outer radius of the grouting circle,
[0200] R i is the groundwater seepage influence radius of aquifer i,
[0201] γ is the weight density of groundwater,
[0202] P h It is the external water pressure of the lining corresponding to the initial groundwater level to the allowable water level in the well.
[0203] Specifically, based on the above formulas (6), (7) and (8), the prediction results of the lining external water pressure at different depths of the lining structure outside the multi-ring structure shaft of the present invention are shown in Table 1 below. In addition, the lining external water pressure is also obtained through computer numerical calculation simulation test, see Figure 4 .
[0204] Table 1 Prediction of external water pressure on lining
[0205]
[0206] It can be seen from Table 1 that starting from the initial groundwater level h0 = 50m, as the depth h increases, the external water pressure P of the lining outside the multi-ring structure shaft increases. h It increases gradually and fluctuates with the difference in permeability Ki of each aquifer.
[0207] like Figure 4 As shown in the figure, the external water pressure P of the lining around the multi-ring structure shaft predicted by the groundwater seepage prediction method applicable to the multi-ring structure shaft h Compared with the results obtained by computer numerical simulation, the results of the two methods are basically consistent.
[0208] It can be seen that the groundwater seepage prediction method applicable to multi-circular structure vertical shafts proposed by the present invention has good accuracy.
[0209] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A groundwater seepage prediction method applicable to multi-circular structure shafts, characterized in that: The steps include: Step 1), obtaining the hydrogeological conditions of the multi-ring structure shaft and the permeability coefficient of each aquifer outside the multi-ring structure shaft; Step 2), respectively determining the permeability coefficient of the lining structure and the permeability coefficient of the grouting ring outside the multi-ring structure shaft; Step 3), analyzing the seepage influence radius of groundwater in each aquifer outside the multi-ring structure shaft; The seepage influence radius is iteratively calculated by the following formula (1): in, R i is the seepage influence radius of groundwater in aquifer i, is the comprehensive permeability coefficient, where K i is the permeability coefficient of aquifer i, K c is the permeability coefficient of the lining structure, K g is the permeability coefficient of the grouting circle, r w is the net shaft radius, r c is the outer radius of the lining, r g is the outer radius of the grouting circle, s i is the drawdown of the water level in aquifer i; The i Calculated by the following formula (2) or (3): in, s i is the water level drawdown of aquifer i from the initial groundwater level to the allowable well water level, i=1~m, b i is the thickness of aquifer i, b j is the thickness of aquifer j, where j = 1 to i, ∑ is the cumulative summation symbol; in, s i is the water level drawdown of aquifer i corresponding to the depth from the allowable well water level to the bottom of the well, i=m+1~n, b m is the thickness of the aquifer m, b j is the thickness of aquifer j, where j = 1~m, ∑ is the cumulative summation symbol; Step 4), predicting the water inflow of each aquifer in the multi-ring structure shaft, the total water inflow, and the external water pressure of the lining structure at different depths of the multi-ring structure shaft.
2. The groundwater seepage prediction method applicable to a multi-circular structure vertical shaft according to claim 1, characterized in that: In step 1), the hydrogeological conditions include the initial groundwater level, the allowable water level in the well, the well bottom depth, the serial number of each aquifer outside the vertical shaft, and the thickness of each aquifer outside the vertical shaft, wherein the initial groundwater level and the thickness of each aquifer outside the vertical shaft are obtained through drilling exploration; the permeability coefficient of each aquifer is measured by on-site pumping or water pressure test.
3. The groundwater seepage prediction method applicable to a multi-circular structure shaft according to claim 2 is characterized in that: The relationship among the initial groundwater level, the allowable well water level and the well bottom depth is well bottom depth ≥ allowable well water level ≥ initial groundwater level.
4. The groundwater seepage prediction method applicable to multi-circular structure shafts according to claim 2 or 3, characterized in that: In step 2), The process of determining the permeability coefficient of the lining structure is as follows: preparing a lining structure made of reinforced concrete material, and obtaining the permeability coefficient of the lining structure by measuring the permeability coefficient through an indoor permeability test; The process of determining the permeability coefficient of the grouting ring is as follows: drilling holes into each aquifer outside the multi-ring structure shaft and injecting slurry, sweeping the holes after the slurry solidifies, and measuring the permeability coefficient of the grouting ring through an on-site water pressure test.
5. The groundwater seepage prediction method applicable to a multi-circular structure shaft according to claim 4, characterized in that: Select a larger initial value of the seepage influence radius and substitute it into the right side of the formula (1). The result is the second intermediate value of the seepage influence radius. The second intermediate value of the seepage influence radius is substituted into the right side of the formula (1) to obtain the third intermediate value of the seepage influence radius. This cycle is repeated until the difference between the intermediate values of two adjacent seepage influence radii is no more than 1 m. The calculation is stopped, and the final value of the seepage influence radius of the groundwater in the aquifer is obtained.
6. The groundwater seepage prediction method applicable to a multi-circular structure shaft according to claim 5, characterized in that: In step 4), the water yield of each aquifer is predicted by the following formula (4): in, Q i is the water yield of aquifer i, i = 1~n, bi is the thickness of aquifer i, K i is the permeability coefficient of aquifer i, K c is the permeability coefficient of the lining structure, K g is the permeability coefficient of the grouting circle, r w is the net shaft radius, r c is the outer radius of the lining, r g is the outer radius of the grouting circle, R i is the groundwater seepage influence radius of aquifer i, s i It is the water level drawdown of aquifer i from the initial groundwater level to the allowable well water level, or the water level drawdown of aquifer i from the allowable well water level to the well bottom depth.
7. The groundwater seepage prediction method applicable to a multi-circular structure shaft according to claim 6, characterized in that: The total water inflow is predicted by the following formula (5): in, Q i is the water yield of aquifer i, i = 1~n, Q w is the total water inflow of the multi-ring structure shaft, ∑ is the cumulative summation symbol.
8. The groundwater seepage prediction method applicable to multi-circular structure vertical shaft according to claim 6, characterized in that: In step 4), the external water pressure of the lining is predicted by the following formula (6) or (7) or (8): P h =0 (6) in, P h is the external water pressure on the lining corresponding to the distance from the wellhead to the initial groundwater level; in, h is the depth between the initial groundwater level and the allowable well water level, h0 is the initial groundwater level, h1 is the allowable water level in the well, K i is the permeability coefficient of aquifer i, K c is the permeability coefficient of the lining structure, K g is the permeability coefficient of the grouting circle, r w is the net shaft radius, r c is the outer radius of the lining, r g is the outer radius of the grouting circle, R i is the groundwater seepage influence radius of aquifer i, γ is the weight density of groundwater, P h It is the external water pressure of the lining corresponding to the initial groundwater level to the allowable well water level; in, h is the depth between the allowable water level in the well and the bottom depth of the well. h1 is the allowable water level in the well, K i is the permeability coefficient of aquifer i, K c is the permeability coefficient of the lining structure, K g is the permeability coefficient of the grouting circle, r w is the net shaft radius, r c is the outer radius of the lining, r g is the outer radius of the grouting circle, R i is the groundwater seepage influence radius of aquifer i, γ is the weight density of groundwater, P h It is the external water pressure of the lining corresponding to the initial groundwater level to the allowable water level in the well.