Construction claim method, device, computer equipment and storage medium

By constructing a claim case database and causal network and conducting mathematical analysis, the problem of unclear claim basis in construction claims was solved and the success rate of claims was improved.

CN114119299BActive Publication Date: 2025-09-16SHENZHEN UNIV
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202111394156.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-23
Publication Date
2025-09-16
Estimated Expiration
2041-11-23

AI Technical Summary

Technical Problem

During the construction process, when the contractor claims compensation from the owner due to construction problems, the basis and decision-making of the claim are not clear enough, resulting in the claim not achieving the expected results.

Method used

By collecting historical claim cases, establishing a claim case database and a claim cause vocabulary database, performing cause matching and network construction, conducting mathematical analysis, extracting response strategies and claim evidence, and providing claim references.

Benefits of technology

It provides construction parties with important reference and decision-making assistance for timely avoiding risks and seizing opportunities for claims, thereby improving the success rate of claims.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114119299B_ABST
    Figure CN114119299B_ABST
Patent Text Reader

Abstract

The present invention discloses a construction claim method, apparatus, computer equipment, and storage medium. The method includes establishing a claim case library and a claim cause vocabulary based on historical claim cases; identifying claim reference cases for use as reference for pending claim cases; extracting the claim cause chains in each pending claim reference case and constructing a claim cause network; mathematically analyzing each claim cause chain and claim cause in the claim cause network to obtain a response strategy for the pending claim case; outputting successful cases containing the claim cause of the pending claim case from the pending claim reference cases, extracting the claim evidence and claim standards of the successful cases, and using them as a claim reference for the pending claim case. The present invention effectively utilizes the big data information in the claim case library. By analyzing the relationship between the claim cause network and the claim cause of the pending claim case, it provides an important reference basis and decision-making assistance for construction parties to timely avoid risks, seize claim opportunities, and successfully claim.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of claim management, and in particular to a construction claim method, device, computer equipment and storage medium. Background Art

[0002] During the construction process, contractors often suffer project losses due to factors such as construction site conditions, climatic conditions, construction progress, changes in market prices, differences and changes in contract terms, specifications and construction drawings, resulting in delays, cost overruns, and even project suspensions.

[0003] Therefore, in many projects, contractors (i.e. construction parties) often make project claims to owners, but the claims process often fails to meet expectations because the basis and decision-making of the claims are not clear enough. Summary of the Invention

[0004] The purpose of the present invention is to provide a construction claim method, device, computer equipment and storage medium, which aims to solve the problem that when a contractor makes a claim to an owner due to engineering problems in existing engineering construction, the basis for the claim and the decision are not clear enough.

[0005] In order to solve the above technical problems, the purpose of the present invention is achieved through the following technical solutions: 1. A construction claim method comprising:

[0006] Collect historical claim cases and establish a claim case database;

[0007] Extracting the causes of claims from the historical claim cases and establishing a database of the causes of claims;

[0008] Matching the claim cause of the pending claim case in the claim cause vocabulary, and finding all historical claim cases containing the claim cause of the pending claim case in the claim case database based on the matching results, and using all the found historical claim cases as reference cases for the pending claim;

[0009] Extracting the claim cause chain in each reference case to be claimed and constructing a claim cause network;

[0010] Performing mathematical analysis on each claim cause chain and claim cause in the claim cause network to obtain a response strategy for the pending claim case;

[0011] A successful case containing the claim cause of the case to be claimed is output from the reference case to be claimed, and the claim evidence and claim standards of the successful case are extracted and used as a claim reference for the case to be claimed.

[0012] In addition, the technical problem to be solved by the present invention is to provide a construction claim device, which includes:

[0013] Case building unit, used to collect historical claim cases and build a claim case database;

[0014] A word library building unit is used to extract the causes of claims from the historical claim cases and build a word library of causes of claims;

[0015] a matching unit, configured to match the claim cause of the pending claim case in a claim cause vocabulary, and find all historical claim cases containing the claim cause of the pending claim case in a claim case database based on the matching results, and use all found historical claim cases as reference cases for the pending claim;

[0016] A network construction unit, configured to extract a claim cause chain from each of the reference cases to be claimed and construct a claim cause network;

[0017] A mathematical analysis unit, configured to perform mathematical analysis on each claim cause chain and claim cause in the claim cause network to obtain a response strategy for the pending claim case;

[0018] The claim reference unit is used to output a successful case containing the claim cause of the case to be claimed from the reference case to be claimed, and to extract the claim evidence and claim standards of the successful case as a claim reference for the case to be claimed.

[0019] In addition, an embodiment of the present invention provides a computer device, which includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the construction claim method described in the first aspect above is implemented.

[0020] In addition, an embodiment of the present invention further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the processor executes the construction claim method described in the first aspect above.

[0021] The embodiments of the present invention disclose a construction claim method, apparatus, computer equipment, and storage medium. The method includes establishing a claim case library and a claim cause vocabulary based on historical claim cases; finding claim reference cases for reference in pending claim cases; extracting the claim cause chain in each pending claim reference case and constructing a claim cause network; mathematically analyzing each claim cause chain and claim cause in the claim cause network to obtain a response strategy for the pending claim case; outputting a successful case containing the claim cause of the pending claim case from the pending claim reference case, and extracting the claim evidence and claim standards of the successful case as a claim reference for the pending claim case. The embodiments of the present invention effectively utilize the big data information of the claim case library. By analyzing the relationship between the claim cause network and the claim cause of the pending claim case, it provides an important reference basis and decision-making assistance for the construction party to timely avoid risks, seize claim opportunities, and successfully claim. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0023] Figure 1 A schematic diagram of a process flow of a construction claim method provided by an embodiment of the present invention;

[0024] Figure 2 A schematic diagram of a sub-process of a construction claim method provided by an embodiment of the present invention;

[0025] Figure 3 A schematic diagram of another sub-flow of the construction claim method provided by an embodiment of the present invention;

[0026] Figure 4 A schematic diagram of another sub-flow of the construction claim method provided by an embodiment of the present invention;

[0027] Figure 5 A schematic diagram of another sub-flow of the construction claim method provided by an embodiment of the present invention;

[0028] Figure 6 A schematic diagram of another sub-flow of the construction claim method provided by an embodiment of the present invention;

[0029] Figure 7 A schematic diagram of another sub-flow of the construction claim method provided by an embodiment of the present invention;

[0030] Figure 8 A schematic diagram of a construction claim network provided by an embodiment of the present invention;

[0031] Figure 9 A schematic block diagram of a construction claim claim apparatus provided by an embodiment of the present invention;

[0032] Figure 10 A schematic block diagram of a computer device provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0033] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making any creative efforts shall fall within the scope of protection of the present invention.

[0034] It will be understood that when used in this specification and the appended claims, the terms “comprises” and “comprising” indicate the presence of described features, integers, steps, operations, elements and / or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or groups thereof.

[0035] It should also be understood that the terminology used in this specification is for the purpose of describing particular embodiments only and is not intended to limit the present invention. As used in the specification and appended claims, the singular forms "a," "an," and "the" are intended to include the plural forms unless the context clearly indicates otherwise.

[0036] It should be further understood that the term "and / or" used in the present description and the appended claims refers to and includes any and all possible combinations of one or more of the associated listed items.

[0037] See also Figure 1 , Figure 1 A schematic diagram of a process flow of a construction claim method provided by an embodiment of the present invention;

[0038] like Figure 1 As shown, the method includes steps S101 to S105.

[0039] S101. Collect historical claim cases and establish a claim case database;

[0040] S102. Extract the causes of claims from historical claim cases and establish a database of the causes of claims;

[0041] In steps S101-S102, historical claim cases are collected and stored according to their characteristic categories. A claim case database is then established. This classification can be categorized by project type, such as building construction or water conservancy. The causes of claims are extracted from these historical claim cases. These are non-contractor factors encountered during the project that cause the contractor to incur expenses or time losses, such as delayed start, cost increases, and design changes. A claim cause vocabulary is then created based on the extracted claim causes for each historical claim case. This construction of a claim case database and claim cause vocabulary facilitates subsequent query matching.

[0042] S103. Match the claim cause of the pending claim case in the claim cause database, and find all historical claim cases containing the claim cause of the pending claim case in the claim case database based on the matching results, and use all the found historical claim cases as reference cases for the pending claim case;

[0043] In step S103, the case to be claimed is a case that needs to be analyzed for claims in this application. It can be a case that is under construction or a case after the construction is completed. By performing query matching through various matching methods such as project category matching, field matching, and word meaning recognition, multiple reference cases to be claimed can be obtained. This provides accurate reference objects for subsequent mathematical analysis, thereby improving the success rate of claims.

[0044] S104. Extract the claim cause chain in each pending claim reference case and construct a claim cause network;

[0045] S105. Perform mathematical analysis on each claim cause chain and claim cause in the claim cause network to obtain a response strategy for the pending claim case;

[0046] S106. Outputting a successful case containing the claim cause of the pending claim case from the pending claim reference case, extracting the claim evidence and claim standard of the successful case and using it as a claim reference for the pending claim case.

[0047] Steps S104-S106 are the process of constructing a claim cause network, then mathematically analyzing the claim cause network and providing a claim reference. This effectively utilizes the big data information of the claim case library and analyzes the relationship between the claim cause network and the claim causes of the pending claim cases, providing important reference and decision-making assistance for the construction party to avoid risks in a timely manner, seize claim opportunities and successfully file claims.

[0048] The process of constructing the claim cause network in step S104 is further described below. Figure 2 As shown, for each reference case to be claimed, follow the steps below:

[0049] S201. Read the claim reason in the reference case to be claimed;

[0050] S202, extracting key claim information from the claim reason and obtaining the claim cause;

[0051] S203. Form a claim cause chain according to the order in which the claim causes occur;

[0052] Steps S201-S203 describe the process of extracting the claim cause chain from the reference case to be claimed. For ease of understanding, a specific embodiment is used for illustration:

[0053] For example, in a reference case where a claim is pending;

[0054] The reason for the claim read was: the owner failed to provide the production and living space for the mechanical and electrical installation section on time, which resulted in the contractor taking two months to start work after arriving at the base, increasing costs.

[0055] Three causes of claim can be raised from the reasons for the claim: failure to provide the construction site on time, delayed start of work, and increased costs.

[0056] The chain of causes of the claim is: failure to provide the construction site on time → delayed start of work → increased costs → claim;

[0057] It should be noted that there may be one or more claim cause chains in a reference case to be claimed.

[0058] Finally, all the claim cause chains in all pending claim reference cases are combined, and a claim cause network represented as an adjacency matrix is ​​constructed with the claim causes as nodes.

[0059] The following is a specific example to introduce the process of constructing a claim cause network;

[0060] First, we introduce the causes of claims in the reference cases to be claimed, as shown in Table 1 (only the parts that need to be exemplified are shown). In addition to Table 1, it also includes the causes of claims under multiple main factors such as design procurement, external risks, contract project definition, etc.

[0061] Table 1

[0062]

[0063]

[0064] For example, the claim in the input pending claim case is caused by engineering change (N1). In the pending claim reference case, the engineering change (N1) will directly lead to an increase in engineering volume (P1) and an increase in cost (P2), that is, (N1, P1) and (N1, P2) are equal to 1.

[0065] like Figure 8As shown, by integrating all claim cause chains, a complete adjacency matrix is ​​generated. The first row and first column of the adjacency matrix are claim causes, representing the nodes of the claim cause network. The non-diagonal cells of the adjacency matrix represent the relationship between two claim causes. If a claim cause causes or affects another claim cause, the value of the corresponding cell is equal to 1, otherwise, the value is 0. All diagonal cells are equal to 0 because the claim cause has no relationship with itself. The adjacency matrix is ​​input into the UCINET 6 for Windows version software, and the claim cause network can be drawn using NetDraw (network analysis and visualization tool). The software can also analyze the characteristic parameters of the claim cause network (node ​​degree, clustering coefficient, network density, etc.).

[0066] The following describes step S105, specifically the process of mathematically analyzing each claim cause chain and claim cause in the claim cause network. Step S105 includes:

[0067] Count the categories and occurrence times of each claim cause chain in the claim cause network, and use a weighted algorithm to calculate the next potential claim cause of the pending claim case;

[0068] Among them, such as Figure 3 As shown in Figure 2, the calculation process of the weighted algorithm is as follows:

[0069] S301. Confirm the claim cause of the pending claim case is the next claim cause in each claim cause chain, and use the next claim cause in each claim cause chain as the claim cause to be calculated in the claim cause chain;

[0070] S302: Multiply the number of occurrences of each claim cause chain by the number of categories of the claim cause chain with its own claim cause to be calculated, and obtain the calculation result of the corresponding claim cause to be calculated;

[0071] S303: The to-be-calculated claim cause with the largest calculated result is used as the next potential claim cause of the to-be-calculated claim case.

[0072] In this embodiment, the purpose of using the above-mentioned weighted algorithm is to predict the next potential claim cause of the claim cause of the pending claim case, so as to know the most likely development of the pending claim case and make preparations in advance, such as dealing with risks and preparing claim supporting materials.

[0073] In one embodiment, if Figure 4 As shown, step S105 further includes:

[0074] S401. The first claim cause in each claim cause chain is regarded as the originating factor;

[0075] S402. The claim cause with the most correlations and the claim cause with the highest betweenness centrality in each claim cause chain is selected as the key claim cause;

[0076] S403. The collection direction of claim materials for pending claim cases shall be based on origin factors and key claim causes.

[0077] This embodiment mainly analyzes the relationship between each claim cause in each claim cause chain, such as Figure 8 In the figure, it can be seen that the engineering change (N1) with only output but no input is the origin factor, that is, the node with only out-degree but no in-degree is the origin factor that causes the claim. The contractor can analyze whether it has fallen behind this factor and supplement the relevant supporting materials as soon as possible. The cost increase (P2) has four edges, indicating that it is a key transportation hub and other information. The node with the highest total degree (total number of edges) and the node with the highest betweenness centrality are regarded as the key claim causes; therefore, the origin factors and key claim causes are nodes with great influence and must be focused on. Therefore, the direction of claim material collection for pending claim cases can also be based on the origin factors and key claim causes.

[0078] In one embodiment, if Figure 5 As shown, step S105 further includes:

[0079] S501. Calculate the clustering coefficient of the claim cause of the pending claim case in the claim cause network, where the clustering coefficient of the claim cause of the pending claim case refers to: the probability that two neighboring nodes of the claim cause of the pending claim case in the claim cause network are connected to each other;

[0080] S502: Select the neighbor node corresponding to the maximum probability as the claim response direction of the pending claim case.

[0081] In this embodiment, the largest or top-ranked neighbor nodes are selected based on the clustering coefficient. These neighbor nodes have high connectivity with the claim causes of pending claims and are easily influenced by each other. In claims management, emergency and prevention plans for these nodes should be prioritized to better control and manage claims.

[0082] In one embodiment, if Figure 6 As shown, step S106 includes:

[0083] S601: Outputting a preset number of successful cases containing the claim cause chain of the pending claim case from the pending claim reference cases;

[0084] S602: Extract the calculation formula of the claim amount, claim evidence and claim negotiation process in the successful case and use them as a reference for the claim case to be claimed.

[0085] In this embodiment, the main purpose is to further output the successful case that best meets the reference of the case to be claimed. The case to be claimed can have one or more claim cause chains. The specific claim cause chain can be output from the claim cause network based on the results of the aforementioned mathematical analysis, or it can be selected by the user from the claim cause network.

[0086] Based on the claim process of successful cases, you can refer to the calculation formula for the claim amount, claim evidence materials, how to communicate and negotiate with the owner, and other strategies, and apply them to the cases to be claimed; of course, you can also output cases with the same claim cause chain as the cases to be claimed and failed claims, and output the reasons for the failure, lessons and experience summary. The output content can all be presented in the form of a report.

[0087] In addition, the present invention can also output the claim success rate, such as Figure 7 As shown, specifically including:

[0088] S701. Confirm one or more claim cause chains of pending claim cases;

[0089] S702. Calculate the proportion of all successful cases corresponding to each claim cause chain in all pending claim reference cases to obtain the claim success rate of the corresponding claim cause chain;

[0090] S703. Filter claim cause chains exceeding a preset ratio as claim cause chains for pending claim cases to be executed.

[0091] In this embodiment, there are one or more claim cause chains in the pending claim case, and usually the claim success rate of each claim cause chain is different. After calculating the corresponding claim success rate of each claim cause chain in the pending claim reference case, the claim cause chains that exceed the preset ratio are selected. The preset ratio here can be set according to specific needs. The claim cause chains that exceed the preset ratio are used as the claim cause chains when executing the claim for the pending claim case. That is to say, the success rate of using the claim cause chains that exceed the preset ratio to claim is relatively higher, thereby maximizing the claim success rate.

[0092] The embodiment of the present invention further provides a construction claim device, which is used to execute any embodiment of the above-mentioned construction claim method. Figure 9 , Figure 9 It is a schematic block diagram of a construction claim device provided by an embodiment of the present invention.

[0093] like Figure 9 As shown, the construction claim device 900 includes: a case establishing unit 901, a vocabulary establishing unit 902, a matching unit 903, a network building unit 904, a mathematical analysis unit 905 and a claim reference unit 906.

[0094] A case establishment unit 901 is used to collect historical claim cases and establish a claim case database;

[0095] The word library building unit 902 is used to extract the causes of claims from historical claim cases and build a word library of causes of claims;

[0096] Matching unit 903, configured to match the claim cause of the pending claim case in the claim cause vocabulary, and find all historical claim cases containing the claim cause of the pending claim case in the claim case database based on the matching results, and use all the found historical claim cases as reference cases for the pending claim case;

[0097] A network construction unit 904 is used to extract the claim cause chain in each pending claim reference case and construct a claim cause network;

[0098] Mathematical analysis unit 905, used to perform mathematical analysis on each claim cause chain and claim cause in the claim cause network to obtain a response strategy for pending claim cases;

[0099] The claim reference unit 906 is used to output a successful case containing the claim cause of the case to be claimed from the reference case to be claimed, and extract the claim evidence and claim standard of the successful case as a claim reference for the case to be claimed.

[0100] The device effectively utilizes the big data information of the claim case library. By analyzing the relationship between the claim cause network and the claim causes of the cases to be claimed, it provides important reference basis and decision-making assistance for the construction party to avoid risks in a timely manner, seize claim opportunities and successfully claim.

[0101] Those skilled in the art will clearly understand that, for the convenience and brevity of description, the specific working processes of the above-described devices and units can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0102] The above-mentioned construction claim device can be implemented in the form of a computer program. The computer program can be used in Figure 10 Runs on the computer equipment shown.

[0103] See also Figure 10 , Figure 10 1 is a schematic block diagram of a computer device provided by an embodiment of the present invention. The computer device 1000 is a server, which can be an independent server or a server cluster composed of multiple servers.

[0104] See Figure 10 The computer device 1000 includes a processor 1002 , a memory, and a network interface 1005 connected via a system bus 1001 , wherein the memory may include a non-volatile storage medium 1003 and an internal memory 1004 .

[0105] The non-volatile storage medium 1003 may store an operating system 10031 and a computer program 10032. When the computer program 10032 is executed, the processor 1002 may execute a construction claim method.

[0106] The processor 1002 is used to provide computing and control capabilities to support the operation of the entire computer device 1000.

[0107] The internal memory 1004 provides an environment for the operation of the computer program 10032 in the non-volatile storage medium 1003. When the computer program 10032 is executed by the processor 1002, the processor 1002 can execute the construction claim method.

[0108] The network interface 1005 is used for network communication, such as providing data information transmission. Those skilled in the art will understand that Figure 10 The structure shown in the figure is merely a block diagram of a portion of the structure related to the solution of the present invention and does not constitute a limitation on the computer device 1000 to which the solution of the present invention is applied. The specific computer device 1000 may include more or fewer components than shown in the figure, or combine certain components, or have a different component arrangement.

[0109] Those skilled in the art will understand that Figure 10 The embodiment of the computer device shown in the figure does not constitute a limitation on the specific composition of the computer device. In other embodiments, the computer device may include more or fewer components than shown in the figure, or combine certain components, or arrange the components differently. For example, in some embodiments, the computer device may only include a memory and a processor. In such an embodiment, the structure and function of the memory and processor are the same as those in the figure. Figure 10 The embodiments shown are consistent and will not be described again here.

[0110] It should be understood that in the embodiment of the present invention, the processor 1002 may be a central processing unit (CPU), and the processor 1002 may also be other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. The general-purpose processor may be a microprocessor or any conventional processor, etc.

[0111] In another embodiment of the present invention, a computer-readable storage medium is provided. The computer-readable storage medium may be a non-volatile computer-readable storage medium. The computer-readable storage medium stores a computer program, wherein when the computer program is executed by a processor, the construction claim method according to an embodiment of the present invention is implemented.

[0112] The storage medium is a physical, non-transient storage medium, for example, a USB flash drive, a mobile hard disk, a read-only memory (ROM), a magnetic disk, or an optical disk, etc., which can store program codes.

[0113] Those skilled in the art will clearly understand that, for the convenience and brevity of description, the specific working processes of the above-described equipment, devices and units can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0114] The above description is merely a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any person skilled in the art can easily conceive of various equivalent modifications or substitutions within the technical scope disclosed in the present invention, and such modifications or substitutions are intended to be within the scope of protection of the present invention. Therefore, the scope of protection of the present invention shall be subject to the scope of protection of the claims.

Claims

1. A construction claim method, characterized in that: include: Collect historical claim cases and establish a claim case database; Extracting the causes of claims from the historical claim cases and establishing a vocabulary of causes of claims; Match the claim cause of the pending claim case in the claim cause vocabulary, and find all historical claim cases containing the claim cause of the pending claim case in the claim case database based on the matching results, and use all the found historical claim cases as reference cases for the pending claim; Extracting the claim cause chain in each reference case to be claimed and constructing a claim cause network; Perform mathematical analysis on each claim cause chain and claim cause in the claim cause network to obtain a response strategy for the case to be claimed; specifically, the following steps are used: count the categories and occurrence times of each claim cause chain in the claim cause network, and use a weighted algorithm to calculate the next potential claim cause of the case to be claimed; wherein, the calculation process of the weighted algorithm is as follows: confirm that the claim cause of the case to be claimed is the next claim cause in each claim cause chain, and use the next claim cause in each claim cause chain as the claim cause to be calculated in the claim cause chain; multiply the number of occurrences of each claim cause chain by the category number of the claim cause chain with its own claim cause to be calculated, and obtain the corresponding calculation result of the claim cause to be calculated; and use the calculation result The largest claim cause to be calculated is used as the next potential claim cause of the case to be claimed; specifically, it also includes: taking the first claim cause of each claim cause chain as the origin factor, taking the claim cause with the most correlations and the claim cause with the highest betweenness centrality in each claim cause chain as the key claim cause, and taking the origin factor and the key claim cause as the claim material collection direction of the case to be claimed; specifically, it also includes: counting the clustering coefficient of the claim cause of the case to be claimed in the claim cause network, and selecting the neighbor node corresponding to the maximum probability as the claim response direction of the case to be claimed, wherein the clustering coefficient of the claim cause of the case to be claimed refers to: the probability that two neighbor nodes of the claim cause of the case to be claimed are connected to each other; A successful case containing the claim cause of the case to be claimed is output from the reference case to be claimed, and the claim evidence and claim standards of the successful case are extracted and used as a claim reference for the case to be claimed.

2. The construction claim method according to claim 1, characterized in that: The step of extracting the claim cause chain from each reference case to be claimed and constructing a claim cause network includes: For each of the reference cases to be claimed: Read the claim reason in the reference case to be claimed; Extracting key claim information from the claim reason and obtaining the cause of the claim; The chain of causes of claim is formed in the order in which the causes of claim appear; Combine all the claim cause chains and construct a claim cause network represented as an adjacency matrix with the claim cause as the node.

3. The construction claim method according to claim 1, characterized in that: Outputting a successful case containing the claim cause of the pending claim case from the pending claim reference case, and extracting the claim evidence and claim standard of the successful case as a claim reference for the pending claim case, includes: Outputting a preset number of successful cases containing the claim cause chain of the pending claim case from the pending claim reference case; The calculation formula for the claim amount, claim evidence and claim negotiation process in the successful case are extracted and used as a reference for the claim case to be claimed.

4. The construction claim method according to claim 3, characterized in that: Also includes: Identify one or more claim cause chains for the pending claim case; Calculate the proportion of all successful cases corresponding to each claim cause chain in all pending claim reference cases to obtain the claim success rate of the corresponding claim cause chain; The claim cause chains exceeding a preset ratio are screened as the claim cause chains for the pending claim cases when executing the claim.

5. A construction claim device, characterized in that: include: Case building unit, used to collect historical claim cases and build a claim case database; A word library building unit is used to extract the causes of claims from the historical claim cases and build a word library of causes of claims; a matching unit, configured to match the claim cause of the pending claim case in a claim cause vocabulary, and find all historical claim cases containing the claim cause of the pending claim case in the claim case database based on the matching results, and use all the found historical claim cases as reference cases for the pending claim; A network construction unit, configured to extract a claim cause chain from each of the reference cases to be claimed and construct a claim cause network; A mathematical analysis unit is used to perform mathematical analysis on each claim cause chain and claim cause in the claim cause network to obtain a response strategy for the case to be claimed; specifically, the unit comprises: counting the categories and the number of occurrences of each claim cause chain in the claim cause network, and using a weighted algorithm to calculate the next potential claim cause of the case to be claimed; wherein, the calculation process of the weighted algorithm is: confirming that the claim cause of the case to be claimed is the next claim cause in each claim cause chain, and using the next claim cause in each claim cause chain as the claim cause to be calculated in the claim cause chain; multiplying the number of occurrences of each claim cause chain by the number of categories of the claim cause chain with its own claim cause to be calculated, and obtaining the corresponding calculation result of the claim cause to be calculated; The calculation result is the largest claim cause to be calculated as the next potential claim cause of the case to be claimed; specifically, it also includes: taking the first claim cause of each claim cause chain as the origin factor, taking the claim cause with the most correlations and the claim cause with the highest betweenness centrality in each claim cause chain as the key claim cause, and taking the origin factor and the key claim cause as the claim material collection direction of the case to be claimed; specifically, it also includes: counting the clustering coefficient of the claim cause of the case to be claimed in the claim cause network, and selecting the neighbor node corresponding to the maximum probability as the claim response direction of the case to be claimed, wherein the clustering coefficient of the claim cause of the case to be claimed refers to: the probability that two neighbor nodes of the claim cause of the case to be claimed are connected to each other; The claim reference unit is used to output a successful case containing the claim cause of the case to be claimed from the reference case to be claimed, and to extract the claim evidence and claim standards of the successful case as a claim reference for the case to be claimed.

6. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein: When the processor executes the computer program, the construction claim method according to any one of claims 1 to 4 is implemented.

7. A computer-readable storage medium, characterized in that The computer-readable storage medium stores a computer program, which, when executed by a processor, causes the processor to perform the construction claim method according to any one of claims 1 to 4.