A hoisting method for a refining tower
Through detailed preparation and pre-installation work at the construction site, combined with the use of crawler cranes, the problems of inconvenient operation and high-altitude operating risks in the hoisting of large refined towers were solved, and an efficient and safe hoisting process was achieved, significantly saving costs and time.
Patent Information
- Application Number
- CN202111672013.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-31
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2041-12-31
AI Technical Summary
When hoisting large-scale refining towers, existing technical methods are inconvenient, laborious, and risky to operate at high altitudes, resulting in high cost and time consumption.
The construction site preparation and foundation treatment are carried out first, steel pipe scaffolding, prefabricated installation of ancillary facilities and electrical lighting are erected, and crawler cranes are used to gradually complete equipment hoisting, reducing high-altitude operations and ensuring safety and efficiency.
It significantly reduces the hoisting cost and time, improves safety and efficiency, reduces the risk of high-altitude operations, and achieves efficient hoisting of the refining tower.
Smart Images

Figure CN114348882B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of refining towers, and in particular to a hoisting method for a refining tower. Background Art
[0002] The refining tower is a tower-type gas-liquid contact device for refining. By utilizing the different volatilities of the components in the mixture, that is, the different vapor pressures of the components at the same temperature, the light components (low-boiling substances) in the liquid phase are transferred to the gas phase, and the heavy components (high-boiling substances) in the gas phase are transferred to the liquid phase, thereby achieving the purpose of separation. The refining tower is also a mass transfer and heat transfer device that is widely used in petrochemical production.
[0003] In the prior art, when hoisting a refining tower, generally, a small or multi-stage refining tower is hoisted first and then the parts on the refining tower are installed. However, when hoisting a large (generally weighing 200 tons) refining tower, the tower is hoisted first and then the parts on the surface are installed by climbing the refining tower. This is not only inconvenient and laborious to operate, but also has a great risk of high-altitude operations. Summary of the invention
[0004] Based on the technical problem that the existing refined tower hoisting method adopts hoisting first and then climbing the refined tower to install the components on its surface, which is not only inconvenient and laborious to operate, but also has a great risk of high-altitude operations, the present invention proposes a hoisting method for a refined tower.
[0005] A method for hoisting a refining tower proposed by the present invention comprises the following steps:
[0006] S1: First, clean up the construction site and clear away obstacles on the transportation route of the refining tower;
[0007] S2: Arrange the construction site, preset five saddles at the construction site, and perform foundation treatment on the areas of the five saddles. Use an excavator to level and compact the main device area before the equipment enters the site, and reinforce the foundation of some areas on the driving route. Restore the equipment after unloading;
[0008] S3: After the equipment is brought to the site, the ladder platform of the equipment is installed first. After the ladder platform is completed, a full-height steel pipe scaffolding is set up on both sides of the refining tower, and then the thermal insulation work of the equipment is completed. Only the five saddle-shaped supports that affect the construction area cannot be constructed for the time being;
[0009] S4: While installing the insulation and ladder platform on site, prefabrication and installation of the auxiliary pipelines of the refining tower are carried out;
[0010] S5: Then install electrical lighting facilities;
[0011] S6: Insulate the attached pipelines;
[0012] S7: After all the auxiliary facilities of the refining tower are installed, the final inspection is carried out. After the inspection is correct, the equipment is hoisted. During the hoisting, wait for the double lifting machine to lift the equipment up 500mm and leave the support. The installation personnel will immediately arrange the insulation finishing of the parts where the support affects the insulation of the equipment. The finishing work is completed as quickly as possible. After completion, the final hoisting of the refining tower is carried out.
[0013] S8: After the 1250-ton crawler crane is selected and assembled, it is moved to the lifting station and the main lifting rigging of the 1250-ton crawler crane is set. Then the tail rigging of the 400-ton crawler crane is set. Then the pipelines or platforms that hinder the lifting are removed, and a 200-ton super-lifting counterweight is placed in advance for trial lifting. The 1250-ton crawler crane and the 400-ton crawler crane slowly lift the hooks to make the equipment 0.2m away from the saddle vehicle.
[0014] S9: Observe the stress of the crane, rigging and balance beam, check the foundation of the crane, verify the weight of the equipment, and start the formal lifting after confirming safety. First, let the 1250-ton crawler crane continue to lift the hook, and the 400-ton crawler crane cooperates with the lifting equipment to make the equipment upright, and then remove the 400-ton crawler crane rigging, the 1250-ton crawler crane is lifted to a working radius of 23m, and the 200-ton super-lifting counterweight is monitored off the ground. The 1250-ton crawler crane rotates counterclockwise toward the direction of the equipment foundation, and adjusts the boom so that the equipment is directly above its foundation. The 1250-ton crawler crane retracts the hook, and the installation unit confirms and adjusts the equipment position, slowly retracts the hook to put the equipment in place. After the installation unit confirms that the equipment has been fixed and the conditions for unhooking have been met, remove the lifting rigging to complete the lifting of the refined tower.
[0015] Preferably, the refining tower paint type is SB1, the outer surface of the refining tower body is wrapped with 0.2mm thick aluminum foil for protection, the insulation is 120mm thick high-temperature glass wool, and the outer protective layer material is 0.7mm galvanized aluminum thin steel plate.
[0016] Preferably, the refined tower lighting facilities are energy-saving LED explosion-proof flange lights, energy-saving LED explosion-proof guardrail lights, explosion-proof aviation flash obstacle lights and explosion-proof aviation flash obstacle lights. The lighting circuit is N19, the cable model specification is ZB-YJV-1KV 2*2.5+PE2.5, and it is protected by DN20 galvanized steel pipe.
[0017] Preferably, the foundation adopts a multi-layer backfill structure. The bottom of the foundation is flattened with an excavator and then the bottom foundation trench is pressed with a press. Rubble is used to fill the ground with a thickness of 350mm-450mm, and then crushed stone with a particle size of 10mm-25mm is spread and filled tightly. Finally, 50mm of stone chips and stone powder mixture is laid and compacted. Finally, a 25-ton vibratory roller is used to slowly and repeatedly roll the ground in the order of light then heavy, edge first then middle, until there are no obvious wheel marks and the crushed stone is not squeezed or moved. The ground after rolling should be level with the existing road surface.
[0018] Compared with the prior art, the present invention provides a method for hoisting a refining tower, which has the following beneficial effects:
[0019] 1. Compared with the traditional hoisting method, the hoisting method of the refining tower significantly saves the hoisting cost. The total cost of the hoisting method of the existing technology is about 2 million yuan, and the cost of the method of first installation and then hoisting is about 500,000 yuan. Among them, the construction of the saddle foundation of this scheme has a total cost of about 50,000 to 60,000 yuan, which is negligible compared with the total hoisting cost;
[0020] 2. Compared with the traditional hoisting method, the hoisting method of the refining tower significantly saves the hoisting time. The hoisting method of the prior art takes about 90 days, while the hoisting method of this scheme takes about 30 days;
[0021] 3. After the components on the refining tower are installed, the total weight of the refining tower will be increased to about 300 tons. At this time, only a main crane of about 1,250 tons is needed to achieve safe lifting. Compared with the traditional 1,200-ton main crane, the cost has increased by about 10,000 yuan, which is negligible compared to the total lifting cost, but it brings significant advantages of time saving, labor saving and safety.
[0022] 4. The hoisting method of the refining tower reduces high-altitude operations and construction costs. The high-altitude engineering is completed on the ground, which is safe and reliable, and reduces unsafe factors to a minimum. All installation works of the tower body are completed at one time, realizing efficient hoisting of the refining tower. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 The present invention is a flowchart of a method for hoisting a refining tower. DETAILED DESCRIPTION
[0024] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0025] In the description of the present invention, it is necessary to understand that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0026] Reference Figure 1 , a method for hoisting a refining tower comprises the following steps:
[0027] Step 1: First, clean up the construction site and clear all obstacles on the transportation route of the refining tower. There must be no hard obstacles over 1 meter in the cleared area. After the refining tower docks at the Land and Sea Port Terminal, it will be transported to the construction site by a large-scale transportation company using a modular vehicle;
[0028] Step 2: Arrange the construction site, preset five saddles at the construction site, and perform foundation treatment on the areas of the five saddles. Use an excavator to level and compact the main device area before the equipment enters the site, and reinforce the foundation of some areas on the driving route. Restore the equipment after unloading. Since the installation time of the auxiliary facilities of the refining tower is relatively long, the foundation of the five saddles needs to be treated to prevent the lower layer of the foundation from causing the equipment to bend. The saddle concrete foundation is 6 meters * 2.5 meters, with a total of 5;
[0029] Step 3: After the equipment arrives at the site, the unpacking acceptance of the equipment is first carried out. After the acceptance is qualified, the preparation work for the installation of the auxiliary facilities begins. During the preparation period for the installation of the auxiliary facilities, the staff needs to prepare the handover and re-test of the equipment foundation in advance to ensure the installation of the equipment, and prepare the purchase of the corresponding auxiliary materials such as pads in advance. Then, the ladder platform of the equipment is installed first. After the ladder platform is completed, a full-hall steel pipe scaffolding is set up on both sides of the refined tower, and then the thermal insulation work of the equipment is carried out. The insulation work of the refined tower equipment is completed, leaving only five saddle-shaped supports that affect the construction area and cannot be constructed temporarily. The steel pipe scaffolding is 65 meters long, 6 meters high, and 1.2 meters wide;
[0030] Step 4: While the insulation and ladder platform are being installed on site, the auxiliary pipelines of the refining tower are prefabricated and installed. There are a total of 17 pipelines. The large-diameter pipelines are 163-PL-53152-200-B25E-ST1, 163-PL-53085-350-A1H-ST1, 163-PG-53135-900-A26E-P, 163-PL-53136-250-A26E-ST1, 163-PL-53082-150-A1H-ST1, of which 163-PL-53085-350-A1H-ST1 and 163-PG-53135-900-A26E-P 82-150-A1H-ST1 is a Hastelloy pipe made of N10675. This pipeline was prefabricated in a special material warehouse and transported to the site for installation. 163-PL-53152-200-B25E-ST1, 163-PG-53135-900-A26E-P, and 163-PL-53136-250-A26E-ST1 are all stainless steel pipes made of 022Cr17Ni12Mo2. These three pipelines were prefabricated on Road 6B and installed after prefabrication. The remaining 12 utility pipelines were prefabricated on site and installed after prefabrication.
[0031] Step 5: Install the electrical lighting facilities, including the tower lights. The N19 circuit threading tube needs to be installed in advance, the cable laying is completed, and all lighting installation work of the refining tower is completed. After the installation of the refining tower is completed, a temporary power supply is connected to meet the requirements of the tower lights.
[0032] Step 6: Insulate the auxiliary pipelines. Since the five material pipelines and steam pipelines all need to be insulated, and four pipelines need steam heating, it is necessary to prepare the steam heating work in advance, and perform heat preservation after the steam heating is completed;
[0033] Step 7: After all the auxiliary facilities of the refining tower are installed, the final inspection is carried out. After the inspection is correct, the equipment is hoisted. When the equipment is lifted by the double lifting machine 500mm away from the support, the installation personnel will immediately arrange for the insulation finishing of the parts where the support affects the insulation of the equipment. The finishing work is completed as quickly as possible, and after completion, the final hoisting of the refining tower is carried out;
[0034] Step 8: After selecting a 1250-ton crawler crane and completing assembly, walk to the hoisting station and set up the main hoisting rigging of the 1250-ton crawler crane. Then use the 400-ton crawler crane to enter the tail position and set up the tail rigging of the 400-ton crawler crane. Then remove the pipelines or platforms that hinder the hoisting, place a 200-ton super-lifting counterweight in advance, and conduct a trial hoisting. The 1250-ton crawler crane and the 400-ton crawler crane slowly lift the hooks to make the equipment 0.2m away from the saddle vehicle.
[0035] Step 9: Observe the stress of the crane, rigging and balance beam, check the foundation of the crane, verify the weight of the equipment, and start the formal lifting after confirming safety. First, let the 1250-ton crawler crane continue to lift the hook, and the 400-ton crawler crane cooperates with the lifting equipment to make the equipment upright, and then remove the 400-ton crawler crane rigging, 1250-ton crawler crane to the working radius of 23m, monitor the 200-ton super-lifting counterweight off the ground, 1250-ton crawler crane counterclockwise rotation toward the direction of the equipment foundation, adjust the boom, so that the equipment is located directly above its foundation, 1250-ton crawler crane hook back, the installation unit confirms and adjusts the equipment position, slowly hook back, put the equipment in place, after the installation unit confirms that the equipment has been fixed and has met the conditions for unhooking, remove the lifting rigging, and complete the lifting of the refined tower.
[0036] In the present invention, the refining tower coating type is SB1, the outer surface of the refining tower body is wrapped with 0.2mm thick aluminum foil for protection, the insulation is 120mm thick high-temperature glass wool, and the outer protective layer material is 0.7mm galvanized aluminum thin steel plate;
[0037] The lighting facilities of the refined tower are energy-saving LED explosion-proof flange lamps, energy-saving LED explosion-proof guardrail lamps, explosion-proof aviation flash obstacle lights (low-intensity light) and explosion-proof aviation flash obstacle lights (medium-intensity light). The lighting circuit is N19, and the cable model specification is ZB-YJV-1KV 2*2.5+PE2.5, which is protected by DN20 galvanized steel pipes.
[0038] The foundation adopts a multi-layer backfill structure. The bottom of the foundation is flattened with an excavator and then the bottom foundation trench is pressed with a press. The rubble is used to fill the thickness of 350mm-450mm, and then gravel with a particle size of 10mm-25mm is spread. The filling is tight, and then 50mm of stone chips and stone powder mixture is laid and compacted. Finally, a 25-ton vibratory roller is used to slowly roll the ground repeatedly in the order of light then heavy, edge first then middle, until there are no obvious wheel marks and the gravel is not squeezed or moved. The ground after rolling should be level with the existing road surface.
[0039] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A method for hoisting a refining tower, characterized in that: The following steps are involved: S1: First, clean up the construction site and clear away obstacles on the transportation route of the refining tower; S2: Arrange the construction site, preset five saddles at the construction site, and perform foundation treatment on the areas of the five saddles. Use an excavator to level and compact the main device area before the equipment enters the site, and reinforce the foundation of some areas on the driving route. Restore the equipment after unloading; S3: After the equipment is brought to the site, the ladder platform of the equipment is installed first. After the ladder platform is completed, a full-height steel pipe scaffolding is set up on both sides of the refining tower, and then the thermal insulation work of the equipment is completed. Only the five saddle-shaped supports that affect the construction area cannot be constructed for the time being; S4: While the insulation and ladder platform are being installed on site, the auxiliary pipelines of the refining tower are prefabricated and installed; S5: Then install electrical lighting facilities; S6: Insulate the attached pipelines; S7: After all the auxiliary facilities of the refining tower are installed, the final inspection is carried out. After the inspection is correct, the equipment is hoisted. During the hoisting, wait for the double lifting machine to lift the equipment up 500mm and leave the support. The installation personnel will immediately arrange the insulation finishing of the parts where the support affects the insulation of the equipment. The finishing work is completed as quickly as possible. After completion, the final hoisting of the refining tower is carried out. S8: After the 1250-ton crawler crane is selected and assembled, it is moved to the lifting station and the main lifting rigging of the 1250-ton crawler crane is set. Then the tail rigging of the 400-ton crawler crane is set. Then the pipelines or platforms that hinder the lifting are removed, and a 200-ton super-lifting counterweight is placed in advance for trial lifting. The 1250-ton crawler crane and the 400-ton crawler crane slowly lift the hooks to make the equipment 0.2m away from the saddle vehicle. S9: Observe the stress of the crane, rigging and balance beam, check the foundation of the crane, verify the weight of the equipment, and start the formal lifting after confirming safety. First, let the 1250-ton crawler crane continue to lift the hook, and the 400-ton crawler crane cooperates with the lifting equipment to make the equipment upright, and then remove the 400-ton crawler crane rigging, the 1250-ton crawler crane is lifted to a working radius of 23m, and the 200-ton super-lifting counterweight is monitored off the ground. The 1250-ton crawler crane rotates counterclockwise toward the direction of the equipment foundation, and adjusts the boom so that the equipment is directly above its foundation. The 1250-ton crawler crane retracts the hook, and the installation unit confirms and adjusts the equipment position, slowly retracts the hook to put the equipment in place. After the installation unit confirms that the equipment has been fixed and the conditions for unhooking have been met, remove the lifting rigging to complete the lifting of the refined tower.
2. The method for hoisting a refining tower according to claim 1, characterized in that: The refining tower paint type is SB1. The outer surface of the refining tower body is wrapped with 0.2mm thick aluminum foil for protection. The insulation is made of 120mm thick high-temperature glass wool, and the outer protective layer material is 0.7mm galvanized aluminum thin steel plate.
3. The method for hoisting a refining tower according to claim 1, characterized in that: The refined tower lighting facilities are energy-saving LED explosion-proof flange lights, energy-saving LED explosion-proof guardrail lights, explosion-proof aviation flash obstacle lights and explosion-proof aviation flash obstacle lights.
4. The method for hoisting a refining tower according to claim 1, characterized in that: The foundation adopts a multi-layer backfill structure.