A BIM technology-based operation and maintenance model establishing method

By establishing models according to the needs of operation and maintenance zones during the construction phase, and then refining and lightweighting them, the problem of the construction model being unable to be continuously used was solved, and the efficient transformation and three-dimensional visualization management of the operation and maintenance model were achieved.

CN114386149BActive Publication Date: 2025-12-16CHINA CONSTR FIRST DIV GROUP CONSTR & DEV +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210029602.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-12
Publication Date
2025-12-16
Estimated Expiration
2042-01-12

AI Technical Summary

Technical Problem

The existing BIM models used in the construction phase cannot be continuously used during the conversion to operation and maintenance models due to different modeling requirements, resulting in repetitive work and low efficiency.

Method used

During the construction phase, models are established according to the needs of operation and maintenance zones. These models are then integrated using modeling software, refined, and lightweighted. Finally, the models are imported into the operation and maintenance platform for data association, enabling three-dimensional visualization management.

Benefits of technology

This effectively avoids redundant modeling, ensures the quality of the operation and maintenance model, provides a three-dimensional visualization medium for the subsequent operation and maintenance platform, and improves work efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114386149B_ABST
    Figure CN114386149B_ABST
Patent Text Reader

Abstract

The application discloses a kind of based on BIM technology's operation and maintenance model establishment method, comprising: establishing construction phase model modeling standard, zoning table, construction phase sample file, operation and maintenance project list, construction phase BIM model is established, construction phase BIM model is refined, and operation and maintenance phase BIM model is obtained, operation and maintenance phase BIM model is lightweight processing, and lightweight operation and maintenance BIM model is obtained, lightweight operation and maintenance BIM model is imported into operation and maintenance platform, and data association is carried out with operation and maintenance management database.The application is established according to the demand of operation and maintenance partition when modeling in construction phase, and the model of partition is established into a whole according to boundary condition, and then refined and imported into operation and maintenance platform, and connected with information marker point.Thereby, effectively avoid construction, operation and maintenance preparation interval a large number of repetitive work or according to operation and maintenance demand resegmentation BIM model, provide display medium for operation and maintenance platform three-dimensional visualization.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The application belongs to the technical field of BIM modeling and construction, and particularly relates to a method for establishing an operation and maintenance model based on BIM technology. BACKGROUND

[0002] BIM technology is a data-based tool applied to engineering design and construction management. Through a parameter model, various project-related information is integrated, shared and transmitted in the whole life cycle of project planning, operation and maintenance, so that engineering and technical personnel can correctly understand and efficiently respond to various building information, and provide a basis for collaborative work for design teams and various construction subjects including building operation units, thereby playing an important role in improving production efficiency, saving costs and shortening construction period. The BIM model has gone through several stages from modeling to construction management, and now to the operation and maintenance model. The BIM model established in the construction stage needs to be converted to the operation and maintenance BIM model in the later stage of the project. The traditional operation and maintenance model is a collection of various professional models after model establishment based on two-dimensional drawings, collision checking and final adjustment. Nowadays, the operation and maintenance model has developed from the traditional two-dimensional model to the current three-dimensional visual model based on BIM. However, in the process of converting the construction model established in the construction stage to the operation and maintenance model, the modeling requirements of the two stages are different, which leads to the fact that the model established in the construction stage cannot be continuously used in the operation and maintenance stage, so the model needs to be re-established in the operation and maintenance stage, resulting in a large amount of repeated work, which not only wastes labor but also makes the work efficiency low. SUMMARY

[0003] In order to solve the above problems, the application provides a method for establishing an operation and maintenance model based on BIM technology to solve the problem that the model established in the construction stage cannot be continuously used in the operation and maintenance stage due to different modeling requirements of the two stages in the process of converting the model established in the construction stage to the operation and maintenance model.

[0004] To achieve the above purpose, the application provides a method for establishing an operation and maintenance model based on BIM technology, which comprises:

[0005] establishing modeling standards, zoning tables and sample files for the construction stage model, and

[0006] establishing modeling standards and operation project lists for the operation stage model;

[0007] establishing a BIM model for the construction stage based on the modeling standards, zoning tables and sample files for the construction stage model;

[0008] refining the BIM model for the construction stage based on the modeling standards for the operation stage model, the operation project lists and the LOD standards for the operation model to obtain a BIM model for the operation stage;

[0009] The BIM model in the operation and maintenance stage is lightweight processed to obtain a lightweight operation and maintenance BIM model;

[0010] The lightweight operation and maintenance BIM model is imported into an operation and maintenance platform and is associated with an operation and maintenance management database.

[0011] According to one specific embodiment of the present application, the construction stage model modeling standards include: project file naming standards, template file establishment standards, two-dimensional family drawing standards, three-dimensional family library management standards and BIM model LOD standards.

[0012] According to one specific embodiment of the present application, the partition table includes a region detail table and a system detail table, wherein the region detail table is divided according to floors, regions, machine rooms and key regions, and the system detail table is divided according to strong current systems, weak current systems, fire alarm systems, water supply and drainage systems, sprinkler systems, fire hydrant systems, ventilation and smoke control systems and air conditioning water systems.

[0013] According to one specific embodiment of the present application, the construction stage template files include civil engineering template files and mechanical and electrical template files.

[0014] According to one specific embodiment of the present application, the operation and maintenance project list includes an energy list, a building automation equipment list, a security list and a fire alarm equipment list, wherein the energy list includes electric energy meters, water meters, gas meters and heat meters; the building automation equipment list includes air conditioning equipment, fans, water supply and drainage equipment, centralized control lighting, electric water valves, electric air valves, coil pipes and fire water pumps; the security list includes video monitoring and access control; and the fire list includes automatic fire alarm and gas fire extinguishing equipment.

[0015] According to one specific embodiment of the present application, the construction stage BIM model is established based on the construction stage model modeling standards, the partition table and the construction stage template files, and includes:

[0016] According to the construction stage model modeling standards and the construction stage template files, a plurality of regional construction BIM models are established under the partition model boundary conditions set in the partition table, wherein the regional construction BIM model includes a building structure model, a mechanical and electrical pipeline model and a decoration model.

[0017] The plurality of regional construction BIM models of at least one layer are connected into one whole according to the boundary coordinates of the plurality of regional construction BIM models to obtain the construction stage BIM model.

[0018] According to one specific embodiment of the present application, the method further includes: performing collision detection on the construction stage BIM model, readjusting conflict components in the construction stage BIM model, and inputting construction stage annotation information on the readjusted construction stage BIM model, wherein the construction stage annotation information includes geometric information data and construction method information data of the construction stage BIM model.

[0019] According to one specific embodiment of the present application, based on the operation and maintenance stage model modeling standard, the operation and maintenance project list and the operation and maintenance model LOD standard are used to refine the construction stage BIM model to obtain the operation and maintenance stage BIM model, which includes:

[0020] According to the operation and maintenance stage model modeling standard and the operation and maintenance project list, the equipment size and appearance, controlled valve and motor components in the construction stage BIM model are refined under the partition model boundary conditions set in the partition table. The refinement standard is according to the operation and maintenance LOD standard. The operation and maintenance stage annotation information is input into the refined construction stage BIM model to obtain the operation and maintenance stage BIM model. The operation and maintenance stage annotation information includes geometric information data and construction method information data of the operation and maintenance stage BIM model.

[0021] According to one specific embodiment of the present application, the operation and maintenance stage BIM model is subjected to lightweight processing to obtain a lightweight operation and maintenance BIM model, which includes:

[0022] The operation and maintenance stage BIM model is scaled as a whole, and the number of polygons of the operation and maintenance stage BIM model is reduced to convert it into a lightweight operation and maintenance BIM model.

[0023] According to one specific embodiment of the present application, the lightweight operation and maintenance BIM model is imported into the operation and maintenance platform and associated with the operation and maintenance management database, which includes:

[0024] A configuration table is established according to the partition table and imported into the operation and maintenance management database. The configuration table stores the identity code of each model component in the partition table, including the boundary coordinates of the model component, the belonging area and the system code.

[0025] The lightweight operation and maintenance BIM model is imported into the operation and maintenance platform, and a one-to-one mapping relationship is established between the geometric information data and the operation information data of the model component of the lightweight operation and maintenance BIM model and the identity code of each model component in the configuration table. The operation information data includes real-time monitoring information data and operation and maintenance information data.

[0026] Compared with the prior art, the BIM technology-based operation and maintenance model establishment method provided by the application can effectively avoid the repeated work caused by the different BIM application points and use requirements during the construction and operation and maintenance preparation period, or the BIM model is segmented again according to the operation and maintenance requirements, thereby guaranteeing the quality of the final operation and maintenance model and providing a display medium for the subsequent three-dimensional visualization of the operation and maintenance platform. BRIEF DESCRIPTION OF DRAWINGS

[0027] Fig. 1 FIG. 1 is a flow chart of a BIM technology-based operation and maintenance model establishment method according to an embodiment of the application.

[0028] Fig. 2 FIG. 2 is a flow chart of a construction stage BIM model establishment method according to an embodiment of the application.

[0029] Fig. 3 FIG. 3 is a flow chart of a method for associating an operation and maintenance model with a database according to an embodiment of the application. DETAILED DESCRIPTION

[0030] In order to make the concept and idea of the application more clear to those skilled in the art, the application is described in detail below in combination with specific embodiments. It should be understood that the embodiments given herein are only a part of all possible embodiments of the application. Those skilled in the art can make improvements, modifications or replacements to part or all of the following embodiments after reading the description of the application, and these improvements, modifications or replacements are also included in the scope of the application.

[0031] In this document, the terms "first", "second" and other similar words are not intended to imply any order, number and importance, but are only used to distinguish different elements. In this document, the terms "one", "a" and other similar words are not intended to mean that there is only one thing, but that the description is only directed to one of the things, and the things can have one or more. In this document, the terms "contain", "include" and other similar words are intended to mean the logical relationship between each other, and cannot be regarded as the spatial structural relationship. For example, "A includes B" is intended to mean that B logically belongs to A, but not that B is located inside A in space. In addition, the meaning of the terms "contain", "include" and other similar words should be regarded as open, not closed. For example, "A includes B" is intended to mean that B belongs to A, but B does not necessarily constitute all of A, and A can also include C, D, E and other elements.

[0032] In this document, the terms "example" and "exemplary" are used as adjectives to indicate a non-limiting example. The use of these terms is not intended to limit or narrow the scope of the disclosure in any way.

[0033] Embodiment 1

[0034] Additional aspects and advantages of embodiments of the present application will be set forth in part in the description that follows, and in part will be obvious from the description, or can be learned by practice of embodiments of the present application. The aspects and advantages of embodiments of the present application will be realized and attained by means of the instrumentalities fully set forth in the written description and attached drawings. Figs. 1-3 According to the embodiment of the present application, a BIM technology-based operation and maintenance model establishment method is provided, which comprises the following steps:

[0035] S1: establishing construction phase model modeling standards, zoning tables and construction phase sample files, and establishing operation and maintenance phase model modeling standards and operation and maintenance project lists.

[0036] S2: establishing a construction phase BIM model based on the construction phase model modeling standards, the zoning tables and the construction phase sample files.

[0037] S3: performing collision detection on the construction phase BIM model, readjusting the conflicting components in the construction phase BIM model, and inputting construction phase annotation information on the readjusted construction phase BIM model, wherein the construction phase annotation information comprises geometric information data and construction method information data of the construction phase BIM model.

[0038] S4: refining the construction phase BIM model based on the operation and maintenance phase model modeling standards, the operation and maintenance project lists and the operation and maintenance model LOD standards to obtain an operation and maintenance phase BIM model.

[0039] S5: performing lightweight processing on the operation and maintenance phase BIM model to obtain a lightweight operation and maintenance BIM model.

[0040] S6: importing the lightweight operation and maintenance BIM model into an operation and maintenance platform and associating the lightweight operation and maintenance BIM model with an operation and maintenance management database.

[0041] Specifically, in step S1, the construction phase model modeling standards include: project file naming standards, template file establishment standards, two-dimensional family drawing standards, three-dimensional family library management standards, and BIM model LOD standards. The BIM model LOD standards further include: building and structure LOD200, local LOD300, mechanical and electrical pipeline LOD300, equipment room LOD300, decoration LOD300, and outdoor landscape LOD200. The zoning table can be divided according to two categories or a combination of two categories, including a region detail table and a system detail table, wherein the region detail table is divided according to floor, region, machine room, and key region, and the system detail table is divided according to strong current system, weak current system, fire alarm system, water supply and drainage system, sprinkler system, fire hydrant system, ventilation and smoke control system, and air conditioning water system. For example, the building and structure and decoration can establish BIM models according to the region boundaries specified in the first type of zoning; the mechanical and electrical systems can establish BIM models according to the boundaries after the combination of the two types. The operation and maintenance project list includes an energy list, a building automation equipment list, a security list, and a fire alarm equipment list, wherein the energy list includes an electricity meter, a water meter, a gas meter, and a heat meter; the building automation equipment list includes air conditioning equipment, a fan, water supply and drainage equipment, centralized lighting, an electric water valve, an electric air valve, a coil pipe, and a fire water pump; the security list includes video monitoring and access control; and the fire list includes automatic fire alarm and gas fire extinguishing equipment. The operation and maintenance phase model modeling standards are further refined operation and maintenance related models based on the modeling annotations of the construction model, including controlled component LOD400, action component LOD400, key special area LOD400, and operation and maintenance project list, and the standard LOD fineness standard in the list according to the model building standard. The construction phase template file includes a civil engineering template file and a mechanical and electrical template file. The civil engineering template file further includes establishing an axis network, elevation, loading civil engineering commonly used families, and the mechanical and electrical template file further includes importing civil engineering axis network elevation, selecting applicable pipe accessory family, pipe system definition naming, CAD export setting, and filter setting.

[0042] Specifically, step S2 includes the following steps based on the construction phase model modeling standards, the zoning table, and the construction phase template file to establish the construction phase BIM model:

[0043] S21: According to the construction phase model modeling standards and the construction phase template file, a plurality of regional construction BIM models are established under the zoning model boundary conditions set in the zoning table, wherein the regional construction BIM model includes a building structure model, a mechanical and electrical pipeline model, and a decoration model.

[0044] S22: According to the boundary coordinates of the plurality of regional construction BIM models of at least one layer, the plurality of regional construction BIM models are connected into one whole to obtain the construction phase BIM model.

[0045] The regional construction BIM model established by the embodiment of the application is a three-dimensional BIM model established according to two-dimensional construction drawings, the building, structure model, mechanical and electrical pipeline model and decoration model are established according to the partition model boundary conditions specified in the partition table, the model fineness is established according to the construction stage model building standard, and the regional construction BIM models of the current layer or multiple layers are connected together as a whole according to the partition boundary conditions to form the construction stage BIM model.

[0046] Specifically, step S4 refines the construction stage BIM model based on the operation and maintenance stage model modeling standard, the operation and maintenance project list and the operation and maintenance model LOD standard to obtain the operation and maintenance stage BIM model, which includes:

[0047] According to the operation and maintenance stage model modeling standard and the operation and maintenance project list, the equipment size and appearance, controlled valve and motor components in the construction stage BIM model are refined under the partition model boundary conditions set in the partition table, the refinement processing standard is according to the operation and maintenance standard LOD standard, and the operation and maintenance stage annotation information is input into the refined construction stage BIM model to obtain the operation and maintenance stage BIM model, wherein the operation and maintenance stage annotation information includes geometric information data and construction method information data of the operation and maintenance stage BIM model. The construction stage BIM model is refined and converted into the operation and maintenance stage BIM model, which is applied in the construction stage for checking collision, visualization, simulation verification and the like, and the construction stage BIM model needs to be converted into the operation and maintenance model which is applied in the operation and maintenance in the future. According to the regions or functional rooms that need to be refined in the partition table and the operation and maintenance project list and the operation and maintenance stage model modeling standard, the model is refined according to the actual size and appearance of the equipment and components determined later, so that the model can be called in the operation and maintenance platform interface to reflect the actual action.

[0048] Specifically, step S5 performs lightweight processing on the operation and maintenance stage BIM model to obtain the lightweight operation and maintenance BIM model, which includes: scaling the operation and maintenance stage BIM model as a whole, and reducing the number of polygons of the operation and maintenance stage BIM model to convert it into the lightweight operation and maintenance BIM model. In the lightweight process, the whole model is scaled as a whole so that its size can be included in the operation and maintenance platform, the number of polygons of the model is reduced, and the model is converted into a surface model. In addition, in the lightweight conversion process, the light is simulated in the software to make the overall display of the converted model more realistic.

[0049] Specifically, step S6 imports the lightweight operation and maintenance BIM model into the operation and maintenance platform and associates it with the operation and maintenance management database, which specifically includes the following steps:

[0050] S61: Establish a configuration table according to the partition table and import it into the operation and maintenance management database, the configuration table stores the identity code of each model component in the partition table, including the boundary coordinates of the model component, the belonging region and the system code.

[0051] S62: Import the lightweight operation and maintenance BIM model into the operation and maintenance platform, and establish a one-to-one mapping relationship between the geometric information data and the operation information data of the model components of the lightweight operation and maintenance BIM model and the identity codes of each model component in the configuration table, wherein the operation information data includes real-time monitoring information data and operation and maintenance information data.

[0052] A configuration table is formulated, and the model component identity codes in each partition table are added to the configuration table, and the identity codes are stored in the configuration table in the form of boundary coordinates + belonging area + system code. The operation and maintenance platform will associate each model component unique identity in the configuration table with the operation and maintenance management database, import the existing geometric information, name, parameter, etc. in the lightweight operation and maintenance BIM model into the operation and maintenance management database, call the model to be displayed in the operation and maintenance platform, and display on the screen. According to the operation and maintenance project list, the data to be displayed of the corresponding model in the operation and maintenance management database is hung with the model unique identity number in a non-geometric information manner, so that the non-geometric information data changes are directly displayed at the corresponding model information hanging place, including real-time monitoring data, operation and maintenance information, etc.

[0053] The operation and maintenance BIM model established by the embodiment of the application includes but is not limited to the following application scenarios when in use, for example, viewing the operation of floor equipment, calling the floor building structure and equipment model through the operation and maintenance management database, loading the equipment operation condition in the information hanging place, for example, viewing the operation of the ventilation system, loading the ventilation system pipeline model and equipment model into the platform through the operation and maintenance management database, loading the equipment operation condition in the information hanging place, the action condition of the electric control valve, the values of various sensors and the equipment energy consumption, for example, when the equipment needs to be regularly maintained, the device all machine rooms or areas can be adjusted into the platform through the operation and maintenance management database model unique identity code after the pre-warning, and all information data related to the equipment are displayed, and the maintenance reminder is pushed to the maintenance personnel through the operation and maintenance platform.

[0054] In summary, the operation and maintenance model establishment method based on the BIM technology provided by the application establishes a construction model according to the partition demand during the modeling in the construction stage, integrates the models established in the partitions into a whole according to the boundary conditions through the modeling software, refines and lightens the models, finally imports the BIM model into the operation and maintenance platform, and hangs the model with the information marking point, and finally realizes the three-dimensional visual operation and maintenance management. Thus, the repetitive work caused by the different BIM application points and use demands during the construction and operation and maintenance period is effectively avoided, the quality of the final operation and maintenance model is ensured, and the display medium for the subsequent three-dimensional visual operation and maintenance platform is provided.

[0055] The concepts, principles and ideas of the present application are described in detail above in connection with the specific embodiments (including examples and instances). It should be understood by those skilled in the art that the embodiments of the present application are not limited to the above-mentioned forms, and any possible improvements, replacements and equivalents of the steps, methods, systems and components in the above-mentioned embodiments can be made by those skilled in the art after reading the present application, which should be considered to fall within the scope of the present application. The scope of protection of the present application is only subject to the claims.

Claims

1. A method for establishing an operation and maintenance model based on BIM technology, characterized in that, The method comprises: establishing a construction phase model modeling standard, a zoning table and a construction phase template file, and establishing a maintenance phase model modeling standard and a maintenance project list; the zoning table comprises a region detail table and a system detail table, wherein the region detail table is divided according to floors, regions, machine rooms and key regions, and the system detail table is divided according to strong current systems, weak current systems, fire alarm systems, water supply and drainage systems, sprinkler systems, fire hydrant systems, ventilation and smoke control systems and air conditioning water systems; a construction phase BIM model is established based on the construction phase model modeling standard, the zoning table and the construction phase template file; the construction phase BIM model is refined based on the maintenance phase model modeling standard, the maintenance project list and a maintenance model LOD standard to obtain a maintenance phase BIM model; the maintenance phase BIM model is subjected to lightweight processing to obtain a lightweight maintenance BIM model, and in the conversion process, light is simulated in the software to make the overall display of the converted model more realistic; the lightweight maintenance BIM model is imported into a maintenance platform and associated with a maintenance management database, including establishing a configuration table based on the zoning table and importing it into the maintenance management database, wherein the configuration table stores the identity code of each model component in the zoning table, including the boundary coordinates of the model component, the region to which it belongs and the system code; the construction phase BIM model is established based on the construction phase model modeling standard, the zoning table and the construction phase template file, and a plurality of region construction BIM models are established under the zoning model boundary conditions set in the zoning table according to the construction phase model modeling standard and the construction phase template file, wherein the region construction BIM model comprises a building structure model, a mechanical and electrical pipeline model and a decoration model; the building structure model and the decoration model are established according to the region boundaries specified in the region detail table in the zoning table, and the mechanical and electrical pipeline model is established according to the boundaries combined from the region detail table and the system detail table in the zoning table; a plurality of region construction BIM models of at least one layer are connected into a whole according to their boundary coordinates to obtain a construction phase BIM model.

2. The BIM technology-based operation and maintenance model establishing method according to claim 1, characterized in that, The construction phase model modeling standard comprises a project file naming standard, a template file establishment standard, a two-dimensional family drawing standard, a three-dimensional family library management standard and a BIM model LOD standard. 3.The BIM technology-based operation and maintenance model establishing method according to claim 1, characterized in that, The construction phase template file comprises a civil engineering template file and a mechanical and electrical template file.

4. The BIM technology-based operation and maintenance model establishing method according to claim 1, characterized in that, The maintenance project list comprises an energy list, a building automation equipment list, a security list and a fire alarm equipment list, wherein the energy list comprises an electricity meter, a water meter, a gas meter and a heat meter; the building automation equipment list comprises air conditioning equipment, a fan, water supply and drainage equipment, centralized lighting, an electric water valve, an electric air valve, a coil pipe and a fire water pump; the security list comprises video monitoring and access control; and the fire alarm equipment list comprises automatic fire alarm and gas fire extinguishing equipment.

5. The BIM technology-based operation and maintenance model establishing method according to claim 1, characterized in that, The method further comprises: performing collision detection on the construction stage BIM model, readjusting conflicting components in the construction stage BIM model, and inputting construction stage annotation information on the readjusted construction stage BIM model, wherein the construction stage annotation information comprises geometric information data and construction method information data of the construction stage BIM model.

6. The BIM technology-based operation and maintenance model establishing method according to claim 1, characterized in that, The construction stage BIM model is refined based on the operation and maintenance stage model modeling standard, the operation and maintenance project list, and the operation and maintenance model LOD standard to obtain an operation and maintenance stage BIM model. According to the operation and maintenance stage model modeling standard and the operation and maintenance project list, the equipment size and appearance, controlled valve and motor components in the construction stage BIM model are refined under the partition model boundary conditions set in the partition table, the refinement standard is in accordance with the operation and maintenance LOD standard, and operation and maintenance stage annotation information is inputted on the refined construction stage BIM model to obtain an operation and maintenance stage BIM model, wherein the operation and maintenance stage annotation information comprises geometric information data and construction method information data of the operation and maintenance stage BIM model.

7. The BIM technology-based operation and maintenance model establishing method according to claim 1, characterized in that, The operation and maintenance stage BIM model is subjected to lightweight processing to obtain a lightweight operation and maintenance BIM model. The operation and maintenance stage BIM model is scaled as a whole, and the number of polygons of the operation and maintenance stage BIM model is reduced to convert it into a lightweight operation and maintenance BIM model. 8.The BIM technology-based operation and maintenance model establishing method according to claim 1, characterized in that, The lightweight operation and maintenance BIM model is imported into an operation and maintenance platform and associated with an operation and maintenance management database, and the operation and maintenance platform further comprises: The lightweight operation and maintenance BIM model is imported into an operation and maintenance platform, and a one-to-one mapping relationship is established between geometric information data and operation information data of model components of the lightweight operation and maintenance BIM model and identity codes of each model component in the configuration table, wherein the operation information data comprises real-time monitoring information data and operation and maintenance information data.

Citation Information

Patent Citations

  • BIM-based constructional engineering operation and maintenance management platform constructing method and system

    CN107515974A

  • Building operation and maintenance management-oriented BIM model lightweight reconstruction method

    CN113360999A