A hydraulic hammer pipeline traction structure for foundation construction and its working method

By using a hydraulic hammer pipeline traction structure with multiple rows of moving components and a winch system in offshore wind turbine foundation construction, the problems of pipeline damage and difficulty in towing are solved, achieving efficient movement of pipelines and preventing joint damage, improving construction efficiency and equipment life.

CN114560413BActive Publication Date: 2024-10-18JIANGSU HENGTONG LAND OCEAN ENG CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202210294962.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-24
Publication Date
2024-10-18
Estimated Expiration
2042-03-24

AI Technical Summary

Technical Problem

During the foundation construction of offshore wind turbines, hydraulic hammer pipelines are easily damaged during the construction process, and are difficult to drag and organize, leading to problems of wear and joint damage.

Method used

A hydraulic hammer pipeline traction structure for foundation construction is designed, which uses multiple rows of moving components and a winch system. It is connected to the hydraulic pipeline through a traction rope to simplify pipeline movement. Guide rollers and winches are used to lift and organize the hydraulic pipeline during the piling process. , to prevent joint damage.

Benefits of technology

It effectively prevents hydraulic pipeline wear and joint damage, simplifies the pipeline movement and arrangement process, and improves construction efficiency and equipment service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114560413B_ABST
    Figure CN114560413B_ABST
Patent Text Reader

Abstract

The present invention provides a foundation construction hydraulic hammer pipeline traction structure and a working method thereof, comprising: a pile-driving ship and a foundation pile, wherein the pile-driving ship is provided with a deck, the foundation pile is provided with a hydraulic hammer, the deck is provided with a hydraulic station, the hydraulic hammer is connected to one end of a hydraulic pipeline, and the other end of the hydraulic pipeline is connected to the hydraulic station, the deck is also provided with multiple rows of moving components, the hydraulic pipeline on the deck is arranged on the moving component, multiple winches are arranged on the periphery of the moving component, the winches are connected to the hydraulic pipeline on the deck through a traction rope, the structure is simple, the hydraulic pipeline is easy to move, and the wear of the hydraulic pipeline is also prevented, and the hydraulic pipeline can be lifted and adjusted in its height direction during the construction process, effectively preventing the technical problem of damage to the hydraulic pipeline joint.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of offshore wind turbine installation, and in particular to a foundation construction hydraulic hammer pipeline traction structure and a working method thereof. Background Art

[0002] During the installation of offshore wind turbines, foundation construction is an important part. In shallow water areas, single pile foundations account for the largest proportion. The single piles of offshore wind turbines are large in size and heavy in weight, and they are deep in the mud and have high precision requirements. Hydraulic hammers are often used for piling during construction, and pile grippers are used for precision adjustment. The hydraulic hammer is lifted to the top of the single pile by a floating crane for hammering. There is a long hydraulic pipeline between the hydraulic hammer and the hydraulic pump station. Due to the high height of the hydraulic hammer at the beginning of piling, a large number of pipelines are suspended in the air, which generates a large force on the joints between the pipelines and the hydraulic hammer, and is easily damaged by long-term use. For this reason, the crane auxiliary hook or the small crane of the pile-driving ship is often used to lift the hydraulic pipeline during construction, which puts higher requirements on the equipment of the crane. At the same time, there are a large number of hydraulic pipelines on the pile-driving ship, which are difficult to drag during construction and difficult to sort out after construction. At the same time, the hydraulic pipeline is in direct contact with the deck, and dragging is easy to cause wear. Summary of the invention

[0003] In order to solve the above technical problems, the present invention provides a foundation construction hydraulic hammer pipeline traction structure and a working method thereof, which has a simple structure, is convenient for moving the hydraulic pipeline, is also beneficial for preventing the wear of the hydraulic pipeline, and effectively prevents the occurrence of technical problems such as damage to the hydraulic pipeline joints.

[0004] In order to achieve the above object, the technical solution of the present invention is as follows:

[0005] A foundation construction hydraulic hammer pipeline traction structure comprises: a pile-driving ship and foundation piles, wherein the pile-driving ship is provided with a deck, the foundation piles are provided with a hydraulic hammer, the deck is provided with a hydraulic station, the hydraulic hammer is connected to one end of a hydraulic pipeline, and the other end of the hydraulic pipeline is connected to the hydraulic station, the deck is also provided with multiple rows of moving components, the hydraulic pipeline on the deck is arranged on the moving components, multiple winches are provided on the periphery of the moving components, and the winches are connected to the hydraulic pipeline on the deck through traction ropes.

[0006] The present invention provides a foundation construction hydraulic hammer pipeline traction structure and a working method thereof, which has a simple structure, is convenient for moving the hydraulic pipeline, is also beneficial for preventing the wear of the hydraulic pipeline, and effectively prevents the technical problem of damage to the hydraulic pipeline joint.

[0007] As a preferred technical solution, the pile-driving ship is provided with a pile gripper, the pile gripper is connected to a first winch, the first winch transmits a first traction rope, and the first traction rope is connected to a hydraulic pipeline through a guide roller.

[0008] As a preferred technical solution, the moving parts in the nth row of moving components and the moving parts in the n+1th row of moving components are arranged in a staggered distribution.

[0009] As a preferred technical solution, the number of moving parts in the nth row of moving components is x; the number of moving parts in the n+1th row of moving components is x+1.

[0010] As a preferred technical solution, the spacing between each two adjacent rows of moving components is equidistant.

[0011] As an optimal technical solution, the moving part includes: a base, moving wheels are arranged at the four corners of one side of the base, baffles are connected to both ends of the other side of the base, the baffles and the base form a groove cavity, and the hydraulic pipelines on the deck are placed in the groove cavity.

[0012] As a preferred technical solution, the winch includes: a second winch, the second winch is arranged on one side of the moving component, the second winch transmits a second traction rope, and the second winch is connected to the hydraulic pipeline on the deck through the second traction rope.

[0013] As a preferred technical solution, the winch includes: a third winch, the third winch is arranged at one end of the moving component, the third winch transmits a third traction rope, and the third winch is connected to the hydraulic pipeline on the deck through the third traction rope.

[0014] As a preferred technical solution, the second winch and the third winch are respectively movably connected to the deck.

[0015] As a preferred technical solution, an upper structure is provided on the deck, and the upper structure is arranged opposite to the pile gripper.

[0016] The present invention also provides a working method of a hydraulic hammer pipeline traction structure for foundation construction, comprising the following steps:

[0017] Before construction, S1 customized the movable parts according to the specifications and length of the hydraulic pipelines, and placed them one by one under the hydraulic pipelines on the deck;

[0018] S2 installs the movable second winch and third winch on the deck, installs the first winch on the top of the pile gripper, and installs the guide roller matching the first winch;

[0019] S3 Before piling, the first winch tightens the lifting hydraulic pipeline through the guide roller, and the floating crane follows to lift the hydraulic hammer so that the pipeline between the hydraulic hammer and the first winch is in a relaxed state until the hydraulic hammer falls into place on the single pile;

[0020] During S4 piling, the hydraulic hammer gradually moves downward, and the first winch follows to lower the hydraulic pipeline, and at the same time, the lowered hydraulic pipeline is placed on the moving parts in sequence;

[0021] After S5 piling is completed, the floating crane lifts the hydraulic hammer and moves it in the upward construction direction until it is lowered to the deck. At the same time, the second winch and the third winch cooperate with each other to recover the hydraulic pipeline;

[0022] After the S6 hydraulic hammer is in place, the second winch and the third winch cooperate with each other to tidy up the hydraulic pipelines and pull the hydraulic pipelines to the stacking area. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a front view of a hydraulic hammer pipeline traction structure for foundation construction;

[0024] Figure 2 It is a top view of a hydraulic hammer pipeline traction structure for foundation construction;

[0025] Figure 3 This is a structural diagram of a moving part in a pipeline traction structure of a hydraulic hammer for foundation construction;

[0026] Among them, 1-pile-driving ship; 2-deck; 3-foundation pile; 4-hydraulic hammer; 5-hydraulic pipeline; 6-moving assembly; 61-moving part; 7-winch; 8-pile gripper; 9-first winch; 10-first traction rope; 11-guide roller; 12-traction rope; 13-hydraulic station; 14-second winch; 15-second traction rope; 16-third winch; 17-third traction rope; 18-hydraulic pipeline on the deck; 19-base; 20-moving wheel; 21-baffle; 22-upper structure; 23-trough cavity. DETAILED DESCRIPTION

[0027] It should be noted that the use of terms such as "first", "second", and "third" to limit components is only for the convenience of distinguishing the corresponding components. Unless otherwise stated, the above terms have no special meaning and therefore cannot be understood as limiting the scope of protection of the present invention.

[0028] The preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings.

[0029] It can be understood that the present invention achieves the purpose of the present invention through some embodiments.

[0030] like Figure 1As shown, the present invention provides a hydraulic hammer pipeline traction structure for foundation construction, comprising: a pile-driving ship 1 and a foundation pile 3, the pile-driving ship 1 is provided with a deck 2, the foundation pile 3 is provided with a hydraulic hammer 4, the deck 2 is provided with a hydraulic station 13, the hydraulic hammer 4 is connected to one end of a hydraulic pipeline 5, the other end of the hydraulic pipeline 5 is connected to the hydraulic station 13, the deck 2 is further provided with multiple rows of moving components 6, the hydraulic pipeline 18 on the deck is arranged on the moving component 6, a plurality of winches 7 are arranged on the periphery of the moving component 6, the winches 7 are pulled by The guide rope 12 is connected to the hydraulic pipeline 18 on the deck; the pile-driving ship 1 is provided with a pile gripper 8, the pile gripper 8 is connected to a first winch 9, the first winch 9 transmits a first traction rope 10, and the first traction rope 10 is connected to the hydraulic pipeline 5 through a guide roller 11; the moving parts 61 in the n-th row of moving components 6 and the moving parts 61 in the n+1-th row of moving components 6 are arranged in a staggered distribution; the number of moving parts 61 in the n-th row of moving components 6 is x; the number of moving parts 61 in the n+1-th row of moving components 6 is x+1; each phase The spacing between two adjacent rows of moving components 6 is equidistant; the moving member 61 includes: a base 19, moving wheels 20 are arranged at the four corners of one side of the base 19, baffles 21 are connected to the two ends of the other side of the base 19, the baffles 21 and the base 19 form a groove cavity 23, and the hydraulic pipeline 18 on the deck is placed in the groove cavity 23; the winch 7 includes: a second winch 14 and a third winch 16, the second winch 14 and the third winch 16 are respectively movably connected to the deck 2, the second winch 14 is arranged on the moving On one side of the moving component 6, the second winch 14 transmits a second traction rope 15, and the second winch 14 is connected to the hydraulic pipeline 18 on the deck through the second traction rope 15; the third winch 16 is arranged at one end of the moving component 6, and the third winch 16 transmits a third traction rope 17, and the third winch 16 is connected to the hydraulic pipeline 18 on the deck through the third traction rope 17; its structure is simple, which is convenient for moving the hydraulic pipeline, and is also beneficial to preventing the wear of the hydraulic pipeline, and effectively preventing the technical problem of damage to the hydraulic pipeline joint.

[0031] The present invention provides a hydraulic hammer pipeline traction structure for foundation construction, wherein the movable member 61 is preferably a trolley, and the hydraulic pipeline 18 on the deck is placed in the trolley. At the same time, a winch 7 is provided on the deck 2, and the winch 7 is convenient for traction of the hydraulic pipeline 5 and is also beneficial for preventing the wear of the hydraulic pipeline 5. A first winch 9 is provided on the top of the pile gripper 8, and the first winch 9 transmits a first traction rope 10, which is connected to the hydraulic pipeline 5 through a guide roller 11, so that the hydraulic pipeline 5 can be lifted and adjusted in its height direction during construction, effectively preventing the technical problem of damage to the joint of the hydraulic pipeline 5.

[0032] like Figure 2As shown, the present invention provides a pipeline traction structure for a hydraulic hammer for foundation construction, wherein the deck 2 is further provided with a plurality of rows of moving components 6, the hydraulic pipeline 18 on the deck is arranged on the moving components 6, a plurality of winches 7 are arranged on the periphery of the moving components 6, and the winches 7 are connected to the hydraulic pipeline 18 on the deck through a traction rope 12; a pile gripper 8 is provided on the pile driving ship 1, a first winch 9 is connected to the top of the pile gripper 8, the first winch 9 transmits a first traction rope 10, and the first traction rope 10 is connected to the hydraulic pipeline 5 through a guide roller 11; the moving parts 61 in the nth row of moving components 6 are staggeredly distributed with the moving parts 61 in the n+1th row of moving components 6; the number of the moving parts 61 in the nth row of moving components 6 is x; the number of the moving parts 61 in the n+1th row of moving components 6 is x; The number of moving parts 61 in a row of moving components 6 is x+1; the spacing between each two adjacent rows of moving components 6 is equidistant; the second winch 14 is arranged on one side of the moving component 6, the second winch 14 transmits a second traction rope 15, and the second winch 14 is connected to the hydraulic pipeline 18 on the deck through the second traction rope 15; the third winch 16 is arranged at one end of the moving component 6, the third winch 16 transmits a third traction rope 17, and the third winch 16 is connected to the hydraulic pipeline 18 on the deck through the third traction rope 17; the second winch 14 and the third winch 16 are respectively movably connected to the deck 2, and the deck 2 is provided with an upper structure 22, and the upper structure 22 is arranged opposite to the pile gripper 8. Multiple winches 7 cooperate with multiple rows of moving components 6 to solve the technical problems of difficulty in dragging the hydraulic pipeline 5 during construction and difficulty in arranging the hydraulic pipeline 5 after construction, and effectively avoid the technical problems of direct contact between the hydraulic pipeline 5 and the deck 2 and easy wear of the hydraulic pipeline 5 caused by dragging.

[0033] like Figure 3 As shown, the present invention provides a moving part, the moving part 61 includes: a base 19, moving wheels 20 are arranged at the four corners of one side of the base 19, baffles 21 are connected to the two ends of the other side of the base 19, the baffles 21 and the base 19 form a groove cavity 23, the hydraulic pipeline 18 on the deck is placed in the groove cavity 23, the structure is simple, the operation is convenient, and the hydraulic pipeline 18 on the deck is easy to move.

[0034] The present invention provides a working method of a hydraulic hammer pipeline traction structure for foundation construction, comprising the following steps:

[0035] S1 customizes the movable parts 61 matching the hydraulic pipeline 5 according to its specifications and length before construction, and places the movable parts 61 one by one under the hydraulic pipeline 18 on the deck;

[0036] S2: Install the movable second winch 14 and the third winch 16 on the deck 2, install the first winch 9 on the top of the pile gripper 8, and install the guide roller 11 matching the first winch 9;

[0037] S3 Before piling, the first winch 9 first tightens the lifting hydraulic pipeline 5 through the guide roller 11, and the floating crane (not shown) follows to lift the hydraulic hammer 4 so that the pipeline between the hydraulic hammer 4 and the first winch 9 is in a relaxed state until the hydraulic hammer 4 falls into place on the single pile;

[0038] During the piling process S4, the hydraulic hammer 4 gradually moves downward, and the first winch 9 follows to lower the hydraulic pipeline 5, and at the same time, the lowered hydraulic pipeline 5 is placed on the moving member 61 in sequence;

[0039] After the piling is completed at S5, the floating crane lifts the hydraulic hammer 4 and moves it in the direction of the upper building 22 until it is lowered onto the deck 2. At the same time, the second winch 14 and the third winch 16 cooperate with each other to recover the hydraulic pipeline 5.

[0040] S6 After the hydraulic hammer 4 is in place, the second winch 14 and the third winch 16 cooperate with each other to tidy up the hydraulic pipeline 5 and pull the hydraulic pipeline 5 to the stacking area.

[0041] The present invention provides a hydraulic hammer pipeline traction structure for foundation construction and a working method thereof. The structure is simple, and the hydraulic pipeline is easy to move and prevent wear of the hydraulic pipeline. At the same time, the hydraulic pipeline is lifted and adjusted in its height direction during construction, and the technical problem of damage to the hydraulic pipeline joint is effectively prevented.

[0042] It is to be understood that the present invention is described by some embodiments, and it is known to those skilled in the art that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. Therefore, the present invention is not limited by the specific embodiments disclosed herein, and all various changes or equivalent substitutions falling within the scope of the claims of the present application are included. In addition, under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. Therefore, the present invention is not limited by the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of the present application are within the scope protected by the present invention.

Claims

1. A hydraulic hammer pipeline traction structure for foundation construction, characterized in that: include: A pile-driving ship and foundation piles, wherein the pile-driving ship is provided with a deck, the foundation piles are provided with a hydraulic hammer, the deck is provided with a hydraulic station, the hydraulic hammer is connected to one end of a hydraulic pipeline, the other end of the hydraulic pipeline is connected to the hydraulic station, a plurality of rows of moving components are also provided on the deck, the hydraulic pipeline on the deck is arranged on the moving components, a plurality of winches are provided on the periphery of the moving components, and the winches are connected to the hydraulic pipeline on the deck through traction ropes.

2. The foundation construction hydraulic hammer pipeline traction structure according to claim 1 is characterized in that: The pile-driving ship is provided with a pile gripper, the pile gripper is connected to a first winch, the first winch transmits a first traction rope, and the first traction rope is connected to a hydraulic pipeline through a guide roller.

3. The pipeline traction structure for hydraulic hammer in foundation construction according to claim 1 is characterized in that: The moving parts in the nth row of moving components and the moving parts in the n+1th row of moving components are arranged in a staggered distribution.

4. The pipeline traction structure for hydraulic hammer in foundation construction according to claim 1 is characterized in that: The spacing between each two adjacent rows of moving components is equidistant, the number of moving components in the nth row of moving components is x; the number of moving components in the n+1th row of moving components is x+1.

5. The pipeline traction structure for hydraulic hammer in foundation construction according to claim 3 is characterized in that: The moving part comprises: a base, moving wheels are arranged at the four corners of one side of the base, baffles are connected to the two ends of the other side of the base, the baffles and the base form a groove cavity, and the hydraulic pipelines on the deck are placed in the groove cavity.

6. The pipeline traction structure for hydraulic hammer in foundation construction according to claim 1, characterized in that: The winch includes: a second winch, the second winch is arranged on one side of the moving component, the second winch transmits a second traction rope, and the second winch is connected to the hydraulic pipeline on the deck through the second traction rope.

7. The pipeline traction structure for hydraulic hammer in foundation construction according to claim 6, characterized in that: The winch also includes: a third winch, which is arranged at one end of the moving component, and the third winch transmits a third traction rope, and the third winch is connected to the hydraulic pipeline on the deck through the third traction rope.

8. The pipeline traction structure for hydraulic hammer in foundation construction according to claim 7, characterized in that: The second winch and the third winch are respectively movably connected to the deck.

9. The pipeline traction structure for hydraulic hammer in foundation construction according to claim 2, characterized in that: An upper structure is arranged on the deck, and the upper structure is arranged opposite to the pile gripper.

10. The working method of the pipeline traction structure of the foundation construction hydraulic hammer according to any one of claims 1 to 9, characterized in that: The following steps are involved: Before construction, S1 customized the movable parts according to the specifications and length of the hydraulic pipelines, and placed them one by one under the hydraulic pipelines on the deck; S2 installs the movable second winch and third winch on the deck, installs the first winch on the top of the pile gripper, and installs the guide roller matching the first winch; S3 Before piling, the first winch tightens the lifting hydraulic pipeline through the guide roller, and the floating crane follows to lift the hydraulic hammer so that the pipeline between the hydraulic hammer and the first winch is in a relaxed state until the hydraulic hammer falls into place on the single pile; During S4 piling, the hydraulic hammer gradually moves downward, and the first winch follows to lower the hydraulic pipeline, and at the same time, the lowered hydraulic pipeline is placed on the moving parts in sequence; After S5 piling is completed, the floating crane lifts the hydraulic hammer and moves it in the upward construction direction until it is lowered to the deck. At the same time, the second winch and the third winch cooperate with each other to recover the hydraulic pipeline; After the S6 hydraulic hammer is in place, the second winch and the third winch cooperate with each other to tidy up the hydraulic pipelines and pull the hydraulic pipelines to the stacking area.