Design method of power quality value-added service scheme considering multi-party participation in harmonic control

By constructing a cost and demand assessment model for nonlinear user power quality management, and combining it with value-added service models such as equipment leasing and ownership transfer, the problem of insufficient demand analysis for harmonic management of nonlinear users was solved, the efficiency of harmonic management and user satisfaction were improved, and the cost and benefits of power quality management were optimized.

CN114580935BActive Publication Date: 2024-11-01ELECTRIC POWER RES INST STATE GRID SHANXI ELECTRIC POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210236094.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-11
Publication Date
2024-11-01
Estimated Expiration
2042-03-11

AI Technical Summary

Technical Problem

Existing technologies lack sufficient analysis of the demand for harmonic mitigation by nonlinear users, resulting in weak willingness to mitigate harmonics. Users' sensitivity to harmonic problems and economic losses are unclear. The distribution of power quality monitoring points on the grid side leads to insufficient understanding of users' power environment. Furthermore, there is a lack of research on value-added service models for harmonic mitigation.

Method used

A nonlinear user power quality governance cost and demand assessment model is constructed using the analytic hierarchy process (AHP). Based on the factors to be considered in harmonic governance, a hierarchical indicator system is established. A value-added service model combining governance equipment leasing and ownership transfer is proposed, involving the power grid company, equipment manufacturers, and users, and clarifying the roles and benefits of each party.

Benefits of technology

It improves the efficiency of harmonic control, clarifies users' demand for high-quality power supply, enables quantitative assessment of the potential for value-added services of high-quality power supply, enhances user satisfaction and the market competitiveness of power grid companies, reduces control costs, and achieves cost optimization and benefit maximization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114580935B_ABST
    Figure CN114580935B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for designing a power quality value-added service scheme considering the participation of multiple parties in harmonic governance. First, the harmonic governance demand of nonlinear users is analyzed from three aspects: equipment failure rate and potential risks, economic loss degree, and potential benefits obtained from the increase of transformer load rate after governance; then, based on the principle of hierarchical analysis method, combined with the factors to be considered in harmonic governance, an index system is established in layers to construct a nonlinear user power quality governance cost and demand evaluation model; finally, combined with the user's harmonic governance needs, a value-added service model combining governance equipment leasing with property transfer is proposed, as well as the roles and benefits of the three parties of power grid companies, equipment manufacturers and nonlinear users in the value-added service. The present invention can clarify the user's demand for high-quality power supply, realize the quantitative evaluation of the potential of high-quality power supply value-added services, promote the development of related work of high-quality power supply value-added services, and guide users to actively participate in the governance of power quality to improve governance efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power quality value-added services, and in particular to a method for designing a power quality value-added service solution taking into account the participation of multiple parties in harmonic control. Background Art

[0002] "Pricing based on quality" will become the direction of the future power market. At present, a large number of distributed energy sources are connected to the grid, large-capacity impact loads are connected, and non-linear loads appear in large numbers in the distribution network, and users have an increasingly strong need for high-quality power supply. Value-added services have broad space in the future power market, and diversified power value-added services will become an important means of competition for power sales companies.

[0003] The access of a large number of nonlinear loads has caused serious harmonic pollution. The presence of a large number of harmonic currents in the power grid will not only produce additional losses and waste of electric energy, but also accelerate the aging of power equipment and shorten its service life. In addition, harmonic currents will also reduce the utilization rate of the power supply equipment capacity and increase the equipment failure rate. What is more serious is that the interaction between harmonic currents and system-side impedance further deteriorates the voltage quality of the public power grid, affecting the stable operation of other power loads connected to the shared bus. Harmonic pollution has become a problem that cannot be ignored in the power grid.

[0004] At present, the key problem of harmonic governance of nonlinear users lies in the insufficient analysis of the demand for user governance. There are two main reasons: first, nonlinear users are the dominant factor causing harmonic pollution problems, but their own sensitivity to harmonic problems and the economic losses caused are unclear, the demand for harmonic governance is vague, and the willingness to govern is weak; second, most of the power quality monitoring points are distributed on the grid side, resulting in unequal information obtained by users, and thus insufficient understanding of their own power consumption environment.

[0005] Many scholars have conducted research on the value-added service model of high-quality power supply. Some scholars have proposed a pricing model for voltage sag control value-added services based on the satisfaction of both power supply and power users, introducing a satisfactory price strategy to alleviate the cost contradiction between the two parties. Some scholars have also proposed a set of high-quality power value-added service strategies for "trading old for new" for users' voltage sag sensitive equipment. However, research on value-added services is still limited to the field of voltage sag. The content and operation model of the harmonic control value-added service model and its actual engineering verification are issues that need to be urgently addressed. Summary of the invention

[0006] In view of the above problems, the purpose of the present invention is to provide a method for designing a power quality value-added service solution taking into account the participation of multiple parties in harmonic governance, which can clarify users' demand for high-quality power supply, realize quantitative evaluation of the potential of high-quality power supply value-added services, promote the development of related work of high-quality power supply value-added services, and guide users to actively participate in power quality governance and improve governance efficiency.

[0007] The technical solution is as follows:

[0008] A design method for a power quality value-added service solution considering multi-party participation in harmonic control, including:

[0009] Step 1: Analyze the harmonic control requirements of nonlinear users from three aspects: equipment failure rate and potential risks, economic loss degree, and potential benefits obtained from the increase in transformer load rate after control;

[0010] Step 2: Based on the principle of hierarchical analysis method and combined with the factors to be considered in harmonic control, a hierarchical index system is established to construct a nonlinear user power quality control cost and demand evaluation model;

[0011] Step 3: Based on the users' harmonic control needs, a value-added service model combining control equipment leasing and property transfer is proposed, as well as the roles and benefits of the power grid company, equipment manufacturers and nonlinear users in the value-added service under this model.

[0012] Furthermore, the analysis of the need for harmonic control of nonlinear users specifically includes: evaluating whether the user is at risk of resonance based on whether the user has installed capacitors and the number of capacitors installed; judging the potential room for improving the load rate based on whether the user's transformer load rate is too low; and judging the need for control of additional equipment losses based on the length of the line and the number of transformers installed by the user.

[0013] Furthermore, the construction of the nonlinear user power quality management cost and demand evaluation model specifically includes:

[0014] Step 2.1: Establish the fuzzy relationship matrix

[0015] Suppose there are m evaluation contents and s evaluation levels; then the evaluation content set is:

[0016] U={μ1,μ2,μ3,…,μ m} (1)

[0017] The evaluation level set is:

[0018] V={v1,v2,v3,…,v s} (2)

[0019] Among them, any two elements in the sets U and V are matched to form the Descartes product of m evaluation contents (μ i ,v j ); the element pair (μ i ,v j ) is denoted as f ij , then the m-order fuzzy relationship matrix F is:

[0020]

[0021] Step 2.2: Classify the evaluation

[0022] According to the characteristics of harmonic control value-added services, the domain V of the demand evaluation level of harmonic control value-added services is defined as: V = {no need, general need, need, relatively need, very need}; because the evaluation content is fuzzy, fuzzy theory is used to fuzzify it, and the value domain η is obtained as follows:

[0023] η={0~2,2~4,4~6,6~8,8~10}

[0024] Step 2.3: Comprehensive evaluation

[0025] Among the indicators at the same level, weights are used to distinguish the importance of an indicator. The weight vector is represented by a normalized vector W. The weight vector W is combined with the fuzzy matrix F to obtain the fuzzy comprehensive evaluation membership vector ξ of the evaluated object:

[0026] ξ=W·F=[ξ1, ξ2,...,ξ s ] (4)

[0027] In the formula, ξ j The membership degree of this state to the jth evaluation level will be ξ j The maximum value corresponds to each level in the evaluation domain V, and the evaluation result is obtained, and then the value-added service plan is customized for each type of user.

[0028] Furthermore, the value-added service model combining the leasing of treatment equipment with the transfer of property rights is specifically as follows:

[0029] The power grid company provides consulting services to users, assesses their governance needs, and designs governance plans; equipment manufacturers provide governance equipment at their expense; users obtain high-quality power supply services by leasing governance equipment and sign a lease contract with the power grid company. Later, users can choose to transfer the ownership of the governance equipment or continue to lease it.

[0030] Furthermore, under the value-added service model combining the leasing of treatment equipment with the transfer of property rights, the benefits to the three parties are as follows:

[0031] (1) After the lease expires, the user chooses to transfer the ownership of the equipment. According to the depreciation rate of the equipment, the user pays the transfer fee and obtains the ownership of the equipment. The total income of the user at this time is P u , the total cost is C u , the formula is as follows:

[0032]

[0033] In the formula, t is year, T is the service life of the treatment equipment, n is the lease term, r is the discount rate, ΔC loss The economic loss caused by harmonics is reduced every year for users after treatment. u is the initial investment cost of the user, C is the rental fee, and C T is the property transfer fee, ΔC om is the equipment operation and maintenance fee, C p is the equipment cost, C R is the equipment scrapping cost, N is the total number of years;

[0034] The total revenue of the equipment manufacturer includes the rental fee and the equipment ownership transfer fee, and the total cost includes the equipment purchase fee and the equipment operation and maintenance fee during the lease period. Among them, the total revenue of the equipment manufacturer P e , total cost C e for:

[0035]

[0036] (2) After the first lease contract of harmonic control equipment expires, the user chooses to continue leasing. At this time, the user's total income is P u , total cost C u for:

[0037]

[0038] The total revenue of the equipment manufacturer is P e , total cost C e for:

[0039]

[0040] The beneficial effects of the present invention are:

[0041] (1) The present invention takes into account the impact of harmonics on nonlinear users. By establishing a nonlinear user power quality management cost and demand evaluation model, it can guide users to actively participate in power quality management and improve management efficiency.

[0042] (2) The present invention proposes a user governance demand assessment method based on the hierarchical analysis method, which can clarify the user's demand for high-quality power supply, realize the quantitative assessment of the potential of high-quality power supply value-added services, promote the development of related work on high-quality power supply value-added services, and effectively improve user satisfaction and the market competitiveness of power grid companies.

[0043] (3) The present invention proposes a multi-party-participated nonlinear user power quality management value-added service model, analyzes the management effect and cost of the service plan, clarifies the economic benefits of all parties, and provides users with a variety of service plan options. It helps to reduce the investment of power quality management funds of all parties, optimize the power quality management cost and maximize the benefits, and improve user product quality, production efficiency, corporate profits and user market competitiveness. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] Figure 1 This is the governance demand level index system of the present invention.

[0045] Figure 2 It is the value-added service composition structure of the present invention.

[0046] Figure 3 This is the primary wiring diagram of the metallurgical plant in the embodiment. DETAILED DESCRIPTION

[0047] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments. The present invention proposes a multi-party participation harmonic management value-added service model based on the hierarchical analysis method. First, a user harmonic economic loss model is constructed from three dimensions: potential risks such as capacitor explosion induced by harmonic amplification, potential benefits brought by increased transformer load rate, and additional losses caused by harmonics. Secondly, through the hierarchical analysis method, the user's demand for harmonic management is quantified, and the feasibility of implementing the harmonic management value-added service is evaluated. Finally, a harmonic value-added service model combining leasing and property transfer with the joint participation of the power grid company, the user, and the equipment manufacturer is proposed to achieve considerable benefits for the three parties.

[0048] Step 1: Analyze the harmonic control needs of nonlinear users from three aspects: equipment failure rate and potential risks, economic loss degree, and potential benefits obtained from the increase in transformer load rate after control:

[0049] First, the equipment failure rate and potential risks mainly include accidents caused by explosion and combustion of capacitors due to resonance and harmonic amplification. When high-order harmonic current flows into the capacitor, the voltage at both ends of the capacitor will be distorted and the peak value will increase, which may cause explosions, fires, power outages, and even personal injury. Second, harmonic problems will cause additional losses to transformers and lines. Third, many nonlinear users usually have a low transformer load rate to avoid harmonics exceeding national standards. Some users also reduce the transformer load rate and get rid of excess loads to avoid exceeding the standard when harmonics exceed the standard. After these users receive harmonic value-added services, the harmonic content can be effectively reduced, so that the transformer load rate has room for improvement and more loads can be connected.

[0050] Combining the three key influencing factors mentioned above, the harmonic control needs of nonlinear users are analyzed. First, based on whether the user has installed capacitors and the number of capacitors installed, it is evaluated whether the user has the risk of resonance. The potential room for improving the load rate is determined by whether the user's transformer load rate is too low. The need for control of additional equipment losses is determined by the length of the line and the number of transformers installed by the user.

[0051] Step 2: Based on the principle of hierarchical analysis method and combined with the factors that need to be considered in harmonic control, a hierarchical indicator system is established to construct a nonlinear user power quality control cost and demand evaluation model.

[0052] The evaluation model is constructed through hierarchical indicators. Based on the principle of hierarchical analysis method and combined with the factors to be considered in harmonic control, the indicator system is established in layers. The indicator layers are as follows from top to bottom: O = {nonlinear user value-added service demand}, H = {economic loss, potential risk, load factor improvement potential}, and the 11 I-layer indicators included in the H-layer indicators, such as Figure 1 shown.

[0053] 1) Establish fuzzy relationship matrix

[0054] Suppose there are m evaluation contents and s evaluation levels; then the evaluation content set is:

[0055] U={μ1,μ2,μ3,…,μ m} (1)

[0056] The evaluation level set is:

[0057] V={v1,v2,v3,…,v s} (2)

[0058] Among them, any two elements in the sets U and V are matched to form the Descartes product of m evaluation contents (μ i ,v j ); the element pair (μ i ,v j ) is denoted as f ij , then the m-order fuzzy relationship matrix F is:

[0059]

[0060] 2) Classification of evaluation levels

[0061] According to the characteristics of harmonic control value-added services, the domain V of the demand evaluation level of harmonic control value-added services is defined as: V = {no need, general need, need, relatively need, very need}. Because the above evaluation content is fuzzy, fuzzy theory is used to fuzzify it, and the value domain η is obtained as:

[0062] η={0~2,2~4,4~6,6~8,8~10}

[0063] 3) Comprehensive evaluation

[0064] Among the indicators at the same level, weights are used to distinguish the importance of an indicator, which is represented by a normalized vector W. Since there are few level indicators in this paper, their weights are directly determined by experts.

[18] .

[0065] By combining the weight vector W with the fuzzy matrix F, we can get the fuzzy comprehensive evaluation membership vector ξ of the evaluated object:

[0066] ξ=W·F=[ξ1, ξ2,…,ξ s ] (4)

[0067] In the formula, ξ j The membership degree of this state to the jth evaluation level will be ξ j The maximum value corresponds to each level in the evaluation domain V, and the evaluation result is obtained, and then the value-added service plan is customized for each type of user.

[0068] Step 3: Based on the users' harmonic control needs, a value-added service model combining control equipment leasing and property transfer is proposed, as well as the roles and benefits of the power grid company, equipment manufacturers and nonlinear users in the value-added service under this model.

[0069] In combination with the user's harmonic control needs, a value-added service model combining control equipment leasing and property transfer is proposed, such as Figure 2 As shown. The power grid company provides consulting services to users, assesses the user's governance needs, and designs governance plans; the equipment manufacturer provides governance equipment; users obtain high-quality power supply services by leasing governance equipment. Users sign a lease contract with the power grid company. After the contract expires, users have two options: Option 1: Transfer of ownership, that is, purchase of installed equipment; Option 2: Choose to continue leasing. The roles and benefits of the three parties in value-added services are as follows:

[0070] 1) Power Grid Company

[0071] The power grid company has a strong credibility. The power grid company assesses the users' need for governance, contacts equipment manufacturers, designs specific governance plans, including the model, capacity and installation location of the governance equipment, and charges consulting fees. This can generate certain economic benefits and attract users to actively participate in governance, thereby reducing harmonic pollution on the power supply side and improving the company's image.

[0072] 2) Equipment manufacturers

[0073] Equipment manufacturers provide governance equipment support for the power grid and are responsible for the installation and operation and maintenance of the equipment. For equipment manufacturers, they only charge leasing fees and asset transfer fees. Although the profit payback period is longer, the overall sales volume of equipment increases, and the net income obtained may be greater than the profit from direct sales of equipment.

[0074] 3) Non-linear users

[0075] The user submits the governance requirements and load information to the power grid company, which then formulates a governance plan. The three parties sign a contract and pay the fees. The equipment manufacturer then installs and debugs the governance equipment according to the contract. For the user, the scheme design and equipment installation and maintenance are provided by the corresponding personnel, with a small initial investment and low risk. The user can also obtain value-added harmonic governance services, thereby bringing economic benefits.

[0076] The initial costs of equipment manufacturers include: governance equipment costs. The initial costs of users include: consulting service fees, installation and commissioning fees, and rental fees, of which users need to pay consulting service and equipment installation and commissioning fees to the power grid company. The benefits of the three parties under each plan are as follows:

[0077] Solution 1: After the lease expires, the user chooses to transfer the ownership of the equipment. According to the depreciation rate of the equipment, the user pays the transfer fee and obtains the ownership of the equipment. The total income of the user is P u , the total cost is C u , the formula is as follows:

[0078]

[0079] C R =α{C p -F(n)} (7)

[0080] In the formula, t is year, T is the service life of the treatment equipment (year), n is the lease term (year), r is the discount rate, ΔC loss The economic loss caused by harmonics is reduced every year for users after treatment. u is the initial investment cost of the user, C is the rental fee, and C T is the property transfer fee, ΔC om is the equipment operation and maintenance fee (year), C p is the equipment cost, C R is the equipment scrapping cost, and N is the total number of years.

[0081] The total revenue of the equipment manufacturer includes the rental fee and the equipment ownership transfer fee, and the total cost includes the equipment purchase fee and the equipment operation and maintenance fee during the lease period. e , total cost C e for:

[0082]

[0083] Option 2: After the first lease contract of harmonic control equipment expires, choose to continue leasing. The total income of the user at this time is P u , total cost C u for:

[0084]

[0085] The total revenue of the equipment manufacturer is P e , total cost C e for:

[0086]

[0087] Example:

[0088] A metallurgical enterprise is a typical 6-pulse rectifier harmonic source power user, with an average annual power consumption of 20 million kW·h. It is equipped with two distribution transformers, each with a capacity of 2500kV·A and a rated voltage of 10 / 0.4kV. The typical data of each distribution transformer load are: apparent power 2007kV·A, active power 1570kW, reactive power 1250kV·A, power factor 0.782, and the main wiring diagram is as follows: Figure 3 As shown. The 5th, 7th, 11th and 13th harmonics have high content, among which the 5th harmonic current is 24.4A, the 7th harmonic current is 17.4A, the 11th harmonic current is 11.12A, and the 13th harmonic current is 9.36A. According to GB / T14595-1993 "Power Quality Public Grid Harmonics", it cannot meet the requirements, deteriorates the power quality of the power grid, and is not conducive to the safe and economic operation of the power grid. According to the local catalog electricity price of 0.75 yuan / (kW·h), it can be calculated that the annual economic loss of the transformer and transmission line caused by harmonics for this user is 557,900 yuan. Combined with the demand index, it is concluded that the user's governance demand level is relatively needed, so it is necessary to govern.

[0089] Taking the above metallurgical enterprise as an example, after simulation analysis of harmonics, the optimal capacity of the user-side filter is designed according to its harmonic emission characteristics and combined with the actual engineering situation.

[0090] A single tuned filter device with a capacity of 1200kVA was selected for treatment, and the total market price was about 540,000 yuan. Referring to the market price and user scale, the power grid company charged a consulting service fee of 90,000 yuan, that is, the net profit of the power grid company was 90,000 yuan. In addition to obtaining certain economic benefits, the power grid company also attracted users to actively participate in harmonic treatment, thereby improving the power quality of the power grid and enhancing the company's image.

[0091] Assuming that the annual operation and maintenance cost is 10% of the equipment cost, the installation and commissioning fee and consulting service fee are the user's initial investment costs, see Table 1.

[0092] Table 1 Lifespan and partial costs of treatment equipment

[0093]

[0094] Calculate the reduction in loss after governance ΔC loss , the result in this example is 383,900 yuan. The power grid company, equipment manufacturer and user agree on a lease term of n = 5 years based on their own development plans and operation conditions. According to formula (13), the depreciation cost is 125,000 yuan.

[0095] After the first lease period (5 years), the user chooses different options and analyzes the total net income of each party in the two lease periods. Option 1: After the lease expires, the user accepts the asset transfer, pays the transfer fee, and obtains the property rights of the governance equipment. Option 2: After the first lease expires, the user continues to lease the service. The benefits of each party are shown in Table 2.

[0096] Table 2 Lifespan and partial costs of treatment equipment

[0097]

[0098] Comparison of the various options shows that after the first lease period, the net income of the three parties is positive and large when Option 1 or Option 2 is adopted. In actual projects, the selection of each option needs to be considered in combination with the needs of all parties.

Claims

1. A method for designing a power quality value-added service solution considering multi-party participation in harmonic control, characterized in that: include: Step 1: Analyze the harmonic control requirements of nonlinear users from three aspects: equipment failure rate and potential risks, economic loss degree, and potential benefits obtained from the increase in transformer load rate after control; Step 2: Based on the principle of hierarchical analysis method and combined with the factors to be considered in harmonic control, a hierarchical index system is established to construct a nonlinear user power quality control cost and demand evaluation model; Step 3: Based on the users' harmonic control needs, a value-added service model combining control equipment leasing and property transfer is proposed, as well as the roles and benefits of the power grid company, equipment manufacturers and nonlinear users in the value-added service under this model; The analysis of the harmonic control requirements of nonlinear users specifically includes: evaluating whether the user has a risk of resonance based on whether the user has installed capacitors and the number of capacitors installed; judging the potential room for load rate improvement based on whether the user's transformer load rate is too low; judging the control requirements for additional equipment losses based on the length of the line and the number of transformers installed by the user; The construction of the nonlinear user power quality management cost and demand evaluation model specifically includes: Step 2.1: Establish the fuzzy relationship matrix Suppose there are m evaluation contents and s evaluation levels; then the evaluation content set is: U={μ1,μ2,μ3,…,μ m } (1) The evaluation level set is: V={v1,v2,v3,…,v s } (2) Among them, any two elements in the sets U and V are matched to form the Descartes product of m evaluation contents (μ i ,v j ); The element pair (μ i ,v j ) is denoted as f ij , then the m-order fuzzy relationship matrix F is: Step 2.2: Classify the evaluation According to the characteristics of harmonic control value-added services, the domain V of the demand evaluation level of harmonic control value-added services is defined as: V = {no need, general need, need, relatively need, very need}; because the evaluation content is fuzzy, fuzzy theory is used to fuzzify it, and the value domain η is obtained as follows: η={0~2,2~4,4~6,6~8,8~10} Step 2.3: Comprehensive evaluation Among the indicators at the same level, weights are used to distinguish the importance of an indicator, and the weight vector is represented by a normalized vector W; The weight vector W is combined with the fuzzy matrix F to obtain the fuzzy comprehensive evaluation membership vector ξ of the evaluated object: ξ=W·F=[ξ1,ξ2,…,ξ s ] (4) In the formula, ξ j The membership degree of this state to the jth evaluation level will be ξ j The maximum value corresponds to each level in the evaluation domain V, and the evaluation result is obtained, and then the value-added service plan is customized for each type of user; The value-added service model combining the leasing of treatment equipment with the transfer of property rights is specifically as follows: The power grid company provides consulting services to users, assesses their governance needs, and designs governance plans; equipment manufacturers provide governance equipment at their expense; users obtain high-quality power supply services by leasing governance equipment and sign a lease contract with the power grid company. Later, users can choose to transfer ownership of the governance equipment or continue to lease it; Under the value-added service model combining governance equipment leasing and property transfer, the benefits to the three parties are as follows: (1) After the lease expires, the user chooses to transfer the ownership of the equipment. According to the depreciation rate of the equipment, the user pays the transfer fee and obtains the ownership of the equipment. The total income of the user at this time is P u , the total cost is C u , the formula is as follows: C R =α{C p -F(n)} (7) In the formula, t is year, T is the service life of the treatment equipment, n is the lease term, r is the discount rate, ΔC loss The economic loss caused by harmonics is reduced every year for users after treatment. u is the initial investment cost of the user, C is the rental fee, and C T is the property transfer fee, ΔC om is the equipment operation and maintenance fee, C p is the equipment cost, C R is the equipment scrapping cost, N is the total number of years; The total revenue of the equipment manufacturer includes the rental fee and the equipment ownership transfer fee, and the total cost includes the equipment purchase fee and the equipment operation and maintenance fee during the lease period. Among them, the total revenue of the equipment manufacturer P e , total cost C e for: (2) After the first lease contract of harmonic control equipment expires, the user chooses to continue leasing. At this time, the user's total income is P u , total cost C u for: The total revenue of the equipment manufacturer is P e , total cost C e for: