A cascading failure search method and system for a high-proportion renewable energy power system

By calculating the voltage index values ​​of new energy grid connection points and current bus nodes, combined with control measures, we can quickly identify cascading fault sequences of high-proportion new energy power systems, solving the problems of analysis complexity and insufficient adaptability in the existing technology, and achieving Quickly identify and analyze cascading faults in new energy power systems.

CN114638381BActive Publication Date: 2024-10-15CHINA ELECTRIC POWER RESEARCH INSTITUTE CO LTD
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202210167141.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-02-23
Publication Date
2024-10-15
Estimated Expiration
2042-02-23

AI Technical Summary

Technical Problem

The analysis of cascading faults in high-proportion new energy power systems is difficult to consider the complex characteristics and uncertainty factors of the power system, and existing methods have shortcomings in quickly identifying cascading fault sequences.

Method used

By calculating the comprehensive index value of the new energy grid connection point voltage and current bus node voltage, the cascading fault sequence after the initial fault is determined, and combined with control measures to determine whether the system collapses, a cascading fault search method and system is formed.

Benefits of technology

It can quickly identify cascading fault sequences in high-proportion new energy power systems, consider the power characteristics of the power system, reduce the complexity of analysis, and improve the adaptability and accuracy of fault search.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114638381B_ABST
    Figure CN114638381B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and system for searching for cascading failures in a high-proportion renewable energy power system, comprising: determining multiple index values ​​of a high-proportion renewable energy power system after the occurrence of the initial fault according to a preset initial fault; judging whether each index in the multiple index values ​​satisfies a condition that they are all less than a preset threshold value, and obtaining a first judgment result; when they are all less than the preset threshold value, judging whether the current fault falls in a DC or renewable energy near zone, and obtaining a second judgment result; when the fault falls in a DC or renewable energy near zone, calculating a voltage index value of a renewable energy grid-connected point and a comprehensive voltage index value of a flow busbar node; setting a next-level fault according to the maximum value of the voltage index value of a renewable energy grid-connected point and the comprehensive voltage index value of a flow busbar node; adding control measures after the fault, and judging whether the system crashes, and obtaining a third judgment result; when the crash occurs, determining a cascading failure sequence corresponding to the initial fault according to the set fault.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power systems, and more specifically, to a method and system for searching for cascading failures in a high-proportion new energy power system. Background Art

[0002] From the perspective of previous major blackouts in the world, large-scale power outages in the power system are almost always caused by cascading failures. In recent years, many cascading failures related to renewable energy have occurred around the world. For example, in the "November 4" blackout in Western Europe in 2006, the cascading tripping of AC lines caused high-frequency disconnection of wind turbines, which further led to an imbalance in supply and demand, and ultimately caused large-scale power outages. In 2011, there were many cascading disconnection accidents of wind turbines in Jiuquan, Gansu and Zhangjiakou, Hebei. The cause was often a short-circuit failure of the component. The wind turbine was cut off due to the action of low-voltage protection, which further caused high-voltage cascading tripping, and ultimately caused a decrease in the grid frequency due to the loss of a large amount of output. The "9.28" blackout in South Australia in 2016 was caused by severe weather that triggered a chain tripping of lines. The voltage continued to drop, causing the wind turbines to be disconnected from the grid, which then caused the important interconnection lines to trip. The system eventually collapsed due to power imbalance; the "8.9" blackout in the UK in 2019 occurred when the proportion of renewable energy was relatively high (40%). The initial fault was only a line tripping caused by lightning strikes. Subsequently, a series of events caused the overcurrent protection of the renewable energy units to be activated one after another, and the accidental protection of the steam unit led to low-frequency load reduction and distributed energy frequency protection.

[0003] These accidents have typical chain reaction characteristics, which have brought adverse effects on the safe and stable operation of electric fields and power grids, and also restricted the further development of new energy. When the penetration rate of new energy is relatively low, its impact on the stability of the system is usually ignored. However, as the proportion of new energy power sources increases, on the one hand, compared with traditional AC systems, new energy units are affected by natural factors and have volatility and randomness, which increases the uncertainty factors that cause chain failures in the system. On the other hand, compared with traditional synchronous machines, new energy units have poorer ability to resist disturbances, and more complex coupling characteristics appear between components in the system, which makes the development and evolution of chain failures constantly present new characteristics and laws.

[0004] At present, the installed capacity of renewable energy power generation in my country has become the first or second largest power source for 22 provincial power grids. The impact of a high proportion of renewable energy grid connection on cascading failures cannot be ignored. Complex mixed characteristics such as high dimension, nonlinearity, time-varying, randomness, and multiple time scales are the difficulties and key points in the search, analysis and research of cascading failures in power systems. The existing cascading failure analysis methods and theoretical systems integrate the theories of multiple disciplines and the characteristics of the power system itself, and the main focus is on three types of methods: complex system theory, complex network theory, and pattern search methods. Methods based on complex system theory, such as power flow entropy and wind power fluctuation entropy indicators, are convenient for having an overall understanding of the system and helping to identify the system operation status in a timely manner. However, the time span of the research is long and the amount of calculation is large. It cannot take into account the dynamic process of the power grid facing instability after the failure of certain links. Similarly, the complex network method focuses on the analysis of network structure and greatly simplifies the operating characteristics of the power system, thus ignoring the power flow constraints and dynamic processes of the power system. The pattern search method starts from the development process of cascading failures, and searches for possible paths of cascading failures step by step through separate power flow calculations or interactive calculations of power flow and transient stability to form an accident chain. The accident chain uses a heuristic search method and combines system safety and stability risk indicators to search for the development path of the next chain failure. This type of method has good adaptability to new energy power systems. However, since the construction of search indicators is subjective, how to conduct detailed modeling of electrical characteristics and take into account uncertainty factors within a certain range to reduce the complexity of the analysis will be the focus of future research. Summary of the invention

[0005] The present invention provides a cascading failure search method and system for a high-proportion renewable energy power system, so as to solve the problem of how to determine the cascading failure sequence of the high-proportion renewable energy power system.

[0006] In order to solve the above problem, according to one aspect of the present invention, a cascading failure search method for a high-proportion new energy power system is provided, the method comprising:

[0007] Step 1, according to a preset initial fault, determining multiple index values ​​of the high-proportion new energy power system after the initial fault occurs;

[0008] Step 2, determining whether each indicator among the multiple indicator values ​​satisfies a condition that each indicator is less than a preset threshold value, and obtaining a first determination result;

[0009] Step 3: when the first judgment result indicates that each indicator satisfies a value less than a preset threshold, determine whether the current fault falls in a DC or renewable energy area, and obtain a second judgment result;

[0010] Step 4: when the second judgment result indicates that the fault is in the DC or renewable energy area, the voltage index value of the renewable energy grid connection point and the comprehensive index value of the DC bus node voltage are calculated;

[0011] Step 5, setting the next level fault according to the maximum value of the voltage index value of the new energy grid connection point and the comprehensive index value of the flow bus node voltage;

[0012] Step 6, adding control measures after the fault, and determining whether the high-proportion new energy power system collapses after the control measures are added, and obtaining a third determination result;

[0013] Step 7: When the third judgment result indicates that the high-proportion new energy power system collapses after adding control measures, determine a chain fault sequence corresponding to the initial fault according to the set fault.

[0014] Preferably, the index values ​​include: line index values, voltage index values ​​of new energy grid connection points, frequency index values ​​of new energy grid connection points or load nodes, and comprehensive index values ​​of commutation bus node voltage.

[0015] Preferably, the method determines the line index value in the following manner, including:

[0016]

[0017] Where k represents the kth line, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; is the line index after the jth link of the ith accident chain of the kth line in the system occurs; is the complex power of line k after the jth link of the i-th fault chain in the system occurs; is the complex power of line k after the j-1th link of the ith fault chain occurs; a is a value between [0,1], which is used to set the weight of the two formulas; is the maximum load complex power of line k;

[0018] The voltage index value of the new energy grid connection point is determined by the following methods, including:

[0019]

[0020] Among them, m represents the mth new energy grid connection point, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; It is the voltage evaluation index of the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the j-1th fault of the i-th fault chain in the system occurs; and are the lower and upper limits of the voltage allowed at the mth renewable energy grid connection point; b is a value between [0,1], which is used to set the weight of the two formulas;

[0021] The frequency index value of the new energy grid connection point or load node is determined by the following methods, including:

[0022]

[0023] Where n is the nth new energy grid connection point or load node, It is the frequency change rate evaluation index of the nth new energy grid connection point / load node after the jth fault of the i-th fault chain in the system; is the calculated value of the frequency change rate of the nth node, which is determined by the system inertia M T It is determined by the ratio of renewable energy to total power generation η and the power shortage ΔP in the power grid; The maximum value of the frequency change rate that causes the protection action;

[0024] The comprehensive index value of the commutation bus node voltage is determined by the following method, including:

[0025]

[0026] Wherein, p is the pth commutation bus in the system. It is the comprehensive evaluation index of the pth commutation bus voltage after the jth fault of the i-th fault chain in the system; and are the short-circuit ratios of the commutation busbar p after the j-1th and jth faults in the i-th fault chain occur, respectively; and are the p-th commutation bus voltage after the j-th fault and j-1-th fault of the i-th fault chain in the system respectively; and are the lower and upper limits of the voltage allowed by the commutation bus p respectively; It is the minimum short-circuit ratio value allowed for the commutation busbar to operate.

[0027] Preferably, the method further comprises:

[0028] When the first judgment result indicates that each indicator value does not meet the requirement of being less than the preset threshold, the next level fault is set according to the current maximum indicator value, and it is directly determined whether the current fault falls in the DC or new energy vicinity to obtain the second judgment result.

[0029] Preferably, the method further comprises:

[0030] When the second judgment result indicates that the fault does not fall in the DC or renewable energy near area, the fault line is set according to the maximum line index value, and multiple index values ​​of the high-proportion renewable energy power system after the fault occurs are calculated, and return to step 2 for recalculation.

[0031] Preferably, the method further comprises:

[0032] When the third judgment result indicates that the high-proportion new energy power system has not collapsed after adding control measures, multiple indicator values ​​are recalculated, and the next level of fault is set according to the current maximum indicator value, and then return to step 6 to recalculate.

[0033] According to another aspect of the present invention, a cascading failure search system for a high-proportion new energy power system is provided, the system comprising:

[0034] A first calculation unit is used to determine, according to a preset initial fault, a plurality of index values ​​of the high-proportion new energy power system after the initial fault occurs;

[0035] A first judgment result obtaining unit, used to judge whether each indicator among the multiple indicator values ​​satisfies a requirement of being less than a preset threshold, and obtain a first judgment result;

[0036] A second judgment result acquisition unit, when the first judgment result indicates that each indicator satisfies a value less than a preset threshold, determines whether the current fault falls in a DC or new energy near zone, and acquires a second judgment result;

[0037] A second calculation unit is used to calculate the voltage index value of the new energy grid connection point and the comprehensive index value of the current bus node voltage when the second judgment result indicates that the fault is located in the DC or new energy near area;

[0038] A fault setting unit, used to set the next level fault according to the maximum value of the voltage index value of the new energy grid connection point and the comprehensive index value of the flow bus node voltage;

[0039] A third judgment result acquisition unit is used to add control measures after a fault occurs, and to determine whether the high-proportion new energy power system collapses after the control measures are added, and to acquire a third judgment result;

[0040] A cascading failure sequence determining unit is used to determine a cascading failure sequence corresponding to the initial fault according to a set fault when the third judgment result indicates that the high-proportion new energy power system collapses after adding control measures.

[0041] Preferably, the index values ​​include: line index values, voltage index values ​​of new energy grid connection points, frequency index values ​​of new energy grid connection points or load nodes, and comprehensive index values ​​of commutation bus node voltage.

[0042] Preferably, the system determines the line index value in the following manner, including:

[0043]

[0044] Where k represents the kth line, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; is the line index after the jth link of the ith accident chain of the kth line in the system occurs; is the complex power of line k after the jth link of the i-th fault chain in the system occurs; is the complex power of line k after the j-1th link of the ith fault chain occurs; a is a value between [0,1], which is used to set the weight of the two formulas; is the maximum load complex power of line k;

[0045] The voltage index value of the new energy grid connection point is determined by the following methods, including:

[0046]

[0047] Among them, m represents the mth new energy grid connection point, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; It is the voltage evaluation index of the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the j-1th fault of the i-th fault chain in the system occurs; and are the lower and upper limits of the voltage allowed at the mth renewable energy grid connection point; b is a value between [0,1], which is used to set the weight of the two formulas;

[0048] The frequency index value of the new energy grid connection point or load node is determined by the following methods, including:

[0049]

[0050] Where n is the nth new energy grid connection point or load node, It is the frequency change rate evaluation index of the nth new energy grid connection point / load node after the jth fault of the i-th fault chain in the system; is the calculated value of the frequency change rate of the nth node, which is determined by the system inertia M T It is determined by the ratio of renewable energy to total power generation η and the power shortage ΔP in the power grid; The maximum value of the frequency change rate that causes the protection action;

[0051] The comprehensive index value of the commutation bus node voltage is determined by the following method, including:

[0052]

[0053] Wherein, p is the pth commutation bus in the system. It is the comprehensive evaluation index of the pth commutation bus voltage after the jth fault of the i-th fault chain in the system; and are the short-circuit ratios of the commutation busbar p after the j-1th and jth faults in the i-th fault chain occur, respectively; and are the p-th commutation bus voltage after the j-th fault and j-1-th fault of the i-th fault chain in the system respectively; and are the lower and upper limits of the voltage allowed by the commutation bus p respectively; It is the minimum short-circuit ratio value allowed for the commutation busbar to operate.

[0054] Preferably, the second judgment result obtaining unit is further used for:

[0055] When the first judgment result indicates that each indicator value does not meet the requirement of being less than the preset threshold, the next level fault is set according to the current maximum indicator value, and it is directly determined whether the current fault falls in the DC or new energy vicinity to obtain the second judgment result.

[0056] Preferably, the system further comprises:

[0057] The third calculation unit is used to set the fault line according to the maximum line index value when the second judgment result indicates that the fault does not fall in the DC or new energy near area, and calculate multiple index values ​​of the high-proportion new energy power system after the fault occurs, and return to the first judgment result acquisition unit for recalculation.

[0058] Preferably, the system further comprises:

[0059] The fourth calculation unit is used to recalculate multiple indicator values ​​when the third judgment result indicates that the high-proportion new energy power system has not collapsed after adding control measures, and set the next level of fault according to the current maximum indicator value, and return to the third judgment result acquisition unit for recalculation.

[0060] The present invention provides a method and system for searching for cascading failures in a high-proportion renewable energy power system. By calculating the indicators of electrical quantity power, voltage and frequency after a high-proportion renewable energy power system failure, a possible cascading failure sequence is determined. This method not only takes into account the power characteristics of the high-proportion renewable energy power system, but also can quickly find the next level of cascading failures. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] A more complete understanding of exemplary embodiments of the present invention may be obtained by referring to the following drawings:

[0062] Figure 1 Flow chart of a cascading failure search method 100 for a high-proportion new energy power system according to an embodiment of the present invention;

[0063] Figure 2 A flowchart of a cascading failure search for a high-proportion new energy power system according to an embodiment of the present invention;

[0064] Figure 3 A schematic diagram of a DC power curve locked after a DC commutation failure fault according to an embodiment of the present invention;

[0065] Figure 4 A schematic diagram of a system frequency deviation after a wind turbine is disconnected from the grid according to an embodiment of the present invention;

[0066] Figure 5 Schematic diagram of the structure of a cascading failure search system 500 for a high-proportion new energy power system according to an embodiment of the present invention. DETAILED DESCRIPTION

[0067] Now, exemplary embodiments of the present invention are described with reference to the accompanying drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. These embodiments are provided to disclose the present invention in detail and completely and to fully convey the scope of the present invention to those skilled in the art. The terms used in the exemplary embodiments shown in the accompanying drawings are not intended to limit the present invention. In the accompanying drawings, the same units / elements are marked with the same reference numerals.

[0068] Unless otherwise specified, the terms (including technical terms) used herein have the commonly understood meanings to those skilled in the art. In addition, it is understood that the terms defined in commonly used dictionaries should be understood to have the same meanings as those in the context of the relevant fields, and should not be understood as idealized or overly formal meanings.

[0069] Figure 1 Flow chart of a cascading failure search method 100 for a high-proportion new energy power system according to an embodiment of the present invention. Figure 1As shown, the cascading failure search method for a high-proportion new energy power system provided by the implementation party of the present invention determines the possible cascading failure sequence by calculating the indexes of the electrical quantity power, voltage and frequency after the high-proportion new energy power system fails, which can not only take into account the power characteristics of the high-proportion new energy power system, but also quickly find the next level of cascading failure. The cascading failure search method 100 for a high-proportion new energy power system provided by the implementation method of the present invention starts from step 101. In step 101, according to a preset initial fault, multiple index values ​​of the high-proportion new energy power system after the occurrence of the initial fault are determined.

[0070] Preferably, the index values ​​include: line index values, voltage index values ​​of new energy grid connection points, frequency index values ​​of new energy grid connection points or load nodes, and comprehensive index values ​​of commutation bus node voltage.

[0071] Preferably, the method determines the line index value in the following manner, including:

[0072]

[0073] Where k represents the kth line, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; is the line index after the jth link of the ith accident chain of the kth line in the system occurs; is the complex power of line k after the jth link of the i-th fault chain in the system occurs; is the complex power of line k after the j-1th link of the ith fault chain occurs; a is a value between [0,1], which is used to set the weight of the two formulas; is the maximum load complex power of line k;

[0074] The voltage index value of the new energy grid connection point is determined by the following methods, including:

[0075]

[0076] Among them, m represents the mth new energy grid connection point, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; It is the voltage evaluation index of the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the j-1th fault of the i-th fault chain in the system occurs; and are the lower and upper limits of the voltage allowed at the mth renewable energy grid connection point; b is a value between [0,1], which is used to set the weight of the two formulas;

[0077] The frequency index value of the new energy grid connection point or load node is determined by the following methods, including:

[0078]

[0079] Where n is the nth new energy grid connection point or load node, It is the frequency change rate evaluation index of the nth new energy grid connection point / load node after the jth fault of the i-th fault chain in the system; is the calculated value of the frequency change rate of the nth node, which is determined by the system inertia M T It is determined by the ratio of renewable energy to total power generation η and the power shortage ΔP in the power grid; The maximum value of the frequency change rate that causes the protection action;

[0080] The comprehensive index value of the commutation bus node voltage is determined by the following method, including:

[0081]

[0082] Wherein, p is the pth commutation bus in the system. It is the comprehensive evaluation index of the pth commutation bus voltage after the jth fault of the i-th fault chain in the system; and are the short-circuit ratios of the commutation busbar p after the j-1th and jth faults in the i-th fault chain occur, respectively; and are the p-th commutation bus voltage after the j-th fault and j-1-th fault of the i-th fault chain in the system respectively; and are the lower and upper limits of the voltage allowed by the commutation bus p respectively; It is the minimum short-circuit ratio value allowed for the commutation busbar to operate.

[0083] Compared with the traditional AC power grid, the cascading failure of the high-proportion renewable energy power system is still dominated by power flow fluctuations in the early stage of evolution, which is manifested as the successive overload of the line, or the overload protection action caused by power fluctuations and reduced stability margin. However, the evolution time scale of the high-proportion renewable energy power system is shorter, the probability of accidents is higher, the electrical characteristics between the grids are stronger, and the voltage and frequency problems are more prominent.

[0084] Therefore, the present invention evaluates and searches for the next level of failure that may occur after a fault occurs, starting from the power fluctuation and stability margin of the line and the possible overload protection action, the voltage of the new energy grid connection point and the possible overcurrent protection action, the frequency change rate of the new energy grid connection point or load node and the possible slip protection action, as well as the bus voltage fluctuation, low voltage and short-circuit ratio change of the converter station and the possible commutation failure protection action.

[0085] Based on the analysis of typical cases of cascading failures in high-proportion renewable energy power systems, two main types of failures are considered: (1) After an AC line fails, as the line is disconnected, the voltage gradually drops, which may cause the renewable energy unit to disconnect from the grid at low voltage. As the distribution of the power flow changes, nearby renewable energy units may further disconnect from the grid. The disconnection of a large area of ​​renewable energy units will cause a shortage of active power and a drop in frequency, which may trigger the low-frequency load reduction device to remove a large amount of load or cause system instability. (2) When a grid component fails, since the DC system is more sensitive to the grid voltage, bus voltage fluctuations may directly cause DC faults and other problems. Once the DC power cannot be sent out for a short time, both the DC sending and receiving grids will experience a short-term power shortage. At this time, the renewable energy grid-connected bus will experience transient overvoltage or frequency problems, causing the unit to disconnect from the grid.

[0086] In view of the above situation, the present invention combines the calculation of the cascading failure search index of the high-proportion new energy power system to generate a cascading failure sequence under a certain initial failure, that is, an accident chain. The process is shown in the attached figure. Figure 2 shown.

[0087] Combination Figure 2 As shown, in the present invention, the initial fault is first determined and set, and four indicators of the high-proportion new energy system after the initial fault occurs are calculated.

[0088] Specifically, it includes:

[0089] 1. Line indicators: Based on the power fluctuation and stability margin of the line, the evaluation indicators of the line are given, taking into account the overload protection action that may be caused by the power fluctuation of the line and the low transmission margin.

[0090]

[0091] Where k represents the kth line, i represents the accident chain caused by the i-th initial fault, j represents the j-th fault that has occurred, and S is the complex power of the line.

[0092] 2. Voltage index value of new energy grid connection point: According to the voltage of new energy grid connection point, the evaluation index of the node is given, and the factor taken into consideration is the overcurrent protection action that may be caused by the voltage drop or fluctuation of the new energy grid connection point.

[0093]

[0094] Among them, m is the busbar of the converter station of the mth new energy grid-connected point.

[0095] 3. Frequency index of new energy grid connection points and load nodes: According to the frequency change rate of new energy grid connection points or load nodes, the evaluation index of the node is given, and the factor taken into account is the slip protection action of the new energy grid connection points or load nodes when there is a power shortage.

[0096]

[0097] Where n is the nth new energy grid connection point and load node, ΔP is the power shortage in the power grid, MT is the system inertia, and η is the ratio of renewable energy to total power generation.

[0098] 4. Comprehensive indicators of commutation bus node voltage: Based on the evaluation indicators of the commutation bus node, the factors are node voltage fluctuation value, low voltage and short-circuit ratio (multi-input short-circuit ratio) indicators, and the DC system commutation failure protection action is considered.

[0099]

[0100] Wherein, P is the Pth converter station bus, KMISCR is the multi-infeed short-circuit ratio index of the converter station bus, and U is the converter station bus voltage.

[0101] In step 102, it is determined whether each indicator in the plurality of indicator values ​​satisfies a value less than a preset threshold, and a first determination result is obtained.

[0102] In step 103, when the first judgment result indicates that each indicator satisfies a value less than a preset threshold, it is determined whether the current fault falls in a DC or new energy vicinity area, and a second judgment result is obtained.

[0103] Preferably, the method further comprises:

[0104] When the first judgment result indicates that each indicator value does not meet the requirement of being less than the preset threshold, the next level fault is set according to the current maximum indicator value, and it is directly determined whether the current fault falls in the DC or new energy vicinity to obtain the second judgment result.

[0105] Combination Figure 2As shown, in the present invention, if the first judgment result indicates that all four indicators are less than 1, it is determined whether the fault is in the DC or renewable energy area to obtain the second judgment result. If the second judgment result indicates that the fault is not in the DC or renewable energy area, it is necessary to continue to set the line fault and calculate the four indicators again; on the contrary, if the second judgment result indicates that the fault is in the DC or renewable energy area, the next step is to calculate the renewable energy and converter station voltage indicators.

[0106] If the first judgment result indicates that all four indicators are less than 1, the next level fault is set according to the current maximum indicator value, and it is directly determined whether the current fault falls in the DC or new energy near area to obtain the second judgment result, and then processed again according to the second judgment result.

[0107] In step 104, when the second judgment result indicates that the fault is located in the DC or renewable energy near area, the renewable energy grid connection point voltage index value and the DC bus node voltage comprehensive index value are calculated.

[0108] In step 105, the next level fault is set according to the maximum value of the voltage index value of the new energy grid connection point and the comprehensive index value of the flow bus node voltage.

[0109] Preferably, the method further comprises:

[0110] When the second judgment result indicates that the fault does not fall in the DC or renewable energy near area, the fault line is set according to the maximum line index value, and multiple index values ​​of the high-proportion renewable energy power system after the fault occurs are calculated, and return to step 102 for recalculation.

[0111] Combination Figure 2 As shown, in the present invention, if the second judgment result indicates that the fault falls in the DC or new energy near area, the voltage index value of the new energy grid connection point and the comprehensive index value of the flow bus node voltage are recalculated according to the index value calculation method, and the next level fault is set according to the maximum value of the voltage index value of the new energy grid connection point and the comprehensive index value of the flow bus node voltage. On the contrary, if the second judgment result indicates that the fault does not fall in the DC or new energy near area, the next level fault line is set according to the maximum line index value, and multiple index values ​​of the high proportion of new energy power system after the fault occurs are calculated, and return to step 102 for recalculation.

[0112] In step 106, control measures are added after the fault, and it is determined whether the high-proportion new energy power system collapses after the control measures are added, and a third determination result is obtained.

[0113] In step 107, when the third judgment result indicates that the high-proportion new energy power system collapses after adding control measures, a chain fault sequence corresponding to the initial fault is determined according to the set fault.

[0114] Preferably, the method further comprises:

[0115] When the third judgment result indicates that the high-proportion new energy power system has not collapsed after adding control measures, multiple indicator values ​​are recalculated, and the next level of fault is set according to the current maximum indicator value, and then return to step 106 for recalculation.

[0116] Combination Figure 2 As shown, in the present invention, after setting the next level fault in step 105, control measures are added, and it is determined whether the system crashes to obtain a third judgment result. If the third judgment result indicates that there is no crash, it is necessary to calculate four indicators and then set the next level fault and enter step 106 for recalculation until the system crashes; if the third judgment result indicates that the system crashes, the chain fault sequence corresponding to the initial fault is determined according to the set fault. If there is no crash, the multiple indicator values ​​are recalculated, and the next level fault is set according to the current maximum indicator value, and the calculation is returned to step 106 for recalculation.

[0117] The present invention determines the possible chain failure sequence by calculating the indicators of electrical quantity power, voltage and frequency, which can not only take into account the power characteristics of the high-proportion new energy power system, but also quickly find the next level of chain failure. Compared with the traditional analysis method of chain failure, the specific analysis is shown in the following table:

[0118]

[0119] Take a new energy transmission system in Northwest my country as an example. Assuming that the proportion of wind power in the system is 45%, a high proportion of new energy is transmitted through UHV DC and 4 AC lines. The busbar of the UHV DC converter station is Tianshan converter station, and the transmission AC lines are Hami-Dunhuang double-circuit line and Yandun-Shazhou double-circuit line.

[0120] The initial fault is set as the disconnection fault of the Hami-Tianshan line. After the index calculation, the indexes of all lines and nodes are less than 1. Therefore, it is necessary to continue to set line faults for iteration. According to the line fluctuation index, the maximum value is the calculated value of Hami-Dunhuang, so the next level fault is set as the disconnection fault of Hami-Dunhuang.

[0121] line Calculation indicators Hami - Dunhuang 0.2 Dunhuang-Mogao 0.012 Bazhou-Tufan 0.001 Yili-Wusu 0.001 Five colors-Changhuan 0.001

[0122] After the Hami-Dunhuang line starts, the Tianshan-Yandun line has the largest fluctuation index according to index calculation. Since the fault occurs near the DC converter station, the bus voltage index of the converter station is calculated and the index value is small. Therefore, Tianshan-Yandun is set as the next level fault first.

[0123]

[0124]

[0125] After the Tianshan-Yandun line was disconnected, the line power flow converged to the outbound AC channels Yandun-Shazhou and Hami-Dunhuang, resulting in large power fluctuations in the outbound AC channels and a significant decrease in the line stability margin. Since the fault occurred in the DC near zone, the voltage index of the Tianshan converter station was calculated, which was greater than 1. Therefore, the next level fault was set as a UHV DC commutation failure fault. The fault stability calculation curve is shown in the attached figure. Figure 3 shown.

[0126] After the commutation failure, the DC was locked. Due to the high transient voltage, 6320MW of wind turbines in the vicinity were disconnected from the grid, and the frequency in the area eventually reached 50.12Hz. Figure 4 After the DC blocking fault occurs, the power grid at the receiving end of the UHV DC also faces a power shortage of 8000MW, but the problem of the receiving end power grid is not within the scope of this invention.

[0127] Figure 5 Schematic diagram of the structure of a cascading failure search system 500 for a high-proportion new energy power system according to an embodiment of the present invention. Figure 5 As shown, a cascading failure search system 500 for a high proportion of new energy power system provided in an embodiment of the present invention includes: a first calculation unit 501, a first judgment result acquisition unit 502, a second judgment result acquisition unit 503, a second calculation unit 504, a fault setting unit 505, a third judgment result acquisition unit 506 and a cascading failure sequence determination unit 507.

[0128] Preferably, the first calculation unit 501 is used to determine, according to a preset initial fault, a plurality of indicator values ​​of the high-proportion new energy power system after the initial fault occurs.

[0129] Preferably, the index values ​​include: line index values, voltage index values ​​of new energy grid connection points, frequency index values ​​of new energy grid connection points or load nodes, and comprehensive index values ​​of commutation bus node voltage.

[0130] Preferably, the system determines the line index value in the following manner, including:

[0131]

[0132] Where k represents the kth line, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; is the line index after the jth link of the ith accident chain of the kth line in the system occurs; is the complex power of line k after the jth link of the i-th fault chain in the system occurs; is the complex power of line k after the j-1th link of the ith fault chain occurs; a is a value between [0,1], which is used to set the weight of the two formulas; is the maximum load complex power of line k;

[0133] The voltage index value of the new energy grid connection point is determined by the following methods, including:

[0134]

[0135] Among them, m represents the mth new energy grid connection point, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; It is the voltage evaluation index of the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the j-1th fault of the i-th fault chain in the system occurs; and are the lower and upper limits of the voltage allowed at the mth renewable energy grid connection point; b is a value between [0,1], which is used to set the weight of the two formulas;

[0136] The frequency index value of the new energy grid connection point or load node is determined by the following methods, including:

[0137]

[0138] Where n is the nth new energy grid connection point or load node, It is the frequency change rate evaluation index of the nth new energy grid connection point / load node after the jth fault of the i-th fault chain in the system; is the calculated value of the frequency change rate of the nth node, which is determined by the system inertia M T It is determined by the ratio of renewable energy to total power generation η and the power shortage ΔP in the power grid; The maximum value of the frequency change rate that causes the protection action;

[0139] The comprehensive index value of the commutation bus node voltage is determined by the following method, including:

[0140]

[0141] Wherein, p is the pth commutation bus in the system. It is the comprehensive evaluation index of the pth commutation bus voltage after the jth fault of the i-th fault chain in the system; and are the short-circuit ratios of the commutation busbar p after the j-1th and jth faults in the i-th fault chain occur, respectively; and are the p-th commutation bus voltage after the j-th fault and j-1-th fault of the i-th fault chain in the system respectively; and are the lower and upper limits of the voltage allowed by the commutation bus p respectively; It is the minimum short-circuit ratio value allowed for the commutation busbar to operate.

[0142] Preferably, the first judgment result obtaining unit 502 is used to determine whether each indicator in the multiple indicator values ​​satisfies a value less than a preset threshold value, and obtain a first judgment result.

[0143] Preferably, the second judgment result acquisition unit 503 is used to determine whether the current fault falls in the DC or new energy vicinity area and obtain the second judgment result when the first judgment result indicates that each indicator is less than a preset threshold.

[0144] Preferably, the second judgment result obtaining unit 503 is further used for:

[0145] When the first judgment result indicates that each indicator value does not meet the requirement of being less than the preset threshold, the next level fault is set according to the current maximum indicator value, and it is directly determined whether the current fault falls in the DC or new energy vicinity to obtain the second judgment result.

[0146] Preferably, the second calculation unit 504 is used to calculate the voltage index value of the new energy grid connection point and the comprehensive index value of the DC bus node voltage when the second judgment result indicates that the fault falls in the DC or new energy near area.

[0147] Preferably, the fault setting unit 505 is used to set the next level fault according to the maximum value of the voltage index value of the new energy grid connection point and the comprehensive index value of the flow bus node voltage.

[0148] Preferably, the third judgment result acquisition unit 506 is used to add control measures after a fault occurs, and to determine whether the high-proportion new energy power system collapses after the control measures are added, to obtain a third judgment result.

[0149] Preferably, the cascading failure sequence determining unit 506 is used to determine a cascading failure sequence corresponding to the initial fault according to a set fault when the third judgment result indicates that the high-proportion new energy power system collapses after adding control measures.

[0150] Preferably, the system further comprises:

[0151] The third calculation unit is used to set the fault line according to the maximum line index value when the second judgment result indicates that the fault does not fall in the DC or new energy near area, and calculate multiple index values ​​of the high-proportion new energy power system after the fault occurs, and return to the first judgment result acquisition unit 502 for recalculation.

[0152] Preferably, the system further comprises:

[0153] The fourth calculation unit is used to recalculate multiple indicator values ​​when the third judgment result indicates that the high-proportion new energy power system has not collapsed after adding control measures, and set the next level of fault according to the current maximum indicator value, and return to the third judgment result acquisition unit 506 for recalculation.

[0154] The cascading failure search system 500 for a high-proportion new energy power system according to an embodiment of the present invention corresponds to the cascading failure search method 100 for a high-proportion new energy power system according to another embodiment of the present invention, and will not be described in detail herein.

[0155] The invention has been described above with reference to a few embodiments. However, it is readily apparent to a person skilled in the art that other embodiments than the ones disclosed above are equally within the scope of the invention, as defined by the appended patent claims.

[0156] Generally, all terms used in the claims are to be interpreted according to their ordinary meaning in the technical field, unless explicitly defined otherwise herein. All references to "a / said / the [means, components, etc.]" are to be openly interpreted as at least one instance of the means, components, etc., unless explicitly stated otherwise. The steps of any method disclosed herein do not necessarily have to be performed in the exact order disclosed, unless explicitly stated otherwise.

[0157] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0158] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0159] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0160] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0161] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents. Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. A method for searching for cascading failures in a high-proportion renewable energy power system, characterized in that: The method comprises: Step 1, according to a preset initial fault, determining multiple index values ​​of the high-proportion new energy power system after the initial fault occurs; Step 2, determining whether each indicator among the multiple indicator values ​​satisfies a condition that each indicator is less than a preset threshold value, and obtaining a first determination result; Step 3: when the first judgment result indicates that each indicator satisfies a value less than a preset threshold, determine whether the current fault falls in a DC or renewable energy area, and obtain a second judgment result; Step 4: when the second judgment result indicates that the fault is in the DC or renewable energy area, the voltage index value of the renewable energy grid connection point and the comprehensive index value of the DC bus node voltage are calculated; Step 5, setting the next level fault according to the maximum value of the voltage index value of the new energy grid connection point and the comprehensive index value of the flow bus node voltage; Step 6, adding control measures after the fault, and determining whether the high-proportion new energy power system collapses after the control measures are added, and obtaining a third determination result; Step 7, when the third judgment result indicates that the high-proportion new energy power system collapses after adding control measures, determining a chain fault sequence corresponding to the initial fault according to the set fault; The index values ​​include: line index value, voltage index value of new energy grid connection point, frequency index value of new energy grid connection point or load node, and comprehensive index value of commutation bus node voltage; The method determines the line index value in the following manner, including: Where k represents the kth line, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; is the line index after the jth link of the ith accident chain of the kth line in the system occurs; is the complex power of line k after the jth link of the i-th fault chain in the system occurs; is the complex power of line k after the j-1th link of the ith fault chain occurs; a is a value between [0,1], which is used to set the weight of the two formulas; is the maximum load complex power of line k; The voltage index value of the new energy grid connection point is determined by the following methods, including: Among them, m represents the mth new energy grid connection point, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; It is the voltage evaluation index of the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the j-1th fault of the i-th fault chain in the system occurs; and are the lower and upper limits of the voltage allowed at the mth renewable energy grid connection point; b is a value between [0,1], which is used to set the weight of the two formulas; The frequency index value of the new energy grid connection point or load node is determined by the following methods, including: Where n is the nth new energy grid connection point or load node, It is the frequency change rate evaluation index of the nth new energy grid connection point / load node after the jth fault of the i-th fault chain in the system; is the calculated value of the frequency change rate of the nth node, which is determined by the system inertia M T It is determined by the ratio of renewable energy to total power generation η and the power shortage ΔP in the power grid; The maximum value of the frequency change rate that causes the protection action; The comprehensive index value of the commutation bus node voltage is determined by the following method, including: Where p is the pth commutation bus in the system, It is the comprehensive evaluation index of the pth commutation bus voltage after the jth fault of the i-th fault chain in the system; and are the short-circuit ratios of the commutation busbar p after the j-1th and jth faults in the i-th fault chain occur, respectively; and are the p-th commutation bus voltage after the j-th fault and j-1-th fault of the i-th fault chain in the system respectively; and are the lower and upper limits of the voltage allowed by the commutation bus p respectively; It is the minimum short-circuit ratio value allowed for the commutation busbar to operate.

2. The method according to claim 1, characterized in that: The method further comprises: When the first judgment result indicates that each indicator value does not meet the requirement of being less than the preset threshold, the next level fault is set according to the current maximum indicator value, and it is directly determined whether the current fault falls in the DC or new energy vicinity to obtain the second judgment result.

3. The method according to claim 1 or 2, characterized in that: The method further comprises: When the second judgment result indicates that the fault does not fall in the DC or renewable energy near area, the fault line is set according to the maximum line index value, and multiple index values ​​of the high-proportion renewable energy power system after the fault occurs are calculated, and return to step 2 for recalculation.

4. The method according to claim 1, characterized in that: The method further comprises: When the third judgment result indicates that the high-proportion new energy power system has not collapsed after adding control measures, multiple indicator values ​​are recalculated, and the next level of fault is set according to the current maximum indicator value, and then return to step 6 to recalculate.

5. A cascading failure search system for a high-proportion renewable energy power system, characterized in that: The system comprises: A first calculation unit is used to determine, according to a preset initial fault, a plurality of index values ​​of the high-proportion new energy power system after the initial fault occurs; A first judgment result obtaining unit, used to judge whether each indicator among the multiple indicator values ​​satisfies a requirement of being less than a preset threshold, and obtain a first judgment result; A second judgment result acquisition unit, when the first judgment result indicates that each indicator satisfies a value less than a preset threshold, determines whether the current fault falls in a DC or new energy near zone, and acquires a second judgment result; A second calculation unit is used to calculate the voltage index value of the new energy grid connection point and the comprehensive index value of the current bus node voltage when the second judgment result indicates that the fault is located in the DC or new energy near area; A fault setting unit, used to set the next level fault according to the maximum value of the voltage index value of the new energy grid connection point and the comprehensive index value of the flow bus node voltage; A third judgment result acquisition unit is used to add control measures after a fault occurs, and to determine whether the high-proportion new energy power system collapses after the control measures are added, and to acquire a third judgment result; a cascading failure sequence determining unit, configured to determine a cascading failure sequence corresponding to the initial fault according to a set fault when the third judgment result indicates that the high-proportion new energy power system collapses after adding control measures; The index values ​​include: line index value, voltage index value of new energy grid connection point, frequency index value of new energy grid connection point or load node, and comprehensive index value of commutation bus node voltage; The system determines the line index value in the following manner, including: Where k represents the kth line, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; is the line index after the jth link of the ith accident chain of the kth line in the system occurs; is the complex power of line k after the jth link of the i-th fault chain in the system occurs; is the complex power of line k after the j-1th link of the ith fault chain occurs; a is a value between [0,1], which is used to set the weight of the two formulas; is the maximum load complex power of line k; The voltage index value of the new energy grid connection point is determined by the following methods, including: Among them, m represents the mth new energy grid connection point, i represents the accident chain caused by the i-th initial fault, and j represents the j-th fault that has occurred; It is the voltage evaluation index of the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the jth fault of the i-th fault chain in the system; is the voltage at the mth renewable energy grid connection point after the j-1th fault of the i-th fault chain in the system occurs; and are the lower and upper limits of the voltage allowed at the mth renewable energy grid connection point; b is a value between [0,1], which is used to set the weight of the two formulas; The frequency index value of the new energy grid connection point or load node is determined by the following methods, including: Where n is the nth new energy grid connection point or load node, It is the frequency change rate evaluation index of the nth new energy grid connection point / load node after the jth fault of the i-th fault chain in the system; is the calculated value of the frequency change rate of the nth node, which is determined by the system inertia M T It is determined by the ratio of renewable energy to total power generation η and the power shortage ΔP in the power grid; The maximum value of the frequency change rate that causes the protection action; The comprehensive index value of the commutation bus node voltage is determined by the following method, including: Where p is the pth commutation bus in the system, It is the comprehensive evaluation index of the pth commutation bus voltage after the jth fault of the i-th fault chain in the system; and are the short-circuit ratios of the commutation busbar p after the j-1th and jth faults in the i-th fault chain occur, respectively; and are the p-th commutation bus voltage after the j-th fault and j-1-th fault of the i-th fault chain in the system respectively; and are the lower and upper limits of the voltage allowed by the commutation bus p respectively; It is the minimum short-circuit ratio value allowed for the commutation busbar to operate.

6. The system according to claim 5, characterized in that The second judgment result obtaining unit is further used for: When the first judgment result indicates that each indicator value does not meet the requirement of being less than the preset threshold, the next level fault is set according to the current maximum indicator value, and it is directly determined whether the current fault falls in the DC or new energy vicinity to obtain the second judgment result.

7. The system according to claim 5 or 6, characterized in that: The system further comprises: The third calculation unit is used to set the fault line according to the maximum line index value when the second judgment result indicates that the fault does not fall in the DC or new energy near area, and calculate multiple index values ​​of the high-proportion new energy power system after the fault occurs, and return to the first judgment result acquisition unit for recalculation.

8. The system according to claim 5, characterized in that The system further comprises: The fourth calculation unit is used to recalculate multiple indicator values ​​when the third judgment result indicates that the high-proportion new energy power system has not collapsed after adding control measures, and set the next level of fault according to the current maximum indicator value, and return to the third judgment result acquisition unit for recalculation.

Citation Information

Patent Citations

  • Power failure risk computing method for electric power system containing double-fed wind power plant

    CN106230024A

  • Planning method and system applicable to ultrahigh-voltage DC external transmission power grid containing high-permeability new energy

    CN108418255A

  • Method and system for cascading failure risk assessment of high proportion wind power grid-connected

    CN109118098A

  • Method and system for identifying cascading failure large event of power grid

    CN110070266A

  • Power grid vulnerability evaluation method under high-proportion renewable energy source access

    CN110705879A