A method for controlling the construction accuracy of drilling holes for guide pipes in tunnel excavation
By using guide wall installation and laser line projector assisted positioning methods in tunnel excavation projects, the problem of guide pipe deviation in pipe shed construction is solved, the drilling accuracy is controlled, and construction stability and support are ensured. Effect.
Patent Information
- Application Number
- CN202210473268.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-04-29
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2042-04-29
AI Technical Summary
In tunnel excavation projects, the guide pipe is prone to deviating during the construction of the pipe shed, resulting in inaccurate drilling accuracy, affecting the construction stability and final support effect.
Using guide wall installation, laser projector assisted positioning and bracket adjustment methods to ensure drilling accuracy, connect guide walls and enclosed piles through planting ribs, use laser projector to measure marking points for positioning and adjustment, and use I-shaped steel and fix the steel bar to reinforce the guide tube to ensure accuracy control during the drilling process.
It effectively improves the accuracy of pipe shed guide pipe drilling construction, ensures stability and final support effect during the construction process, avoids pipe shed deviation, and enhances the reinforcement and water-stop performance of the advanced large pipe shed.
Smart Images

Figure CN114658449B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of engineering construction, and in particular to a method for controlling the construction accuracy of a guide pipe drilling hole in a tunnel dark excavation pipe shed. Background Art
[0002] The advance large pipe shed is an advance support structure for shallow buried underground structural engineering. Its essence is to pre-drill holes and install thick-walled steel pipes with large inertia moment on the buried arc of the lining arch ring of the underground tunnel or structural engineering to be excavated, which plays a temporary advance support role to prevent soil collapse and surface subsidence, so as to ensure the safe operation of excavation and subsequent support technology. In the existing pipe shed construction method, the pipe shed often deviates during the drilling process, which limits the drilling length of the pipe shed at one time.
[0003] At present, pipe shed construction is very common in underground tunnel projects. During pipe shed construction, construction operators usually use pre-buried guide pipes first, and then drive the pipe shed piles into the side walls of the construction guide tunnel through the guide pipes to form an advanced large pipe shed. Since the guide pipes are prone to deviation during the construction process, resulting in inaccurate precision, the guide pipes need to be further reinforced to ensure their stability during the construction process. At the same time, the pipe shed is also prone to deviation due to the deviation of the drilling rig's sight during the construction process, resulting in the direction of the pipe shed pipes being deviated after being driven into the soil. The final advanced large pipe shed cannot fully play the role of reinforcement and water stopping. Summary of the invention
[0004] The purpose of the present invention is to provide a method for controlling the construction accuracy of guide pipe drilling in a tunnel dark excavation pipe rack, by which the problems and difficulties of controlling the construction accuracy of guide pipe drilling can be fully solved.
[0005] The present invention adopts the following technical solution:
[0006] A method for controlling the construction accuracy of a guide pipe drilling hole in a tunnel dark excavation pipe shed, characterized in that it comprises the following steps:
[0007] Step S1. installing the guide wall, wherein the guide wall and the retaining piles are connected by embedded reinforcement;
[0008] Step S2. Set up the working platform and the drilling rig in place, and ensure that the axis of the drilling rig drill pipe coincides with the axis of the orifice pipe;
[0009] Step S3. Drilling: The height of the drilling platform is determined according to the adjustable range of the drilling rig and the drilling sequence. Since the drilling sequence of the drilling rig is from high hole position to low hole position, the platform position is gradually lowered from top to bottom to meet the drilling needs;
[0010] Step S4. Laser line projector assisted positioning: during the drilling operation, a laser line projector is used to measure the mark point as the positioning point, and the offset adjustment is made during the drilling process of the pipe-roof pipe. A positioning adjustment is made once a section of the pipe-roof pipe is to be drilled;
[0011] Step S5. Adjust the bracket to adjust the drilling offset of the pipe shed pipe by adjusting the bracket to ensure the accuracy of the pipe shed construction;
[0012] Step S6. Install the grout stop plug. After the entire pipe rack pipe is drilled in, install the grout stop plug and start drilling the next pipe rack pipe.
[0013] Furthermore, the guide wall comprises a guide tube, an I-beam and fixed steel bars, wherein the guide tube is fixed above the I-beam, and adjacent guide tubes are connected by fixed steel bars.
[0014] Furthermore, the guide wall construction steps are as follows:
[0015] Step S11. The guide wall and the retaining piles are connected by embedded reinforcement, and the I-beam and the reinforcement are welded and positioned at the bottom of the guide pipe;
[0016] Step S12. Pre-embed the guide tube and weld it to the I-beam after retesting;
[0017] Step S13. Using fixed steel bars to perform double-sided welding on the guide tube;
[0018] Step S14: After the guide wall is installed and its accuracy is verified, the formwork is sealed and concrete is poured.
[0019] Furthermore, in step S2, the tunnel entrance pipe scaffolding construction platform adopts an excavation platform or a steel pipe scaffolding platform.
[0020] Furthermore, the step S4 specifically includes the following steps:
[0021] Step S41. Set up a laser line projector at the rear of the pipe shed construction to ensure that the bubble is centered and projected toward the middle wall of the guide wall;
[0022] Step S42. Set a measurement mark point at the intersection of the horizontal and vertical directions of the laser projection point. The measurement mark point is affixed with an adhesive "+" sign sticker at a position that coincides with the laser focus to ensure that no displacement occurs;
[0023] Step S43. Use a tower ruler to measure the distance between the initial state of the pipe rack pipe and the laser (horizontally and vertically) to ensure that the displacement is controlled within ±1mm after each drilling;
[0024] Step S44. When the laser projector is used for a long time or intermittently, if the "+" sign sticker does not overlap with the laser, the previously used sticker can be torn off and a new sticker can be pasted to the laser overlap position to control the accuracy of the pipe roof pipe drilling.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] 1. The present invention improves on the traditional guide tube construction method by arranging an I-beam inside the guide tube and reinforcing the guide tube by welding with steel bars to ensure the integrity of the guide tube, better control its accuracy during the construction process, and ensure its stability during installation, welding and concrete pouring.
[0027] 2. In the process of traditional underground tunnel pipe-roof construction, the pipe-roof pipes are constructed by directly drilling with a drilling rig, which cannot guarantee the accuracy of the pipe-roof pipes during drilling and usually causes deviation. The present invention can effectively solve this problem by using a laser line projector to assist in precision control, thereby ensuring the overall accuracy of the pipe-roof pipes when they are drilled into the guide pipe.
[0028] 3. The present invention adopts a bracket to support the pipe shed during construction, adjusts the deviation of the pipe shed pipes during construction, and ensures that the accuracy of the construction process is effectively controlled. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 is a front view of the guide wall of the present invention;
[0030] Figure 2 is a side view of the guide wall of the present invention without concrete being poured;
[0031] Figure 3 It is a large-scale drawing of pouring concrete for the guide wall of the present invention;
[0032] Figure 4 It is a schematic diagram of laser projection of the present invention;
[0033] Figure 5 This is a front view of the laser projection marking point of the present invention;
[0034] Figure 6 It is a side view of the laser projection marking point of the present invention;
[0035] In the figure, 1-guide tube, 2-I-beam, 3-fixed steel bar, 4-pipe rack pipe, 5-laser line projector, 6-measurement mark point, 7-tower ruler, 8-bracket. DETAILED DESCRIPTION
[0036] In order to make the purpose, technical solution and effect of the present invention clearer and more specific, the present invention is further described in detail in combination with specific embodiments. The drawings are only used for exemplary descriptions, and only show schematic diagrams, not physical drawings, and cannot be understood as limitations on this patent; in order to better illustrate the embodiments of the present invention, some parts and device connections in the drawings are omitted, enlarged or reduced, and do not represent the size of the actual product; for those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.
[0037] Embodiment 1:
[0038] This embodiment provides a method for controlling the construction accuracy of drilling holes for guide pipes in tunnel excavation. The first part is the guide wall construction part, such as Figure 1-3 As shown in the figure, this part is mainly composed of guide pipe 1, I-beam 2 and some fixed steel bars 3. After pouring, a guide wall is formed. Its function is to provide guide positioning holes for the later pipe shed construction and ensure the accuracy of the pipe shed construction process. The second part is mainly the drilling construction accuracy control method, such as Figure 4-6 As shown, it mainly controls the vertical and horizontal precision of the pipe 4 driven into the pipe shed by the laser line projector 5 to ensure the effective precision in the construction process of the advanced large pipe shed. If the node position of the device is not specified, it is uniformly connected by welding.
[0039] The following is a detailed description of a structural column reinforcement auxiliary binding device and a construction method of the present invention in conjunction with the accompanying drawings:
[0040] 1. Guide wall installation:
[0041] ① The guide wall and the retaining piles are connected by embedded reinforcement, and the I-beam 2 is welded to the steel bar and positioned at the bottom of the guide pipe;
[0042] ② Pre-embed the guide tube and weld it to the I-beam 2 after retesting;
[0043] ③ Use fixed steel bars 3 to perform double-sided welding on the guide tube 1, as shown in the attached figure for details;
[0044] ④ After the guide wall is installed and its accuracy is verified, seal the formwork and pour concrete.
[0045] 2. Set up the working platform and put the drilling rig in place: The construction platform of the tunnel mouth pipe shed adopts an excavation platform or a steel pipe scaffolding platform. It uses a combination of total station, hanging line and drill rod guidance to make repeated adjustments to ensure that the axis of the drill rod of the drilling rig coincides with the axis of the hole mouth pipe.
[0046] 3. Drilling: The following pipe drilling process is adopted. The height of the drilling rig platform is determined according to the adjustable range of the drilling rig and the drilling sequence. Since the drilling sequence of the drilling rig is from high hole position to low hole position, the platform position is gradually lowered from top to bottom to meet the drilling needs.
[0047] 4. Laser line projector assisted positioning: During the drilling operation, a laser line projector 5 is used to measure the mark point 6 as the positioning point to adjust the position of the pipe-roof pipe 4 during the drilling process. A positioning adjustment is made once a section of the pipe-roof pipe 4 is drilled;
[0048] 5. Adjust the bracket: adjust the drilling offset of the pipe 4 of the pipe shed by adjusting the bracket 8 to ensure the accuracy of the pipe shed construction;
[0049] 6. Install the grout stop plug: After the pipe rack pipe 4 is drilled in as a whole, install the grout stop plug and start drilling the next pipe rack pipe 4.
[0050] In step 4 above, if Figure 4 and 5 As shown, the intersection of the horizontal and vertical cross lasers emitted by the laser line projector 5 is the measurement mark point 6. The measurement mark point 6 changes with the laser line projector 5 from time to time. The operation steps are as follows:
[0051] 1. Set up a laser line projector 5 at the rear of the pipe 4 construction to ensure that the water bubble is centered and projected toward the middle wall of the guide wall;
[0052] 2. Set the measurement mark point 6 at the intersection of the horizontal and vertical directions of the laser projection point. The measurement mark point 6 is pasted with an adhesive "+" sign sticker at the position that coincides with the laser focus to ensure that there is no displacement;
[0053] 3. Use the tower ruler 7 to measure the distance between the initial state of the pipe rack pipe 4 and the laser (horizontally and vertically) to ensure that the displacement is controlled within ±1mm after each drilling;
[0054] 4. When the laser projection device 5 is used for a long time or intermittently, if the "+" sign sticker does not overlap with the laser, the previously used sticker can be torn off and a new sticker can be pasted to the laser overlap position to control the drilling accuracy of the pipe rack pipe 4.
[0055] In the above embodiment, during the construction process, if the laser line projector 5 is displaced, it can be judged by observing its horizontal bubble. If the bubble is in the center, it is considered that it has not been displaced; if the bubble is offset, it is considered that it has been displaced, and the instrument is re-erected to keep the bubble in the center. During the construction process, if the "+" sign sticker is displaced, it can be judged by whether it coincides with the laser beam. If the sticker coincides with the laser beam, it is considered that it has not been displaced; if the sticker does not coincide with the laser beam, observe whether the instrument bubble is centered to determine whether the sticker has been displaced. If it has been displaced, a new sticker can be re-pasted to the laser overlap position to readjust the position of the sticker. During the construction process, if the pipe-roof pipe 4 is displaced, it can be judged by the horizontal and vertical scales measured by the tower ruler 7 with the pipe-roof pipe 4 in the initial state. If the scale does not exceed the initial scale ±1mm, it is considered that it has not been displaced; if the scale exceeds the initial scale ±1mm, it is considered that it has been displaced, and it can be adjusted by adjusting the bracket 8 to control its scale within the range of the initial scale ±1mm.
[0056] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. A method for controlling the construction accuracy of drilling holes in a tunnel cover pipe shed guide pipe, characterized in that: The steps include: Step S1. installing the guide wall, wherein the guide wall and the retaining piles are connected by embedded reinforcement; Step S2. Set up the construction platform of the hole pipe shed and put the drilling rig in place, ensuring that the axis of the drilling rig drill rod coincides with the axis of the hole pipe; Step S3. Drilling, the height of the drilling platform is determined according to the adjustable range of the drilling rig and the drilling sequence. Since the drilling sequence of the drilling rig is from high hole position to low hole position, the platform position is gradually lowered from top to bottom to meet the drilling needs; Step S4. Laser line projection instrument assists positioning. During the drilling operation, a laser line projection instrument is used to measure the mark point as the positioning point, and the pipe rack pipe is adjusted during the drilling process. A positioning adjustment is made once a section of the pipe rack pipe is drilled; The step S4 specifically includes the following steps: Step S41. Set up a laser line projector at the rear of the pipe shed construction to ensure that the bubble is centered and projected toward the middle wall of the guide wall; Step S42. Set a measurement mark point at the intersection of the horizontal and vertical directions of the laser projection point. The measurement mark point is affixed with an adhesive "+" sign sticker at the position that coincides with the laser focus to ensure that no displacement occurs; Step S43. Use a tower ruler to measure the distance between the initial state of the pipe rack pipe and the laser focus to ensure that the displacement is controlled within ±1mm after each drilling; Step S44. When the laser line projector is used for a long time or intermittently, if the "+" sign sticker does not coincide with the laser focus, tear off the previously used sticker and re-stick a new sticker to the position that coincides with the laser focus to control the drilling accuracy of the pipe rack pipe; Step S5. Adjust the bracket used to support the pipe of the pipe rack, and adjust the drilling offset of the pipe rack pipe by adjusting the bracket to ensure the accuracy of the pipe rack construction; Step S6. Install the grout stopper. After the entire pipe rack pipe is drilled in, install the grout stopper and start drilling the next pipe rack pipe.
2. A method for controlling the construction accuracy of drilling holes in a tunnel cover pipe shed according to claim 1, characterized in that: The guide wall comprises a guide tube, an I-beam and fixed steel bars, wherein the guide tube is fixed above the I-beam, and adjacent guide tubes are connected by fixed steel bars.
3. A method for controlling the construction accuracy of drilling holes in a tunnel cover pipe shed according to claim 2, characterized in that: The guide wall construction steps are as follows: Step S11. The guide wall and the retaining piles are connected by embedded reinforcement, and the I-beam and the reinforcement are welded and positioned at the bottom of the guide pipe; Step S12. Pre-embed the guide tube and weld it to the I-beam after retesting; Step S13. Using fixed steel bars to perform double-sided welding on the guide tube; Step S14: After the guide wall is installed and its accuracy is verified, the formwork is sealed and concrete is poured.
4. The method for controlling the construction accuracy of drilling holes in a tunnel cover pipe shed according to claim 1 is characterized in that: In step S2, the tunnel entrance pipe scaffolding construction platform adopts an excavation platform or a steel pipe scaffolding platform.