A wind farm cluster active power coordinated control method based on hierarchical model

Through the active power coordination control method of wind farm clusters based on hierarchical model, combined with wavelet transformation and support vector machine algorithm for prediction and optimization scheduling, the contradiction between complex scheduling and rapid control of wind farm clusters is solved, and the wind power output and scheduling accuracy is improved. Reduced control deviation and fluctuation frequency.

CN114665519BActive Publication Date: 2024-11-05HOHAI UNIV
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202111539331.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-15
Publication Date
2024-11-05
Estimated Expiration
2041-12-15

AI Technical Summary

Technical Problem

The active power scheduling control of the wind farm group faces the contradiction between complexity and rapidity, and the wind power power prediction accuracy is negatively correlated with the period, resulting in serious wind power reduction and affecting the scheduling and control of the power system.

Method used

The active power coordination control method of wind farm clusters based on hierarchical model is adopted, combined with wavelet transformation analysis, autoregressive moving average model and least squares support vector machine algorithm for short-term and ultra-short-term power multi-step prediction, and the wind power system is decomposed into multiple controls Partitioning, rolling optimization is carried out layer by layer, and the amount to be adjusted is allocated through the secondary dynamic matrix control algorithm, and self-corrects in real time to achieve closed-loop control.

Benefits of technology

It improves the accuracy and robustness of wind power grid-connected scheduling, maximizes wind power output, reduces control deviations and fan power fluctuation frequency, and realizes a dynamic balance between optimized scheduling and real-time control of wind power system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114665519B_ABST
    Figure CN114665519B_ABST
Patent Text Reader

Abstract

The present invention discloses a wind farm cluster active power coordinated control method based on a hierarchical model, comprising the following steps: using a combined prediction model to perform short-term and ultra-short-term power multi-step prediction to obtain active power multi-time scale prediction information; obtaining the corresponding active power expected value and adjustment amount; establishing an improved multi-time scale optimization scheduling model based on a hierarchical model prediction control structure; allocating active power to be adjusted based on a quadratic dynamic matrix control algorithm; performing real-time self-correction on the wind turbine control error, formulating a hierarchical feedback correction strategy, and correcting the plan deviation layer by layer from bottom to top to achieve closed-loop control of the wind power system. The present invention can coordinate the contradiction between complex scheduling and fast real-time control of the system under large-scale wind power grid connection, and achieve good scheduling of wind power grid connection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power system operation and control, and in particular to a wind farm cluster active power coordinated control method based on a hierarchical model. Background Art

[0002] The wind power industry has become one of the fastest-growing new energy industries with its advantages of cleanliness, environmental protection, and economy. With the continuous expansion of the scale of wind power grid connection, the dispatching and control of wind power active power has gradually tended to cluster. However, the uncertainty and anti-peaking characteristics of wind power output have led to increasingly serious wind curtailment and power rationing, which has brought severe challenges to the dispatching and control of power systems. Therefore, formulating an active power optimization dispatching strategy for wind farm groups considering wind power output characteristics is the current research focus. There are two main methods to improve dispatching accuracy: improving wind power prediction accuracy and optimizing active power dispatching and control methods. To solve the above problems, model predictive control (MPC) has been widely introduced into the active power control of wind power systems as a finite time domain rolling optimization control method, which mainly consists of three links: prediction model, rolling time domain optimization, and self-correction. Compared with other active power control methods, the advantage of MPC is that it can adapt to the uncertain external environment through rolling optimization, update the local optimal solution, and use real-time information for feedforward-feedback control to achieve self-correction, suppress disturbances, and improve the robustness of control.

[0003] Wind farm group is a complex system with uncertainty, nonlinearity and time-varying characteristics. Its active power dispatching and control is a multi-objective optimization problem, and the performance indicators and time scales of optimal dispatching and real-time control are essentially different. Therefore, the contradiction between the complexity of wind power system optimal dispatching and the rapidity of real-time control is a key problem that needs to be solved urgently. The hierarchical control with the "decomposition-coordination" idea is an effective way to solve such problems. Hierarchical control mainly has two hierarchical control structures: spatial division and temporal division. MPC is combined with spatial hierarchical control to divide the entire wind power system into five control partitions: cluster planning and dispatching layer, farm group optimization allocation layer, single farm optimization allocation layer, unit cluster control layer and single machine active power control layer. A multi-objective optimal dispatching model is established for each layer, which is refined step by step and coordinated between levels, which helps to improve the accuracy of optimal dispatching and reduce control deviation.

[0004] In order to improve the accuracy of wind power prediction, the following three methods are generally used to improve the prediction accuracy: strengthening wind power data management and preprocessing, optimizing prediction models and various prediction links, and studying prediction error characteristics analysis and compensation methods. However, complex prediction models will reduce the prediction speed while achieving high-precision predictions, which will have an adverse impact on active power scheduling and control. Therefore, the structural complexity of the prediction model needs to be considered when performing active power optimization scheduling. Since the wind power prediction cycle is negatively correlated with the prediction accuracy, multi-time scale coordination is also an effective way to weaken the adverse effects of wind power output characteristics. In existing studies, the minimum time scale for wind power to participate in scheduling is generally set to 5 minutes, and adding a scheduling link with a shorter control cycle has a more obvious impact on the wind power consumption level and system robustness. Summary of the invention

[0005] In view of the deficiencies in the prior art, the present invention provides a wind farm cluster active power coordinated control method based on a hierarchical model, which can coordinate the contradiction between complex system scheduling and fast real-time control under large-scale wind power grid connection, and realize good scheduling of wind power grid connection.

[0006] To achieve the above object, the present invention adopts the following technical solutions:

[0007] The embodiment of the present invention proposes a wind farm cluster active power coordinated control method based on a hierarchical model, and the control method comprises the following steps:

[0008] S1: Establish a combined prediction model based on wavelet transform analysis, autoregressive moving average model, and least squares support vector machine algorithm, use the combined prediction model to perform short-term and ultra-short-term power multi-step prediction, and obtain active power multi-time scale prediction information;

[0009] S2: Determine the operation mode of the wind farm cluster according to the day-ahead forecast value of the wind farm cluster and the grid dispatch plan value, and obtain the corresponding active power expected value and adjustment amount according to the operation mode; the operation mode of the wind farm cluster includes the dispatch plan tracking mode and the maximum power tracking mode;

[0010] S3: Establish an improved multi-time scale optimization scheduling model based on hierarchical model predictive control structure, divide the entire wind farm cluster into five control partitions: cluster planning scheduling layer, farm cluster rolling optimization layer, single farm optimization allocation layer, unit cluster control layer, and single machine power management layer, and perform rolling optimization layer by layer;

[0011] S4: Allocate active power to be regulated based on the quadratic dynamic matrix control algorithm;

[0012] S5: Perform real-time self-correction on wind turbine control errors, formulate a hierarchical feedback correction strategy, correct the planned deviation layer by layer from bottom to top, and realize closed-loop control of the wind power system.

[0013] Furthermore, in step S1, the process of using the combined prediction model to perform short-term and ultra-short-term power multi-step prediction includes the following sub-steps:

[0014] S1.1: Select the db6 wavelet basis function to decompose the original wind speed and wind power time series into four layers, namely high-frequency signals D1, D2, D3, D4 and low-frequency signal A4;

[0015] S1.2: Screen and delete high-frequency interference signals including D1 and D2;

[0016] S1.3: Two monomer models are used to predict the remaining components. The ARMA model is used to predict the high-frequency components with violent fluctuations, and the LSSVM algorithm is used to predict the low-frequency series with slow fluctuations.

[0017] S1.4: Superimpose the prediction results of each component to obtain the final wind power prediction value

[0018] Furthermore, in step S2, the operation mode of the wind farm cluster is determined according to the day-ahead forecast value of the wind farm cluster and the grid dispatch plan value, and the process of obtaining the corresponding expected active power value and adjustment amount according to the operation mode includes the following sub-steps:

[0019] S2.1: judge the day-ahead forecast value of the wind farm cluster and the grid dispatch plan value. If the day-ahead forecast result of the wind farm cluster is greater than the system dispatch instruction, it is determined that the wind farm cluster is in the dispatch plan tracking mode; otherwise, it is determined that the wind farm cluster is in the maximum power tracking mode;

[0020] S2.2: Obtain the expected value of the overall active power of the wind farm cluster according to the following formula: and adjustment amount

[0021]

[0022]

[0023] in is the scheduling instruction issued by the system at time t+Δt, Δt=1h, and are the predicted power of wind farm j in farm group i at time t+Δt and the actual power at time t, respectively.

[0024] Furthermore, step S3, the process of establishing an improved multi-time scale optimization scheduling model based on a hierarchical model predictive control (HMPC) structure includes the following sub-steps:

[0025] S3.1: Dynamic grouping based on wind power forecast information:

[0026] S3.1.1: Generate a wind farm active power forecast trend set with a time interval of 1h based on the wind power forecast value in step S1 Calculate the trend change factor T i,t :

[0027]

[0028]

[0029] In formula (3) is the ultra-short-term predicted power of the wind farm; in formula (4), sign(x) is the sign function, is the difference between the power prediction values ​​of two adjacent sampling points;

[0030] S3.1.2: Introducing power range difference Δ i and fluctuation threshold η i Two statistical concepts are used as clustering indicators:

[0031]

[0032] Among them, P i N is the installed capacity of wind farm i;

[0033] S3.1.3: Based on the grouping index, the wind farm clusters are divided into four types of farm groups: power increase group, power reduction group, power constant group, and power oscillation group, and the farm group output priority is determined according to the grouping results;

[0034] S3.2: For the cluster scheduling layer, the farm groups and their quantity C involved in active power regulation are determined according to the active power to be regulated in step S2 and the farm group output order in step S3.1.3:

[0035] If the cluster runs in the scheduling tracking mode, the optimization control goal of the cluster scheduling layer is to maximize the wind power output while smoothing the wind power fluctuation as much as possible. The objective function expression is:

[0036]

[0037]

[0038] In formula (6), N is the number of wind farms in each cluster, represents the optimal output of wind farm group i in the period t+Δt, α i1 and α i2 is the error weight coefficient, and α i1 +α i2=1; Formula (7) is the constraint condition, including the scheduling plan tracking constraint, the farm group output limit constraint, and the farm group output ramp constraint. M is the number of farm groups in the wind power cluster, P i min and P i max Respectively represent the minimum and maximum output of field group i, C clu is the wind power cluster ramp rate limit, Installed capacity for wind power clusters;

[0039] If the cluster operates in the maximum power tracking mode, the control objective of the cluster scheduling layer becomes to maximize the wind power tracking accuracy. The objective function expression is:

[0040]

[0041]

[0042] S3.3: For the wind farm rolling optimization layer, the active power allocation plan is corrected based on the latest ultra-short-term predicted power. The optimization time domain is 1 hour and the rolling cycle is 30 minutes. The wind farm rolling optimization layer takes tracking the instructions issued by the wind farm group, smoothing the power fluctuation of the wind farm and maximizing the output of the wind farm as the optimization goals. The objective function is shown in the following formula:

[0043]

[0044]

[0045] In formula (10), represents the optimal allocation value of wind farm j, is the predicted value of wind farm j at time t+Δt′, Δt′=30min, R is the rolling number, R=2, and only the result when k=1 is issued for each optimization; Formula (11) includes low predicted power constraints, command tracking constraints, and wind farm and farm group climbing constraints.

[0046] S3.4: For the single-field optimization allocation layer connecting the field group and the machine group, the power generation potential and operating conditions of the wind turbines are used as the classification basis, and the dynamic classification of the units is carried out every 15 minutes:

[0047] S3.4.1: Based on the actual wind speed information v(t), the wind turbine operation area is divided into low wind speed area, medium wind speed area and high wind speed area; combined with the predicted wind speed v at the next moment pre (t+Δt″) determines the start and stop of the unit;

[0048] The criteria for starting the unit are:

[0049]

[0050] Where v ci and v co is the cut-in and cut-out wind speed of the fan; the units that meet the following inequalities are classified as shutdown units:

[0051]

[0052] S3.4.2: Calculate the power change rate k based on the historical output, actual output and predicted output of the wind turbine jm , generating the trend change factor β jm :

[0053]

[0054] Where P jmN is the rated installed capacity of unit m in wind farm j;

[0055] S3.4.3: Based on actual wind speed information v(t) and trend change factor β jm , divide the wind turbines into 11 types of groups: low wind speed power increase, low wind speed power unchanged, low wind speed power reduction, medium wind speed power increase, medium wind speed power unchanged, medium wind speed power reduction, high wind speed power increase, high wind speed power unchanged, high wind speed power reduction, start-up groups, and shutdown groups, and determine the output power priority of each group;

[0056] S3.5: According to the active power allocation value of wind farm j in step S3.3 and the classification result and priority in step S3.4, the group and number g participating in active power control (APC) are determined. The rolling optimization algorithm of the group control layer is expressed as:

[0057] for R=1∶2

[0058]

[0059] end

[0060] in represents the output power of the group not participating in active power control (APC) at time t+Δt″, Δt″=15min, It represents the optimal output of the group participating in active power regulation; the final output power of each group at time t+Δt″ is

[0061] S3.6: After the single-field optimization allocation layer issues the allocation instruction to the unit group control layer, the unit group control layer performs rolling optimization every 5 minutes and allocates active power to the single-field optimization allocation layer; the rolling control objective function of the unit group control layer is:

[0062]

[0063]

[0064] In formula (16) is the optimal power of fan j in cluster i at time t+Δt″′, Δt″′=5min, m is the total number of fans in cluster i;

[0065] S3.7: The single-field optimization distribution layer performs active power control every 1 minute within 5 minutes; the single machine uses its own active power control system (APC system) to perform rolling optimization and feedback correction of active power; the control target of the single machine power management layer is to minimize the deviation between the unit output power and the distribution instructions issued by the group control layer, and the performance indicators of rolling optimization per minute are:

[0066] J err =(P ij,t+1 -P ij,t ) 2 (40)

[0067]

[0068] Where P ij,t+1 and P ij,t The target value at the next moment and the real-time power at moment t are respectively; the constraints include the wind turbine output power limit and climbing limit.

[0069] Furthermore, in step S4, the process of allocating the active power to be adjusted based on the quadratic dynamic matrix control algorithm includes the following sub-steps:

[0070] The incremental algorithm is used to construct the secondary optimization performance index. The optimal output power and active power adjustment are used as output variables and control input variables respectively. The relationship between the two is obtained according to the proportional superposition characteristics as shown below:

[0071] P opt (t+Δt)=P real (t)+AΔP opt (t+Δt) (42)

[0072] Where P opt (t+Δt) and ΔP opt (t+Δt) represents the planned output matrix and power control increment matrix at time t+Δt, Δt represents the rolling period of each layer, A is the active power control (APC) target change matrix, if the control target changes, the corresponding element of the matrix is ​​1, otherwise it is 0; the objective function and constraint conditions of each layer of the optimization scheduling model are simultaneously vectorized into a standard quadratic form, and the control increment matrix ΔP is obtained by performing a quadratic programming solution online through MATLAB opt(t+Δt).

[0073] Furthermore, in step S5, a hierarchical feedback correction strategy is formulated, and the process of correcting the plan deviation layer by layer from bottom to top includes the following sub-steps:

[0074] S51, the output power after feedback correction It is expressed as:

[0075]

[0076] S52, use the following formula to correct the plan deviation from bottom to top layer by layer:

[0077]

[0078] Where W is the error weight matrix, E is the error matrix, and T is the optimization period of each layer.

[0079] Based on the traditional active power dispatching of the power grid and the "5min-15min-60min" intelligent dispatching model, the present invention further refines the rolling control time scale into "1min-5min-15min-30min-60min", formulates an improved multi-time scale active power dispatching strategy for wind farm clusters, overcomes the negative impact of wind power output characteristics, maximizes wind power output, minimizes control deviation, and reduces the frequency of wind turbine output power fluctuations while improving the tracking accuracy of the dispatching plan.

[0080] The beneficial effects of the present invention are:

[0081] The proposed method for coordinated control of active power of wind farm clusters based on hierarchical model can maximize wind power output, minimize control deviation, and reduce the frequency of wind turbine power fluctuation as much as possible while improving the tracking accuracy of scheduling plan. The rolling time domain optimization strategy based on QDMC converts the power variation into control variables, and executes the feedback correction link at the same time, so that the optimization result is accurate and reliable, which can effectively deal with the uncertainty and anti-peak characteristics of wind power output, weaken the impact of prediction error on active power scheduling control, and achieve the dynamic balance between wind power system optimization scheduling and real-time control, as well as the friendly scheduling of wind power clusters by the power system. BRIEF DESCRIPTION OF THE DRAWINGS

[0082] Figure 1 This is a flowchart of short-term and ultra-short-term power multi-step prediction based on WT-LSSVM-ARMA in a specific implementation manner of the present invention.

[0083] Figure 2 This is a flow chart of the active power prediction process of the present invention.

[0084] Figure 3The invention provides an improved multi-time-scale active power control timing diagram in a specific implementation manner of the present invention. DETAILED DESCRIPTION

[0085] The present invention will now be described in further detail with reference to the accompanying drawings.

[0086] It should be noted that the terms such as "upper", "lower", "left", "right", "front", "back", etc. cited in the invention are only for the convenience of description and are not used to limit the scope of implementation of the present invention. Changes or adjustments in their relative relationships should be regarded as the scope of implementation of the present invention without substantially changing the technical content.

[0087] See also Figure 1 This embodiment provides a wind farm cluster active power coordinated control method based on hierarchical model predictive control, comprising the following steps:

[0088] S1: A combined prediction model based on wavelet transform (WT) analysis, autoregressive moving average (ARMA) model, and least squares support vector machine (LSSVM) algorithm is established to obtain multi-time scale prediction information of active power.

[0089] S2: Determine the WFC operation mode based on the day-ahead forecast value of the wind farm cluster (WFC) and the grid dispatch plan value, and obtain the expected value and adjustment amount of active power.

[0090] S3: Establish an improved multi-time scale optimization scheduling model based on the hierarchical model predictive control (HMPC) structure.

[0091] S4: The active power to be regulated is allocated based on the quadratic dynamic matrix control (QDMC) algorithm.

[0092] S5: Perform real-time self-correction on wind turbine control errors, formulate a hierarchical feedback correction strategy, correct the planned deviation layer by layer from bottom to top, and realize closed-loop control of the wind power system.

[0093] See also Figure 2 In step S1, a prediction model based on the fusion of WT, LSSVM and ARMA models is selected to perform short-term and ultra-short-term power multi-step prediction. The specific prediction process is as follows:

[0094] S1.1: Select the db6 wavelet basis function to decompose the original wind speed and wind power time series into four layers, namely high frequency (HF) signals D1, D2, D3, D4 and low frequency (LF) signal A4.

[0095] S1.2: Filter and delete high-frequency interference signals including D1 and D2 to improve prediction accuracy.

[0096] S1.3: The remaining components are predicted by the individual models. The ARMA model is used for the high-frequency components with violent fluctuations, and the LSSVM algorithm is used for the low-frequency series with slow fluctuations.

[0097] S1.4: Superimpose and synthesize the prediction results of each component to obtain the final wind power prediction value.

[0098] In step S2, according to the relationship between the predicted power and the dispatch instruction in step S1.4, WFC can be summarized into the following two operating modes: if the WFC day-ahead prediction result is greater than the system dispatch instruction, the WFC is in the "dispatch plan tracking" mode; if the day-ahead prediction result is less than the system dispatch instruction, the WFC is in the "maximum power tracking" mode. After determining the operating mode, the expected value of the overall active power of the WFC is obtained. and adjustment amount

[0099]

[0100]

[0101] in is the scheduling instruction issued by the system at time t+Δt, Δt=1h, and are the predicted power of wind farm j in farm group i at time t+Δt and the actual power at time t, respectively.

[0102] See also Figure 3 In step S3, the improved multi-time scale optimization scheduling model based on the HMPC structure divides the entire wind farm cluster into five control partitions: cluster planning scheduling layer, farm group rolling optimization layer, single farm optimization allocation layer, unit cluster control layer, and single machine power management layer. The optimization scheduling model of each layer is built as follows:

[0103] S3.1: This embodiment proposes a dynamic grouping strategy based on wind power prediction information: according to the power prediction value in step S1.4, a wind farm active power prediction trend set with a time interval of 1h is generated. Then calculate the trend change factor T i,t , the expression is as follows:

[0104]

[0105]

[0106] In formula (3) is the ultra-short-term predicted power of the wind farm. In formula (4), sign(x) is the sign function, is the difference between the power prediction values ​​of two adjacent sampling points.

[0107] Further introduce the "power difference" Δ i and the “fluctuation threshold” η i The two statistical concepts are used as clustering indicators, and the expression is shown in formula (5).

[0108]

[0109] Among them, P i N is the installed capacity of wind farm i.

[0110] Based on the above grouping indicators, wind power clusters are divided into four types of clusters: power increase group, power reduction group, power constant group, and power oscillation group. The output priority of the clusters is determined according to the grouping results. The power output priority is shown in Table 1.

[0111] Table 1 Output priority of farm groups

[0112] Scheduling instruction changes Output priority Power increase 1>4>3>2 Power reduction 2>4>3>1

[0113] At the cluster level, the farm groups and their quantity C involved in active power regulation are determined according to the active power to be regulated in step S2 and the farm group output order in step S3.1. If the cluster operates in the "dispatching plan tracking" mode, the optimization control goal of this layer is to maximize the wind power output while smoothing the wind power fluctuation as much as possible. The objective function expression is:

[0114]

[0115]

[0116] In formula (6), N is the number of wind farms in each cluster, represents the optimal output of wind farm group i in the period t+Δt, α i1 and α i2 is the error weight coefficient, and α i1 +α i2 =1. Formula (7) is the constraint condition, which mainly includes the scheduling plan tracking constraint, the farm group output limit constraint, and the farm group output ramp constraint. M is the number of farm groups in the wind power cluster, P i min and P i max Respectively represent the minimum and maximum output of field group i, C clu is the wind power cluster ramp rate limit, Installed capacity for wind power clusters.

[0117] If the cluster operates in the "maximum power tracking" mode, the control objective of this layer becomes to maximize the wind power tracking accuracy. The objective function expression is:

[0118]

[0119]

[0120] S3.3: The wind farm rolling optimization layer amends the active power allocation plan based on the latest ultra-short-term predicted power. The optimization time domain is 1 hour, and the rolling cycle is 30 minutes. The optimization objectives of this layer are to track the instructions issued by the wind farm group, smooth the power fluctuation of the wind farm, and maximize the output of the wind farm. The objective function is shown in the following formula:

[0121]

[0122]

[0123] In formula (10), represents the optimal allocation value of wind farm j, is the predicted value of wind farm j at time t+Δt′, Δt′=30min, R is the rolling number, R=2, and each optimization only sends the result when k=1. Formula (11) includes low predicted power constraint, command tracking constraint, and wind farm and farm group climbing constraint.

[0124] S3.4: The single field layer connects the field group and the machine group, and plays a bridging role in APC. Improving the active power control accuracy of the wind farm is the core task of this layer. The present invention uses the power generation potential and operating conditions of the wind turbines as the classification basis, and performs dynamic classification of the units every 15 minutes.

[0125] According to the actual wind speed information v(t), the wind turbine operation area is roughly divided into low wind speed area, medium wind speed area and high wind speed area; combined with the predicted wind speed v at the next moment pre (t+Δt″) determines the start and stop of the unit.

[0126] For example, the judgment criteria for starting the unit are as follows:

[0127]

[0128] Where v ci and v co is the cut-in and cut-out wind speed of the fan. The units that meet the following inequalities are classified as shutdown units:

[0129]

[0130] The second classification basis is the wind turbine active power trend change factor. The present invention calculates the power change rate k based on the wind turbine historical output, actual output and predicted output. jm , generating the trend change factor β jm , dynamically classify the units and effectively solve the problem of active power distribution in the field. Trend change factor βjm Through formula (14), we can get:

[0131]

[0132] Where P jmN is the rated installed capacity of unit m in wind farm j.

[0133] Based on the above classification criteria, wind turbines are divided into 11 categories, namely, low wind speed power increase, low wind speed power unchanged, low wind speed power reduction, medium wind speed power increase, medium wind speed power unchanged, medium wind speed power reduction, high wind speed power increase, high wind speed power unchanged, high wind speed power reduction, starting units, and shutting units, and the output power priority of each unit group is determined accordingly.

[0134] S3.5: According to the active power distribution value of wind farm j in step S3.3 and the classification result and priority in step S3.4, the group and number g participating in APC are determined. The layer rolling optimization algorithm can be expressed as:

[0135] for R=1∶2

[0136]

[0137] end

[0138] in represents the output power of the cluster not participating in APC at time t+Δt″, Δt″=15min, and It represents the optimal output of the group participating in active power regulation. Finally, the output power of each group at time t+Δt″ is

[0139] S3.6: After the single field layer issues the allocation instruction to the unit layer, the unit layer performs rolling optimization every 5 minutes and allocates active power to the single machine layer. In order to further improve the dispatching accuracy and reduce the fluctuation frequency of wind turbines, the rolling control objective function of this layer is set as:

[0140]

[0141]

[0142] In formula (16) is the optimized power of fan j in cluster i at time t+Δt″′, Δt″′=5min, and m is the total number of fans in cluster i.

[0143] S3.7: The single machine layer performs active power control every 1 minute within 5 minutes. The single machine realizes rolling optimization and feedback correction of active power through its own APC system. The control target of the single machine power management layer is to minimize the deviation between the unit output power and the allocation instructions issued by the group control layer. Therefore, the performance index of rolling optimization per minute is:

[0144] J err =(P ij,t+1 -P ij,t ) 2 (62)

[0145]

[0146] Where P ij,t+1 and P ij,t The next moment target value and the real-time power at moment t are respectively. The constraints mainly include wind turbine output power limit and ramp limit.

[0147] In step S4, the QDMC algorithm uses an incremental algorithm to construct a secondary optimization performance index, taking the optimal output power and active power adjustment as output variables and control input variables respectively. The relationship between the two is obtained according to the proportional superposition characteristics as follows:

[0148] P opt (t+Δt)=P real (t)+AΔP opt (t+Δt) (20)

[0149] Where P opt (t+Δt) and ΔP opt (t+Δt) represents the planned output matrix and power control increment matrix of each fleet at time t+Δt, Δt represents the rolling cycle of each layer, A is the APC target change matrix, if the control target changes, the corresponding element of the matrix is ​​1, otherwise it is 0. To ensure the consistency of the model, the objective function and constraint conditions of each layer of the optimization scheduling model are simultaneously vectorized into a standard quadratic form, and the control increment matrix ΔP opt (t+Δt) can be obtained by solving the quadratic programming online through MATLAB.

[0150] In step S5, the hierarchical feedback correction strategy is used to correct the planned deviation layer by layer from bottom to top, and the fan control error is corrected through the self-correction link. Output power after feedback correction It can be expressed as:

[0151]

[0152]

[0153] Where W is the error weight matrix, E is the error matrix, and T is the optimization period of each layer.

[0154] The above are only preferred embodiments of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should be regarded as the protection scope of the present invention.

Claims

1. A wind farm cluster active power coordinated control method based on a hierarchical model, characterized in that: The control method comprises the following steps: S1: Establish a combined prediction model based on wavelet transform analysis, autoregressive moving average model, and least squares support vector machine algorithm, use the combined prediction model to perform short-term and ultra-short-term power multi-step prediction, and obtain active power multi-time scale prediction information; S2: Determine the operation mode of the wind farm cluster according to the day-ahead forecast value of the wind farm cluster and the grid dispatch plan value, and obtain the corresponding active power expected value and adjustment amount according to the operation mode; the operation mode of the wind farm cluster includes the dispatch plan tracking mode and the maximum power tracking mode; S3: Establish an improved multi-time scale optimization scheduling model based on hierarchical model predictive control structure, divide the entire wind farm cluster into five control partitions: cluster planning scheduling layer, farm cluster rolling optimization layer, single farm optimization allocation layer, unit cluster control layer, and single machine power management layer, and perform rolling optimization layer by layer; S4: Allocate active power to be adjusted based on the quadratic dynamic matrix control algorithm; S5: Perform real-time self-correction of wind turbine control errors, formulate hierarchical feedback correction strategies, correct plan deviations layer by layer from bottom to top, and realize closed-loop control of wind power systems; In step S1, the process of using the combined prediction model to perform short-term and ultra-short-term power multi-step prediction includes the following sub-steps: S1.1: Select the db6 wavelet basis function to decompose the original wind speed and wind power time series into four layers, namely high-frequency signals D1, D2, D3, D4 and low-frequency signal A4; S1.2: Screen and delete high-frequency interference signals including D1 and D2; S1.3: Two monomer models are used to predict the remaining components. The ARMA model is used to predict the high-frequency components with violent fluctuations, and the LSSVM algorithm is used to predict the low-frequency series with slow fluctuations. S1.4: superimpose and synthesize the prediction results of each component to obtain the final wind power prediction value; In step S2, the operation mode of the wind farm cluster is determined according to the day-ahead forecast value of the wind farm cluster and the grid dispatch plan value, and the process of obtaining the corresponding active power expected value and adjustment amount according to the operation mode includes the following sub-steps: S2.1: judge the day-ahead forecast value of the wind farm cluster and the grid dispatch plan value. If the day-ahead forecast result of the wind farm cluster is greater than the system dispatch instruction, it is determined that the wind farm cluster is in the dispatch plan tracking mode; otherwise, it is determined that the wind farm cluster is in the maximum power tracking mode; S2.2: Obtain the expected value of the overall active power of the wind farm cluster according to the following formula: and adjustment amount in is the scheduling instruction issued by the system at time t+Δt, Δt=1h, and are the predicted power of wind farm j in farm group i at time t+Δt and the actual power at time t, respectively; Step S3, the process of establishing an improved multi-time scale optimization scheduling model based on a hierarchical model predictive control structure includes the following sub-steps: S3.1: Dynamic grouping based on wind power forecast information: S3.1.1: Generate a wind farm active power forecast trend set with a time interval of 1h based on the wind power forecast value in step S1 Calculate the trend change factor T i,t : In formula (3) k = 0, 15, 30, 45, 60 is the ultra-short-term predicted power of the wind farm; in formula (4), sign(x) is the sign function, m=15,30,45,60, n=0,15,30,45 is the difference between the power prediction values ​​of two adjacent sampling points; S3.1.2: Introducing power range difference Δ i and fluctuation threshold η i Two statistical concepts are used as clustering indicators: Among them, P i N is the installed capacity of wind farm i; S3.1.3: Based on the grouping index, the wind farm clusters are divided into four types of farm groups: power increase group, power reduction group, power constant group, and power oscillation group, and the farm group output priority is determined according to the grouping results; S3.2: For the cluster scheduling layer, the farm groups and their quantity C involved in active power regulation are determined according to the active power to be regulated in step S2 and the farm group output order in step S3.1.3: If the cluster runs in the scheduling tracking mode, the optimization control goal of the cluster scheduling layer is to maximize the wind power output while smoothing the wind power fluctuation as much as possible. The objective function expression is: In formula (6), N is the number of wind farms in each cluster, represents the optimal output of wind farm group i in the period t+Δt, α i1 and α i2 is the error weight coefficient, and α i1 +α i2 =1; Formula (7) is the constraint condition, including the scheduling plan tracking constraint, the farm group output limit constraint, and the farm group output ramp constraint. M is the number of farm groups in the wind power cluster, P i min and P i max Respectively represent the minimum and maximum output of field group i, C clu is the wind power cluster ramp rate limit, Installed capacity for wind power clusters; If the cluster operates in the maximum power tracking mode, the control objective of the cluster scheduling layer becomes to maximize the wind power tracking accuracy. The objective function expression is: S3.3: For the wind farm rolling optimization layer, the active power allocation plan is corrected based on the latest ultra-short-term predicted power. The optimization time domain is 1 hour and the rolling cycle is 30 minutes. The wind farm rolling optimization layer takes tracking the instructions issued by the wind farm group, smoothing the power fluctuation of the wind farm and maximizing the output of the wind farm as the optimization goals. The objective function is shown in the following formula: In formula (10) represents the optimal allocation value of wind farm j, is the predicted value of wind farm j at time t+Δt', Δt'=30min, R is the rolling number, R=2, and only the result when k=1 is issued for each optimization; Formula (11) includes low predicted power constraints, command tracking constraints, and wind farm and farm group climbing constraints; S3.4: For the single-field optimization allocation layer connecting the field group and the machine group, the power generation potential and operating conditions of the wind turbines are used as the classification basis, and the dynamic classification of the units is carried out every 15 minutes: S3.4.1: Based on the actual wind speed information v(t), the wind turbine operation area is divided into low wind speed area, medium wind speed area and high wind speed area; combined with the predicted wind speed v at the next moment pre (t+Δt”) determines the start and stop of the unit; The criteria for starting the unit are: Where v ci and v co is the cut-in and cut-out wind speed of the fan; the units that meet the following inequalities are classified as shutdown units: S3.4.2: Calculate the power change rate k based on the historical output, actual output and predicted output of the wind turbine jm , generating the trend change factor β jm : Where P jmN is the rated installed capacity of unit m in wind farm j; S3.4.3: Based on actual wind speed information v(t) and trend change factor β jm , divide the wind turbines into 11 types of groups, including low wind speed power increase, low wind speed power unchanged, low wind speed power reduction, medium wind speed power increase, medium wind speed power unchanged, medium wind speed power reduction, high wind speed power increase, high wind speed power unchanged, high wind speed power reduction, start-up groups, and shutdown groups, and determine the output power priority of each group; S3.5: According to the active power allocation value of wind farm j in step S3.3 and the classification result and priority in step S3.4, the group and number g participating in active power control are determined. The rolling optimization algorithm of the group control layer is expressed as: for R=1:2 end in represents the output power of the group not participating in active power control at time t+Δt”, Δt″=15min, It represents the optimal output of the group participating in active power regulation; the final output power of each group at time t+Δt” is S3.6: After the single-field optimization allocation layer issues the allocation instruction to the unit group control layer, the unit group control layer performs rolling optimization every 5 minutes and allocates active power to the single-field optimization allocation layer; the rolling control objective function of the unit group control layer is: In formula (16) is the optimal power of fan j in cluster i at time, Δt”’=5min, m is the total number of fans in cluster i; S3.7: The single-field optimization distribution layer performs active power control every 1 minute within 5 minutes; the single machine uses its own APC system to perform rolling optimization and feedback correction of active power; the control target of the single machine power management layer is to minimize the deviation between the unit output power and the distribution instructions issued by the group control layer, and the rolling optimization performance indicators per minute are: mice err =(P ij,t+1 -P ij,t ) 2 (18) Where P ij,t+1 and P ij,t The target value at the next moment and the real-time power at moment t are respectively; the constraints include the wind turbine output power limit and the ramp limit; In step S4, the process of allocating the active power to be adjusted based on the quadratic dynamic matrix control algorithm includes the following sub-steps: The incremental algorithm is used to construct the secondary optimization performance index. The optimal output power and active power adjustment are used as output variables and control input variables respectively. The relationship between the two is obtained according to the proportional superposition characteristics as shown below: P opt (t+Δt)=P real (t)+AΔP opt (t+Δt) (20) Where P opt (t+Δt) and ΔP opt (t+Δt) represents the planned output matrix and power control increment matrix at time t+Δt, Δt represents the rolling period of each layer, A is the active power control target change matrix, if the control target changes, the corresponding element of the matrix is ​​1, otherwise it is 0; the objective function and constraint conditions of each layer of the optimization scheduling model are simultaneously vectorized into a standard quadratic form, and the control increment matrix ΔP is obtained by performing a quadratic programming solution online through MATLAB opt (t+Δt); In step S5, a hierarchical feedback correction strategy is formulated, and the process of correcting the plan deviation layer by layer from bottom to top includes the following sub-steps: S51, the output power after feedback correction It is expressed as: S52, use the following formula to correct the plan deviation from bottom to top layer by layer: Where W is the error weight matrix, E is the error matrix, and T is the optimization period of each layer.

Citation Information

Patent Citations

  • Hierarchical multi-level grid regulation system and method for large building load cluster

    CN107046301A

  • Wind power cluster trajectory prediction and hierarchical control method

    CN107769254A

  • Multi-time-space layering comprehensive frequency modulation control system based on fan cluster

    CN113489073A

  • Prediction Method of Short-Term Wind Speed and Wind Power and Power Supply Line Voltage Prediction Method Therefore

    KR1020140018497A