A kind of automatic installation equipment for high altitude steel beam and construction method thereof
By using automatic installation equipment of corrupt leg support, guide rail and electric push rod in the installation of high-altitude steel beams, the problems of low installation efficiency and high safety risks in the existing technology are solved, and an efficient and safe steel beam installation process is achieved.
Patent Information
- Application Number
- CN202210313646.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-28
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2042-03-28
AI Technical Summary
The existing high-altitude steel beam installation methods have problems such as long mechanical occupation time, time-consuming and labor-intensive manual adjustment, low accuracy, and high safety risks.
An automatic installation device including corbel support, guide rail, horizontal electric push rod and vertical electric push rod is designed to achieve automatic correction and position adjustment of steel beams through these components to ensure installation accuracy and safety.
It improves the installation efficiency of steel beams, reduces labor costs, reduces safety risks, and achieves an efficient and safe installation process.
Smart Images

Figure CN114776036B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of high-altitude steel beam installation, and in particular to automatic installation equipment for high-altitude steel beams and a construction method thereof. Background Art
[0002] The installation of existing high-altitude steel frame steel beams is done by deploying an installation worker at each end, hoisting the steel beam with a tower crane, and pulling the steel beam into place with a traction rope. When the steel beam is hoisted to the corresponding span, it is manually adjusted, and then the connecting plate is installed and the temporary bolts are positioned and connected. This construction method has the disadvantages of long machine occupancy time, time-consuming and labor-intensive manual adjustment, low precision, and high safety risks. Summary of the invention
[0003] In order to overcome the deficiencies of the above technologies, the present invention provides an automatic installation device for high-altitude steel beams and a construction method thereof to improve the installation efficiency of high-altitude steel beams.
[0004] The technical solution adopted by the present invention to overcome the technical problems is: an automatic installation device for high-altitude steel beams, comprising:
[0005] two corbels;
[0006] Two guide rails, the sides of the two guide rails are respectively connected to the two corbel supports through horizontal electric push rods; the horizontal electric push rods on both sides are connected through a butt-jointed mother-and-child sleeve rod;
[0007] Two steel beam supports, the sides of the two steel beam supports are respectively slidably connected to the two guide rails, and the bottoms of the two steel beam supports are respectively connected to the two guide rails through vertical electric push rods.
[0008] Preferably, the guide rail is made of I-beam.
[0009] Preferably, the horizontal electric push rods are arranged in three groups.
[0010] The present invention also discloses a construction method for the automatic installation equipment of high-altitude steel beams, comprising the following steps:
[0011] S1. Install one installation device on each of the left and right installation steel columns, and install two brackets of the installation device on both sides of the brackets on the installation steel columns;
[0012] S2. The horizontal electric push rods on both sides are connected by docking the mother-and-child sleeve rods, the installation equipment is locked, and the horizontal electric push rods and vertical electric push rods are used to adjust the plane and vertical surface to within the installation specification error range;
[0013] S3. Use the vertical transport machinery to hoist the installation steel beam into place, adjust the steel beam support to the corresponding elevation through the vertical electric push rod, and use the steel beam support to support the installation steel beam to achieve early unhooking of the vertical transport machinery;
[0014] S4. By adjusting the horizontal electric push rod, the installation steel beam is positioned between the two installation steel columns. The reserved space is adjusted by combining the horizontal electric push rod with the vertical electric push rod to perform pushing movements to achieve the control of the installation accuracy of the steel beam and position it. Then the connecting plate is installed to complete the installation of the entire steel beam.
[0015] Compared with the prior art, the beneficial effects of the present invention are:
[0016] 1. The present invention uses the steel column bracket as a support and adjustment platform, which can realize automatic correction at high altitude and efficient unhooking of the tower crane. The electric push rod helps to adjust the misalignment of the steel beam, and the horizontal electric push rod can also ensure that the steel beam is anti-overturning, and the vertical electric push rod can also support the steel beam well, which not only ensures the safety of the operation, but also realizes the efficiency of the hoisting machinery.
[0017] 2. The present invention is easy to operate, intelligent and effective, safe and stable, can avoid the operational risks caused by falling from heights, is highly practical, easy to install and can be turned around, greatly improves the efficiency of steel beam installation, reduces labor costs, and avoids unnecessary risks. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic structural diagram of an embodiment of the present invention.
[0019] Figure 2 It is a construction schematic diagram of an embodiment of the present invention.
[0020] In the figure, 1. Guide rail; 2. Vertical electric push rod; 3. Docking mother-and-child sleeve rod; 4. Steel beam support; 5. Horizontal electric push rod; 6. Corbel support; 7. Install steel beam; 8. Install steel column. DETAILED DESCRIPTION
[0021] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below with reference to specific diagrams. Example
[0022] An automatic installation device for high-altitude steel beams, such as Figure 1As shown, it includes: two corbel supports 6 arranged opposite to each other, two steel beam supports 4 and two guide rails 1, the guide rail 1 is made of I-beam, the steel beam support 4 includes an L-shaped bottom plate, the upper end of the L-shaped bottom plate is provided with a clamp, and the lower end of the L-shaped bottom plate is provided with a stiffening plate to ensure the flatness and stability of the steel beam. The sides of the two guide rails 1 are respectively connected to the two corbel supports 6 through three groups of horizontal electric push rods 5, the output end of the horizontal electric push rod 5 is fixedly connected to the guide rail 1, and the opposite sides of the horizontal electric push rods 5 on both sides are connected through the docking mother-and-child sleeve rods 3; the sides of the two steel beam supports 4 are respectively slidably connected to the two guide rails 1, the bottoms of the two steel beam supports 4 are respectively connected to the two guide rails 1 through vertical electric push rods 2, and the output end of the vertical electric push rod 2 is fixedly connected to the stiffening plate of the steel beam support 4.
[0023] like Figure 2 As shown, the construction method of the automatic installation equipment includes the following steps:
[0024] S1, install a mounting device on each of the mounting steel columns 8 on the left and right sides, and install two bracket supports 6 of the mounting device on both sides of the brackets on the mounting steel columns 8;
[0025] S2, the horizontal electric push rods 5 on both sides are fixedly connected by docking the mother-and-child sleeve rods 3, the installation equipment is locked, and the horizontal electric push rods 5 and the vertical electric push rods 2 are adjusted to the error range of the installation specification in the plane and vertical plane;
[0026] S3, using the vertical transport machinery to hoist the installation steel beam 7 into place, adjusting the steel beam support 4 to the corresponding elevation through the vertical electric push rod 2, and using the steel beam support 4 to support the installation steel beam 7, so as to realize the early unhooking of the vertical transport machinery;
[0027] S4. By adjusting the horizontal electric push rod 5, the installation steel beam 7 is positioned between the two installation steel columns 8. The space reserved in the design is adjusted, and the horizontal electric push rod 5 and the vertical electric push rod 2 are combined to perform pushing movements to achieve control of the installation accuracy of the steel beam and position it. Then the connecting plate is installed to complete the installation of the entire steel beam.
[0028] The present invention uses the steel column bracket as a support and adjustment platform, which can realize high-altitude automatic correction and efficient unhooking of the tower crane. The electric push rod helps to adjust the misalignment of the steel beam, and the horizontal electric push rod 5 can also ensure that the steel beam is anti-overturning, and the vertical electric push rod 2 can also support the steel beam well, which not only ensures the safety of the operation, but also realizes the efficiency of the hoisting machinery.
[0029] It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the present invention, so they have no substantial technical significance. Any modification of the structure, change of the proportion relationship or adjustment of the size, without affecting the effect and purpose that can be produced by the present invention, should still fall within the scope of the technical content disclosed by the present invention. At the same time, the terms such as "upper", "lower", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description, and are not used to limit the scope of the implementation of the present invention. The change or adjustment of their relative relationship should also be regarded as the scope of the implementation of the present invention without substantially changing the technical content.
[0030] The above is a detailed description of the present invention in conjunction with the embodiments of the drawings. A person skilled in the art can make various variations of the present invention according to the above description. Therefore, certain details in the embodiments should not constitute a limitation of the present invention, and the scope of protection of the present invention shall be the scope defined by the attached claims.
Claims
1. An automatic installation device for high-altitude steel beams, It is characterized in that include: two corbels; Two guide rails, the sides of the two guide rails are respectively connected to the two corbel supports through horizontal electric push rods; the horizontal electric push rods on both sides are connected through a butt-jointed mother-and-child sleeve rod; Two steel beam supports, the sides of the two steel beam supports are respectively slidably connected to the two guide rails, and the bottoms of the two steel beam supports are respectively connected to the two guide rails through vertical electric push rods; The construction method for the automatic installation equipment of high-altitude steel beams comprises the following steps: S1. Install one installation device on each of the left and right installation steel columns, and install two brackets of the installation device on both sides of the bracket on the installation steel column; S2. The horizontal electric push rods on both sides are connected by docking the mother-and-child sleeve rods, the installation equipment is locked, and the horizontal electric push rods and vertical electric push rods are used to adjust the plane and vertical surface to within the error range of the installation specification; S3. Use the vertical transport machinery to hoist the installation steel beam into place, adjust it to the corresponding elevation through the vertical electric push rod, and use the steel beam support to support the installation steel beam to achieve early unhooking of the vertical transport machinery; S4. By adjusting the horizontal electric push rod, the installation steel beam is positioned between the two installation steel columns. The reserved space is adjusted by combining the horizontal electric push rod with the vertical electric push rod to perform pushing movements to achieve the control of the installation accuracy of the steel beam and position it. Then the connecting plate is installed to complete the installation of the entire steel beam.
2. The automatic installation equipment for high-altitude steel beams according to claim 1, It is characterized in that The guide rail is made of I-beam.
3. The automatic installation equipment for high-altitude steel beams according to claim 1, It is characterized in that The horizontal electric push rods are arranged in three groups.