A method for installing a floodlighting system

By using prefabricated aluminum profile fasteners and stainless steel self-tapping screws on the stone curtain wall, the problems of stone damage and low construction efficiency caused by traditional installation methods are solved, and a more efficient installation process and more beautiful effect are achieved.

CN114811535BActive Publication Date: 2024-11-01SHANGHAI BAOYE BUILDING DECORATION CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210451309.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-26
Publication Date
2024-11-01
Estimated Expiration
2042-04-26

AI Technical Summary

Technical Problem

The method of installing floodlight lighting systems in traditional stone curtain walls will damage the integrity of the stone and low construction efficiency, resulting in damage to the stone curtain wall and long construction time.

Method used

Using the combination method of prefabricated aluminum profile fasteners and stainless steel self-tapping screws, the self-tapping screws are inserted at the joints of the stone surface layer of the curtain wall without drilling, and the use of double-sided patches and structural adhesives ensures a firm installation. Sex and aesthetics.

Benefits of technology

The drilling process of the stone surface layer is reduced, damage is avoided, construction efficiency and aesthetics are improved, and construction time and cost are shortened.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114811535B_ABST
    Figure CN114811535B_ABST
Patent Text Reader

Abstract

The invention relates to an installation method of a floodlighting system, comprising the following steps: determining a lamp trough fixing position on a curtain wall stone surface layer; gluing a prefabricated aluminum profile fastener to the lamp trough fixing position on the curtain wall stone; inserting one end of a stainless steel self-tapping screw through the prefabricated aluminum profile fastener and into a joint of the curtain wall stone surface layer; installing a lighting lamp; on the one hand, compared with a traditional method of installing a fixing component for fixing a floodlighting system, the method reduces the curtain wall stone surface layer drilling process, saves construction time and cost, and avoids damage to the curtain wall stone surface layer caused by drilling; on the other hand, by adopting the prefabricated aluminum profile fastener, the operation is simple, thereby improving the construction efficiency and shortening the construction time; at the same time, the overall aesthetics of the lamp trough after molding is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building decoration, and in particular to an installation method of a floodlighting system. Background Art

[0002] At present, the construction area of ​​stone curtain walls is expanding, and the application of floodlighting systems is becoming more and more common. The traditional stone curtain wall installation of floodlighting systems requires the use of special tools to open holes in the stone curtain walls to install fixed components for fixing the floodlighting systems.

[0003] However, the traditional way of installing fixed components will destroy the integrity of the stone curtain wall, and the construction process will easily cause damage to the stone curtain wall; at the same time, it will lead to low construction efficiency. Summary of the invention

[0004] In view of the shortcomings of the prior art, the purpose of the present invention is to provide an installation method of a floodlighting system, which has the advantages of avoiding damage to the stone curtain wall and ensuring the integrity of the stone curtain wall; at the same time, it improves the construction efficiency and shortens the construction period.

[0005] The above-mentioned invention object of the present invention is achieved through the following technical solution: A method for installing a floodlighting system comprises the following steps:

[0006] Determine the fixing position of the light trough on the stone surface of the curtain wall;

[0007] Adhere the prefabricated aluminum profile fasteners to the light trough fixing positions on the curtain wall stone;

[0008] Pass one end of the stainless steel self-tapping screw through the prefabricated aluminum profile fastener and insert it into the joint of the curtain wall stone surface layer;

[0009] Install lighting.

[0010] Preferably, the method for installing the floodlighting system provided by the present invention, wherein the fixing position of the light trough is determined on the stone surface layer of the curtain wall, specifically comprises:

[0011] After the construction of the curtain wall stone surface layer is completed and accepted, the light trough points are laid out and positioned according to the given drawings;

[0012] Hang a plumb line on the top of the curtain wall stone, measure and determine the fixed position of the lamp trough after the plumb line is stable, and mark the fixed position of the lamp trough;

[0013] Determine the fixing positions of the remaining light troughs.

[0014] Preferably, the method for installing the floodlighting system provided by the present invention, wherein the prefabricated aluminum profile fasteners are glued to the lamp trough fixing positions on the curtain wall stone, specifically comprises:

[0015] Paste the double-sided tape on the light trough fixing position on the curtain wall stone;

[0016] Applying structural adhesive on opposite sides of the double-sided tape;

[0017] The prefabricated aluminum profile fastener is adhered to the double-sided adhesive tape.

[0018] Preferably, the installation method of the floodlighting system provided by the present invention, after determining the fixing position of the lamp trough on the curtain wall stone surface layer and before gluing the prefabricated aluminum profile fasteners to the fixing position of the lamp trough on the curtain wall stone, further includes: cleaning the dust and laitance on the surface of the curtain wall stone surface layer.

[0019] Preferably, in the installation method of the floodlighting system provided by the present invention, the depth of the stainless steel self-tapping screws inserted into the joint is greater than or equal to 50 mm.

[0020] Preferably, in the installation method of the floodlighting system provided by the present invention, the prefabricated aluminum profile fastener includes a first horizontal plate, a second horizontal plate, a first vertical plate and a second vertical plate, the first horizontal plate and the second horizontal plate are spaced apart and arranged on the first vertical plate, and the end of the second horizontal plate facing away from the first vertical plate is connected to the top of the second vertical plate; the first horizontal plate, the second horizontal plate and the first vertical plate are jointly arranged to form an installation cavity, and the second horizontal plate, the second vertical plate and the first vertical plate are jointly arranged to form a receiving cavity.

[0021] Preferably, the installation method of the floodlighting system provided by the present invention, after inserting one end of the stainless steel self-tapping screw through the prefabricated aluminum profile fastener and into the joint of the curtain wall stone surface layer, and before installing the lighting lamp, also includes: covering the prefabricated aluminum profile fastener with a cover plate to shield the stainless steel self-tapping screw.

[0022] Preferably, the installation method of the floodlighting system provided by the present invention, wherein one end of the stainless steel self-tapping screw is inserted through the prefabricated aluminum profile fastener and is inserted into the joint of the curtain wall stone surface layer, specifically comprises: the first end of the stainless steel self-tapping screw is accommodated in the installation cavity, and the second end of the stainless steel self-tapping screw is inserted through the first vertical plate and is inserted into the joint of the curtain wall stone surface layer.

[0023] Preferably, the installation method of the floodlighting system provided by the present invention is to cover the prefabricated aluminum profile fasteners with a cover plate to cover the stainless steel self-tapping screws, specifically comprising: the cover plate is covered on the open end of the installation cavity to form a closed installation cavity.

[0024] Preferably, in the method for installing a floodlighting system provided by the present invention, the step of installing the lighting lamp specifically comprises: installing the lighting lamp in the accommodating cavity.

[0025] In summary, the beneficial technical effects of the present invention are as follows: the installation method of the floodlighting system provided in the present application comprises the following steps: determining the fixing position of the lamp trough on the curtain wall stone surface layer; gluing the prefabricated aluminum profile fasteners at the fixing position of the lamp trough on the curtain wall stone; inserting one end of the stainless steel self-tapping screw through the prefabricated aluminum profile fasteners and inserting them into the joints of the curtain wall stone surface layer; installing the lighting lamps; on the one hand, compared with the traditional method of installing the fixing components for fixing the floodlighting system, the drilling process of the curtain wall stone surface layer is reduced, the construction time cost is saved, and the damage of the curtain wall stone surface layer caused by drilling is avoided; on the other hand, by adopting the prefabricated aluminum profile fasteners, the operation is simple, thereby improving the construction efficiency and shortening the construction time; at the same time, the overall aesthetics of the lamp trough after forming is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a flow chart of the installation method of the floodlighting system provided by the embodiment of the present invention.

[0027] Figure 2 It is a schematic diagram of the installation structure of the floodlighting system provided by an embodiment of the present invention.

[0028] Figure 3 It is a schematic diagram of the structure of the prefabricated aluminum profile fastener in the floodlighting system provided by an embodiment of the present invention.

[0029] Figure 4 It is a schematic diagram of the structure of a cover plate in a floodlighting system provided by an embodiment of the present invention.

[0030] In the figure, 1. curtain wall stone surface layer; 2. prefabricated aluminum profile fasteners; 21. first horizontal plate; 22. second horizontal plate; 23. first vertical plate; 231. first part; 232. second part; 24. second vertical plate; 25. installation cavity; 26. accommodating cavity; 27. clamping platform; 271. first inclined surface; 272. second inclined surface; 3. stainless steel self-tapping screws; 4. double-sided tape; 5. structural adhesive; 6. cover plate; 61. clamping plate; 611. stopper; 6111. first inclined surface; 6112. second inclined surface; 6113. clamping slot; 7. connector; 8. lighting lamp. DETAILED DESCRIPTION

[0031] The present invention is further described in detail below in conjunction with the accompanying drawings.

[0032] Reference Figure 1 and Figure 2 , is a method for installing a floodlighting system disclosed in the present invention, comprising the following steps:

[0033] S101. Determine a light trough fixing position on the curtain wall stone surface layer 1.

[0034] Wherein, S101, determining the fixing position of the light trough on the curtain wall stone surface layer 1, specifically includes:

[0035] S1011. After the construction of the curtain wall stone surface layer 1 is completed and accepted, the light trough points are laid out and positioned according to the given drawings.

[0036] S1012. Hang a plumb line at the top of the curtain wall stone. After the plumb line is stable, measure and determine the fixed position of the light trough, and make a mark at the fixed position of the light trough.

[0037] S1013, determine the fixing positions of the remaining light troughs.

[0038] Specifically, the above steps S1011 and S1012 are repeated to determine the fixing positions of the remaining lamp troughs. By determining the fixing positions of the lamp troughs, the installation of the lighting lamps 8 at a later stage is facilitated.

[0039] S102, gluing the prefabricated aluminum profile fastener 2 to the lamp trough fixing position on the curtain wall stone.

[0040] Among them, S102, gluing the prefabricated aluminum profile fastener 2 to the fixed position of the lamp trough on the curtain wall stone, specifically includes:

[0041] S1021, stick the double-sided sticker 4 to the fixed position of the light trough on the curtain wall stone.

[0042] Specifically, a double-sided sticker 4 with a thickness of 5 mm is pasted on the fixed position of the lamp trough on the curtain wall stone.

[0043] S1022, applying structural adhesive 5 on two opposite sides of the double-sided tape 4.

[0044] Specifically, Figure 1 Taking the position shown as an example, structural adhesive 5 is applied to the upper and lower ends of the double-sided sticker 4, thereby preventing the double-sided sticker 4 from warping and deformation, and improving the firmness of the connection between the double-sided sticker 4 and the curtain wall stone surface layer 1.

[0045] S1023, bonding the prefabricated aluminum profile fastener 2 onto the double-sided tape.

[0046] Furthermore, in the present embodiment, S101, after determining the fixing position of the lamp trough on the curtain wall stone surface layer 1, S102, before gluing the prefabricated aluminum profile fastener 2 to the fixing position of the lamp trough on the curtain wall stone, it also includes: cleaning the dust and slurry on the surface of the curtain wall stone surface layer 1; by cleaning the surface of the curtain wall stone surface layer 1, the connection strength between the double-sided sticker 4 and the curtain wall stone surface layer 1 is improved.

[0047] Continue to refer to Figure 2 and Figure 3 In this embodiment, the prefabricated aluminum profile fastener 2 includes a first horizontal plate 21, a second horizontal plate 22, a first vertical plate 23 and a second vertical plate 24. The first horizontal plate 21 and the second horizontal plate 22 are spaced apart on the first vertical plate 23, and the end of the second horizontal plate 22 facing away from the first vertical plate 23 is connected to the top of the second vertical plate 24; the first horizontal plate 21, the second horizontal plate 22 and the first vertical plate 23 are jointly arranged to form an installation cavity 25, and the second horizontal plate 22, the second vertical plate 24 and the first vertical plate 23 are jointly arranged to form a receiving cavity 26.

[0048] Specifically, the first horizontal plate 21 is connected to the top end of the first vertical plate 23, one end of the second horizontal plate 22 is connected to the first vertical plate 23, and the first horizontal plate 21 and the second horizontal plate 22 are spaced apart by a preset distance; wherein, the first horizontal plate 21 and the second horizontal plate 22 are located on the same side of the first vertical plate 23, and the second horizontal plate 22 separates the first vertical plate 23 into a first part 231 and a second part 232, and the first horizontal plate 21, the second horizontal plate 22 and the first part 231 are jointly arranged to form an installation cavity 25.

[0049] The top end of the second vertical plate 24 is connected to an end of the second horizontal plate 22 facing away from the first vertical plate 23 . The second vertical plate 24 , the second horizontal plate 22 and the second portion 232 are jointly arranged to form an accommodating cavity 26 .

[0050] It should be noted that Figure 3 Taking the shown orientation as an example, the first portion 231 of the first vertical plate 23 is the portion above the second horizontal plate 22 , and the second portion 232 of the first vertical plate 23 is the portion below the second horizontal plate 22 .

[0051] Furthermore, in this embodiment, a platform 27 is provided on the first horizontal plate 21 and the second horizontal plate 22. The platform 27 extends toward the interior of the installation cavity 25 along the extension direction of the first vertical plate 23. A first inclined surface 271 and a second inclined surface 272 are provided at one end of the platform 27 which is away from the first horizontal plate 21 or the second horizontal plate 22.

[0052] S103, insert one end of the stainless steel self-tapping screw 3 through the prefabricated aluminum profile fastener 2 and insert it into the joint of the curtain wall stone surface layer 1; by providing the stainless steel self-tapping screw 3, the firmness of the connection between the prefabricated aluminum profile fastener 2 and the curtain wall stone surface layer 1 is further improved.

[0053] Continue to refer to Figure 1 and Figure 2, wherein S103, inserting one end of the stainless steel self-tapping screw 3 through the prefabricated aluminum profile fastener 2 into the joint of the curtain wall stone surface layer 1, specifically includes: the first end of the stainless steel self-tapping screw 3 is accommodated in the installation cavity 25, and the second end of the stainless steel self-tapping screw 3 is inserted into the joint of the curtain wall stone surface layer 1 through the first vertical plate 23.

[0054] Specifically, the central axis of the stainless steel self-tapping screw 3 is parallel to the horizontal plane, the first end of the stainless steel self-tapping screw 3 is accommodated in the installation cavity 25, the second end of the stainless steel self-tapping screw 3 passes through the first part 231 and the double-sided tape 4 in sequence and is inserted at the joint, and the second end of the stainless steel self-tapping screw 3 needs to be driven into the connecting piece 7 at the corner of the curtain wall.

[0055] The stainless steel self-tapping screw 3 is inserted into the joint to a depth greater than or equal to 50 mm.

[0056] S104, installing the lighting lamp 8.

[0057] Wherein, S104, installing the lighting lamp 8, specifically includes:

[0058] The lighting lamp 8 is installed in the accommodating cavity 26 .

[0059] Furthermore, in the present embodiment, after S103, passing one end of the stainless steel self-tapping screw 3 through the prefabricated aluminum profile fastener 2 and being inserted into the joint of the curtain wall stone surface layer 1, S104, before installing the lighting lamp 8, it also includes: covering the prefabricated aluminum profile fastener 2 with a cover plate 6 to cover the stainless steel self-tapping screw 3; by providing the cover plate 6, the stainless steel self-tapping screw 3 is prevented from being exposed to the outside, thereby improving the aesthetics of the installation of the lighting lamp 8.

[0060] The cover plate 6 is disposed on the prefabricated aluminum profile fastener 2 to shield the stainless steel self-tapping screws 3 , which specifically includes: the cover plate 6 is disposed on the open end of the installation cavity 25 to form a closed installation cavity 25 .

[0061] Exemplarily, the cover plate 6 and the prefabricated aluminum profile fastener 2 can be connected by gluing. Of course, the cover plate 6 and the prefabricated aluminum profile fastener 2 can also be connected by snapping.

[0062] Continue to refer to Figure 2 and Figure 4 In an achievable manner in which the cover plate 6 is connected to the prefabricated aluminum profile fastener 2 by snap-connection, the cover plate 6 is arranged opposite and parallel to the first vertical plate 23, and two clips 61 are arranged on the side of the cover plate 6 facing the first vertical plate 23. The two clips 61 are arranged at intervals, and the two clips 61 are perpendicular to the cover plate 6, and the clips 61 are arranged one-to-one with the card platform 27.

[0063] Among them, a stopper 611 is provided at one end of the clamping plate 61 away from the cover plate 6 to form a clamping groove 6113 between the cover plate 6, the clamping plate 61 and the stopper plate. During use, the clamping platform 27 is inserted into the clamping groove 6113 to connect the cover plate 6 with the prefabricated aluminum profile.

[0064] Specifically, the stop portion 611 is provided with a first inclined surface 6111 and a second inclined surface 6112, wherein the first inclined surface 6111 is adapted to the first inclined surface 271, and the second inclined surface 6112 is adapted to the second inclined surface 272; when installing the cover 6, the first inclined surface 6111 is fitted with the first inclined surface 271, and the first inclined surface 6111 slides along the first inclined surface 271 until the card platform 27 is inserted into the card slot 6113, so as to realize the connection between the cover 6 and the prefabricated aluminum profile fastener 2; when disassembling the cover 6, the second inclined surface 6112 is fitted with the second inclined surface 272, and the second inclined surface 6112 slides along the second inclined surface 272 until the card platform 27 slides out of the card slot 6113, so as to realize the disassembly of the cover 6.

[0065] It should be noted that the linear density range of the prefabricated aluminum profile fastener 2 is 0.8Kg / m-0.9Kg / m, and the linear density range of the cover plate 6 is 0.08Kg / m-0.09Kg / m. In this embodiment, the linear density of the prefabricated aluminum profile fastener 2 is 0.876Kg / m, and the linear density of the cover plate 6 is 0.089Kg / m.

[0066] The specific process of the installation method of the floodlighting system provided in this embodiment is as follows: after the construction of the curtain wall stone surface layer 1 is completed and accepted, the lamp trough points are laid out and positioned according to the drawings, a plumb line is hung at the top of the curtain wall stone, and after the plumb line is stable, the lamp trough fixing position is measured and determined, and a mark is made at the lamp trough fixing position, and the above steps are repeated to determine the remaining lamp trough fixing positions; then the dust and slurry on the surface of the curtain wall stone surface layer 1 are cleaned, and the prefabricated aluminum profile fastener 2 is pasted on the lamp trough fixing position on the curtain wall stone through the double-sided tape 4; one end of the ST3.5 stainless steel self-tapping screw 3 is passed through the first part 231 and driven into the joint of the curtain wall stone surface layer 1; a cover plate 6 with a length of 26.2 mm, a thickness of 1 mm, and a linear density of 0.089 Kg / m is provided at the opening end of the installation cavity 25; and then the lighting lamp 8 is installed in the accommodating cavity 26.

[0067] The installation method of the floodlighting system provided in the present application comprises the following steps: determining a lamp trough fixing position on a curtain wall stone surface layer 1; gluing a prefabricated aluminum profile fastener 2 to the lamp trough fixing position on the curtain wall stone; inserting one end of a stainless steel self-tapping screw 3 through the prefabricated aluminum profile fastener 2 and into the joint of the curtain wall stone surface layer 1; installing a lighting lamp 8; on the one hand, compared with the traditional method of installing a fixing component for fixing a floodlighting system, the drilling process of the curtain wall stone surface layer 1 is reduced, the construction time cost is saved, and the damage of the curtain wall stone surface layer 1 caused by drilling is avoided; on the other hand, by adopting the prefabricated aluminum profile fastener 2, the operation is simple, thereby improving the construction efficiency and shortening the construction time; at the same time, the overall aesthetics of the lamp trough after forming is improved.

[0068] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the statement "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.

[0069] Finally, it should be noted that: Obviously, the above embodiments are only examples for clearly explaining the present invention, and are not intended to limit the implementation methods. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the scope of protection of the present invention.

Claims

1. A method for installing a floodlighting system, characterized in that: The steps include: Determine the fixing position of the light trough on the stone surface of the curtain wall; Adhere the prefabricated aluminum profile fasteners to the light trough fixing positions on the curtain wall stone; Pass one end of the stainless steel self-tapping screw through the prefabricated aluminum profile fastener and insert it into the joint of the curtain wall stone surface layer; Install lighting; The prefabricated aluminum profile fastener comprises a first horizontal plate, a second horizontal plate, a first vertical plate and a second vertical plate, the first horizontal plate and the second horizontal plate are spaced apart and arranged on the first vertical plate, and an end of the second horizontal plate facing away from the first vertical plate is connected to the top end of the second vertical plate; The first horizontal plate, the second horizontal plate and the first vertical plate are jointly arranged to form an installation cavity, and the second horizontal plate, the second vertical plate and the first vertical plate are jointly arranged to form a receiving cavity; After one end of the stainless steel self-tapping screw is inserted through the prefabricated aluminum profile fastener and inserted into the joint of the curtain wall stone surface layer, and before the lighting lamp is installed, the method further includes: A cover plate is provided on the prefabricated aluminum profile fastener to cover the stainless steel self-tapping screws; The step of inserting one end of the stainless steel self-tapping screw through the prefabricated aluminum profile fastener and inserting it into the joint of the curtain wall stone surface layer specifically includes: The first end of the stainless steel self-tapping screw is accommodated in the installation cavity, and the second end of the stainless steel self-tapping screw passes through the first vertical plate and is inserted into the joint of the curtain wall stone surface layer; The first horizontal plate and the second horizontal plate are located on the same side of the first vertical plate, the second horizontal plate divides the first vertical plate into a first part and a second part, and the first horizontal plate, the second horizontal plate and the first part are jointly arranged to form an installation cavity; The top end of the second vertical plate is connected to an end of the second horizontal plate facing away from the first vertical plate, and the second vertical plate, the second horizontal plate and the second portion are jointly arranged to form a receiving cavity; The installation of the lighting lamp specifically includes: The lighting lamp is installed in the accommodating cavity.

2. The method for installing a floodlighting system according to claim 1, characterized in that: Determining the fixing position of the light trough on the curtain wall stone surface layer specifically includes: After the construction of the curtain wall stone surface layer is completed and accepted, the light trough points are laid out and positioned according to the given drawings; Hang a plumb line on the top of the curtain wall stone, measure and determine the fixed position of the lamp trough after the plumb line is stable, and mark the fixed position of the lamp trough; Determine the fixing positions of the remaining light troughs.

3. The method for installing a floodlighting system according to claim 1, characterized in that: The method of gluing the prefabricated aluminum profile fasteners to the lamp trough fixing positions on the curtain wall stone material specifically includes: Paste the double-sided tape on the light trough fixing position on the curtain wall stone; Applying structural adhesive on opposite sides of the double-sided tape; The prefabricated aluminum profile fastener is adhered to the double-sided tape.

4. The method for installing a floodlighting system according to claim 1, characterized in that: After determining the fixing position of the lamp trough on the surface layer of the curtain wall stone, and before gluing the prefabricated aluminum profile fasteners at the fixing position of the lamp trough on the curtain wall stone, the method further includes: The dust and floating slurry on the surface of the curtain wall stone surface layer are cleaned.

5. The method for installing a floodlighting system according to claim 1, characterized in that: The stainless steel self-tapping screw is inserted into the joint to a depth greater than or equal to 50 mm.

6. The method for installing a floodlighting system according to claim 1, characterized in that: A cover plate is provided on the prefabricated aluminum profile fastener to cover the stainless steel self-tapping screws, specifically comprising: The cover plate is arranged on the open end of the installation cavity to form a closed installation cavity.