Basement top slab drainage system and construction technology
By reserving drainage ditches on the basement roof and setting up height-adjustable water pipes and protective mechanisms, the problem of water accumulation during the construction process was solved, efficient drainage was achieved, and construction safety and efficiency were improved.
Patent Information
- Application Number
- CN202210459143.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-04-26
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2042-04-26
AI Technical Summary
During the construction process, pits are easily formed on the basement roof, causing water to accumulate, affecting construction progress and safety. Existing drainage methods are inefficient and take a long time, making it difficult to clean them thoroughly.
After the basement roof construction is completed, the drainage ditch area is reserved, and the slope layer, waterproof layer and isolation layer are constructed on both sides of it, and height-adjustable tapered water pipes and U-shaped drainage pipes are set up, combined with rotating columns and protective mechanisms. , forming a stable drainage system.
It effectively solves the problem of water accumulation on the roof, improves drainage efficiency and stability, ensures the normal progress of the construction process, and reduces the investment in manpower and equipment.
Smart Images

Figure CN114855963B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a basement top plate drainage system and a construction process. Background Art
[0002] At present, domestic residential areas and complex buildings that are developed and constructed in batches are usually designed with large basements, which are used as underground garages or other commercial purposes. The main characteristics of this type of basement are: first, the area is large, generally occupying almost the entire site except for the construction loop; second, the top plate elevation is lower than the outdoor floor elevation, so that outdoor pipe networks can be laid on it, roads can be built and greening can be carried out.
[0003] After the basement roof structure is completed, according to the construction process and site arrangement (for example, waterproofing can only be constructed after the roof post-casting strip is cast and sealed; during the construction of the above-ground structure, the basement roof can be used as a place for the transportation, storage and processing of construction materials, personnel activities and passage), generally after a period of time, the upper waterproof layer, external pipe network and backfill soil are constructed. In this process, a large pit is formed in the basement roof area, and water accumulates in it when it encounters it. Especially in the rainy season, it is very easy to cause rainwater to recharge and accumulate, resulting in the inability to carry out normal construction, delaying the construction period, and affecting safe and civilized construction. A large amount of equipment and manpower are required to pump out water, which is inefficient, has a long cycle, is not completely eliminated, and is extremely difficult to clean. Summary of the invention
[0004] The object of the present invention is to provide a construction process for a basement top plate drainage system, which comprises the following steps:
[0005] S1. After the basement top slab construction is completed, reserve the drainage ditch area;
[0006] S2. Construct a slope leveling layer on the top plates on both sides of the drainage ditch area;
[0007] S3. A waterproof layer, an isolation layer, and a waterproof protective layer are sequentially arranged above the slope leveling layer;
[0008] S4. Form a drainage ditch 200mm wide and 1200mm deep.
[0009] Furthermore, the waterproof layer, the isolation layer and the waterproof protective layer are all sealed and compacted with fine stone concrete on one side wall close to the drainage ditch.
[0010] Another object of the present invention is to provide a basement roof drainage system, which is manufactured using the above-mentioned construction process, and the drainage system includes a plurality of drainage ditches arranged on the basement roof.
[0011] A number of pre-buried holes penetrating the basement ceiling are provided at the bottom of the drainage ditch. Height-adjustable water pipes are installed in the pre-buried holes. The top of the water pipe is a conical tube, and the bottom of the water pipe is connected to a drainage pipe through a joint. The drainage pipe has a U-shaped section.
[0012] Furthermore, a cylindrical inner sleeve is fixed in the embedded hole, the bottom of the water receiving pipe is in the shape of a circular tube and is spirally fixed to the inner wall of the inner sleeve, and a cover plate is detachably installed near the top of the drainage ditch, with water-permeable holes on both side edges, and a driving mechanism for adjusting the height of the water receiving pipe is installed on the cover plate.
[0013] Furthermore, the driving mechanism includes a rotating column rotatably mounted on the cover plate, the top end of the rotating column penetrates the cover plate and is fixed with a turntable, the bottom end of the rotating column extends into the water receiving pipe and is transmission-connected to the water receiving pipe for transmitting torque.
[0014] Furthermore, a positioning ring is fixed on the inner wall of the water receiving pipe, and a plurality of positioning grooves are formed along the inner side of the positioning ring. A plurality of positioning blocks that slide in cooperation with the positioning grooves are distributed circumferentially at the bottom of the rotating column, and the height of the positioning blocks is greater than the longitudinal depth of the positioning grooves.
[0015] Furthermore, there are protective mechanisms around the top of the water receiving pipe, which include a bottom ring, a top ring, and a telescopic tube detachably installed between the bottom ring and the top ring. The bottom ring is used to be installed and fixed to the bottom surface of the drainage ditch, and the top ring is used to be installed and fixed to the top of the water receiving pipe, and the telescopic tube is a corrugated hose.
[0016] Furthermore, an annular sealing plate is fixed to the bottom surface of the drainage ditch on the outer peripheral side of the water receiving pipe, the bottom of the bottom ring is pressed on the sealing plate, and through holes are circumferentially provided on the bottom ring and the sealing plate, and a plurality of mounting holes are provided on the bottom surface of the drainage ditch at the bottom of the sealing plate, expansion sleeves are preset in the mounting holes, and expansion bolts are installed in each expansion sleeve, and the expansion bolts pass through the through holes on the bottom ring and the sealing plate in turn.
[0017] Furthermore, the telescopic tube includes two layers, an inner tube and an outer tube, and the two ends of the inner tube and the outer tube are respectively fixed by a locking mechanism, a bottom ring and a top ring, and a side wall of the water receiving pipe is provided with a rotating groove along the circumferential direction, and a rotating plate is movably arranged in the rotating groove. A plurality of connecting bolts are passed through the top of the top ring, and the ends of the connecting bolts are spirally connected to the rotating plate.
[0018] The beneficial effects of the present invention are as follows: the present invention proposes a construction process for a basement roof drainage system and a drainage system formed by the process. The present invention optimizes the construction process, and later forms a roof drainage system by making a slope finding layer, a waterproof layer, an isolation layer, and a waterproof protective layer in a very small area. The system can effectively solve the problems of water accumulation and drainage in the roof after the basement roof post-casting zone is closed. The drainage system includes a bottom surface drainage part formed by a drainage ditch and a floor drain drainage part composed of a plurality of water connecting pipes installed at the bottom of the drainage ditch. The system works stably and reliably, and has a good drainage effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0020] Figure 1 is a cross-sectional view of a drainage ditch in a drainage system provided by an embodiment of the present invention;
[0021] Figure 2 It is a structural schematic diagram of a drainage ditch and its internal structure in a drainage system provided by an embodiment of the present invention;
[0022] Figure 3 The present invention Figure 2 A magnified image of point A;
[0023] Figure 4 The present invention Figure 2 A magnified view of point B;
[0024] Figure 5 The present invention Figure 3 Enlarged view of point C;
[0025] Figure 6 The present invention Figure 5 The schematic diagram of the structure after the rotary plate and rotary groove are added;
[0026] Figure 7 The present invention Figure 6 Enlarged view of point D.
[0027] Icons: basement top plate 1, slope layer 2, waterproof layer 3, isolation layer 4, waterproof protective layer 5, drain pipe 6, joint 7, cover plate 8, water hole 801, turntable 9, drain ditch 10, embedded hole 11, water connecting pipe 12, positioning groove 13, inner sleeve 14, water hole 15, rotating column 16, positioning block 17, positioning ring 18, telescopic tube 19, expansion bolt 20, bottom ring 21, sealing plate 22, expansion sleeve 23, mounting hole 24, top ring 25, connecting bolt 26, nut 27, screw 28, slewing plate 30, slewing groove 31, limit groove 32, mounting groove 33, spring 34, limit rod 35. DETAILED DESCRIPTION
[0028] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0029] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.
[0030] In the present invention, unless otherwise clearly specified and limited, a first feature being above or below a second feature may include the first and second features being in direct contact, or may include the first and second features not being in direct contact but being in contact through another feature between them. Moreover, a first feature being above, above, and above a second feature includes the first feature being directly above and obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being below, below, and below a second feature includes the first feature being directly below and obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0031] Example:
[0032] This embodiment provides a construction process for a basement top plate drainage system, which includes the following steps:
[0033] S1. After the construction of the basement top slab 1 is completed, a drainage ditch area is reserved;
[0034] S2, constructing slope leveling layer 2 on the top plates on both sides of the drainage ditch area;
[0035] S3, sequentially arrange a waterproof layer 3, an isolation layer 4, and a waterproof protective layer 5 on the top of the slope leveling layer 2;
[0036] S4. Form a drainage ditch 10 with a width of 200 mm and a depth of 100 mm.
[0037] Furthermore, the waterproof layer 3, the isolation layer 4, and the waterproof protective layer 5 are all sealed and compacted with fine stone concrete on one side wall near the drainage ditch 10, which can prevent water from penetrating into the waterproof layer from the side wall.
[0038] Another object of the present invention is to provide a basement roof drainage system, which is made by the above-mentioned construction process. The drainage system includes a plurality of drainage ditches 10 arranged on the basement roof 1. A plurality of pre-buried holes 11 penetrating the basement roof are also provided at the bottom of the drainage ditch 10. A height-adjustable water receiving pipe 12 is installed in the pre-buried hole 11. The top of the water receiving pipe 12 is a conical tube, and the bottom of the water receiving pipe 12 is connected to a drainage pipe 6 through a joint 7. The drainage pipe 6 has a U-shaped section. The present invention sets a pre-buried hole in the drainage ditch to facilitate the installation of the longitudinally arranged water receiving pipe 12. The water receiving pipe 12 can share the drainage pressure when the drainage volume of the drainage ditch is large, so that the whole drainage system works more stably and efficiently. At the same time, the height-adjustable water receiving pipe 12 can be conveniently adjusted. When the water depth in the drainage ditch 10 reaches a certain position, the water receiving pipe 12 will play a role in auxiliary drainage.
[0039] For details, please refer to Figure 2 as well as Figure 4 A cylindrical inner sleeve 14 is fixed in the embedded hole 11. The inner sleeve 14 can be made of stainless steel alloy, which can ensure its long-term stable operation and is not easy to rust. The bottom of the water receiving pipe 12 is a round tube and is spirally fixed to the inner wall of the inner sleeve 14. The water receiving pipe 12 is also made of stainless steel alloy. A cover plate 8 is detachably installed near the top of the drainage ditch. There are water holes 801 on the edges of both sides of the cover plate 8, and a driving mechanism for adjusting the height of the water receiving pipe 12 is installed on the cover plate 8. When the cover plate 8 is installed, its two ends are respectively fixed to the side walls on both sides of the drainage ditch 10. During the specific construction, steel bars can be embedded in the slope layer and the isolation layer so that the ends of the steel bars extend out of the slope to facilitate the later use of the cover plate 8 for fixing.
[0040] Please refer to the specific Figure 2 In this embodiment, the driving mechanism includes a rotating column 16 rotatably mounted on the cover plate 8. The top end of the rotating column 16 penetrates the cover plate 8 and is fixed with a turntable 9. The bottom end of the rotating column 16 extends into the water receiving pipe 12 and is transmission-connected to the water receiving pipe 12 to transmit torque. For details, please refer to Figure 4A positioning ring 18 is fixed to the inner wall of the water receiving pipe 12, and a plurality of positioning grooves 13 are formed along the inner side of the positioning ring 18. A plurality of positioning blocks 17 are distributed circumferentially at the bottom of the rotating column 16 and are slidably matched with the positioning grooves 13, and the height of the positioning blocks 17 is greater than the longitudinal depth of the positioning grooves 13. By manually driving the turntable 9 to rotate, the rotating column 16 can be driven to rotate, so that the torque is transmitted by the matching of the positioning blocks and the positioning grooves 13, so that the water receiving pipe 12 and the inner sleeve 14 are relatively lifted and lowered under the action of the spiral connection, so as to achieve the purpose of adjusting the height of the water receiving pipe 12.
[0041] Refer again Figure 2 , Figure 3 The top of the water receiving pipe 12 is provided with a protective mechanism, which includes a bottom ring 21, a top ring 25, and a telescopic tube 19 detachably mounted between the bottom ring 21 and the top ring 25. The bottom ring 21 is used to be mounted and fixed to the bottom surface of the drainage ditch 10, and the top ring 25 is used to be mounted and fixed to the top of the water receiving pipe 12, and the telescopic tube 19 is a corrugated hose. The protective mechanism can prevent the water receiving pipe from being used for a long time, accumulating dirt and other impurities around it, and making it impossible to rotate the water receiving pipe 12, so that its operation is stable and reliable.
[0042] exist Figure 3 It can be seen that the bottom surface of the drainage ditch is fixed with an annular sealing plate 22 on the outer peripheral side of the water receiving pipe, the bottom of the bottom ring 21 is pressed on the sealing plate 22, and through holes are circumferentially provided on the bottom ring 21 and the sealing plate 22. A plurality of mounting holes 24 are provided on the bottom surface of the drainage ditch 10 at the bottom of the sealing plate 22, and expansion sleeves 23 are preset in the mounting holes 24, and expansion bolts 20 are installed in each expansion sleeve 23, and the expansion bolts 20 pass through the through holes on the bottom ring 21 and the sealing plate 22 in sequence. In the present invention, a plurality of water-permeable holes 15 are provided on the shell of the water receiving pipe 12 extending out of the inner sleeve.
[0043] In order to ensure that the protective mechanism can continue to work stably when adjusting the height of the water receiving pipe 12, the telescopic pipe 19 proposed by the present invention includes two layers, an inner pipe and an outer pipe, and the two ends of the inner pipe and the outer pipe are respectively fixed by a locking mechanism and a bottom ring 21 and a top ring 25, and a rotating groove 31 is opened along the circumferential direction of the side wall of the water receiving pipe 12, and a rotating plate 30 is movably arranged in the rotating groove 31. A plurality of connecting bolts 26 are pierced on the top of the top ring 25, and the ends of the connecting bolts 26 are all spirally connected to the rotating plate 30. Please refer to Figure 5 In the present invention, an interlayer is provided between the inner tube and the outer tube, and the upper and lower ends of the inner tube and the outer tube are respectively fitted with the opposite sides of the top ring and the bottom ring, and are fixed by a locking mechanism. The locking mechanism includes a screw 28 that passes through the inner tube, the outer tube and the bottom ring or the top ring, and nuts are spirally installed at both ends of the screw 28.
[0044] The present invention proposes a construction process for a basement roof drainage system and a drainage system formed by the process. The present invention optimizes the construction process, and laterally constructs a slope finding layer, a waterproof layer, an isolation layer, and a waterproof protective layer in a very small area to form a roof drainage system, which can effectively solve the problems of water accumulation and drainage in the roof after the basement roof post-casting zone is closed. The drainage system includes a bottom surface drainage part formed by a drainage ditch and a floor drain drainage part composed of a plurality of water connecting pipes installed at the bottom of the drainage ditch. The system works stably and reliably, and has a good drainage effect.
[0045] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A basement roof drainage system, the drainage system comprising a plurality of drainage ditches arranged on the basement roof; A plurality of pre-buried holes penetrating the top plate of the basement are also provided at the bottom of the drainage ditch, and a height-adjustable water receiving pipe is installed in the pre-buried hole. The top of the water receiving pipe is a conical tube, and the bottom of the water receiving pipe is connected to a drainage pipe through a joint, and the drainage pipe has a U-shaped section; A cylindrical inner sleeve is fixed in the embedded hole, the bottom of the water receiving pipe is in the shape of a circular tube and is spirally fixed to the inner wall of the inner sleeve, a cover plate is detachably installed near the top of the drainage ditch, water permeable holes are provided at the edges of both sides of the cover plate, and a driving mechanism for adjusting the height of the water receiving pipe is installed on the cover plate; The driving mechanism comprises a rotating column rotatably mounted on the cover plate, the top end of the rotating column penetrates the cover plate and is fixed with a rotating disk, the bottom end of the rotating column extends into the water receiving pipe and is transmission-connected to the water receiving pipe for transmitting torque; A positioning ring is fixed on the inner wall of the water receiving pipe, and a plurality of positioning grooves are formed on the inner side of the positioning ring along the circumference. A plurality of positioning blocks are distributed circumferentially at the bottom of the rotating column and are slidably matched with the positioning grooves, and the height of the positioning blocks is greater than the longitudinal depth of the positioning grooves. The top of the water receiving pipe is provided with a protective mechanism around it, and the protective mechanism includes a bottom ring, a top ring, and a telescopic tube detachably installed between the bottom ring and the top ring, the bottom ring is used to be installed and fixed with the bottom surface of the drainage ditch, the top ring is used to be installed and fixed with the top of the water receiving pipe, and the telescopic tube is a corrugated hose; The bottom surface of the drainage ditch is fixed with an annular sealing plate on the outer peripheral side of the water receiving pipe, the bottom of the bottom ring is pressed on the sealing plate, and the bottom ring and the sealing plate are circumferentially provided with through holes, and a plurality of mounting holes are provided on the bottom surface of the drainage ditch at the bottom of the sealing plate, and expansion sleeves are preset in the mounting holes, and expansion bolts are installed in each expansion sleeve, and the expansion bolts pass through the through holes on the bottom ring and the sealing plate in sequence; The telescopic tube comprises two layers, an inner tube and an outer tube, and the two ends of the inner tube and the outer tube are respectively fixed by a locking mechanism, a bottom ring and a top ring, and a side wall of the water receiving pipe is provided with a revolving groove along the circumferential direction, and a revolving plate is movably arranged in the revolving groove, and a plurality of connecting bolts are passed through the top of the top ring, and the ends of the connecting bolts are spirally connected to the revolving plate.
2. The construction process of a basement top slab drainage system according to claim 1, characterized in that: The steps include: S1. After the basement top slab construction is completed, reserve the drainage ditch area; S2. Construct a slope leveling layer on the top plates on both sides of the drainage ditch area; S3, sequentially arrange a waterproof layer, an isolation layer, and a waterproof protective layer on the top of the slope leveling layer; S4. Form a drainage ditch 200mm wide and 100mm deep.
3. The construction process of a basement top plate drainage system according to claim 2 is characterized in that: The waterproof layer, the isolation layer and the waterproof protection layer are all sealed and compacted with fine stone concrete on one side wall close to the drainage ditch.