A method and system for acquiring power grid operation status based on multi-source data integration

By using the ARMA model to calculate the measurement error and performing a weighted sum in the power grid state estimation, and combining the PMU and RTU data to correct the remote signals, the problem of insufficient real-time performance of the power grid state estimation is solved, and the power grid operating status is quickly and accurately obtained.

CN114925973BActive Publication Date: 2024-10-22NARI TECH CO LTD +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210384220.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-13
Publication Date
2024-10-22
Estimated Expiration
2042-04-13

AI Technical Summary

Technical Problem

Traditional power grid state estimation methods have insufficient real-time performance when reflecting the actual status of the power grid and cannot quickly respond to the rapidly changing needs of the power grid. Moreover, data from different data sources are not shared, and differences in accuracy and coverage lead to a long update cycle of state estimation results.

Method used

Calculate the measurement error at the current moment through the ARMA model based on historical PMU measurement error and RTU measurement error, combine the PMU and RTU measurement data to perform a weighted sum calculation of telemetry, and correct the remote signal based on the telemetry to obtain the power grid operating status , improve the real-time and accuracy of data.

Benefits of technology

It achieves rapid updates and high real-time acquisition of the power grid's operating status, ensures the accuracy and real-time nature of the data, and meets the data generation needs when the power grid changes rapidly.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114925973B_ABST
    Figure CN114925973B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and system for acquiring the operation status of a power grid based on multi-source data integration. On the basis of the state estimation result, the present invention integrates PMU measurement data and RTU measurement data with faster data update, calculates the telemetry quantity, and corrects the telesignal quantity according to the telemetry quantity, thereby realizing the acquisition of the operation status of the power grid. Compared with the existing method, the real-time performance of the acquisition of the operation status of the power grid is improved; and when integrating the data, the present invention takes into account the historical PMU measurement error and the historical RTU measurement error, thereby ensuring the accuracy of the integrated data.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a method and system for acquiring power grid operation status based on multi-source data integration, and belongs to the field of power system dispatching automation. Background Art

[0002] With the rapid development of UHV DC and the rapid increase in installed capacity of new energy, the operation mode of the power grid is becoming increasingly complex. There is a strong uncertainty on the power generation side and the load side. The rapid fluctuation of new energy and impact loads cause the operation mode of the power grid to change rapidly under normal conditions, which puts forward higher requirements for more timely situation awareness methods of the power grid.

[0003] The wide-area measurement data acquisition and monitoring system provides important information support for real-time monitoring of power grids. However, different data sources not only do not share data, but also have large differences in acquisition accuracy, coverage, and sampling frequency. As one of the functions of the energy management system, state estimation uses the redundancy of the real-time measurement system to improve data accuracy, eliminate erroneous information caused by random interference, and then obtain or predict the operating status of the system. It is the main data source for online safety and stability analysis. For large-scale interconnected power grids, traditional state estimation needs to integrate the state estimation results of different dispatching agencies to form the state estimation results of the entire network. The update cycle of the results is usually 1 to 5 minutes. Due to the time-consuming data forwarding of multi-level dispatching agencies and the state estimation itself, the state estimation is not real-time enough in reflecting the actual state of the power grid. Summary of the invention

[0004] The present invention provides a method and system for acquiring power grid operation status based on multi-source data integration, which solves the problems disclosed in the background technology.

[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is:

[0006] A method for acquiring power grid operation status, comprising:

[0007] Determine the current PMU measurement error and the current RTU measurement error based on the historical PMU measurement error and the historical RTU measurement error; wherein the PMU measurement error is the error value between the PMU measurement and the state estimation result corresponding to the PMU measurement, the RTU measurement error is the error value between the RTU measurement and the state estimation result corresponding to the RTU measurement, and the state estimation result is the result output by the state estimation function in the dispatching automation system;

[0008] Calculate the current moment telemetry according to the current moment PMU measurement, the current moment PMU measurement error, the current moment RTU measurement and the current moment RTU measurement error;

[0009] According to the current telemetry quantity, the telemetering quantity at the current moment is corrected according to the principle that the telemetry quantity has a higher credibility than the telemetering quantity;

[0010] The power grid operation status is obtained based on the current telemetry quantity and the corrected current telesignal quantity.

[0011] Before determining the current PMU measurement error and the current RTU measurement error, the current PMU measurement and the current RTU measurement are also checked; if the current measurement is erroneous data, they are directly discarded; if the current measurement is normal data, they are directly used; if the current measurement is alarm data, they are corrected according to the boundary value before use.

[0012] The current PMU measurement error is determined based on the ARMA model of historical PMU measurement errors; the current RTU measurement error is determined based on the ARMA model of historical RTU measurement errors.

[0013] According to the current PMU measurement, the current PMU measurement error, the current RTU measurement and the current RTU measurement error, the current telemetry is calculated, including:

[0014] Calculate the sum of the errors between the PMU measurement at the previous moment and the PMU measurement at the current moment, and calculate the sum of the errors between the RTU measurement at the current moment and the RTU measurement at the current moment;

[0015] Calculate the weighted sum of the two sum values ​​and use the weighted sum as the telemetry value at the current moment.

[0016] The weighted coefficient used in calculating the weighted sum is obtained based on the historical PMU measurement error and the historical RTU measurement error. The calculation process includes:

[0017] Calculate the weighting coefficients at each historical moment based on the historical PMU measurement errors and historical RTU measurement errors;

[0018] According to the weighted coefficients at each historical moment, a fitting curve of the weighted coefficients is obtained;

[0019] According to the fitting curve of the weighting coefficient, the weighting coefficient at the current moment is calculated.

[0020] The formula for calculating the weighted coefficient of each historical moment is:

[0021]

[0022] in, For the historical moment l The weighting coefficient of For the historical moment l The PMU measurement error, For the historical moment lRTU measurement error.

[0023] The formula for the fitting curve of the weighted coefficient is:

[0024] λ n (t)=f[t0]+f[t0,t1](t-t0)+f[t0,t1,t2](t-t0)(t-t1)

[0025] +…+f[t0,t1,t2,…,t n ](t-t0)(t-t1)…(tt n-1 )

[0026] Among them, t0~t n is n+1 historical moments, parameter i and j are both integers, 0≤i<j≤n and i+1≠j, For the historical moment i1 The weighting coefficient, i1 is an integer, i1∈[0,n], parameter i2 is an integer, i2∈[0,n-1].

[0027] A power grid operation status acquisition system, comprising:

[0028] A measurement error evaluation module is used to determine the current PMU measurement error and the current RTU measurement error based on historical PMU measurement errors and historical RTU measurement errors; wherein the PMU measurement error is the error value between the PMU measurement and the state estimation result corresponding to the PMU measurement, the RTU measurement error is the error value between the RTU measurement and the state estimation result corresponding to the RTU measurement, and the state estimation result is the result output by the state estimation function in the dispatching automation system;

[0029] A telemetry calculation module, used to calculate the telemetry at the current moment according to the PMU measurement at the current moment, the PMU measurement error at the current moment, the RTU measurement at the current moment, and the RTU measurement error at the current moment;

[0030] The correction module is used to correct the current moment telemetering quantity according to the current moment telemetering quantity and the principle that the telemetering quantity credibility is higher than the telemetering quantity;

[0031] The state acquisition module is used to obtain the power grid operation state according to the current telemetry value and the corrected current telesignal value.

[0032] The telemetry calculation module includes:

[0033] A sum calculation module is used to calculate the sum of the error between the PMU measurement at the previous moment and the PMU measurement at the current moment, and to calculate the sum of the error between the RTU measurement at the current moment and the RTU measurement at the current moment;

[0034] The weighted sum module is used to calculate the weighted sum of the two sum values ​​and use the weighted sum as the telemetry value at the current moment.

[0035] The telemetry calculation module also includes a weighting coefficient module for calculating the weighting coefficient used in the weighted sum calculation module according to the historical PMU measurement error and the historical RTU measurement error;

[0036] The weighting coefficient module includes:

[0037] A historical weighted coefficient calculation module is used to calculate the weighted coefficients at each historical moment according to the historical PMU measurement error and the historical RTU measurement error;

[0038] A fitting module is used to obtain a fitting curve of the weighted coefficient according to the weighted coefficient of each historical moment;

[0039] The weighting coefficient calculation module is used to calculate the weighting coefficient at the current moment according to the fitting curve of the weighting coefficient.

[0040] A computer-readable storage medium storing one or more programs, wherein the one or more programs include instructions, and when the instructions are executed by a computing device, the computing device executes a method for acquiring a power grid operation status.

[0041] A computing device includes one or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and are configured to be executed by the one or more processors, and the one or more programs include instructions for executing a method for acquiring a power grid operation status.

[0042] The beneficial effects achieved by the present invention are as follows: based on the state estimation result, the present invention integrates PMU measurement data and RTU measurement data with faster data update, calculates the telemetry quantity, and corrects the telesignal quantity according to the telemetry quantity, thereby realizing the acquisition of the power grid operation status. Compared with the existing method, the real-time acquisition of the power grid operation status is improved; and when integrating the data, the present invention takes into account the historical PMU measurement errors and the historical RTU measurement errors, thereby ensuring the accuracy of the integrated data. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 The figure is a flow chart of a method for acquiring power grid operation status. DETAILED DESCRIPTION

[0044] The present invention will be further described below in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the protection scope of the present invention.

[0045] like Figure 1 As shown, a method for obtaining the operation status of a power grid includes the following steps:

[0046] Step 1, determining the current PMU measurement error and the current RTU measurement error based on the historical PMU measurement error and the historical RTU measurement error; wherein the PMU measurement error is the error value between the PMU measurement and the state estimation result corresponding to the PMU measurement, the RTU measurement error is the error value between the RTU measurement and the state estimation result corresponding to the RTU measurement, and the state estimation result is the result output by the state estimation function in the dispatching automation system;

[0047] Step 2, calculating the current moment telemetry value according to the current moment PMU measurement, the current moment PMU measurement error, the current moment RTU measurement and the current moment RTU measurement error;

[0048] Step 3, based on the current telemetry value, the current telemetering value is corrected according to the principle that the telemetry value has a higher credibility than the telemetering value;

[0049] Step 4, obtaining the power grid operation status according to the current telemetry value and the corrected current telesignal value.

[0050] Based on the state estimation result, the above method integrates the PMU measurement data and RTU measurement data with faster data update, calculates the telemetry quantity, and corrects the telesignal quantity according to the telemetry quantity, thereby realizing the acquisition of the power grid operation status. Compared with the existing method, the real-time acquisition of the power grid operation status is improved; and when integrating the data, the present invention takes into account the historical PMU measurement errors and the historical RTU measurement errors, thereby ensuring the accuracy of the integrated data.

[0051] The traditional grid state estimation function derives the status information of the entire network equipment based on the grid measurement values, which can reflect the real-time operating status of the entire network equipment. However, its result update cycle is usually 1 to 5 minutes, which is difficult to meet the data generation needs when the grid changes rapidly.

[0052] The RTU measurement data acquisition frequency is 0.1~5Hz, and the measurement coverage is wide, but there are shortcomings such as low data accuracy and long sampling period; the PMU measurement data acquisition frequency is 50~100Hz, which has the advantages of high accuracy and low delay, but the coverage rate is not high. If the RTU measurement data and PMU measurement data with a faster acquisition frequency are used to obtain the power grid operation status, then the real-time requirements can be met. However, due to the above shortcomings of RTU measurement data and PMU measurement data, they cannot be used directly, and multiple data sources need to be integrated based on the state estimation results.

[0053] Based on the above ideas, the PMU measurement data and the RTU measurement data at the current moment are obtained. The obtained data cannot be used directly. It is necessary to first use the equipment limit range to check the PMU measurement data and the RTU measurement data at the current moment. The inspection results are generally normal data, alarm data, and error data. If the current moment measurement is error data, it is directly discarded; if the current moment measurement is normal data, it is directly used; if the current moment measurement is alarm data, it is corrected according to the boundary value before use. In particular, if one of the PMU measurement data and the RTU measurement data is error data, only the other normal data will be used later.

[0054] According to the historical PMU measurement error and the historical RTU measurement error, the current PMU measurement error and the current RTU measurement error are determined. Specifically, the current PMU measurement error is determined according to the ARMA model of the historical PMU measurement error; the current RTU measurement error is determined according to the ARMA model of the historical RTU measurement error.

[0055] Integrate the above multi-source data, that is, calculate the current telemetry according to the current PMU measurement, the current PMU measurement error, the current RTU measurement and the current RTU measurement error. The specific process can be:

[0056] 1) Calculate the sum of the errors between the PMU measurement at the previous moment and the PMU measurement at the current moment, and calculate the sum of the errors between the RTU measurement at the current moment and the RTU measurement at the current moment;

[0057] 2) Calculate the weighted sum of the two sum values ​​and use the weighted sum as the telemetry value at the current moment.

[0058] The current telemetry measurement formula can be expressed as:

[0059] y=λ(y1+y1′)+(1-λ)(y2+y′2)

[0060] Where y is the current telemetry measurement after multi-source data integration, λ is the weighting coefficient, y1 is the PMU measurement at the previous moment, y′1 is the PMU measurement error at the previous moment, y2 is the RTU measurement at the current moment, ′y2 is the RTU measurement error at the current moment.

[0061] The above weighted coefficient is calculated based on the historical PMU measurement error and the historical RTU measurement error. In particular, if the node only has PMU measurement, λ is 1, and if the node only has RTU measurement, λ is 0.

[0062] The specific process of calculating the weighted coefficient can be:

[0063] 21) Calculate the weighting coefficients at each historical moment based on the historical PMU measurement error and the historical RTU measurement error;

[0064] The formula for the weighted coefficient of each historical moment can be:

[0065]

[0066] in, For the historical moment l The weighting coefficient of For the historical moment l The PMU measurement error, For the historical moment l RTU measurement error.

[0067] 22) According to the weighted coefficients at each historical moment, a fitting curve of the weighted coefficients is obtained.

[0068] The formula for the fitting curve of the weighted coefficient can be:

[0069] λ n (t)=f[t0]+f[t0,t1](t-t0)+f[t0,t1,t2](t-t0)(t-t1)

[0070] +…+f[t0,t1,t2,…,t n ](t-t0)(t-t1)…(tt n-1 )

[0071] Among them, t0~t n is n+1 historical moments, parameter i and j are both integers, 0≤i<j≤n and i+1≠j, f[t i1 ]=λ ti1 For the historical moment i1 The weighting coefficient, i1 is an integer, i1∈[0,n], parameter i2 is an integer, i2∈[0,n-1].

[0072] 23) Calculate the weighting coefficient at the current moment according to the fitting curve of the weighting coefficient.

[0073] According to the current telemetry, the telemetering quantity is corrected according to the principle that the telemetry reliability is higher than the telemetering quantity. The specific process can be:

[0074] According to the principle that the credibility of telemetry is higher than that of telesignaling, we can know that: for node injection or branch terminals whose absolute value of telemetry is greater than the specified threshold value, the directly connected circuit breaker and the switches on both sides of it must be in the closed position; based on the above principle, correct the circuit breakers and switches in the open position, and check whether the live equipment can be connected after closing the circuit breaker and switch. If the connection cannot be made, an alarm will be prompted.

[0075] After the current telemetering quantity is corrected, the power grid operation status is obtained according to the current telemetering quantity and the corrected current telemetering quantity. The specific process can be:

[0076] Based on the remote signal values ​​of circuit breakers and switches and the connection relationship of equipment, the topological node and topological island information are obtained through the topological analysis of the station and the whole network. Based on the known node injection and network topology, the whole network power flow is obtained through power flow calculation.

[0077] Based on the state estimation results, the above method integrates multiple data sources such as PMU measurement data and RTU measurement data with faster data update, takes into account the different characteristics and advantages of PMU measurement data, RTU measurement data, and state estimation, and improves the real-time performance of the power flow results of the entire network; when integrating the current moment data, the historical errors of the PMU and RTU measurement data of each electrical quantity and the state estimation results are considered respectively, ensuring the accuracy of the integrated data.

[0078] Based on the same technical solution, the present invention also discloses a software system of the above method, a method system for obtaining the operation status of a power grid, comprising:

[0079] A measurement error evaluation module is used to determine the current PMU measurement error and the current RTU measurement error based on historical PMU measurement errors and historical RTU measurement errors; wherein the PMU measurement error is the error value between the PMU measurement and the state estimation result corresponding to the PMU measurement, the RTU measurement error is the error value between the RTU measurement and the state estimation result corresponding to the RTU measurement, and the state estimation result is the result output by the state estimation function in the dispatching automation system;

[0080] The telemetry calculation module is used to calculate the telemetry at the current moment according to the PMU measurement at the current moment, the PMU measurement error at the current moment, the RTU measurement at the current moment, and the RTU measurement error at the current moment.

[0081] The telemetry calculation module includes:

[0082] The sum calculation module is used to calculate the sum of the error between the PMU measurement at the previous moment and the PMU measurement at the current moment, and calculate the sum of the error between the RTU measurement at the current moment and the RTU measurement at the current moment.

[0083] A weighting coefficient module, used to calculate the weighting coefficient used in the weighted sum calculation module according to the historical PMU measurement error and the historical RTU measurement error;

[0084] The weighting coefficient module includes:

[0085] A historical weighted coefficient calculation module is used to calculate the weighted coefficients at each historical moment according to the historical PMU measurement error and the historical RTU measurement error;

[0086] A fitting module is used to obtain a fitting curve of the weighted coefficient according to the weighted coefficient of each historical moment;

[0087] The weighting coefficient calculation module is used to calculate the weighting coefficient at the current moment according to the fitting curve of the weighting coefficient.

[0088] The weighted sum module is used to calculate the weighted sum of the two sum values ​​and use the weighted sum as the telemetry value at the current moment.

[0089] The correction module is used to correct the current moment's telemetering quantity according to the current moment's telemetering quantity and the principle that the credibility of the telemetering quantity is higher than the telemetering quantity.

[0090] The state acquisition module is used to obtain the power grid operation state according to the current telemetry value and the corrected current telesignal value.

[0091] In the above software system, the data processing flow and method of each module are consistent and will not be described in detail here.

[0092] Based on the same technical solution, the present invention also discloses a computer-readable storage medium storing one or more programs, wherein the one or more programs include instructions, and when the instructions are executed by a computing device, the computing device executes a method for acquiring a power grid operation status.

[0093] Based on the same technical solution, the present invention also discloses a computing device, comprising one or more processors, one or more memories and one or more programs, wherein the one or more programs are stored in the one or more memories and are configured to be executed by the one or more processors, and the one or more programs include instructions for executing a method for acquiring a power grid operation status.

[0094] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0095] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0096] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0097] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0098] The above are merely embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are included in the scope of the claims of the present invention to be approved.

Claims

1. A method for acquiring power grid operation status, characterized in that: include: Determine the current PMU measurement error and the current RTU measurement error based on the historical PMU measurement error and the historical RTU measurement error; wherein the PMU measurement error is the error value between the PMU measurement and the state estimation result corresponding to the PMU measurement, the RTU measurement error is the error value between the RTU measurement and the state estimation result corresponding to the RTU measurement, and the state estimation result is the result output by the state estimation function in the dispatching automation system; Calculate the sum of the error between the PMU measurement at the previous moment and the PMU measurement at the current moment, calculate the sum of the error between the RTU measurement at the current moment and the RTU measurement at the current moment, calculate the weighted sum of the two sums, and use the weighted sum as the telemetry value at the current moment; According to the current telemetry quantity, the telemetering quantity at the current moment is corrected according to the principle that the telemetry quantity has a higher credibility than the telemetering quantity; The power grid operation status is obtained based on the current telemetry quantity and the corrected current telesignal quantity.

2. A method for acquiring power grid operation status according to claim 1, characterized in that: Before determining the current PMU measurement error and the current RTU measurement error, the current PMU measurement and the current RTU measurement are also checked; if the current measurement is erroneous data, they are directly discarded; if the current measurement is normal data, they are directly used; if the current measurement is alarm data, they are corrected according to the boundary value before use.

3. A method for acquiring power grid operation status according to claim 1, characterized in that: The current moment PMU measurement error is determined based on the ARMA model of historical PMU measurement errors; The current RTU measurement error is determined based on the ARMA model of the historical RTU measurement error.

4. A method for acquiring power grid operation status according to claim 1, characterized in that: The weighted coefficient used in calculating the weighted sum is obtained based on the historical PMU measurement error and the historical RTU measurement error. The calculation process includes: Calculate the weighting coefficients at each historical moment based on the historical PMU measurement errors and historical RTU measurement errors; According to the weighted coefficients at each historical moment, a fitting curve of the weighted coefficients is obtained; According to the fitting curve of the weighting coefficient, the weighting coefficient at the current moment is calculated.

5. A method for acquiring power grid operation status according to claim 4, characterized in that: The formula for calculating the weighted coefficient of each historical moment is: in, For the historical moment l The weighting coefficient of For the historical moment l The PMU measurement error, For the historical moment l RTU measurement error.

6. A method for acquiring power grid operation status according to claim 4, characterized in that: The formula for the fitting curve of the weighted coefficient is: λ n (t)=f[t0]+f[t0,t1](t-t0)+f[t0,t1,t2](t-t0)(t-t1) +…+f[t0,t1,t2,…,t n ](t-t0)(t-t1)…(t-t n-1 ) Among them, t0~t n is n+1 historical moments, parameter i and j are both integers, 0≤i<j≤n and i+1≠j, For the historical moment i1 The weighting coefficient, i1 is an integer, i1∈[0,n], parameter i2 is an integer, i2∈[0,n-1].

7. A power grid operation status acquisition system, characterized in that: include: A measurement error evaluation module is used to determine the current PMU measurement error and the current RTU measurement error based on historical PMU measurement errors and historical RTU measurement errors; wherein the PMU measurement error is the error value between the PMU measurement and the state estimation result corresponding to the PMU measurement, the RTU measurement error is the error value between the RTU measurement and the state estimation result corresponding to the RTU measurement, and the state estimation result is the result output by the state estimation function in the dispatching automation system; A telemetry calculation module, used to calculate the telemetry at the current moment according to the PMU measurement at the current moment, the PMU measurement error at the current moment, the RTU measurement at the current moment, and the RTU measurement error at the current moment; The telemetry calculation module includes: A sum calculation module is used to calculate the sum of the error between the PMU measurement at the previous moment and the PMU measurement at the current moment, and to calculate the sum of the error between the RTU measurement at the current moment and the RTU measurement at the current moment; A weighted sum module is used to calculate the weighted sum of the two sum values ​​and use the weighted sum as the telemetry value at the current moment; The correction module is used to correct the current moment telemetering quantity according to the current moment telemetering quantity and the principle that the telemetering quantity credibility is higher than the telemetering quantity; The state acquisition module is used to obtain the power grid operation state according to the current telemetry value and the corrected current telesignal value.

8. A system for acquiring power grid operation status according to claim 7, characterized in that: The telemetry calculation module also includes a weighting coefficient module for calculating the weighting coefficient used in the weighted sum calculation module according to the historical PMU measurement error and the historical RTU measurement error; The weighting coefficient module includes: A historical weighted coefficient calculation module is used to calculate the weighted coefficients at each historical moment according to the historical PMU measurement error and the historical RTU measurement error; A fitting module is used to obtain a fitting curve of the weighted coefficient according to the weighted coefficient of each historical moment; The weighting coefficient calculation module is used to calculate the weighting coefficient at the current moment according to the fitting curve of the weighting coefficient.

9. A computer-readable storage medium storing one or more programs, characterized in that: The one or more programs include instructions which, when executed by a computing device, cause the computing device to perform the method according to any one of claims 1 to 6.

10. A computing device, characterized in that include: One or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and are configured to be executed by the one or more processors, and the one or more programs include instructions for executing the method according to any one of claims 1 to 6.