A pre-buried de-airing grouting device and grouting construction method

Through the pre-embedded voiding grouting device, grouting pipes and pressure monitoring devices are used to perform grouting in the filling body, which solves the problems of damage and inability to repeat grouting in the treatment of voiding disease in concrete structures in the existing technology, and achieves Safe and efficient grouting process.

CN114960390BActive Publication Date: 2024-10-08CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210623070.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-01
Publication Date
2024-10-08
Estimated Expiration
2042-06-01

AI Technical Summary

Technical Problem

When dealing with voiding disease in concrete structures, the existing technology easily damages the concrete structure, cannot repeat grouting, and cannot monitor the grouting pressure, resulting in excessive grouting pressure and damage to the concrete structure.

Method used

A pre-embedded emptying grouting device is designed, which includes a grouting pipe embedded in the filling body and a pressure monitoring device. One end of the grouting pipe extends to the filling body, and a check valve is set to prevent the slurry from flowing back. The pressure The monitoring device monitors the grouting pressure in real time to prevent the pressure from being too high.

Benefits of technology

It achieves repeated grouting without damaging the concrete structure, can monitor the grouting pressure in real time, prevent damage to the concrete structure caused by excessive grouting pressure, and improves the safety and efficiency of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114960390B_ABST
    Figure CN114960390B_ABST
Patent Text Reader

Abstract

The embodiment of the present application discloses a pre-buried de-veining grouting device and a grouting construction method, which relates to the field of concrete structure de-veining disease treatment, and solves the problem that grouting cannot be repeated during grouting, and the concrete structure needs to be destroyed to arrange the grouting pipe and the pressure at the grouting point cannot be monitored, resulting in damage to the concrete structure. The pre-buried de-veining grouting device includes: a grouting pipe and a pressure monitoring device, wherein the grouting pipe is pre-buried inside the built-up body, close to the interface between the built-up body and the concrete structure, one end of the grouting pipe extends outside the built-up body for conveying slurry, and a check valve is provided at the other end of the grouting pipe for preventing the slurry after grouting into the de-veining part from flowing back into the grouting pipe; the pressure monitoring device is provided in the grouting pipe for monitoring the grouting pressure in the grouting pipe. The pre-buried de-veining grouting device provided in the embodiment of the present application is used for grouting into a de-veining position.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The embodiments of the present application relate to the field of concrete structure void repair, and in particular to a pre-buried void grouting device and a grouting construction method. Background Art

[0002] For concrete structures and filled objects, voids are a common disease, and voids mostly occur at the interface between filled objects and concrete structures, especially in railway engineering and highway engineering. There are many types of filled objects in railway engineering and highway engineering, including underconsolidated foundation soil, fill, soft soil and other types. Since the geology of these filled objects is relatively complex, especially when affected by rain erosion or changes in underground soil layers, voids can easily occur between the filled objects and the concrete structure, which may cause defects such as uneven settlement, misalignment, and cracks in the concrete structure, affecting safety.

[0003] In order to treat the void disease, a variety of grouting methods have been developed, that is, grouting is poured into the void position to fill and repair the void position, and after the grouting hardens and solidifies, the purpose of re-supporting the concrete structure is achieved. However, in the related art, in order to arrange grouting facilities at the void position, the fill and concrete structure will be excavated, for example, the fill and concrete structure will be excavated to arrange the formwork, etc. This method will cause damage to the concrete structure; in the related art, when the void disease occurs, repeated grouting cannot be performed, and the grouting pressure cannot be monitored during grouting, and excessive grouting pressure will cause damage to the concrete structure. Summary of the invention

[0004] In order to solve the above problems, the embodiments of the present application provide a pre-buried hollow grouting device and a grouting construction method, which have the following advantages: it does not damage the concrete structure, can repeat the grouting, can monitor the grouting pressure, and prevent the grouting pressure from being too high and causing damage to the concrete structure.

[0005] In order to achieve the above-mentioned purpose, the technical solution of the embodiment of the present application is implemented as follows:

[0006] In the first aspect, the embodiment of the present application provides a pre-buried de-airing grouting device, including: a grouting pipe and a pressure monitoring device. The grouting pipe is pre-buried inside the compacted body, near the interface between the compacted body and the concrete structure, one end of the grouting pipe extends outside the compacted body for conveying slurry, and the other end of the grouting pipe is provided with a check valve for preventing the slurry after grouting into the de-airing part from flowing back into the grouting pipe; the pressure monitoring device is provided in the grouting pipe for monitoring the grouting pressure in the grouting pipe.

[0007] The pre-buried de-emptied grouting device provided in the embodiment of the present application is pre-buried in the grouting pipe and the pressure monitoring device in the built-up body, and near the interface between the built-up body and the concrete structure. When the interface between the built-up body and the concrete structure is de-emptied, the grouting pipe can be directly connected to the grouting equipment to perform grouting at the de-emptied position, without drilling holes in the concrete structure, and without excavating the built-up body and the concrete structure to arrange the grouting facilities, which will not cause damage to the concrete structure. At the same time, a check valve is arranged at the other end of the grouting pipe away from the grouting inlet. When grouting is performed in the grouting pipe, the check valve is opened due to the effect of the grouting pressure, so that the slurry smoothly enters the de-emptied position; after the grouting is completed, the pressure in the grouting pipe disappears, and the slurry in the de-emptied position still maintains a certain pressure. At this time, the pressure of the slurry in the de-emptied position will close the check valve to prevent the slurry in the de-emptied position from flowing back to the grouting pipe. At this time, the slurry in the grouting pipe is cleaned by cleaning the residual slurry in the grouting pipe. If the interface between the fill and the concrete structure is de-emptied again, the grouting pipe can be used to continue grouting. Therefore, the pre-buried de-emptying grouting device provided in the embodiment of the present application can be used to repeat the grouting. In addition, a pressure monitoring device is also provided in the grouting pipe, which can monitor the pressure of the slurry in the grouting pipe during grouting. In the early stage of grouting, when the grouting pressure in the grouting pipe does not change significantly, it means that the de-emptied area is not yet filled with slurry and grouting still needs to be continued; in the later stage of grouting, when it is monitored that the grouting pressure is relatively high, and when the grouting pressure reaches the warning value of concrete structure damage, the grouting is stopped, which can protect the original concrete structure and prevent the original concrete structure from being compressed and damaged due to excessive grouting pressure.

[0008] In a possible implementation of the present application, the pressure monitoring device includes a pressure monitoring instrument and a wire, one end of the wire is connected to the monitoring instrument, and the other end of the wire extends outside the filling body.

[0009] In a possible implementation of the present application, the grouting pipe includes a main grouting pipe and a branch grouting pipe. A plurality of branch grouting pipes are arranged at intervals at the interface between the compacted body and the concrete structure and connected to the main grouting pipe. One end of the main grouting pipe extends outside the compacted body.

[0010] In a possible implementation of the present application, the branch grouting pipe is movably connected to the main grouting pipe.

[0011] The pre-buried de-hollowing grouting device provided in the embodiment of the present application movably connects the branch grouting pipe to the main grouting pipe. The main grouting pipe and the branch grouting pipe can be prefabricated in advance according to the scale of the filling body, and then the main grouting pipe and the branch grouting pipe can be assembled at the construction site, thereby improving the scope of use of the pre-buried de-hollowing grouting device provided in the embodiment of the present application.

[0012] In a possible implementation of the present application, the pressure monitoring instrument is arranged in the main grouting pipe at a position close to the branch grouting pipe.

[0013] In a possible implementation of the present application, a bend is provided at one end of the branch grouting pipe away from the main grouting pipe, and the bend faces one side of the built-up body.

[0014] In a possible implementation of the present application, the check valve is disposed at an end of the elbow away from the main grouting pipe.

[0015] In a possible implementation of the present application, a demoulding device is provided on the check valve, and the demoulding device is used to prevent the slurry from adhering to the check valve after hardening.

[0016] In a possible implementation of the present application, a cleaning device is provided in the grouting pipe, and the cleaning device is used to clean the grouting pipe.

[0017] The pre-buried de-veining grouting device provided in the embodiment of the present application can clean the slurry in the grouting pipe by means of a cleaning device before hardening, so that the passage in the grouting pipe can be kept unobstructed. When the filling body is de-veined again, the grouting pipe can be used for repeated grouting.

[0018] In a possible implementation of the present application, a pipe plug is provided at one end of the main grouting pipe extending out of the landfill.

[0019] In a second aspect, an embodiment of the present application provides a grouting construction method, the grouting construction method comprising:

[0020] Step S01: making a grouting pipe: assembling a grouting pipe according to the size of the interface between the compacted body and the concrete structure, installing a pressure monitoring device in the grouting pipe, and installing a check valve at one end of the grouting pipe corresponding to the interface between the compacted body and the concrete structure;

[0021] Step S02: pre-embed grouting pipes and pressure monitoring devices: before the construction of the concrete structure, grouting pipes and pressure monitoring devices are arranged in the compacted body near the interface between the compacted body and the concrete structure, and the grouting pipes are extended outside the compacted body;

[0022] Step S03: Grouting construction: When the filling body is de-cavitated, grouting is carried out into the grouting pipe using grouting equipment; and the pressure monitoring device is connected to the pressure analysis system to monitor the grouting pressure in the grouting pipe. When the grouting pressure in the grouting pipe reaches the warning value of concrete structure damage, the grouting is stopped.

[0023] In a possible implementation of the present application, after step S03, the method further includes step S04: maintaining the grouting pipe, cleaning the grouting pipe with a cleaning device, and sealing the pipe opening of the grouting pipe with a pipe plug after cleaning the grouting pipe.

[0024] In a possible implementation of the present application, when the compacted body suffers from hollowing out again, step S03 and step S04 are repeated, and grouting may be repeated.

[0025] The grouting construction method provided in the embodiment of the present application has the same technical effect as that of not damaging the concrete structure, being able to repeat grouting, and being able to monitor the grouting pressure to prevent the concrete structure from being damaged due to excessive grouting pressure because the grouting construction method adopts the embedded degassing device provided in the first aspect for grouting. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 A cross-sectional view of a pre-buried de-hollowing grouting device provided in an embodiment of the present application;

[0027] Figure 2 A top view of the pre-buried de-hollowing grouting device provided in an embodiment of the present application;

[0028] Figure 3 A schematic diagram of a main grouting pipe of a pre-buried de-airing grouting device provided in an embodiment of the present application;

[0029] Figure 4 A schematic diagram of a branch grouting pipe of a pre-buried de-hollowing grouting device provided in an embodiment of the present application;

[0030] Figure 5 A schematic diagram of a check valve of a pre-buried degassing grouting device provided in an embodiment of the present application;

[0031] Figure 6 A schematic diagram of a cleaning device for a pre-buried de-hollowing grouting device provided in an embodiment of the present application;

[0032] Figure 7 Schematic diagram of the grouting construction method provided in the embodiment of the present application Figure 1 ;

[0033] Figure 8 Schematic diagram of the grouting construction method provided in the embodiment of the present application Figure 2 .

[0034] Reference numerals:

[0035] 1- grouting pipe; 11- main grouting pipe; 12- branch grouting pipe; 13- reserved interface; 14- connection interface; 15- elbow; 16- check valve; 17- cleaning device; 2- pressure monitoring device; 21- pressure monitoring instrument; 22- conductor; 3- fill; 4- concrete structure; 5- empty position; 6- pipe plug. DETAILED DESCRIPTION

[0036] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the specific technical solution of the present application will be further described in detail below in conjunction with the drawings in the embodiments of the present application. The following embodiments are used to illustrate the present application, but are not used to limit the scope of the present application.

[0037] In the embodiments of the present application, the terms "first" and "second" are used for descriptive purposes only and are not to be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the embodiments of the present application, unless otherwise specified, "multiple" means two or more.

[0038] In addition, in the embodiments of the present application, directional terms such as "up", "down", "left" and "right" are defined relative to the orientation of the components in the drawings. It should be understood that these directional terms are relative concepts. They are used for relative description and clarification, and they may change accordingly according to the changes in the orientation of the components in the drawings.

[0039] In the embodiments of the present application, unless otherwise clearly specified and limited, the term "connection" should be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection or an indirect connection through an intermediate medium.

[0040] In the embodiments of the present application, the terms "include", "comprises" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the presence of other identical elements in the process, method, article or device including the element.

[0041] In the embodiments of the present application, words such as "exemplary" or "for example" are used to indicate examples, illustrations or descriptions. Any embodiment or design described as "exemplary" or "for example" in the embodiments of the present application should not be interpreted as being more preferred or more advantageous than other embodiments or designs. Specifically, the use of words such as "exemplary" or "for example" is intended to present related concepts in a specific way.

[0042] The embodiment of the present application provides a pre-embedded hollowing grouting device. Pre-embedding is a construction method commonly used in the engineering field. It is a construction method in which the components are first arranged at the installation position before pouring concrete, and then the concrete is poured. The construction of building projects, road projects or other civil engineering projects generally involves excavating the foundation, then filling the excavated foundation with backfill or fine sand as required, and finally pouring concrete on the filling body to eventually form the target project. The filling body generally has a certain degree of looseness. Under the influence of geological conditions or when washed by rainwater, hollowing and other diseases are prone to occur between the filling body and the upper concrete structure. In order to treat the hollowing disease, the method of grouting the hollow position is often used, that is, pouring slurry into the hollow position to fill it, so that the slurry fills the hollow position. After the slurry hardens, it plays a supporting role on the upper concrete structure to achieve the purpose of repair.

[0043] At present, the commonly used grouting method requires drilling or other construction on the upper concrete structure to arrange the grouting pipe, which requires damaging the original concrete structure and cannot monitor the grouting pressure. When the grouting pressure is too high, it is easy to cause the upper concrete structure to be compressed and damaged.

[0044] In view of this, an embodiment of the present application provides a pre-buried de-cavitation grouting device and a grouting construction method, which can solve the above-mentioned problems.

[0045] In order to more clearly illustrate the pre-buried de-airing grouting device provided in the embodiment of the present application, a detailed description is given below with reference to the accompanying drawings.

[0046] In a first aspect, an embodiment of the present application provides a pre-buried de-cavitation grouting device.

[0047] Reference Figure 1 The pre-buried de-veining grouting device provided in the embodiment of the present application comprises: a grouting pipe 1 and a pressure monitoring device 2. The grouting pipe 1 is pre-buried in the compact 3, near the interface between the compact 3 and the concrete structure 4, and one end of the grouting pipe 1 extends outside the compact 3 as a grouting inlet, which is used to transport slurry to the de-veining position 5. The other end of the grouting pipe 1 away from the grouting inlet is provided with a check valve 16, which is used to prevent the slurry from flowing back to the grouting pipe 1 after grouting into the de-veining position. The pressure monitoring device 2 is arranged in the grouting pipe 1, and is used to monitor the grouting pressure in the grouting pipe 1.

[0048] The pre-buried de-veining grouting device provided in the embodiment of the present application pre-buries the grouting pipe 1 in the fill body 3 near the interface between the fill body 3 and the concrete structure 4 in advance. When de-veining occurs near the interface between the fill body 3 and the concrete structure 4, the grouting pipe 1 can be directly used for grouting. Specifically, the grouting equipment is connected to the grouting pipe 1, and slurry is poured into the grouting pipe 1, so as to grout the de-veining position 5. There is no need to drill holes in the concrete structure 4, nor is there any need to excavate the fill body 3 or the concrete structure 4 to arrange the grouting facilities, and the concrete structure 4 will not be damaged. At the same time, a check valve 16 is provided at one end of the grouting pipe 1 away from the grouting inlet. When grouting is performed in the grouting pipe 1, the check valve 16 is opened due to the grouting pressure, so that the slurry can smoothly enter the emptying position 5. After the grouting is completed, the pressure in the grouting pipe 1 disappears, while the slurry at the emptying position 5 still maintains a certain pressure. At this time, the pressure of the slurry at the emptying position 5 will close the check valve 16 to prevent the slurry at the emptying position 5 from flowing back to the grouting pipe 1. At this time, the slurry in the grouting pipe 1 is cleaned by cleaning the residual slurry in the grouting pipe 1. If the interface between the building body 3 and the concrete structure 4 is empty again, the grouting pipe 1 can be continuously used for grouting. Therefore, the pre-buried emptying grouting device provided in the embodiment of the present application can be used for repeated grouting. In addition, a pressure monitoring device 2 is also provided in the grouting pipe 1, which can monitor the grouting pressure in the grouting pipe 1 during grouting. In the early stage of grouting, when the pressure monitored by the pressure monitoring device 2 does not change significantly, it means that the empty position 5 is not yet filled with slurry and grouting needs to be continued. In the later stage of grouting, when the pressure monitoring device 2 detects that the pressure becomes larger and reaches the warning value of concrete structure 4 damage, grouting is stopped. This can protect the concrete structure 4 and prevent the concrete structure 4 from being damaged by pressure due to excessive grouting pressure.

[0049] It should be noted that the pre-buried de-cavitation grouting device provided in the embodiment of the present application can transport a variety of slurries to choose from, which can be cement-based slurry, such as cement mortar, cement clay slurry or non-shrinkage cement slurry, etc.; it can also be chemical slurry, such as epoxy resin slurry, polyurethane slurry or silicate slurry, etc. There are many choices for the shape of the grouting pipe 1, for example, a circular, square or other shaped pipe can be selected. Preferably, the embodiment of the present application selects a circular pipe as the grouting pipe 1. The circular shape is conducive to the transportation of the fluid and is easy to arrange. Moreover, the circular pipe can disperse the stress. Under the same conditions, the circular pipe bears a larger force. There are also many choices for the size of the grouting pipe 1, which can be selected according to the specific scale of the project. It is advisable that the size of the grouting pipe 1 does not affect the integrity of the structure. Preferably, a grouting pipe 1 with a diameter of 20 to 30 mm can be selected. There are also many choices for the material of the grouting pipe 1, and a grouting pipe 1 made of carbon steel, a grouting pipe 1 made of stainless steel, a grouting pipe 1 made of polyvinyl chloride or a grouting pipe 1 made of type III polypropylene can be selected. The grouting pipe 1 made of stainless steel is corrosion-resistant and has strong strength and toughness, but the cost is high. The grouting pipe 1 made of polyvinyl chloride or type III polypropylene is also corrosion-resistant, and the strength and toughness also meet the use requirements of grouting, and the cost is low. The embodiment of the present application does not limit the above description.

[0050] On this basis, the pressure monitoring device 2 includes a pressure monitoring instrument 21 and a wire 22, one end of the wire 22 is connected to the pressure monitoring instrument 21, and the other end extends to the outside of the compacted body 3, so as to be connected to the pressure analysis system outside the compacted body 3. In this way, the pressure monitoring instrument 21 can monitor the grouting pressure, transmit the pressure information to the pressure analysis system through the wire 22, and confirm whether to continue grouting according to the grouting pressure. There are many options for the pressure monitoring instrument 21. The commonly used pressure monitoring instruments 21 in the engineering field include: spring pressure gauges, vibrating wire pressure gauges or airbag pressure gauges, etc. There are also many shapes of the pressure monitoring instrument 21. Preferably, a round cake-shaped pressure monitoring instrument 21 can be selected. The round cake-shaped pressure monitoring instrument 21 has the advantages of small space occupation, no influence on the main structure, easy layout and not easy to damage, and can be flexibly arranged. There are also many options for the wire 22, and a general cable can be selected, or an armored cable can be selected. The armored cable can withstand large tension, pressure, etc., and can be suitable for harsh environments. The embodiment of the present application does not limit the types of the pressure monitoring instrument 21 and the wire 22.

[0051] It should be noted that multiple pressure monitoring instruments 21 can be arranged according to actual needs. Figure 2 , are three pressure monitoring instruments 21 arranged, which are not limited in this embodiment of the present application.

[0052] In addition, refer to Figure 1 and Figure 2In the pre-buried de-hollowing grouting device provided in the embodiment of the present application, the grouting pipe 1 includes a main grouting pipe 11 and a branch grouting pipe 12, and the diameter of the main grouting pipe 11 is larger than the diameter of the branch grouting pipe 12. A plurality of branch grouting pipes 12 are arranged at intervals in the compacted body 3 near the interface between the compacted body 3 and the concrete structure 4, and are connected to the main grouting pipe 11, and one end of the main grouting pipe extends outside the compacted body 3. After the grouting equipment is connected to the pipe mouth of the main grouting pipe 11, the slurry can reach the de-hollowing position 5 after being transported by the branch grouting pipe 12, thereby achieving the purpose of grouting the de-hollowing position 5. After the slurry is dispersed by the branch grouting pipe 12, it can be grouted to a larger area where the branch grouting pipe 12 is arranged. By setting the main grouting pipe 11 and the branch grouting pipe 12, the grouting range is expanded; and by setting the main grouting pipe 11 and the branch grouting pipe 12, the amount of the grouting pipe 1 can also be saved, saving the construction cost.

[0053] Furthermore, the branch grouting pipe 12 is movably connected to the main grouting pipe 11. In this way, the main grouting pipe 11 and the branch grouting pipe 12 can be prefabricated in advance according to the layout requirements, and can be prefabricated in a prefabrication workshop, which can improve the construction efficiency, and then the main grouting pipe 11 and the branch grouting pipe 12 can be assembled in the fill 3 at the construction site. There are many options for the movably connected mode between the branch grouting pipe 12 and the main grouting pipe 11. They can be connected together by threads, can be connected together by quick connectors, or can be connected together by a snap-on structure, which is not limited in the embodiments of the present application. The main grouting pipe 11 can be processed in a prefabrication workshop, and a reserved interface 13 connected to the branch grouting pipe 12 can be made. For example, the reserved interface 13 can be threaded. Then, the main grouting pipe 11 and the branch grouting pipe 12 can be assembled on site. In addition, the position of the reserved interface 13 connected to the branch grouting can be determined on the main grouting pipe 11 according to the layout requirements of the branch grouting pipe 12, referring to Figure 3 There are three reserved interfaces 13 in the figure, and they are arranged on the same side of the main grouting pipe 11. According to actual needs, multiple reserved interfaces 13 can be reserved, and the arrangement positions can also be flexibly selected, which is not limited in the embodiments of the present application.

[0054] Reference Figure 4 The end of the branch grouting pipe 12 connected to the main grouting pipe 11 is provided with a connection interface 14, which can be a threaded structure. At the same time, a corresponding threaded structure is provided on the reserved interface 13 on the main grouting pipe 11 connected to the branch grouting pipe 12. In this way, the branch grouting pipe 12 is connected to the main grouting pipe 11 by rotating the branch grouting pipe 12. In order to maintain the seal, a sealing tape can be wrapped around the threaded structure. It should be noted that the branch grouting pipe 12 can also be connected to the main grouting pipe 11 through other connection structures, which is not limited in the embodiments of the present application.

[0055] It should be noted that, in order to more accurately monitor the grouting pressure in the grouting pipe 1, in some embodiments of the present application, the pressure monitoring instrument 21 is arranged in the main grouting pipe 11 near the branch grouting pipe 12. Figure 2 The pressure monitoring instrument 21 is arranged at the position where the main grouting pipe 11 connects the branch grouting pipe 12. In this way, the grouting pressure in the grouting pipe 1 can be measured more accurately, and the measured grouting pressure is close to the grouting pressure at the emptying position 5.

[0056] Further, an elbow 15 is provided at one end of the branch grouting pipe 12 away from the main grouting pipe 11, and the elbow 15 faces one side of the compacted body 3, which can be more conducive to the flow of slurry toward the de-hollowing position 5. The elbow 15 can be a separate elbow 15 connected to the branch grouting pipe 12, or it can be a self-contained elbow 15 on the branch grouting pipe 12, and the embodiment of the present application is not limited to this. For the case where a separate elbow 15 is connected to the branch grouting pipe 12, a thread can also be provided to connect the elbow 15 to the branch grouting pipe 12, and a sealing tape can also be wrapped around the threaded connection to ensure sealing, and the direction of the elbow 15 can be adjusted by adjusting the thickness of the sealing tape so that the elbow 15 faces one side of the compacted body 3. For the case where the branch grouting pipe 12 comes with a elbow 15, the direction of the elbow 15 can be adjusted by adjusting the thickness of the sealing tape of the thread at the connection between the branch grouting pipe 12 and the main grouting pipe 11 so that the elbow 15 faces one side of the compacted body 3.

[0057] Reference Figure 4 A check valve 16 is provided at one end of the elbow 15 away from the main grouting pipe 11, and the check valve 16 allows the flow direction to be from the branch grouting pipe 12 toward one end of the compacted body 3. Since the slurry poured into the emptying position 5 has a certain pressure, the check valve 16 is provided at the tail end of the elbow 15 to prevent the slurry poured into the emptying position 5 from flowing back along the elbow 15 to the branch grouting pipe 12 and the main grouting pipe 11. The check valve 16 and the elbow 15 can be a whole, and the integrated assembly is completed in the factory. For the elbow 15 made of polyvinyl chloride or type III polypropylene, a check valve 16 with a shell structure of the corresponding material can be selected, and the check valve 16 and the elbow 15 are welded together by hot melt welding. The embodiments of the present application are not limited to this.

[0058] Reference Figure 5 In the embodiment of the present application, a single butterfly valve check valve 16 is used, and a double butterfly valve check valve 16 or other check valves 16 may also be selected, and the embodiment of the present application is not limited to this.

[0059] On this basis, a demoulding device is provided on the check valve 16 to prevent the slurry from hardening and adhering to the check valve 16. For example, a coating agent or a demoulding paper is applied to the check valve 16 to isolate the check valve 16 from the slurry, so that no slurry will remain on the check valve 16, and no slurry will harden and adhere to the check valve 16, so that the check valve 16 can meet the requirements of multiple grouting.

[0060] It should be noted that, refer to Figure 6 A cleaning device 17 is also provided in the main grouting pipe 11 and the branch grouting pipe 12. The cleaning device 17 is used to clean the main grouting pipe 11 and the branch grouting pipe 12 after the grouting is completed. The cleaning device 17 can be a cleaning pipe fixed in advance in the main grouting pipe 11 and the branch grouting pipe 12. For example, the cleaning device 17 can be a thinner pipe fixed in the upper part of the main grouting pipe 11 and the branch grouting pipe 12, and one-way nozzles are arranged at intervals on the cleaning pipe. This can prevent the slurry from entering the cleaning pipe during grouting. By pouring clean water into the cleaning pipe, the slurry in the main grouting pipe 11 and the branch grouting pipe 12 is rinsed clean, and there will be no situation where the slurry hardens and blocks the main grouting pipe 11 and the branch grouting pipe 12. In this way, after the compact 3 is emptied again, the main grouting pipe 11 and the branch grouting pipe 12 can still be used for grouting to achieve the purpose of repeated grouting. It should be noted that for the convenience of display, in Figure 6 The pressure monitoring device 2 is not shown.

[0061] In addition, refer to Figure 1 , Figure 2 , Figure 3 and Figure 6 A pipe plug 6 is provided at one end of the grouting pipe 1 extending out of the compacted body 3, and the grouting pipe 1 is closed by the pipe plug 6 when grouting is not performed. This can prevent debris from entering the grouting pipe 1 and clogging the grouting pipe 1, thereby ensuring the smooth flow of the grouting pipe 1.

[0062] In the second aspect, the present application embodiment provides a grouting construction method, specifically, referring to Figure 7 , including the following steps:

[0063] Step S01: making a grouting pipe 1: assembling the grouting pipe 1 according to the size of the interface between the compacted body 3 and the concrete structure 4, installing a pressure monitoring device in the grouting pipe 1, and installing a check valve 16 at one end of the grouting pipe 1 corresponding to the interface between the compacted body 3 and the concrete structure 4;

[0064] Step S02: pre-embed the grouting pipe 1 and the pressure monitoring device 2: before the construction of the concrete structure 4, arrange the grouting pipe 1 and the pressure monitoring device 2 in the compacted body 3 near the interface between the compacted body 3 and the concrete structure 4, and extend the grouting pipe 1 to the outside of the compacted body 3;

[0065] Step S03: Grouting construction: When the fill body 3 is de-hollowed, grouting is performed into the grouting pipe 1 using grouting equipment; and the pressure monitoring device 2 is connected to the pressure analysis system to monitor the grouting pressure at the de-hollowing position 5. When the grouting pressure at the de-hollowing position 5 reaches the warning value for damage to the concrete structure 4, the grouting is stopped.

[0066] Specifically, first, the grouting pipe 1 should be manufactured according to the size of the interface between the compacted body 3 and the concrete structure 4. The grouting pipe 1 can be laid at the interface between the compacted body 3 and the concrete structure 4, or it can be laid at a location where a voiding defect is expected to occur; then, a pressure monitoring device 2 is installed in the grouting pipe 1, and a check valve 16 is installed at one end of the grouting pipe 1 corresponding to the interface between the compacted body 3 and the concrete structure 4.

[0067] Then, before the construction of the concrete structure 4, the grouting pipe 1 and the pressure monitoring device 2 are arranged in the compacted body 3, and the grouting pipe 1 and the pressure monitoring device 2 are arranged near the interface between the compacted body 3 and the concrete structure 4, and then the grouting pipe 1 and the pressure monitoring device 2 are pre-buried in the compacted body 3. In order to ensure the fixation of the grouting pipe 1 and the pressure monitoring device 2, the grouting pipe 1 and the pressure monitoring device 2 can be fixed by steel bars or other devices, and then the other end of the steel bar is extended out of the compacted body 3. When the concrete structure 4 on the upper part of the compacted body 3 is constructed, the steel bars connecting the grouting pipe 1 and the pressure monitoring device 2 are cast together, so that when the compacted body 3 is emptied, the grouting pipe 1 and the pressure monitoring device 2 can be ensured to be in the predetermined position, and such fixation can ensure that the grouting pipe 1 and the pressure monitoring device 2 are not easily damaged.

[0068] Further, see Figure 8 , after step S03, the method further includes step S04: maintaining the grouting pipe 1: cleaning the grouting pipe 1 with the cleaning device 17, and sealing the pipe opening of the grouting pipe 1 with the pipe plug 6 after the grouting pipe 1 is cleaned. The grouting pipe 1 can be cleaned with clean water, so that the slurry remaining in the grouting pipe 1 can flow out, so that the grouting pipe 1 remains unobstructed, and after cleaning the grouting pipe 1, sealing the pipe opening of the grouting pipe 1 with the pipe plug 6 can also prevent debris from entering the grouting pipe 1.

[0069] It should be noted that when the compacted body 3 is de-hollowed again, steps S03 and S04 are repeated to repeat the grouting. Since the grouting pipe 1 is cleaned after grouting, there is no residual slurry in the grouting pipe 1, so the grouting pipe 1 will not be blocked due to the hardening of the slurry. After each grouting, the grouting pipe 1 is cleaned and can be reused for grouting.

[0070] The serial numbers of the embodiments of the present application are only for description and do not represent the advantages and disadvantages of the embodiments. The above are only preferred embodiments of the present application, and do not limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made by using the contents of the present application specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present application.

Claims

1. A pre-buried de-hollowing grouting device, characterized in that: include: A grouting pipe is pre-buried in the compacted body, near the interface between the compacted body and the concrete structure, and is used for grouting the voids generated at the interface between the compacted body and the concrete structure. One end of the grouting pipe extends outside the compacted body and is used for conveying slurry. A check valve is provided at the other end of the grouting pipe to prevent the slurry after grouting into the voids from flowing back into the grouting pipe. The grouting pipe comprises a main grouting pipe and a branch grouting pipe. A plurality of the branch grouting pipes are arranged at intervals at the interface between the compacted body and the concrete structure and connected to the main grouting pipe for dispersing the grout in the main grouting pipe to expand the grouting range. One end of the main grouting pipe extends outside the compacted body. A pressure monitoring device is arranged in the grouting pipe, and is used to monitor the grouting pressure in the grouting pipe, and stop grouting when the grouting pressure reaches a warning value of concrete structure destruction; A cleaning device is provided in the grouting pipe, and the cleaning device is used to clean the grouting pipe after the grouting is completed, so as to repeat the grouting for the voids generated again at the interface between the filling body and the concrete structure.

2. The pre-buried de-hollowing grouting device according to claim 1 is characterized in that: The pressure monitoring device comprises a pressure monitoring instrument and a wire, one end of the wire is connected to the monitoring instrument, and the other end of the wire extends outside the filling body.

3. The pre-buried de-hollowing grouting device according to claim 1 is characterized in that: The branch grouting pipe is movably connected to the main grouting pipe.

4. The pre-buried de-hollowing grouting device according to claim 3 is characterized in that: The pressure monitoring device is arranged in the main grouting pipe at a position close to the branch grouting pipe.

5. The pre-buried de-hollowing grouting device according to claim 1 is characterized in that: A bend is provided at one end of the branch grouting pipe away from the main grouting pipe, and the bend faces one side of the compacted body.

6. The pre-buried de-hollowing grouting device according to claim 5, characterized in that: The check valve is arranged at one end of the elbow away from the main grouting pipe.

7. The pre-buried de-hollowing grouting device according to claim 6, characterized in that: The check valve is provided with a demoulding device, and the demoulding device is used to prevent the slurry from adhering to the check valve after hardening.

8. The pre-buried de-hollowing grouting device according to claim 1, characterized in that: One end of the grouting pipe extending out of the building body is provided with a pipe plug.

9. A grouting construction method, using the pre-buried hollowing grouting device according to any one of claims 1 to 8, characterized in that: The following steps are involved: Step S01: manufacturing the grouting pipe: assembling the grouting pipe according to the size of the interface between the compacted body and the concrete structure, installing the pressure monitoring device in the grouting pipe, and installing the check valve at one end of the grouting pipe corresponding to the interface between the compacted body and the concrete structure; Step S02: pre-burying the grouting pipe and the pressure monitoring device: before the construction of the concrete structure, arranging the grouting pipe and the pressure monitoring device in the compacted body near the interface between the compacted body and the concrete structure, and extending the grouting pipe outside the compacted body; Step S03: Grouting construction: When the filling body is de-cavitated, grouting is performed into the grouting pipe using grouting equipment; and the pressure monitoring device is connected to the pressure analysis system to monitor the grouting pressure in the grouting pipe. When the grouting pressure in the grouting pipe reaches the warning value of concrete structure damage, the grouting is stopped.

10. The grouting construction method according to claim 9, characterized in that: After step S03, the method further includes step S04: maintaining the grouting pipe: cleaning the grouting pipe by using a cleaning device, and sealing the pipe opening of the grouting pipe by using a pipe plug after cleaning the grouting pipe.