A Convergence Monitoring Method for Shield Tunnel Lining Ring

By proposing the inclination conversion formula and optimal installation point method in the shield tunnel, the accuracy of wireless monitoring under the non-vertical line symmetric lining ring structure is solved, and real-time and accurate convergence monitoring of the shield tunnel lining ring is realized. Ensures construction safety and operation stability.

CN114964122BActive Publication Date: 2024-11-22GUANGZHOU UNIVERSITY +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210444288.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-25
Publication Date
2024-11-22
Estimated Expiration
2042-04-25

AI Technical Summary

Technical Problem

In shield tunnels, under the non-vertical line-symmetrical assembly of lining ring structure, existing wireless monitoring technology is difficult to effectively convert the inclination sensor data to real-time horizontal convergence changes, and lacks guidance on guidance and installation position guidance, resulting in inaccurate monitoring.

Method used

A horizontal convergence formula for inclination conversion of lining rings for non-vertical line symmetric assembly and an optimal installation point method for cross-sections is proposed. Through the finite element model and relative error evolution method, the optimal installation position of the inclination sensor is determined. Combining the principles of correction idioms and force methods, the inclination angle conversion convergence deformation formula is calculated to achieve real-time and accurate horizontal convergence monitoring.

Benefits of technology

It realizes accurate conversion of wireless monitoring of mid-inclination sensor data, provides the optimal installation position of the section, ensures real-time deformation monitoring and construction risk warning of shield tunnel lining rings, and improves monitoring accuracy and timeliness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114964122B_ABST
    Figure CN114964122B_ABST
Patent Text Reader

Abstract

The present invention discloses a convergence monitoring method for shield tunnel lining rings, step 1: establishing a lining ring model; step 2: determining the deformation basis of radial horizontal convergence of the lining ring and the calculation formula for inclination conversion convergence deformation based on the finite element model analysis of the lining ring and the following basic assumptions; step 3: obtaining the optimal installation position of the pipe segment of the section; the present invention can accurately guide the installation position of the wireless inclination sensor in the section, and at the same time, cooperate with the wireless sensor to convert the inclination data collected by the sensor into the corresponding horizontal convergence in real time, so as to be applied to the wireless monitoring network system to realize real-time and accurate monitoring. Obtain the real-time deformation of the lining structure, and timely and effectively warn of possible construction risks.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of wireless monitoring of subway shield tunnels, in particular to a convergence monitoring method for a shield tunnel lining ring. Background Art

[0002] Compared with other types of transportation, rail transit is fast, efficient, has a large passenger volume, and has a high punctuality rate. It can greatly alleviate urban congestion and is an indispensable part of building an urban transportation system. Among various rail transit structural forms, shield tunnels have the characteristics of high construction efficiency, guaranteed structural quality, large-scale mechanization, and little disturbance to the surface. They are widely used in rail transit section tunnel construction. In the development of shield tunnels, insufficient safety assessment of the tunnel structure will lead to some structural diseases, such as excessive structural deformation, which will affect the operation and service life of the track. Therefore, it is particularly necessary to monitor the health of the structure. For the monitoring of deformation in the tunnel, the horizontal radial convergence of the tunnel lining is an important indicator. Whether the indicator value is within the safety threshold plays a very important role in traffic safety.

[0003] The traditional shield tunnel lining horizontal convergence is mainly measured by measuring the change of radial chord length, including convergence meter method, total station non-directional free station method and other methods. The measurement of radial chord length is still mainly manual, with limited frequency, and some emergency situations in the tunnel cannot be monitored in time. In recent years, with the advancement of wireless sensing technology, the automatic horizontal radial convergence of the pipe segment has been realized through inclination sensors. This automated method has the advantages of high frequency, low energy consumption, good environmental adaptability, etc. However, in the actual monitoring process, since the assembly points of the existing prefabricated lining ring F blocks are changed according to actual needs, the lining ring structure is no longer symmetrical about the vertical line. Therefore, for this non-vertically symmetrical lining ring, how to convert the inclination change of the inclination sensor into real-time and effective horizontal convergence change during wireless monitoring, there is currently a lack of effective guiding theory, conversion formula and actual installation position guidance. Summary of the invention

[0004] The purpose of the present invention is to address the above-mentioned shortcomings in the existing method of horizontal convergence of inclination conversion of inclination sensors in wireless monitoring. The present invention proposes a formula for horizontal radial convergence of inclination conversion in a lining straight ring assembled with non-vertical lines symmetrically and the optimal installation point of the cross section, so as to solve the problem of horizontal convergence wireless perception in a straight ring assembled with non-vertical lines symmetrically.

[0005] To achieve the above-mentioned object, the present invention provides the following technical solutions: a convergence monitoring method for a shield tunnel lining ring;

[0006] The steps include:

[0007] Step 1: Establish a lining ring model;

[0008] The lining ring types include straight ring, left-turn ring and right-turn ring; the straight ring, left-turn ring and right-turn ring are assembled with 45° staggered joints; the straight ring is assembled with 3 standard blocks, 2 adjacent blocks and 1 capping block, the standard block is B block, the adjacent block is L block, and the capping block is F block, and B block, L block and F block are all pipe segments; the entire lining ring is 360 degrees, divided into a point every 22.5 degrees, and the top position is defined as the 0 point, which is also the 16th point; in the clockwise direction, a point is divided into every 22.5 degrees, and the number is There are 16 points in total, from 1 to 16. The biggest difference between the left and right turning rings and the straight rings is that the assembly points of the F blocks are different. For the left and right turning rings, the wedge volume must be considered. The assembly points of the F blocks can be changed at any time and are not fixed at any specific points. For the lining straight ring, the F blocks have fixed assembly points. Different from the traditional understanding that the F blocks are located at 0 points or 16 points, there are only two ways to assemble the F blocks in the straight section, the F blocks are at 1 point or the F blocks are at 15 points. The lining rings in the straight section are spliced ​​with 45-degree staggered seams.

[0009] Step 2: Based on the finite element model analysis of the lining ring and the following basic assumptions, determine the deformation basis of the radial horizontal convergence of the lining ring and the calculation formula for the convergence deformation of the inclination conversion:

[0010] (1) Assume that the rotation of the segment is a planar rotation and ignore the deformation of the segment itself, that is, the corresponding adjacent blocks and standard blocks are considered to be rigid bodies;

[0011] (2) It is assumed that the horizontal radial convergence is mainly caused by the rotation of the standard block and the adjacent block;

[0012] (3) Assume that the rotation center of the standard block is at the outer end point and the rotation center of the adjacent block is at the center of the outer arc surface;

[0013] Step 3: Obtain the optimal installation position of the segment of the section;

[0014] The theoretical assumption of step 2 is based on the premise that the segment is a rigid body;

[0015] In actual engineering, the pipe segment is not a strict rigid body, but a deformable body. Therefore, in practical applications, the inclination value of the pipe segment measured by the inclination sensor varies according to different installation positions. In order to determine the optimal installation point of the pipe segment of the tunnel section, the relative error evolution method is used to define the optimal section as follows: compared with other positions, the inclination change value at the installation point of the pipe segment is substituted into the derived inclination conversion convergence deformation calculation formula. The convergence value obtained by conversion is closest to the actual radial horizontal convergence value, and the position of the radial horizontal convergence value is considered to be the optimal installation position of the section.

[0016] Taking into account the reduction of bending stiffness of the segment joint part and further considering the distribution of partial bending moment in the case of misaligned joints, the calculation process is relatively simple and the calculation results are relatively reasonable. In order to obtain the optimal installation position of the segment of the section, the corresponding section with the F block installation point as point 1 is selected, and the modified conventional method is used to analyze the internal force of the lining structure and the inclination value of each installation point is solved according to the basic principle of the force method. Further, according to the definition of the optimal installation position, the analytical solution and error inversion method are used to find the installation position with the smallest absolute value of the relative error.

[0017] Preferably, the calculation formula for the inclination conversion convergence deformation in step 3 includes: a lining ring expansion state formula and a lining ring contraction state formula;

[0018] The lining ring expansion state formula is:

[0019] In triangle OAA 1 According to the sine theorem, we can get:

[0020]

[0021] In the triangle CBB 1 According to the sine theorem, we can get:

[0022]

[0023] The actual radial horizontal convergence is:

[0024] ΔD=ΔD l +ΔD2

[0025] Where R is the outer radius of the segment, e1 is the angle of rotation of the standard block around the outer end point, e2 is the angle of rotation of the adjacent block, α1, α2, θ1, θ2 are angles, which are determined when the segments are assembled and are known angles.

[0026] The shrinkage state formula of the lining ring is:

[0027] In triangle OAA 1 According to the sine theorem, we can get:

[0028]

[0029] In the triangle CBB 1 According to the sine theorem, we can get:

[0030]

[0031] The actual radial horizontal convergence is:

[0032] ΔD=ΔD1+ΔD2

[0033] In formulas (1), (2), (3), and (4), R is the outer radius of the segment, e1 is the angle of rotation of the standard block around the outer end point, e2 is the angle of rotation of the adjacent block, and α1, α2, θ1, and θ2 are angles that are determined when the segment is assembled and are known angles.

[0034] A state of contraction and expansion or expansion and contraction

[0035] Specifically, the above expansion and contraction formulas are caused by the adjacent blocks and standard blocks rotating clockwise or counterclockwise around their respective rotation points in the cross section, that is, the rotation of the standard block and the adjacent block is independent, that is, formulas (1), (2), (3) and (4) can be used in combination according to actual conditions. Therefore, if the expansion and contraction are performed at the same time, the actual radial horizontal convergence is (1) + (4) or (2) + (3).

[0036] Preferably, the "load-structure" calculation methods for the internal forces of Chinese lining structures in step 3 include the following four methods: conventional method, modified conventional method, multi-hinged circular ring method, and beam-spring method.

[0037] Compared with the prior art, the present invention has the following beneficial effects:

[0038] The calculation results of the present invention can accurately guide the installation position of the wireless inclination sensor in the section, and at the same time, the inclination data collected by the sensor can be converted into the corresponding horizontal convergence in real time with the wireless sensor, so as to be applied to the wireless monitoring network system to achieve real-time and accurate monitoring. The real-time deformation of the lining structure can be obtained, and the possible construction risk can be warned in a timely and effective manner. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] Figure 1 It is a plane schematic diagram of a lining straight ring with the F block installation point being 1 point in an embodiment of the present invention;

[0040] Figure 2 It is a plane schematic diagram of a lining straight ring with the F block installation point at 15 points in an embodiment of the present invention;

[0041] Figure 3 It is a schematic diagram of finite element force deformation of a lining straight ring with the F block installation point at point 1 in an embodiment of the present invention;

[0042] Figure 4 It is a schematic diagram of finite element stress and deformation of a lining straight ring with the F block installed at point 15 in an embodiment of the present invention;

[0043] Figure 5 Schematic diagram of conversion of inclination angle and chord length in an embodiment of the present invention (expanded state);

[0044] Figure 6Schematic diagram of conversion of inclination angle and chord length in an embodiment of the present invention (contracted state);

[0045] Figure 7 It is a schematic diagram of calculation of the modified usage method in an embodiment of the present invention;

[0046] Figure 8 It is a schematic diagram of a lining cross section in an embodiment of the present invention;

[0047] Fig. 9 It is a schematic diagram of the installation angle direction of the adjacent block and the standard block in the embodiment of the present invention;

[0048] Fig.10 is the distribution of the absolute value of the relative error of block B with the measurement position in the embodiment of the present invention;

[0049] Fig.11 : is the distribution of the absolute value of the L block relative error with the measurement position in the embodiment of the present invention. DETAILED DESCRIPTION

[0050] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0051] As attached Figure 1-11 As shown, the present invention provides a technical solution: a convergence monitoring method for a shield tunnel lining ring, based on the typical strata and structural parameters of the shield tunnel of the northern extension section of Shenzhen Metro Line 13 (see Table 1), combined with the modified conventional method and the error inversion method, an analytical method for the optimal installation position of the cross-section is proposed.

[0052] The load calculation diagram of the modified conventional method is as follows Figure 7 as shown; Figure 8 As shown in the schematic diagram of the lining structure, take the lining linear ring with F block installed at 1 as an example, where the total number of segments is 6, the outer diameter of the lining is 6.7m, and the inner diameter of the lining is 6.0m; the concrete grade of the segment is C50, the actual width of the segment is 1.5m, and the bulk density of the segment is 23.0KN / m 3 The distance H from the ground surface to the top of the tunnel is 14m, and the average water level is 3.5m deep.

[0053] Table 1 Soil layer information of typical sections of Shenzhen Metro Line 13 North Extension

[0054]

[0055]

[0056] According to the specification "Technical Specification for Railway Tunnel Shield Method TB 10181-2017", "For reference, the design η of flat-plate segments is 0.8 and ζ is 0.3". In this case, the lining segments are flat-plate shaped, and the modified conventional method correlation coefficients are selected according to the specification, where the bending stiffness efficiency η is 0.8 and the moment increase rate ζ is 0.3.

[0057] In order to better process the calculation data, the following definition is given, such as Fig. 9 As shown, the bottom position of the B block and the L block is used as the starting line for calculating the installation angle, and the installation angle direction increases in the direction shown in the figure.

[0058] The specific method analysis and result description process are as follows:

[0059] (a) The inclination angle changes of different parts of the standard segment and the adjacent segment are substituted into the derived conversion formula to obtain the converted horizontal diameter convergence value;

[0060] (b) Compare the converted horizontal convergence with the horizontal diameter convergence value obtained by the modified conventional analytical method, and calculate the relative error percentage;

[0061] (c) According to (b), the distribution diagram of the absolute value of the relative error of each point in the standard block and the adjacent block is obtained and normalized (where Respectively represent the central angles of the standard block and adjacent block segments) (see Fig.10 , Fig.11 );

[0062] The data results of the absolute value distribution diagram of the relative error in conversion mentioned in (c) are analyzed:

[0063] from Fig.10 It can be seen that the relative errors caused by different installation angles are obviously different, and the overall error curve presents a groove shape; in the range of 0°-33.75°, as the installation angle increases, the relative error continues to decrease, and finally at 33.75° it is 1.15%, close to zero, at this time the converted horizontal diameter converges closest to the theoretical value; in the range of 33.75°-67.5°, as the installation angle increases, the relative error continues to increase, and the maximum relative error is nearly 350%, obviously the error is too large at this time, the data is completely distorted and the deviation is too large. From the overall perspective of the standard block segment, the relative error is the smallest when the installation angle is close to 1 / 2, that is, in the middle of the inner arc surface of the standard block, which can be defined as the optimal installation position of the standard block.

[0064] from Fig.11It can be seen that the relative error difference caused by the different installation angles of adjacent blocks is also very obvious. The overall error curve is irregular and has no obvious characteristics. There are two local low points. At 7.5°, the relative error is 1.72%, which is close to zero. At 45°, the relative error is 21%, which is at the low point in the local range. On the overall curve, the maximum relative error can reach 340%, which is obtained at 30°. Obviously, the error is too large at this time, the data is completely distorted and the deviation is too large. In the range of 3.75°-11.25°, the relative error drops from 6% to 1.7% and then rises to 14.3%. After that, the overall relative error curve fluctuates greatly. At the second local low point, the relative error is also at a large position. From the overall perspective of the adjacent block segment, the installation angle is close to 1 / 10, and the relative error is the smallest. At this time, it can be defined as the optimal installation position of the adjacent block.

[0065] Therefore, the optimal installation position of the cross section should be placed in different parts of different blocks. Taking the F block installed at the 1-point position as an example, the inclination sensor should be placed in the middle of its inner arc surface at the standard block, that is, at the 1 / 2 center angle position; the inclination sensor should be placed at the inner arc surface corresponding to the 1 / 10 center angle at the adjacent block. For the F block installed at the 15-point position, the calculation principle, method and calculation results are basically the same as those at the 1-point position, except that the positions of the standard block and the adjacent block are swapped at the same side. Therefore, this article will no longer elaborate on the convergence formula derivation and result analysis of the F block installed at the 15-point position, and the derivation formula and result analysis of the 1-point position can be used as a reference.

[0066] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A method for monitoring the convergence of a shield tunnel lining ring, characterized in that: The steps include: Step 1: Establish a lining ring model; The lining ring types include straight ring, left-turn ring and right-turn ring; the straight ring, left-turn ring and right-turn ring are assembled with 45° staggered joints; the straight ring is assembled with 3 standard blocks, 2 adjacent blocks and 1 capping block, the standard block is B block, the adjacent block is L block, and the capping block is F block, and B block, L block and F block are all pipe segments; the entire lining ring is 360 degrees, divided into a point every 22.5 degrees, and the top position is defined as the 0 point, which is also the 16th point; in the clockwise direction, a point is divided into every 22.5 degrees, and the number is There are 16 points in total, from 1 to 16. The biggest difference between the left and right turning rings and the straight rings is that the assembly points of the F blocks are different. For the left and right turning rings, the wedge volume must be considered. The assembly points of the F blocks can be changed at any time and are not fixed at any specific points. For the lining straight ring, the F blocks have fixed assembly points. Different from the traditional understanding that the F blocks are located at 0 points or 16 points, there are only two ways to assemble the F blocks in the straight section, the F blocks are at 1 point or the F blocks are at 15 points. The lining rings in the straight section are spliced ​​with 45-degree staggered seams. Step 2: Based on the finite element model analysis of the lining ring and the following basic assumptions, determine the deformation basis of the radial horizontal convergence of the lining ring and the calculation formula for the convergence deformation of the inclination conversion: (1) Assuming that the rotation of the segment is a planar rotation, the deformation of the segment itself is ignored, that is, the corresponding adjacent blocks and standard blocks are considered to be rigid bodies; (2) It is assumed that the horizontal radial convergence is mainly caused by the rotation of the standard block and the adjacent block; (3) Assume that the rotation center of the standard block is at the outer end point and the rotation center of the adjacent block is at the center of the outer arc surface; Step 3: Obtain the optimal installation position of the segment of the section; The theoretical assumption of step 2 is based on the premise that the segment is a rigid body; In actual engineering, the pipe segment is not a strict rigid body, but a deformable body. Therefore, in practical applications, the inclination value of the pipe segment measured by the inclination sensor varies according to different installation positions. In order to determine the optimal installation point of the pipe segment of the tunnel section, the relative error evolution method is used to define the optimal section as follows: compared with other positions, the inclination change value at the installation point of the pipe segment is substituted into the derived inclination conversion convergence deformation calculation formula. The convergence value obtained by conversion is closest to the actual radial horizontal convergence value, and the position of the radial horizontal convergence value is considered to be the optimal installation position of the section. Considering the reduction of bending stiffness of the segment joint part and further considering the distribution of partial bending moment in the case of misaligned joints, the calculation process is relatively simple and the calculation results are relatively reasonable; in order to obtain the optimal installation position of the segment of the section, the corresponding section with the F block installation point as point 1 is selected, and the internal force of the lining structure is analyzed by the modified conventional method, and the inclination value of each installation point is solved according to the basic principle of the force method. Further, according to the definition of the optimal installation position, the analytical solution and error inversion method are used to find the installation position with the smallest absolute value of relative error; The inclination angle conversion convergence deformation calculation formula in step 3 includes: lining ring expansion state formula, lining ring contraction state formula; The lining ring expansion state formula is: In triangle OAA 1 According to the sine theorem, we can get: (1) In the triangle CBB 1 According to the sine theorem, we can get: (2) The actual radial horizontal convergence is: Where R is the outer radius of the segment, e1 is the angle of rotation of the standard block around the outer end point, e2 is the angle of rotation of the adjacent block, α1, α2, θ1, θ2 are angles, which are determined when the segment is assembled and are known angles; The shrinkage state formula of the lining ring is: In triangle OAA 1 According to the sine theorem, we can get: (3) In the triangle CBB 1 According to the sine theorem, we can get: (4) The actual radial horizontal convergence is: In formulas (1), (2), (3), and (4), R is the outer radius of the segment, e1 is the angle of rotation of the standard block around the outer end point, e2 is the angle of rotation of the adjacent block, and α1, α2, θ1, and θ2 are angles that are determined when the segment is assembled and are known angles.

2. A method for monitoring the convergence of a shield tunnel lining ring according to claim 1, characterized in that: The "load-structure" calculation methods for the internal force of the lining structure in step 3 include the following four methods: conventional method, modified conventional method, multi-hinged circular ring method, and beam-spring method.