Scheduling method, system and terminal based on load-side monitoring
Through a dispatching method based on load-side monitoring, the Dijkstra algorithm is used to select the optimal dispatch line, which solves the problem of grid dispatch lag and achieves timely satisfaction of load-side demands, which has wide application prospects.
Patent Information
- Application Number
- CN202210748222.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-29
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2042-06-29
AI Technical Summary
Existing power grid dispatching methods cannot meet the actual demand of the load side in a timely manner, resulting in hysteresis in dispatching.
A dispatching method based on load-end monitoring is adopted to determine the target load end by monitoring real-time power, and use the Dijkstra algorithm to select the best dispatch line from the dispatch center to the target load end from the regional power grid topology, and perform status debugging to enable the best dispatch line. Supply power to the target load terminal.
It realizes the timely adjustment of the scheduling plan according to the load-end demand and meets the load-end demand in time. The design principle is reliable, the structure is simple, and it has wide application prospects.
Smart Images

Figure CN115051470B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power supply dispatching, and in particular to a dispatching method, system and terminal based on load-end monitoring. Background Art
[0002] At present, most power grid dispatching centers generate a dispatching plan based on the demands reported by all parties, and then control the switching status of each dispatching node according to the dispatching plan to complete the dispatching. This dispatching method is too rough and cannot be debugged in time according to the actual demands of the load end, thus resulting in a lag in dispatching. Summary of the invention
[0003] In view of the problem that the prior art has scheduling lags and cannot meet the load-side demand in a timely manner, the present invention provides a scheduling method, system and terminal based on load-side monitoring to solve the above technical problems.
[0004] In a first aspect, the present invention provides a scheduling method based on load-side monitoring, comprising:
[0005] Monitor the real-time power of each load end, and determine the target load end according to the real-time power of each load end;
[0006] Obtain the dispatching parameters and average dispatching time of all dispatching nodes in the region, and import the dispatching parameters and average dispatching time of each dispatching node into the regional power grid topology;
[0007] The dispatch weight is generated according to the dispatch parameters and average dispatch time of each dispatch node, and the Dijkstra algorithm is used to screen the best dispatch route from the dispatch center to the target load end from the regional power grid topology;
[0008] By debugging the status of the dispatching nodes through which the optimal dispatching line passes, the optimal dispatching line is enabled to supply power to the target load end.
[0009] Further, monitoring the real-time power of each load end and determining the target load end according to the real-time power of each load end includes:
[0010] When each scheduling node maintains the current scheduling parameters, a power threshold of each load end is generated;
[0011] Monitor the difference between the real-time power of the load end and the power threshold, and calculate whether the ratio of the difference to the power threshold reaches the set threshold:
[0012] If so, the corresponding load end ID is output as the target load end information.
[0013] Furthermore, the dispatching parameters and average dispatching time of all dispatching nodes in the region are obtained, and the dispatching parameters and average dispatching time of each dispatching node are imported into the regional power grid topology, including:
[0014] Obtaining the dispatching parameters and average dispatching time of all dispatching nodes in the dispatching area under the dispatching center, wherein the dispatching parameters indicate the activation status of each branch line under the dispatching node; and the average dispatching time indicates the operation time used by the dispatching node to change the activation status of the branch line under its jurisdiction once;
[0015] A structure is created for each dispatching node in the regional power grid topology, and the dispatching parameters and average dispatching time of the dispatching node are saved to the corresponding dispatching node structure. The regional power grid topology includes a dispatching center, dispatching nodes at various levels, and a connection line topology structure of each load end.
[0016] Furthermore, the dispatch weight is generated according to the dispatch parameters and average dispatch time of each dispatch node, and the Dijkstra algorithm is used to screen the best dispatch line from the dispatch center to the target load end from the regional power grid topology, including:
[0017] Determine whether the branch line under the dispatching node associated with the target load end is in the open state according to the dispatching parameters:
[0018] If yes, the weight of the branch line associated with the dispatching node is 1;
[0019] If not, the weight of the associated branch line of the scheduling node is 1+t, where t is the average scheduling time of the scheduling node.
[0020] Furthermore, by debugging the status of the dispatching nodes through which the optimal dispatching line passes, the optimal dispatching line is enabled to supply power to the target load end, including:
[0021] The upper-level dispatching node of the branch line in the best dispatching line that is in a closed state is debugged to switch the branch line in a closed state to an enabled state.
[0022] In a second aspect, the present invention provides a dispatching system based on load-side monitoring, comprising:
[0023] A load monitoring unit, used to monitor the real-time power of each load end and determine the target load end according to the real-time power of each load end;
[0024] A data acquisition unit, used to acquire the dispatching parameters and average dispatching time of all dispatching nodes in the region, and import the dispatching parameters and average dispatching time of each dispatching node into the regional power grid topology;
[0025] The line generation unit is used to generate the dispatch weight according to the dispatch parameters and average dispatch time of each dispatch node, and select the best dispatch line from the dispatch center to the target load end from the regional power grid topology by using the Dijkstra algorithm;
[0026] The state debugging unit is used to enable the best scheduling line to supply power to the target load end by debugging the state of the scheduling node through which the best scheduling line passes.
[0027] Furthermore, the load monitoring unit includes:
[0028] A threshold generation module is used to generate a power threshold of each load end when each scheduling node maintains the current scheduling parameters;
[0029] A power monitoring module, used to monitor the difference between the real-time power of the load end and the power threshold, and calculate whether the ratio of the difference to the power threshold reaches a set threshold;
[0030] The target determination module is used to output the corresponding load end ID as the target load end information if the ratio of the difference to the power threshold reaches a set threshold.
[0031] Furthermore, the data acquisition unit includes:
[0032] A data acquisition module is used to obtain the dispatching parameters and average dispatching time of all dispatching nodes in the dispatching area under the dispatching center, wherein the dispatching parameters indicate the activation status of each branch line under the dispatching node; and the average dispatching time indicates the operation time used by the dispatching node to change the activation status of the branch line under its jurisdiction once;
[0033] The data saving module is used to create a structure for each dispatching node in the regional power grid topology, and save the dispatching parameters and average dispatching time of the dispatching node to the corresponding dispatching node structure. The regional power grid topology includes the dispatching center, dispatching nodes at all levels and the connection line topology of each load end.
[0034] In a third aspect, a terminal is provided, including:
[0035] processor, memory, wherein:
[0036] The memory is used to store computer programs.
[0037] The processor is used to call and run the computer program from the memory, so that the terminal executes the above-mentioned terminal method.
[0038] According to a fourth aspect, a computer storage medium is provided, wherein the computer-readable storage medium stores instructions, and when the instructions are executed on a computer, the computer executes the methods described in the above aspects.
[0039] The beneficial effect of the present invention is that the scheduling method, system and terminal based on load-end monitoring provided by the present invention can timely adjust the scheduling plan according to the load-end demand, thereby meeting the load-end demand in a timely manner.
[0040] In addition, the invention has a reliable design principle, a simple structure and a very broad application prospect. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0042] Figure 1 is a schematic flow chart of a method according to an embodiment of the present invention.
[0043] Figure 2 is a schematic block diagram of a system according to an embodiment of the present invention.
[0044] Figure 3 A schematic diagram of the structure of a terminal provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0045] In order to enable those skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0046] Figure 1 is a schematic flow chart of a method according to an embodiment of the present invention. Figure 1 The execution entity may be a scheduling system based on load-side monitoring.
[0047] like Figure 1 As shown, the method includes:
[0048] Step 110, monitoring the real-time power of each load end, and determining the target load end according to the real-time power of each load end;
[0049] Step 120, obtaining the dispatching parameters and average dispatching time of all dispatching nodes in the region, and importing the dispatching parameters and average dispatching time of each dispatching node into the regional power grid topology;
[0050] Step 130, generating a dispatch weight according to the dispatch parameters and average dispatch time of each dispatch node, and using the Dijkstra algorithm to select the best dispatch route from the dispatch center to the target load end from the regional power grid topology;
[0051] Step 140 , enabling the best scheduling line to supply power to the target load end by debugging the status of the scheduling nodes through which the best scheduling line passes.
[0052] To facilitate understanding of the present invention, the scheduling method based on load-end monitoring provided by the present invention is further described below based on the principle of the scheduling method based on load-end monitoring of the present invention and in combination with the process of scheduling based on load-end monitoring in the embodiment.
[0053] Specifically, the scheduling method based on load-side monitoring includes:
[0054] S1. Monitor the real-time power of each load end, and determine the target load end according to the real-time power of each load end.
[0055] While each scheduling node maintains the current scheduling parameters, a power threshold for each load end is generated; the difference between the real-time power of the load end and the power threshold is monitored, and the ratio of the difference to the power threshold is calculated to see whether it reaches the set threshold: if so, the corresponding load end ID is output as the target load end information.
[0056] Once the branch lines enabled in the regional power grid topology are completely determined, the maximum power of each load end, i.e., the power threshold, is also determined. Therefore, the power thresholds of each load end under various branch line activation scenarios are saved in advance. Thus, the power thresholds of each load end can be determined according to the current scheduling parameters. The load end includes, for example, a community access end and an industrial park access end.
[0057] Regularly monitor the power at the load end. The power value can be collected every 10 minutes, the difference between the power value and the power threshold of the load end is calculated, the absolute value of the difference is taken, the ratio of the absolute value of the difference to the power threshold is calculated, and then it is determined whether the ratio reaches the set threshold. If the threshold is reached, it is determined that the actual power of the load end is too high and scheduling is required.
[0058] S2. Obtain the dispatching parameters and average dispatching time of all dispatching nodes in the region, and import the dispatching parameters and average dispatching time of each dispatching node into the regional power grid topology.
[0059] Obtain the dispatching parameters and average dispatching time of all dispatching nodes in the dispatching area under the dispatching center. The dispatching parameters indicate the activation status of each branch line under the dispatching node; the average dispatching time indicates the operation time used by the dispatching node to change the activation status of the branch line under its jurisdiction once; create a structure for each dispatching node in the regional power grid topology, and save the dispatching parameters and average dispatching time of the dispatching node to the corresponding dispatching node structure. The regional power grid topology includes the dispatching center, dispatching nodes at all levels, and the connecting line topology of each load end.
[0060] The method for obtaining the dispatching parameters of the dispatching node is that the dispatching node reports the switching status of each branch line under its jurisdiction to the dispatching center after each dispatching operation. The dispatching center records the time taken by each dispatching node from receiving the dispatching instruction to completing the dispatching instruction, and then calculates the average time of multiple dispatches to obtain the average dispatching time of the dispatching node.
[0061] S3. Generate dispatch weights according to the dispatch parameters and average dispatch time of each dispatch node, and use the Dijkstra algorithm to screen out the best dispatch route from the dispatch center to the target load end from the regional power grid topology.
[0062] According to the dispatching parameters, it is determined whether the subordinate branch line of the dispatching node associated with the target load end is in the open state: if so, the weight of the subordinate branch line associated with the dispatching node is 1; if not, the weight of the subordinate branch line associated with the dispatching node is 1+t, where t is the average dispatching time of the dispatching node.
[0063] The Dijkstra algorithm is used to select the best dispatching line from all dispatching lines from the dispatching center to the target load end in the regional power grid topology. The dispatching line refers to the connection line from the dispatching center to the load end in the regional power grid topology. The connection line may include multiple dispatching nodes and corresponding branch lines. The dispatching center in the regional power grid topology is the only starting point. The dispatching nodes and corresponding branch lines form a line network. The dispatching center can select multiple lines from the line network to connect to the load end. This connection line is the dispatching line. Since each dispatching line passes through different dispatching nodes, the Dijkstra algorithm is used to select the best dispatching line with the shortest dispatching time based on the weights of the dispatching nodes on the line. Dijkstra algorithm: Dijkstra algorithm is a typical shortest path algorithm used to calculate the shortest path from one node to other nodes. Its main feature is to expand outward layer by layer with the starting point as the center (breadth-first search idea) until it reaches the end point.
[0064] S4. By debugging the status of the dispatching nodes through which the optimal dispatching line passes, the optimal dispatching line is enabled to supply power to the target load end.
[0065] The upper-level dispatching node of the branch line in the best dispatching line that is in a closed state is debugged to switch the branch line in a closed state to an enabled state.
[0066] like Figure 2 As shown, the system 200 includes:
[0067] The load monitoring unit 210 is used to monitor the real-time power of each load end and determine the target load end according to the real-time power of each load end;
[0068] The data acquisition unit 220 is used to acquire the dispatching parameters and average dispatching time of all dispatching nodes in the region, and import the dispatching parameters and average dispatching time of each dispatching node into the regional power grid topology;
[0069] The line generation unit 230 is used to generate a dispatch weight according to the dispatch parameters and average dispatch time of each dispatch node, and select the best dispatch line from the dispatch center to the target load end from the regional power grid topology by using the Dijkstra algorithm;
[0070] The state debugging unit 240 is used to enable the best scheduling line to supply power to the target load end by debugging the state of the scheduling node through which the best scheduling line passes.
[0071] Optionally, as an embodiment of the present invention, the load monitoring unit includes:
[0072] A threshold generation module is used to generate a power threshold of each load end when each scheduling node maintains the current scheduling parameters;
[0073] A power monitoring module, used to monitor the difference between the real-time power of the load end and the power threshold, and calculate whether the ratio of the difference to the power threshold reaches a set threshold;
[0074] The target determination module is used to output the corresponding load end ID as the target load end information if the ratio of the difference to the power threshold reaches a set threshold.
[0075] Optionally, as an embodiment of the present invention, the data acquisition unit includes:
[0076] A data acquisition module is used to obtain the dispatching parameters and average dispatching time of all dispatching nodes in the dispatching area under the dispatching center, wherein the dispatching parameters indicate the activation status of each branch line under the dispatching node; and the average dispatching time indicates the operation time used by the dispatching node to change the activation status of the branch line under its jurisdiction once;
[0077] The data saving module is used to create a structure for each dispatching node in the regional power grid topology, and save the dispatching parameters and average dispatching time of the dispatching node to the corresponding dispatching node structure. The regional power grid topology includes the dispatching center, dispatching nodes at all levels and the connection line topology of each load end.
[0078] Figure 3 A schematic diagram of the structure of a terminal 300 provided in an embodiment of the present invention. The terminal 300 can be used to execute the scheduling method based on load-side monitoring provided in an embodiment of the present invention.
[0079] The terminal 300 may include: a processor 310, a memory 320 and a communication unit 330. These components communicate via one or more buses. Those skilled in the art will appreciate that the server structure shown in the figure does not limit the present invention, and it may be a bus structure or a star structure, and may include more or fewer components than shown in the figure, or combine certain components, or arrange the components differently.
[0080] The memory 320 can be used to store the execution instructions of the processor 310, and the memory 320 can be implemented by any type of volatile or non-volatile storage terminal or a combination thereof, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic memory, flash memory, magnetic disk or optical disk. When the execution instructions in the memory 320 are executed by the processor 310, the terminal 300 can perform some or all of the steps in the following method embodiments.
[0081] The processor 310 is the control center of the storage terminal, and uses various interfaces and lines to connect various parts of the entire electronic terminal. It runs or executes software programs and / or modules stored in the memory 320, and calls data stored in the memory to perform various functions of the electronic terminal and / or process data. The processor can be composed of an integrated circuit (IC), for example, it can be composed of a single packaged IC, or it can be composed of a plurality of packaged ICs with the same or different functions. For example, the processor 310 can include only a central processing unit (CPU). In the embodiment of the present invention, the CPU can be a single computing core or multiple computing cores.
[0082] The communication unit 330 is used to establish a communication channel so that the storage terminal can communicate with other terminals, receive user data sent by other terminals or send user data to other terminals.
[0083] The present invention also provides a computer storage medium, wherein the computer storage medium may store a program, and when the program is executed, the program may include some or all of the steps in each embodiment provided by the present invention. The storage medium may be a magnetic disk, an optical disk, a read-only memory (ROM) or a random access memory (RAM).
[0084] Therefore, the present invention can timely adjust the scheduling plan according to the load-side demand, thereby timely meeting the load-side demand. The technical effects that can be achieved by this embodiment can be found in the description above and will not be repeated here.
[0085] Those skilled in the art can clearly understand that the technology in the embodiments of the present invention can be implemented by means of software plus a necessary general hardware platform. Based on this understanding, the technical solution in the embodiments of the present invention, in essence or in other words, the part that contributes to the prior art, can be embodied in the form of a software product, which is stored in a storage medium such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a disk or an optical disk, and other media that can store program codes, including several instructions for enabling a computer terminal (which can be a personal computer, a server, or a second terminal, a network terminal, etc.) to perform all or part of the steps of the methods described in each embodiment of the present invention.
[0086] In this specification, the same or similar parts between the various embodiments can be referred to each other. In particular, for the terminal embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the description in the method embodiment.
[0087] In the several embodiments provided by the present invention, it should be understood that the disclosed systems and methods can be implemented in other ways. For example, the system embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of systems or units, which can be electrical, mechanical or other forms.
[0088] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0089] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.
[0090] Although the present invention has been described in detail by referring to the accompanying drawings and in combination with the preferred embodiments, the present invention is not limited thereto. Without departing from the spirit and essence of the present invention, a person of ordinary skill in the art may make various equivalent modifications or substitutions to the embodiments of the present invention, and these modifications or substitutions shall be within the scope of the present invention. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed by the present invention, and all of these shall be within the scope of protection of the present invention. Therefore, the scope of protection of the present invention shall be subject to the scope of protection of the claims.
Claims
1. A scheduling method based on load-side monitoring, characterized in that: include: Monitor the real-time power of each load end, and determine the target load end according to the real-time power of each load end; Obtain the dispatching parameters and average dispatching time of all dispatching nodes in the region, and import the dispatching parameters and average dispatching time of each dispatching node into the regional power grid topology; The dispatch weight is generated according to the dispatch parameters and average dispatch time of each dispatch node, and the Dijkstra algorithm is used to screen the best dispatch route from the dispatch center to the target load end from the regional power grid topology; By debugging the status of the dispatching nodes through which the optimal dispatching line passes, the optimal dispatching line is enabled to supply power to the target load end; Monitor the real-time power of each load end and determine the target load end according to the real-time power of each load end, including: When each scheduling node maintains the current scheduling parameters, a power threshold of each load end is generated; Monitor the difference between the real-time power of the load end and the power threshold, and calculate whether the ratio of the difference to the power threshold reaches the set threshold: If yes, the corresponding load end ID is output as the target load end information; Obtain the dispatch parameters and average dispatch time of all dispatch nodes in the region, and import the dispatch parameters and average dispatch time of each dispatch node into the regional power grid topology, including: Obtaining the dispatching parameters and average dispatching time of all dispatching nodes in the dispatching area under the dispatching center, wherein the dispatching parameters indicate the activation status of each branch line under the dispatching node; and the average dispatching time indicates the operation time used by the dispatching node to change the activation status of the branch line under its jurisdiction once; A structure is created for each dispatching node in the regional power grid topology, and the dispatching parameters and average dispatching time of the dispatching node are saved to the corresponding dispatching node structure. The regional power grid topology includes a dispatching center, dispatching nodes at various levels, and a connection line topology structure of each load end.
2. The method according to claim 1, characterized in that The dispatch weight is generated according to the dispatch parameters and average dispatch time of each dispatch node, and the Dijkstra algorithm is used to screen the best dispatch line from the dispatch center to the target load end from the regional power grid topology, including: Determine whether the branch line under the dispatching node associated with the target load end is in the open state according to the dispatching parameters: If yes, the weight of the branch line associated with the dispatching node is 1; If not, the weight of the associated branch line of the scheduling node is 1+t, where t is the average scheduling time of the scheduling node.
3. The method according to claim 1, characterized in that By debugging the status of the dispatching nodes through which the optimal dispatching line passes, the optimal dispatching line is enabled to supply power to the target load end, including: The upper-level dispatching node of the branch line in the best dispatching line that is in a closed state is debugged to switch the branch line in a closed state to an enabled state.
4. A dispatching system based on load-side monitoring, characterized in that: include: A load monitoring unit, used to monitor the real-time power of each load end and determine the target load end according to the real-time power of each load end; A data acquisition unit, used to acquire the dispatching parameters and average dispatching time of all dispatching nodes in the region, and import the dispatching parameters and average dispatching time of each dispatching node into the regional power grid topology; The line generation unit is used to generate the dispatch weight according to the dispatch parameters and average dispatch time of each dispatch node, and select the best dispatch line from the dispatch center to the target load end from the regional power grid topology by using the Dijkstra algorithm; A state debugging unit is used to enable the best scheduling line to supply power to the target load end by debugging the state of the scheduling node through which the best scheduling line passes; The load monitoring unit comprises: A threshold generation module is used to generate a power threshold of each load end when each scheduling node maintains the current scheduling parameters; A power monitoring module, used to monitor the difference between the real-time power of the load end and the power threshold, and calculate whether the ratio of the difference to the power threshold reaches a set threshold; a target determination module, configured to output the corresponding load end ID as target load end information if the ratio of the difference to the power threshold reaches a set threshold; The data acquisition unit comprises: A data acquisition module is used to obtain the dispatching parameters and average dispatching time of all dispatching nodes in the dispatching area under the dispatching center, wherein the dispatching parameters indicate the activation status of each branch line under the dispatching node; and the average dispatching time indicates the operation time used by the dispatching node to change the activation status of the branch line under its jurisdiction once; The data saving module is used to create a structure for each dispatching node in the regional power grid topology, and save the dispatching parameters and average dispatching time of the dispatching node to the corresponding dispatching node structure. The regional power grid topology includes the dispatching center, dispatching nodes at all levels and the connection line topology of each load end.
5. A terminal, characterized in that: include: processor; A memory for storing execution instructions of the processor; The processor is configured to execute the method according to any one of claims 1 to 3.
Citation Information
Patent Citations
AGC signal correction system optimized by adopting RTU
CN112332428A
Demand-based regional power grid dispatching method and system, terminal and storage medium
CN112803427A