A method for detecting multiple states of underground pipelines and pipe corridors

Through the Internet of Things sensing equipment and multi-state algorithm models, combined with multi-factor strategies and integrated algorithms, the operation and maintenance risk assessment of underground pipelines and pipe corridors is realized, which solves the problem of the inability to quantitatively assess operation and maintenance risks in the existing technology and reduces risk events. Impact on lives, lives and property.

CN115099482BActive Publication Date: 2024-10-15HANGZHOU WATER DATA INTELLIGENCE TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210700781.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-21
Publication Date
2024-10-15
Estimated Expiration
2042-06-21

Smart Images

  • Figure CN115099482B_ABST
    Figure CN115099482B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for detecting multiple states of underground pipelines and pipe corridors. It specifically includes the following steps: obtaining real-time state data and real-time risk data through IoT sensing devices installed in underground pipelines and pipe corridors; establishing a multiple state algorithm model for equipment, and judging the current equipment operation state through multiple data of equipment; establishing a comprehensive operation risk assessment algorithm model, and adopting a multi-factor strategy combined with an integrated algorithm to obtain a comprehensive operation risk assessment value; and realizing the operation monitoring of underground pipelines and pipe corridors, the dispatching of operation tasks and the processing of receipts, and the simulation of the impact of risk events through the comprehensive operation risk assessment value. The beneficial effects of the present invention are: through a multiple and quantitative assessment method for the operation and maintenance risk state of underground pipelines and pipe corridors, further handling hidden dangers before risk events occur, or reducing the impact and losses caused by the events to people's lives, lives, property and other aspects after the risk events occur (but not yet over).
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field related to underground pipelines and pipe galleries, and in particular to a method for detecting multiple states of underground pipelines and pipe galleries. Background Art

[0002] Underground pipelines are pipes laid underground for the transportation of liquids, gases or loose solids. There are many types of modern underground pipelines, including circular, elliptical, semi-elliptical, multi-circular, oval, rectangular (single hole, double hole and multi-hole), horseshoe and other cross-sectional forms, and they are built with steel, cast iron, concrete, reinforced concrete, prestressed concrete, brick, stone, asbestos cement, clay, plastic, fiberglass (reinforced plastic) and other materials. Underground comprehensive pipeline corridors can effectively prevent the "zipper road" phenomenon, so that technicians do not need to repeatedly dig the road surface, and can repair, maintain, expand and transform various pipelines in the pipeline corridor; at the same time, it greatly reduces the time for pipeline repairs.

[0003] Existing underground pipelines and pipeline corridors cannot conduct multi-dimensional and quantitative assessments of their operation and maintenance risk status, so they cannot efficiently deal with hidden dangers before risk events occur, or reduce the impact and losses caused by risk events to people's lives, lives, property, etc. after risk events occur (but not yet over). Summary of the invention

[0004] The present invention aims to overcome the above-mentioned deficiencies in the prior art and provides a method for detecting multiple states of underground pipelines and pipe galleries that can perform multiple and quantitative evaluations.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] A method for detecting multiple states of underground pipelines and pipe corridors, comprising the following steps:

[0007] (1) Data collection layer: Real-time status data and risk data are obtained through IoT sensing devices installed in underground pipelines and pipe corridors;

[0008] (2) Algorithm model layer: Establish a multivariate equipment status algorithm model to judge the current equipment operation status through multivariate equipment data. The algorithm outputs three qualitative results: intact, incomplete, and faulty.

[0009] (3) Algorithm model layer: Establish a comprehensive operation risk assessment algorithm model, and use a multi-factor strategy combined with an integrated algorithm to obtain a comprehensive operation risk assessment value;

[0010] (4) Application layer: Through comprehensive operational risk assessment values, it can monitor the operation of underground pipelines and tunnels, dispatch operational tasks and process receipts, as well as simulate the impact of risk events.

[0011] This method uses a multi-dimensional and quantitative assessment method to assess the operation and maintenance risk status of underground pipelines and pipe corridors, and further deal with hidden dangers before risk events occur, or reduce the impact and losses caused by the events to people's lives, lives, property, etc. after the risk events occur (but not yet over).

[0012] Preferably, in step (1), the IoT sensing device includes a liquid level transmitter, a pressure transmitter, an ultrasonic level meter, a radar level meter, a water quality sensor, an abnormal switch, a gas sensor, and an electromagnetic flow meter; the risk data acquisition method is as follows: through daily inspections of underground pipelines and corridors by operators and managers, statistical data of various risk events and daily operation data are acquired through work order operation data.

[0013] Preferably, in step (2), the device multivariate state algorithm model is as follows:

[0014] Assume that the training set data D(x1,x2,...,x t ) There are t states in total. A binary SVM is constructed between each two states using the LIBSVM method. For the i-th and j-th data, training a binary SVM is to solve the quadratic programming problem:

[0015]

[0016] The superscript t represents the parameter of the binary SVM between class i and class j; the subscript t represents the index of the sample in the union of class i and class j; φ represents the nonlinear mapping from input space to feature space; the training set data D(x1,x2,...,x t ) t They correspond to the IoT sensing devices to obtain real-time status data and risk data, w represents the weight, b represents the random number, ζ represents the relaxation coefficient, st(w ij ) T φ(x t ) represents the calculation result after mapping the weight and input value, x t Represents the input value, y t represents the prediction result, ζ ij t It represents the relaxation coefficient of the formula for calculating the input value, T is the transposition symbol, and C is the penalty term of the relaxation system;

[0017] Index i, j∈{1,...,M}, i<j, a total of training is required binary SVMs, each class contains N / M samples on average, so each dual problem contains 2N / M variables on average;

[0018] The decision function of binary SVM between class i and class j is:

[0019]

[0020] The above formula is used to determine whether the state belongs to class i or class j. Represents the prediction result of the new value, x new represents the input value, sign represents the sign function, represents the calculation result of the vector machine and the input value, Represents the weight value of historical results, k(x t , x new ) represents the calculation result between the input values;

[0021] For new data, use voting strategy for classification:

[0022] Each binary SVM analyzes the new data X according to its decision function new There is a prediction, taking the binary SVM between class i and class j as an example, if for X new The prediction is class i, and the accuracy is α; if X new The prediction is class j, and the accuracy is β; then X new The type probability is P(X new ):

[0023]

[0024] The category with the highest final probability is X new Prediction of; X new {Complete, incomplete, faulty}.

[0025] Preferably, in step (3), the factor parameters in the multi-factor strategy are as follows: the risk of operating personnel includes the professional ability of personnel, the basic ability score of personnel, the technical skills training and safety training score, the labor discipline score, the hidden danger score, and the accident score; the operation risk includes the quantified risk score of a certain type of operation in the underground pipeline and the corridor, the control measure score, the related information score, the importance score, and the scope of influence; the disaster weather risk is the impact of the current disaster weather on the operation task, and this factor is determined by the uniqueness of the specific disaster weather.

[0026] Preferably, in step (3), the above factors or their combination factors are screened by a multi-factor strategy to have a positive impact on the comprehensive operation risk assessment value, and the corresponding multi-factor data set C is used as the data input of the integration algorithm. The integration algorithm refers to the bagging integration algorithm of support vector machine and random forest, which is as follows:

[0027] Given a training set C of size n, the bagging ensemble algorithm uniformly and with replacement selects m subsets Ci of size n' as new training sets; using the regression algorithm on these m training sets, we can get x support vector machine models and y, y = mx random forest models, and then by taking the average value, we can get the bagging result:

[0028]

[0029] Among them, SVR1...SVR X Refers to multiple support vector machine regression models, RF1...RF Y Refers to multiple random forest models.

[0030] As a preference, in step (4), the underground pipeline and pipe gallery operation monitoring provides basic operation management tools for underground pipeline and pipe gallery operators, and provides common visual data charts for system users.

[0031] As a preferred embodiment, in step (4), the operation task dispatching and processing receipt actually apply the output results of the equipment multi-state detection and comprehensive operation task risk assessment algorithm model layer to ensure the normal and orderly operation of the system. The specific operation process is as follows:

[0032] (41) Work order initiation: The work order initiation is triggered when the current risk status of the equipment is abnormal, and then combined with the comprehensive operation risk assessment link to confirm the work order information and processing standard information;

[0033] (42) Internal and external repair order processing: on-site abnormality processing after the order is received by the person who receives the order;

[0034] (43) Processing completed: The order receiver fills in the work order information and submits the order settlement application;

[0035] (44) Acceptance stage: Acceptance is graded according to risk level. The more important the risk, the more senior the safety manager needs to sign off on the acceptance.

[0036] (45) Historical data records: All processes generate historical data, which will serve as the standard basis for future comprehensive operation risk assessments; namely, risk data input for equipment multi-state detection and comprehensive operation task risk assessment algorithm model layer;

[0037] (46) Complete the checkout.

[0038] Preferably, in step (4), the risk event impact simulation is used to simulate the impact and loss caused by the assumed risk on people's daily life, life and property, and the system user applies it to emergency drills for special risk failures.

[0039] The beneficial effects of the present invention are: through a multi-dimensional and quantitative assessment method of the operation and maintenance risk status of underground pipelines and pipe corridors, hidden dangers can be further dealt with before risk events occur, or after risk events occur (but not yet over) the impact and losses caused by the events to people's lives, lives, property and other aspects can be reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] Figure 1 It is a method design framework diagram of the present invention;

[0041] Figure 2 is a flow chart of the method of the present invention;

[0042] Figure 3 is a schematic diagram of the data acquisition layer of the present invention;

[0043] Figure 4 It is a schematic diagram of the device multivariate state algorithm model in the present invention;

[0044] Figure 5 It is a flow chart of the operation task dispatching and processing receipt in the present invention. DETAILED DESCRIPTION

[0045] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0046] like Figure 1 , Figure 2 In the embodiment described, a method for detecting multiple states of underground pipelines and pipe corridors specifically includes the following steps:

[0047] (1) Data collection layer: Real-time status data such as flow rate, pressure, water age, pipe network load, overflow, etc. are obtained through IoT sensing devices installed in underground pipelines and pipe corridors, and real-time risk data is also obtained;

[0048] like Figure 3 As shown, IoT sensing devices include liquid level transmitters, pressure transmitters, ultrasonic level meters, radar level meters, water quality sensors, abnormal movement switches, gas sensors, electromagnetic flow meters, etc.

[0049] The method for obtaining risk data is as follows: Through daily inspections of underground pipelines and pipeline corridors, and work order operation data, statistical data of various risk events and daily operation data are obtained.

[0050] (2) Algorithm model layer: Establish an equipment multivariate state algorithm model, and use the equipment multivariate data to judge the current equipment operation status. The algorithm outputs three qualitative results: intact, incomplete, and faulty (incomplete and faulty are both abnormal states). The algorithm mainly uses the multi-class SVM: LIBSVM algorithm model (the part involving quantitative indexes uses a normalized percentage system). The equipment multivariate state algorithm model is as follows:

[0051] Assume that the training set data D(x1,x2,...,x t ) has a total of t states, and a binary SVM is constructed between each two states using the LIBSVM method. Figure 4 Take (a) as an example, there are three types of (two-dimensional) data, the dotted line d 12 represents the decision boundary of binary SVM between class 1 and class 2 data, d 13 represents the decision boundary between class 1 and class 3, d 23 It represents the decision boundary between category 2 and category 3. For the i-th and j-th data, training a binary SVM is to solve the quadratic programming problem:

[0052]

[0053] The superscript t represents the parameter of the binary SVM between class i and class j; the subscript t represents the index of the sample in the union of class i and class j; φ represents the nonlinear mapping from input space to feature space; the training set data D(x1,x2,...,x t ) t The corresponding IoT sensing devices obtain real-time status data, such as flow rate, pressure, water age, pipe network load, overflow and other sensing data, as well as risk data such as return order disposal operations. w represents the weight, b represents the random number, ζ represents the relaxation coefficient, and st(w ij ) T φ(x t ) represents the calculation result after mapping the weight and input value, x t Represents the input value, y t represents the prediction result, ζ ij t It represents the relaxation coefficient of the formula for calculating the input value, T is the transposition symbol, and C is the penalty term of the relaxation system;

[0054] Index i, j∈{1,...,M}, i<j, a total of training is required binary SVMs, each class contains N / M samples on average, so each dual problem contains 2N / M variables on average;

[0055] The decision function of binary SVM between class i and class j is:

[0056]

[0057] The above formula is used to determine whether the state belongs to class i or class j. Represents the prediction result of the new value, x new represents the input value, sign represents the sign function, represents the calculation result of the vector machine and the input value, Represents the weight value of historical results, k(x t , x new ) represents the calculation result between the input values;

[0058] For new data, use voting strategy for classification:

[0059] Each binary SVM analyzes the new data X according to its decision function new There is a prediction (vote), taking the binary SVM between class i and class j as an example, if for X new The prediction is class i, and the accuracy is α; if X new The prediction is class j, and the accuracy is β; then X new The type probability is P(X new ):

[0060]

[0061] The category with the highest final probability is X new Prediction of X new {Complete, incomplete, faulty}.

[0062] (3) Algorithm model layer: Establish a comprehensive operation risk assessment algorithm model, and use a multi-factor strategy combined with an integrated algorithm to obtain a comprehensive operation risk assessment value;

[0063] The factor parameters used in the multi-factor strategy are as follows:

[0064] The risks to operating personnel include personnel professional capabilities, personnel basic ability scores, technical skills training and safety training scores, labor discipline scores, hidden danger scores, accident scores, etc.

[0065] Operational risks include the quantified risk score of a certain type of operation in underground pipelines and utility corridors, the control measures score, the related information score, the importance score, the scope of impact and other factors.

[0066] Disaster weather risk refers to the impact of the current disastrous weather on the operation task, and this factor is determined by the uniqueness of the specific disastrous weather.

[0067] The above factors or their combination factors are screened through multi-factor strategy to have a positive impact on the comprehensive operation risk assessment value, and the corresponding multi-factor data set C is used as the data input of the integration algorithm. The integration algorithm refers to the Bagging integration algorithm of Support Vector Machine (SVR) and Random Forest (RF), as follows:

[0068] Given a training set C of size n, the bagging ensemble algorithm selects m subsets Ci of size n' from it uniformly and with replacement (i.e. using the bootstrap sampling method) as new training sets; using the regression algorithm on these m training sets, we can get x support vector machine models and y, y = mx random forest models, and then by taking the average value, we can get the bagging result:

[0069]

[0070] Among them, SVR1...SVR X Refers to multiple support vector machine regression models, RF1...RF Y Refers to multiple random forest models.

[0071] (4) Application layer: Through comprehensive operational risk assessment values, it can monitor the operation of underground pipelines and pipe corridors, dispatch operational tasks and process receipts, as well as simulate the impact of risk events;

[0072] Underground pipeline and pipeline gallery operation monitoring provides basic operation and management tools for underground pipeline and pipeline gallery operators, and provides common visual data charts for system users.

[0073] The task dispatching and processing receipts put the output results of the equipment multi-state detection and comprehensive task risk assessment algorithm model layer into practical application to ensure the normal and orderly operation of the system, such as Figure 5 The specific operation process is as follows:

[0074] (41) Work order initiation: The work order initiation is triggered when the current risk status of the equipment is abnormal. Combined with the comprehensive operation risk assessment link, the work order information, processing standards and other information are confirmed;

[0075] (42) Internal and external repair order processing: on-site abnormality processing after the order is received by the person who receives the order;

[0076] (43) Processing completed: The order receiver fills in the work order information and submits the order settlement application;

[0077] (44) Acceptance stage: Acceptance is graded according to risk levels. The more important the risk, the more senior the safety manager needs to sign off on the acceptance.

[0078] (45) Historical data records: All processes generate historical data, which will serve as the standard basis for future comprehensive operation risk assessments; namely, risk data input for equipment multi-state detection and comprehensive operation task risk assessment algorithm model layer;

[0079] (46) Complete the checkout.

[0080] Risk event impact simulation is used to simulate the impact and losses caused by assumed risks on people's lives, lives, properties and other aspects. System users apply it to emergency drills for special risk failures.

[0081] This method uses a multi-dimensional and quantitative assessment method to assess the operation and maintenance risk status of underground pipelines and pipe corridors, and further deal with hidden dangers before risk events occur, or reduce the impact and losses caused by the events to people's lives, lives, property, etc. after the risk events occur (but not yet over).

Claims

1. A method for detecting multiple states of underground pipelines and pipe galleries, characterized in that: The specific steps include: (1) Data collection layer: Real-time status data and risk data are obtained through IoT sensing devices installed in underground pipelines and pipe corridors; (2) Algorithm model layer: Establish a multivariate state algorithm model for equipment, and use multivariate data of equipment to determine the current equipment operation status. The algorithm outputs three qualitative results: intact, incomplete, and faulty. The multivariate state algorithm model for equipment is as follows: Assume that the training set data D(x1,x2,...,x t ) There are t states in total. A binary SVM is constructed between each two states using the LIBSVM method. For the i-th and j-th data, training a binary SVM is to solve the quadratic programming problem: Where, the superscript ij represents the parameter of the binary SVM between class i and class j; the subscript t represents the index of the sample in the union of class i and class j; φ represents the nonlinear mapping from input space to feature space; the training set data D(x1,x2,...,x t ) t They correspond to the IoT sensing devices to obtain real-time status data and risk data, w represents the weight, b represents the random number, ζ represents the relaxation coefficient, st(w ij ) T φ(x t ) represents the calculation result after mapping the weight and input value, x t Represents the input value, y t represents the prediction result, ζ ij t It represents the relaxation coefficient of the formula for calculating the input value, T is the transposition symbol, and C is the penalty term of the relaxation system; Indices \(i, j\in\{1,\ldots,M\}\), \(i < j\), a total of binary SVMs need to be trained. Each class contains \(N / M\) samples on average. Therefore, each dual problem contains \(2N / M\) variables on average; The decision function of binary SVM between class i and class j is: The above formula is used to determine whether the state belongs to class i or class j. Represents the prediction result of the new value, x new represents the input value, sign represents the sign function, represents the calculation result of the vector machine and the input value, Represents the weight value of historical results, k(x t , x new ) represents the calculation result between the input values; For new data, use voting strategy for classification: Each binary SVM analyzes the new data X according to its decision function new There is a prediction, taking the binarySVM between class i and class j as an example, if for X new The prediction is class i, and the accuracy is α; if X new The prediction is class j, and the accuracy is β; then X new The type probability is P(X new ): The category with the highest final probability is X new Prediction of; X new {complete, incomplete, faulty}; (3) Algorithm model layer: Establish a comprehensive operation risk assessment algorithm model, and use a multi-factor strategy combined with an integrated algorithm to obtain a comprehensive operation risk assessment value; the factor parameters in the multi-factor strategy are as follows: the risk of operating personnel includes personnel professional ability, personnel basic ability score, technical skills training and safety training score, labor discipline score, hidden danger score, and accident score; the operation risk includes the quantified risk score of a certain type of operation in underground pipelines and pipe corridors, the control measures score, the related information score, the importance score, and the scope of influence; the disaster weather risk is the impact of the current disaster weather on the operation task, and this factor is determined by the uniqueness of the specific disaster weather; the above factors or their combined factors are screened through a multi-factor strategy to have a positive impact on the comprehensive operation risk assessment value, and the corresponding multi-factor data set C is used as the data input of the integrated algorithm. The integrated algorithm refers to the bagging integrated algorithm of support vector machine and random forest, as follows: Given a training set C of size n, the bagging ensemble algorithm uniformly and with replacement selects m subsets Ci of size n' as new training sets; using the regression algorithm on these m training sets, we can get x support vector machine models and y, y = mx random forest models, and then by taking the average value, we can get the bagging result: Among them, SVR1...SVR X Refers to multiple support vector machine regression models, RF1...RF Y refers to multiple random forest models; (4) Application layer: Through comprehensive operational risk assessment values, it can monitor the operation of underground pipelines and pipe corridors, dispatch operational tasks and process receipts, as well as simulate the impact of risk events.

2. A method for detecting multiple states of underground pipelines and pipe galleries according to claim 1, characterized in that: In step (1), the IoT sensing devices include liquid level transmitters, pressure transmitters, ultrasonic level meters, radar level meters, water quality sensors, abnormal movement switches, gas sensors, and electromagnetic flow meters; the risk data acquisition method is as follows: through daily inspections of underground pipelines and pipeline corridors, work order operation data is used to obtain statistical data on various risk events and daily operation data.

3. A method for detecting multiple states of underground pipelines and pipe galleries according to claim 1, characterized in that: In step (4), the underground pipeline and pipeline corridor operation monitoring provides basic operation management tools for the underground pipeline and pipeline corridor operation managers, and provides common visual data charts for system users.

4. A method for detecting multiple states of underground pipelines and pipe galleries according to claim 1, characterized in that: In step (4), the task dispatching and processing receipts actually apply the output results of the equipment multi-state detection and comprehensive task risk assessment algorithm model layer to ensure the normal and orderly operation of the system. The specific operation process is as follows: (41) Work order initiation: The work order initiation is triggered when the current risk status of the equipment is abnormal, and then combined with the comprehensive operation risk assessment link to confirm the work order information and processing standard information; (42) Internal and external repair order processing: on-site abnormality processing after the order is received by the person who receives the order; (43) Processing completed: The order receiver fills in the work order information and submits the order settlement application; (44) Acceptance stage: Acceptance is graded according to risk level. The more important the risk, the more senior the safety manager needs to sign off on the acceptance. (45) Historical data records: All processes generate historical data, which will serve as the standard basis for future comprehensive operation risk assessments; namely, risk data input for equipment multi-state detection and comprehensive operation task risk assessment algorithm model layer; (46) Complete the checkout.

5. The method for detecting multiple states of underground pipelines and pipe galleries according to claim 1 is characterized in that: In step (4), the risk event impact simulation is used to simulate the impact and loss caused by the assumed risk on people's lives, lives, and property. The system user applies it to emergency drills for special risk failures.