A deepwater cofferdam purlin and inner support assembly and lowering device and use method thereof

By assembling and lowering devices for cofferdams and internal supports, the construction sequence of deepwater cofferdams has been changed, and steel sheet piles have been inserted and driven first for cofferdams. This has solved the problems of steel sheet pile insertion accuracy and difficulty in closing, improved construction quality and efficiency, and improved the construction quality and efficiency of steel sheet piles. Welding and assembly are carried out on the water surface, which simplifies the construction process.

CN115125957BActive Publication Date: 2024-10-18CHINA CONSTR FIRST DIV GROUP CONSTR & DEV +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202210599928.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-30
Publication Date
2024-10-18
Estimated Expiration
2042-05-30

AI Technical Summary

Technical Problem

In the existing deepwater cofferdam construction method, the steel sheet pile insertion and driving accuracy is poor, and the installation sequence of the cofferdam and internal supports is limited, resulting in low construction efficiency, poor airtightness and difficulty in closing.

Method used

The purlin and inner support assembly and lowering device is used, including hoops, lower guide beams and assembly platforms, so that the purlin and inner support can be assembled on the water and lowered as a whole. This changes the traditional construction sequence so that the purlin is first driven with steel sheet piles, which solves the problem Steel sheet pile driving accuracy and closure issues, and welding and assembly on the water surface.

Benefits of technology

It improves the quality and efficiency of construction, solves the problems of poor insertion accuracy and difficulty in closing steel sheet piles, achieves efficient assembly and lowering of purlins and inner supports, simplifies the construction process, and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115125957B_ABST
    Figure CN115125957B_ABST
Patent Text Reader

Abstract

The present invention discloses a device for assembling and lowering a purlin and an inner support of a deepwater cofferdam and a method for using the device. The device comprises a hoop, a lower guide beam, and an assembly platform. The hoop comprises two symmetrical semicircular ring hoop plates, and the two sides of the hoop plates are bent outward to form mounting ears. The mounting ears on one side of the hoop are connected to the lower guide beam by high-strength bolts, and the mounting ears on the other side of the hoop are locked by high-strength bolts, which are used to lock the hoop on the casing connected to the height. The lower guide beam is vertically arranged, and the side of the lower guide beam facing away from the hoop is fixedly connected to the assembly platform. The present invention realizes a construction method of first assembling the purlin and the inner support, and then inserting and driving the steel sheet piles, which fundamentally solves the problem of low insertion and driving precision of the steel sheet piles and difficulty in closing the joints, improves the construction quality and efficiency, and has a simple structure, low cost, and is easy to use.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of deepwater cofferdam construction, and in particular to a deepwater cofferdam purlin and inner support assembly and lowering device and a use method thereof. Background Art

[0002] At present, most deep-water cofferdams are constructed by first driving steel sheet piles, then pumping water in layers, and then installing purlins and internal supports in layers. When installing purlins and internal supports, they must be installed in order from the upper layer to the lower layer. This construction method has the following defects: 1. It affects the driving and closure accuracy of steel sheet piles, resulting in poor airtightness of the cofferdam structure, and causes problems such as difficulty in closure or leakage of the cofferdam; 2. When installing purlins and internal supports, since they can only be installed layer by layer from top to bottom, when installing the lower internal supports and purlins, in order to allow the components to pass through the upper internal supports and be transported to the designated location, the purlins and internal support structures need to be divided into small units, and welding can only be completed in the internal area of ​​the cofferdam during construction, which is not conducive to welding quality control, low construction efficiency, and not conducive to construction period control.

[0003] In view of this, the present invention is proposed. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a deep-water cofferdam purlin and inner support assembly and lowering device, so that the purlin and inner support can be assembled on the water and then lowered as a whole, effectively improving the construction quality and efficiency, thereby overcoming the shortcomings of the prior art.

[0005] In order to solve the above technical problems, the present invention provides a deep-water cofferdam purlin and inner support assembly and lowering device, including a hoop, a lower guide beam, and an assembly platform. The hoop includes two symmetrical semicircular hoop plates, and the two sides of the hoop plates are bent outward to form mounting ears. The mounting ears on one side of the hoop are connected to the lower guide beam by high-strength bolts, and the mounting ears on the other side of the hoop are locked by high-strength bolts, which are used to lock the hoop on the heightened casing. The lower guide beam is vertically arranged, and the side of the lower guide beam facing away from the hoop is fixedly connected to the assembly platform.

[0006] As an improvement of the present invention, the assembling platform is located below the hoop.

[0007] Furthermore, a stopper is fixedly connected to the side of the lower guide beam, the stopper and the clamp are located on the same side, and the stopper is located between the lower guide beam and the casing to maintain the distance between the lower guide beam and the casing to ensure that the lower guide beam is vertical when moving downward.

[0008] Furthermore, several lower guide beams can be vertically connected into one by connecting steel plates.

[0009] Furthermore, a wedge-shaped limiting block is installed between the clamping hoop at the lowered position and the casing.

[0010] In addition, the present invention also provides a device for splicing and lowering the purlins and internal supports of a deep-water cofferdam, so that it can realize a construction method in which the purlins and internal supports are assembled first and then the steel sheet piles are driven in, thereby solving the problem of poor driving accuracy of the steel sheet piles and difficulty in closing the joints, thereby overcoming the shortcomings of the prior art.

[0011] In order to solve the above technical problems, the present invention provides a method for using a deepwater cofferdam purlin and inner support splicing and lowering device, which uses the above-mentioned deepwater cofferdam fence and inner support assembling and lowering device to assemble and lower the cofferdam and the inner support, and the specific steps include:

[0012] S1. Raise the casing of bored piles to serve as a support platform;

[0013] S2. Make the hoop on site according to the diameter of the casing, determine the height of the lower guide beam according to the installation spacing of the purlin, process the lower guide beam on site, and install the assembly platform and block, and assemble multiple devices for standby use;

[0014] S3. Determine the installation height according to the design spacing of the cofferdam purlin and the inner support, measure the elevation of the casing with a level, and install the wedge-shaped limit block;

[0015] S4. Lower the device so that the clamp is in close contact with the upper part of the wedge-shaped limit block, lock the clamp, and install the casings one by one in sequence;

[0016] S5. The processed purlins and inner supports are hoisted on the assembly platform by crane, and the first layer of purlins and inner supports are assembled by manual welding;

[0017] S6. Vertically connect another device to the device previously installed on the casing through the connecting steel plate, and properly tighten the high-strength bolts of the second clamp;

[0018] S7. Loosen the high-strength bolts of the first section of the clamp, and hoist the second-layer purlin and the inner support onto the assembly platform of the second section of the device by a crane to complete the assembly of the second-layer purlin and the inner support;

[0019] S8. Drop the second clamp to the wedge-shaped limit block and tighten the high-strength bolts of the second clamp;

[0020] S9. According to steps S6-S8, the assembly and lowering of the third layer of purlins and inner supports are completed.

[0021] After adopting such a design, the present invention has at least the following advantages:

[0022] 1. The traditional deep-water cofferdam construction sequence is to first drive the steel sheet piles, and then assemble the purlins and the inner supports. The purlins and the inner supports assembly and lowering device and the use method provided by the present invention can realize the assembly of the purlins and the inner supports first, and then drive the steel sheet piles. When driving the steel sheet piles, the purlins can be used as a guide, and the steel sheet piles can be easily closed by driving them close to the purlins, which fundamentally solves the problem of difficult closure or water leakage of steel sheet piles in the traditional construction sequence.

[0023] 2. The cofferdam and the inner support are welded and assembled on the assembly platform located above the water, which effectively improves the construction quality. The assembly and lowering order of the cofferdam and the inner support is from the lower layer to the upper layer, which makes the construction more convenient. In addition, there is no need to decompose the inner support into small units. The inner support can be highly prefabricated on site, which reduces the amount of welding on site and improves the construction efficiency.

[0024] 3. The deepwater cofferdam purlin and inner support assembly and lowering device provided by the present invention has a simple structure, low cost, and is easy to use. It can be manufactured on site, and only two crawler cranes are needed to complete the overall lowering of the purlin and inner support. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] The above is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0026] Figure 1 The invention provides a schematic diagram of the top view of the structure of a deepwater cofferdam purlin and inner support assembly and lowering device.

[0027] Figure 2 The present invention is a schematic diagram of the main structure of a deepwater cofferdam purlin and inner support assembly and lowering device provided by the present invention.

[0028] Figure 3 The invention discloses an overall arrangement diagram of a deepwater cofferdam purlin and inner support assembly and lowering device for construction.

[0029] Figure 4 It is a schematic diagram of the installation of the first section of the deepwater cofferdam purlin and internal support assembly and lowering device.

[0030] Figure 5 This is a schematic diagram of the assembly of the first-layer purlins and internal supports.

[0031] Figure 6 It is a schematic diagram of the installation of the second section of the deepwater cofferdam purlin and internal support assembly and lowering device.

[0032] Figure 7 This is a schematic diagram of the assembly of the second-floor purlins and internal supports.

[0033] Figure 8It is a schematic diagram of the installation of the assembly and lowering device of the cofferdam purlin and inner support of the third section of deep-water cofferdam.

[0034] Fig. 9 This is a schematic diagram of the assembly of the third-floor purlin and internal support.

[0035] Explanation of the reference numerals: 1. Clamp; 2. Lower guide beam; 3. Assembly platform; 4. High-strength bolt; 5. Stop block; 6. Casing; 7. Wedge-shaped limit block; 8. Connecting steel plate; 9. Purlin; 10. Internal support. DETAILED DESCRIPTION

[0036] See also Figure 1 to Figure 2 The present invention provides a device for assembling and lowering a purlin and an inner support of a deepwater cofferdam, comprising a hoop 1, a lower guide beam 2, an assembly platform 3 and a stopper 5. The hoop 1 comprises two symmetrical semicircular ring-shaped hoop plates, and the two sides of the hoop plates are bent outward to form mounting ears. One side mounting ear is connected to the lower guide beam 2 by a high-strength bolt 4. The lower guide beam 2 is vertically arranged to support the hoop 1 and the assembly platform 3. The assembly platform 3 is fixedly connected to the lower guide beam 2 and is located below the side facing away from the hoop 1. The hoop 1 is used to be installed on the casing 6 connected to the height and is locked by the high-strength bolt 4. The stopper 5 is fixedly connected to the side of the lower guide beam 2, on the same side as the hoop 1 and located at the lowering of the hoop 1. The stopper 5 is blocked between the lower guide beam 2 and the casing 6 to maintain the distance between the lower guide beam 2 and the casing 6 to ensure that the lower guide beam 2 is vertical when moving downward.

[0037] It should be noted that, when in use, multiple devices need to be connected together according to the number of layers of the surrounding purlin 9 and the inner support 10. When connected, multiple devices are connected together by installing a connecting steel plate 8 between several lower guide beams 2. In the lowered position, the position of the clamp 1 is pre-positioned by setting a wedge-shaped limit block 7 on the casing 6, and the clamp 1 is locked against the upper part of the wedge-shaped limit block 7.

[0038] See also Figures 3 to 9 The present invention also provides a method for using a device for assembling and lowering a deepwater cofferdam purlin and inner support. In this embodiment, the number of layers of the purlin 9 and the inner support 10 is three, that is, three sections of the device provided by the present invention need to be connected together for use, and the purlin 9 and the inner support 10 are assembled layer by layer from bottom to top. The specific steps of use are as follows:

[0039] S1, raise the casing 6 of the bored pile to serve as a support platform;

[0040] S2, make the hoop 1 on site according to the diameter of the casing 6, determine the height of the lower guide beam 2 according to the installation spacing of the surrounding purlin, process the lower guide beam on site, and install the assembly platform 3 and the stopper 5, and assemble multiple devices for standby use;

[0041] S3. Determine the installation height according to the design spacing between the purlin 9 and the inner support 10, measure the elevation of the casing 6 using a level, and install the wedge-shaped limit block 7;

[0042] S4, lower the device so that the clamp 1 is in close contact with the upper part of the wedge-shaped limit block 7, lock the clamp 1, and install the casings 6 one by one in sequence;

[0043] S5, hoisting the processed purlins 9 and inner supports 10 on the assembly platform 3 by crane, and completing the assembly of the first layer of purlins 9 and inner supports 10 by manual welding;

[0044] S6. Vertically connect another device to the device previously installed on the casing 6 through the connecting steel plate 8, and properly tighten the high-strength bolts 4 of the second section of the clamp 1;

[0045] S7, loosen the high-strength bolts 4 of the first section of the hoop 1, and hoist the second-layer purlin 9 and the inner support 10 onto the assembly platform 3 of the second section of the device by a crane, completing the assembly of the second-layer purlin 9 and the inner support 10;

[0046] S8, drop the second section of the clamp 1 to the wedge-shaped limit block 7, and tighten the high-strength bolt 4 of the second section of the clamp 1;

[0047] S9. According to steps S6-S8, the assembly and lowering of the third layer of purlins 9 and inner supports 10 are completed.

[0048] The invention provides a deepwater cofferdam purlin and inner support assembly and lowering device and a use method thereof, which changes the construction sequence of the traditional deepwater cofferdam. The device provided by the invention can first complete the assembly of the purlin and the inner support and then drive the steel sheet piles, which fundamentally solves the problem of low driving accuracy of the steel sheet piles and difficulty in closing the joints, thereby improving the construction quality and efficiency.

[0049] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Those skilled in the art may make some simple modifications, equivalent changes or modifications using the technical contents disclosed above, which all fall within the protection scope of the present invention.

Claims

1. A method for using a deepwater cofferdam purlin and inner support assembly and lowering device, characterized in that: A deep-water cofferdam fence and inner support assembly and lowering device is used to assemble and lower the cofferdam and inner support; The deepwater cofferdam purlin and inner support assembly and lowering device comprises a hoop, a lower guide beam, and an assembly platform, wherein the hoop comprises two symmetrical semicircular ring hoop plates, and both sides of the hoop plates are bent outward to form mounting ears, and a mounting ear on one side of the hoop is connected to the lower guide beam by a high-strength bolt, and a mounting ear on the other side of the hoop is locked by a high-strength bolt, and is used to lock the hoop on the casing connected to the height, and the lower guide beam is vertically arranged, and a side of the lower guide beam facing away from the hoop is fixedly connected to the assembly platform; A stopper is fixedly connected to the side of the lower guide beam, the stopper and the clamp are located on the same side, and the stopper is blocked between the lower guide beam and the casing to maintain the distance between the lower guide beam and the casing to ensure that the lower guide beam is vertical when moving downward; Several lower guide beams can be vertically connected into one by connecting steel plates; The assembly platform is located below the hoop; The clamp is provided with a wedge-shaped limit block between the lowered position and the casing; The specific steps include: S1. Raise the casing of bored piles to serve as a support platform; S2. Make the hoop on site according to the diameter of the casing, determine the height of the lower guide beam according to the installation spacing of the purlin, process the lower guide beam on site, and install the assembly platform and block, and assemble multiple devices for standby use; S3. Determine the installation height according to the design spacing of the cofferdam purlin and the inner support, measure the elevation of the casing with a level, and install the wedge-shaped limit block; S4. Lower the device so that the clamp is in close contact with the upper part of the wedge-shaped limit block, lock the clamp, and install the casings one by one in sequence; S5. The processed purlins and inner supports are hoisted on the assembly platform by crane, and the first layer of purlins and inner supports are assembled by manual welding; S6. Vertically connect another device to the device previously installed on the casing through the connecting steel plate, and properly tighten the high-strength bolts of the second clamp; S7. Loosen the high-strength bolts of the first section of the clamp, and hoist the second-layer purlin and the inner support onto the assembly platform of the second section of the device by a crane to complete the assembly of the second-layer purlin and the inner support; S8. Drop the second clamp to the wedge-shaped limit block and tighten the high-strength bolts of the second clamp; S9. According to steps S6-S8, the assembly and lowering of the third layer of purlins and inner supports are completed.