Three-way temporary restraint construction method for tower area of steel-concrete composite beam
By using a three-way temporary restraint method in bridge construction, combined with reaction seats, temporary horizontal poles, vertical cushions and horizontal temporary restraints, the safety and stability problems of restraint structures in traditional construction are solved, and the problem of restraint structure in extreme weather is achieved. The high wind and torsion resistance reduces steel beam damage and maximizes the use of permanent structural space.
Patent Information
- Application Number
- CN202210962039.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-11
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2042-08-11
AI Technical Summary
In traditional bridge construction, the temporary restraint method of steel-concrete combined beams has problems such as welding damage, excessive stress and complicated installation. Especially in the longitudinal, transverse and vertical restraints in the tower area, it is difficult to ensure the safety and stability of the structure, especially In extremely bad weather.
A three-way temporary restraint construction method is adopted, including longitudinal restraint, vertical restraint and lateral restraint. Through the combined design of reaction seat, temporary horizontal rod, vertical copy pad and lateral temporary restraint, permanent dampers and grouting materials are used to fill the gaps. Ensure the safety and stability of the restraint structure and provide wind and torsion resistance in extreme weather conditions.
It effectively reduces the damage to steel beams, ensures the structural safety of the tower area and the wind resistance stability of bridge construction, avoids welding damage, maximizes the use of permanent structure installation space, and provides additional force support in extreme weather .
Smart Images

Figure CN115198667B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of bridge construction, in particular to a three-way temporary restraint construction method for a steel-concrete combined beam tower area. Background Art
[0002] The steel-concrete composite beam is a beam that connects the steel beam and the bridge deck with shear nails to form a whole so that the two can bear the force together, which can give full play to the tensile strength of steel and the compressive strength of concrete. The steel beam is composed of a steel main beam and a cross beam. The steel main beam adopts a double-sided box section, and the upper flange, web and lower flange form a closed box structure. Figure 1 .
[0003] In order to reduce the impact of the long length of the double cantilever construction of the steel-concrete composite beam and enhance the wind resistance and static stability of the entire bridge construction process, it is necessary to set up temporary constraints in the tower area, mainly including longitudinal temporary constraints, vertical temporary constraints and transverse temporary constraints.
[0004] The traditional vertical temporary restraint is to install a high-quality rolled threaded steel reaction device at the pedestal position of the vertical support in the tower area and fix it to the steel beam to limit the vertical displacement of the steel beam; the horizontal temporary restraint is to install a steel pipe at the web of the steel beam in the tower area and tighten it against the tower column wall to limit the horizontal displacement of the steel beam; the longitudinal temporary restraint is to set up crossed parallel steel cables to connect the pedestal and steel beam of the vertical support in the tower area to limit the longitudinal displacement of the steel beam.
[0005] When installing traditional vertical temporary restraints, it is necessary to weld the fine-rolled threaded steel reaction device to the bottom of the steel beam. Due to the large stress of the steel beam in the tower area, the welding process will cause the local cross-section of the steel beam to be weakened, resulting in excessive local stress in the steel beam; the horizontal temporary restraint uses steel pipes and the web of the steel beam to tighten. With the long cantilever construction of the steel-concrete composite beam, the force on the steel pipe gradually increases. The web of the steel beam tightened by the steel pipe is at risk of excessive stress and local instability; when constructing the longitudinal temporary restraint cross cable, it is necessary to pre-embed a channel on the vertical support pad stone in the tower area, which has a great impact on the arrangement of the pad stone steel bars, affecting the force on the vertical support pad stone in the tower area, and the installation is complicated, making it difficult to accurately position. Summary of the invention
[0006] The purpose of the invention is to provide a three-way temporary restraint construction method for a steel-concrete combined beam tower area.
[0007] The object of the present invention is achieved in that:
[0008] There are three types of formal constraints during the construction of steel-concrete composite beams. The specific structural forms are shown in Figure 1 and Figure 2 :
[0009] (1) Vertical restraint: Install the vertical support on the tower area vertical support pad and bolt it to the tower area steel main beam;
[0010] Installation time of vertical restraint: The vertical support is initially installed after the steel beam positioning in the tower area is completed. The bolts connecting the vertical support and the steel main beam are not installed yet. Before the steel beam is closed, the bolts connecting the vertical support and the steel main beam are tightened into place.
[0011] (2) Lateral restraint: A wind stopper is provided in the middle of the beam in the tower area, and the beam and wind stopper are connected and fixed by lateral supports;
[0012] Transverse restraint installation timing: After the steel beams in the tower area are positioned, the vertical supports are initially positioned, and then the transverse supports are installed in place;
[0013] (3) Longitudinal restraint: Use a permanent damper to connect with the permanent damper base embedded in the tower area vertical support pad stone and the permanent damper base at the bottom of the tower area steel main beam;
[0014] Timing of longitudinal restraint installation: After the steel beams are connected, install the permanent damper and bolt the permanent damper to the permanent damper base on the pedestal of the vertical support of the tower area and the permanent damper base on the steel main beam of the tower area.
[0015] Because the formal constraints of the steel-concrete composite beam are installed during the steel beam closure, in order to resist the influence of wind loads during the cantilever construction of the steel-concrete composite beam, temporary constraints need to be set in the tower area. In order to ensure that the vertical supports are not subject to force during construction and to ensure the structural safety of the vertical supports, vertical temporary constraints and longitudinal temporary constraints to limit the longitudinal displacement of the steel beam in the bridge direction need to be set in the tower area.
[0016] In order to further strengthen the control of extremely severe windy weather and give full play to the structural characteristics of the steel-concrete composite beam that "steel beam and bridge deck" are jointly subjected to force, temporary transverse constraints are set between the tower beams as insurance. The temporary transverse constraints need to ensure that they do not participate in the force during the long cantilever construction of the steel-concrete composite beam. However, in extremely severe weather, when the steel beam undergoes lateral torsion, the temporary transverse constraints are subjected to force together with the steel beam and bridge deck.
[0017] The three-way temporary restraint structure of the steel-concrete composite beam tower area of the present invention is specifically as follows:
[0018] 1. Longitudinal temporary restraint:
[0019] There are two types of longitudinal temporary restraints:
[0020] (1) Reaction seat:
[0021] It consists of an upper base of a reaction seat, a lower corbel of a reaction seat and a connecting plate. The upper base of the reaction seat is welded to the steel main beam at the steel beam manufacturing plant, and the lower corbel of the reaction seat is bolted to the upper base of the reaction seat by a connecting plate. A first gap is left between the reaction seat and the vertical support pad stone of the tower area and is filled with support grouting material.
[0022] (2) Temporary horizontal rod:
[0023] With the help of the installation position of the permanent damper, a temporary horizontal rod is set up and bolted to the permanent damper base of the pad stone and the permanent damper base of the steel main beam;
[0024] 2. Vertical temporary constraints:
[0025] The vertical temporary restraint adopts the double insurance of "vertical support" + "vertical pads on both sides of the vertical support"; that is, the vertical pads are installed in layers on both sides of the vertical support. When installing the vertical pads, the top is first closely attached to the bottom of the steel main beam, and the bottom gap is leveled by the support grouting material;
[0026] 3. Temporary horizontal restraint:
[0027] The transverse temporary restraint is designed as a double-layer structure, that is, the lower layer is a steel structure and the upper layer is a concrete structure. The steel panel of the lower steel structure of the transverse temporary restraint is pressed against the upper flange of the steel main beam, and a fourth gap is left between the stiffening plate distributed at the bottom of the steel panel of the lower steel structure of the transverse temporary restraint and the upper flange of the steel main beam. A third gap is left between the upper concrete of the transverse temporary restraint and the bridge deck and filled with a rubber pad for soft contact. A second gap is reserved between the main tower and the transverse temporary restraint and filled with bearing grouting material.
[0028] After the steel beams in the tower area were positioned, transverse supports were installed to limit the transverse torsion of the steel beams due to wind loads during the construction of long cantilevered steel beams. The temporary transverse restraints set up adopted the structural form of "the steel panel of the lower steel structure adjacent to the steel beam is tightened against the upper flange of the steel main beam, a gap is left between the stiffening plate and the upper flange of the steel main beam, a gap is left between the upper concrete structure and the bridge deck and filled with rubber pads for soft contact, and the steel structure adjacent to the main tower is consolidated with the main tower through the support grouting material". This ensures that the temporary transverse restraint does not participate in the load during the construction of the long cantilever of the steel-concrete composite beam. However, in extremely severe weather, when the steel beam undergoes transverse torsion, the temporary transverse restraint is subjected to load together with the steel beam and the bridge deck.
[0029] A three-way temporary restraint construction method for a steel-concrete composite beam tower area, the specific steps are as follows:
[0030] Step 1: Analyze the temporary restraint reaction force of the tower area and the extreme weather wind load during the long cantilever erection of the steel-concrete composite beam, and calculate the maximum reaction force of the temporary restraint of the tower area under the most unfavorable state;
[0031] Step 2: Considering the design concept of "permanent and temporary" temporary constraints in the tower area, a longitudinal temporary constraint is designed, that is, a temporary horizontal rod at the installation position of the permanent damper and a reaction seat consolidated with the vertical support pad stone of the tower area. The reaction seat is composed of an upper base of the reaction seat, a connecting plate and a lower corbel of the reaction seat; the vertical temporary constraint is a vertical pad, which is installed on both sides of the vertical support and participates in the force together with the vertical support;
[0032] Step 3: Considering the impact of extreme weather such as typhoon weather, further strengthen the wind resistance of the longitudinal temporary restraint, set up wind-resistant torsion devices, i.e. lateral temporary restraints, in the tower area as insurance to limit the lateral torsion of the steel beam under wind load;
[0033] Step 4: The upper base of the reaction seat, the lower bracket of the reaction seat, the connecting plate, the permanent damper base of the pad stone, the permanent damper base of the steel main beam and the temporary horizontal rod are processed in the steel beam manufacturing plant according to the requirements of the design drawings; the upper base of the reaction seat and the permanent damper base of the steel main beam are welded at the corresponding positions of the bottom of the steel main beam in the steel beam manufacturing plant;
[0034] Step 5: The steel beams in the tower area are positioned and installed according to the monitoring and design requirements. After acceptance, the vertical supports are initially positioned and installed, but the connecting bolts between the vertical supports and the steel main beams are not installed for the time being;
[0035] Step 6: Choose a time period with stable temperature at night to install temporary vertical restraints, namely vertical pads: first, mark the installation position of the vertical pads on the vertical support pads of the tower area, paying attention to the correspondence with the outer web of the steel main beam and the inner web of the steel main beam, and then install the vertical pads to the bottom of the steel main beam in layers according to the thickness of each layer of cm, and finally make the vertical pads fit tightly with the bottom of the steel main beam, and use the support grouting material to fill the gap between the bottom of the vertical pad and the vertical support pads of the tower area;
[0036] Step 7: Install the temporary horizontal rod for longitudinal temporary restraint. First, connect and fix one end of the temporary horizontal rod with the permanent damper base of the steel main beam and tighten the bolts. Then temporarily lock the other end of the temporary horizontal rod with the permanent damper base of the pad stone on the vertical support pad stone of the tower area. Insert the bolts into the installation holes without tightening them for the time being.
[0037] Step 8: Install the reaction seat with longitudinal temporary restraint: the lower bracket of the reaction seat and the upper base of the reaction seat are fixed by bolting through the connecting plate, and the connecting bolts are tightened according to the construction pre-tension;
[0038] Step 9: After completion, tighten the connecting bolts between the temporary horizontal rod and the permanent damper base of the pad stone. After the bolts are tightened, use the support grouting material to fill the gap between the lower corbel of the reaction seat and the vertical support pad stone of the tower area, that is, fill the first gap to prevent the reaction seat from shifting;
[0039] Step 10: Install the lateral support according to the designed position;
[0040] Step 11: During the night when the temperature is stable, measure the actual size of the installation position of the temporary transverse restraint on site, and focus on measuring the distance between the steel panel and stiffening plate of the lower steel structure of the temporary transverse restraint and the upper flange of the steel main beam, to ensure that after the installation of the temporary transverse restraint is completed, the steel panel of the lower steel structure of the temporary transverse restraint is tightly attached to the top of the upper flange of the steel main beam, and the stiffening plate distributed at the bottom of the steel panel and the upper flange of the steel main beam have a fourth gap;
[0041] Step 12: Cut the lower steel structure with temporary horizontal restraint in the factory, and weld the steel panel of the lower steel structure with temporary horizontal restraint, the stiffening plate and anchor steel bars at the bottom of the steel panel into a whole in the factory;
[0042] Step 13: First, install the lower steel structure of the transverse temporary restraint, ensure that the steel panel of the lower steel structure of the transverse temporary restraint is tightly pressed against the upper flange of the steel main beam, and leave a fourth gap between the stiffening plate distributed at the bottom of the steel panel and the upper flange of the steel main beam, then pour the upper concrete of the transverse temporary restraint during the night when the temperature is stable, and focus on vibrating and compacting the layout position of the anchor steel bars; before pouring the upper concrete of the transverse temporary restraint, use rubber pads to fill the third gap between the upper concrete of the transverse temporary restraint and the bridge deck to achieve "soft contact";
[0043] Step 14: Finally, install the grouting plugging plate at the bottom of the transverse temporary restraint, and use the support grouting material to fill the second gap between the main tower and the transverse temporary restraint. At this point, the three-way temporary restraint construction of the steel-concrete composite beam tower area is completed.
[0044] The vertical temporary restraint in step two adopts double insurance of "vertical support" and "vertical pads set on both sides of the vertical support".
[0045] The longitudinal temporary restraint in step 2 limits the "bidirectional" displacement of the steel beam, limiting the displacement of the main beam toward the side span and the displacement of the main beam toward the middle span, while also having the function of resisting the horizontal rotation caused by wind loads.
[0046] The temporary restraint of the tower area in step 2 takes into account the design concept of "combining permanent and temporary". The temporary horizontal rods of the longitudinal temporary restraints use the installation position of the permanent damper, and there is no need to add additional components to the steel beam.
[0047] The vertical pads on both sides of the vertical support in step 2 are installed in layers, and the vertical pads correspond to the inner web of the steel main beam and the outer web of the steel main beam.
[0048] In step 2, to ensure that the vertical pad is dense and stable, the vertical pad must first be brought into contact with the bottom of the steel main beam and tightened, and then grouting is performed at the bottom of the vertical pad to level it.
[0049] The reaction seat of the longitudinal temporary restraint in step 2 is composed of an upper base, a lower corbel, and a connecting plate. The upper base and the lower corbel are bolted together through a splicing plate to form a whole. The bolted structure can be quickly locked and is easy to disassemble and assemble.
[0050] The bolts connecting the vertical supports to the steel main beam in step five will not be installed for the time being to ensure that during the long cantilever construction of the steel-concrete composite beam, the main load-bearing component is the vertical pad in the tower area, and the vertical supports do not participate in the load, ensuring the safety of the vertical support structure in the tower area. If the vertical pad in the tower area fails, the vertical supports can serve as an insurance.
[0051] The order of installation of the three-way temporary restraints in the tower area in steps five to fourteen is to install the vertical temporary restraints first, then install the temporary horizontal bars of the longitudinal temporary restraints, fix the temporary horizontal bars at one end, and after the installation of the reaction seats of the longitudinal temporary restraints is completed and before the reaction seats are grouted, fix the other end of the temporary horizontal bars. During the night when the temperature is stable, grouting is performed to consolidate the gap between the reaction seats and the vertical support pad stones, and finally the lateral restraints of the tower area are constructed.
[0052] In step nine and fourteen, the gap between the lower corbel of the reaction seat and the vertical support pad stone of the tower area, i.e. the first gap, and the gap between the main tower and the temporary horizontal restraint, i.e. the second gap, need to be filled with support grouting material during the night when the temperature is stable.
[0053] In step 11, the temporary transverse restraint is designed as a double-layer structure, that is, the lower layer is a steel structure and the upper layer is a concrete structure; the temporary transverse restraint adopts the structural form of "the steel panel of the lower steel structure is pressed against the upper flange of the steel main beam, a gap is left between the stiffening plate and the upper flange of the steel main beam, a gap is left between the upper concrete structure and the bridge deck and filled with rubber pads for soft contact, and the steel structure adjacent to the main tower is consolidated with the main tower through the support grouting material" to ensure that the temporary transverse restraint does not participate in the load during the long cantilever construction of the steel-concrete composite beam, but in extremely severe weather, when the steel beam undergoes lateral torsion, the temporary transverse restraint is subjected to load together with the steel beam and the bridge deck.
[0054] In step 11, the temporary transverse restraint needs to be cut according to the actual size of the on-site installation location to ensure installation accuracy. The steel panel of the lower steel structure of the temporary transverse restraint is tightly pressed against the upper flange of the steel main beam, and a gap is left between the stiffening plate and the upper flange of the steel main beam. This allows the temporary transverse restraint to play a role in extremely severe weather. In non-extremely severe weather, the upper concrete structure and the bridge deck achieve "soft contact" through rubber pads and do not participate in the force.
[0055] The present invention has the following characteristics:
[0056] (1) In order to reduce the damage to the steel beam, the concept of "permanent and temporary combination" was considered when setting the longitudinal temporary restraint. With the help of the permanent damper installation position, reaction seats and temporary horizontal bars were set to resist the translation caused by the unbalanced cable force and the horizontal rotation caused by the wind load, and to limit the "two-way" displacement of the steel-concrete composite beam under the long cantilever construction state: the reaction seat limits the displacement of the steel-concrete composite beam toward the middle span during the long cantilever construction, and the temporary horizontal bar limits the displacement of the steel-concrete composite beam toward the side span during the long cantilever construction;
[0057] (2) The vertical temporary restraint adopts the double insurance of "vertical support" + "vertical pads on both sides of the support". The vertical pads correspond to the webs of the steel main beams. Their main function is to resist the influence of wind loads during the cantilever construction of the steel-concrete composite beam and to ensure that the vertical supports do not participate in the load during the long cantilever construction of the steel-concrete composite beam. The load is borne by the vertical pads, ensuring the safety of the vertical support structure in the tower area.
[0058] (3) The steel face plate of the steel structure is set up with temporary transverse restraints. The upper flange of the steel main beam is pressed against the steel face plate. However, a gap is left between the stiffening plate distributed below the steel face plate and the upper flange of the steel main beam, and a "soft contact" is achieved between the steel face plate and the bridge deck by filling with rubber skin. This ensures that the temporary transverse restraint does not participate in the load under normal conditions of long cantilever construction of the steel-concrete composite beam. It only plays a role in extreme weather when the steel beam undergoes transverse torsion, thereby limiting the transverse torsion of the steel beam.
[0059] On the basis of the above technical solution, compared with the prior art, the advantages of the present invention are:
[0060] 1. The present invention designs three-way temporary constraints: vertical constraints consisting of formal supports and vertical pads on both sides of the formal supports, longitudinal constraints consisting of temporary horizontal bars and reaction seats, and transverse constraints set between tower beams;
[0061] 2. The three-way constraint in the tower area is set to reduce the impact of the long length of the cantilever construction main beam of the steel-concrete composite beam, strengthen the wind resistance and static stability of the whole bridge construction process, and take into account the lateral torsion of the steel beam in extreme weather, so as to give full play to the joint force characteristics of the "steel beam and bridge deck" of the steel-concrete composite beam;
[0062] 3. The three-way temporary restraint in the present invention does not need to cause welding damage to the steel beam, and maximizes the use of the permanent structure installation space of the steel-concrete composite beam;
[0063] 4. Temporary transverse constraints are set between the tower beams, and gaps are reserved between the steel main beam and the concrete bridge deck. Under strong wind conditions, they participate in the load. This can ensure that the main beam does not participate in the load during the long cantilever construction, but when the steel beam undergoes transverse torsion, it will be subjected to the load together with the steel beam and the concrete bridge deck. BRIEF DESCRIPTION OF THE DRAWINGS
[0064] Figure 1 It is a schematic diagram of the formal constraints of the steel-concrete composite beam after the bridge is completed in the present invention (after the bridge is completed);
[0065] Figure 2 for Figure 1 A–A schematic diagram;
[0066] Figure 3 It is a schematic diagram of the installation of the vertical support after the steel beam of the tower area of the steel-concrete composite beam in the present invention is positioned (during the cantilever construction period);
[0067] Figure 4 for Figure 3 Schematic diagram of B–B direction;
[0068] Figure 5 It is a schematic diagram of the installation of vertical temporary restraint and longitudinal temporary restraint of the tower area of the steel-concrete composite beam in the present invention (during cantilever construction);
[0069] Figure 6 It is a schematic diagram of the temporary transverse restraint elevation of the tower area of the steel-concrete composite beam in the present invention (during cantilever construction);
[0070] Figure 7 It is the detailed elevation drawing of the temporary transverse restraint of the tower area of the steel-concrete composite beam in the present invention (during the cantilever construction period);
[0071] Figure 8 It is a schematic diagram of the horizontal temporary restraint plane of the tower area of the steel-concrete composite beam in the present invention (during cantilever construction);
[0072] Fig. 9 It is a detailed plan view of the temporary transverse restraint of the tower area of the steel-concrete composite beam in the present invention (during cantilever construction);
[0073] In the figure: 1-main tower, 2-bridge deck, 3-upper flange of steel main beam, 4-steel main beam, 5-outer web of steel main beam, 6-inner web of steel main beam, 7-bottom of steel main beam, 8-vertical support, 9-pedestal of vertical support in tower area, 10-cross beam, 11-transverse support, 12-pedestal of permanent damper, 13-permanent damper, 14-permanent damper of steel main beam, 15-upper base of reaction seat, 16-connecting plate, 17-corbel under reaction seat, 18-first gap, 19-vertical pad, 20-temporary horizontal rod, 21-transverse temporary restraint, 22-second gap, 23-upper concrete of transverse temporary restraint, 24-anchor steel bar, 25-third gap, 26-grouting plugging plate, 27-stiffening plate, 28-steel panel, 29-transverse wind stopper, 30-fourth gap. DETAILED DESCRIPTION
[0074] The present invention will be further described in detail below with reference to the accompanying drawings and in combination with embodiments.
[0075] A three-way temporary restraint construction method for a steel-concrete composite beam tower area, the specific steps are as follows:
[0076] Step 1: Analyze the temporary restraint reaction force of the tower area and the extreme weather wind load during the long cantilever erection of the steel-concrete composite beam, and calculate the maximum reaction force of the temporary restraint of the tower area under the most unfavorable state;
[0077] Step 2: Considering the design concept of "permanent and temporary" temporary constraints in the tower area, a longitudinal constraint is designed, that is, a temporary horizontal rod 20 at the installation position of the permanent damper 13 and a reaction seat consolidated with the tower area vertical support pad 9, the reaction seat is composed of a reaction seat upper base 15, a connecting plate 16 and a reaction seat lower corbel 17; the vertical temporary constraint is a vertical pad 19, which is installed on both sides of the vertical support 8 and participates in the force together with the vertical support 8;
[0078] Step 3: Considering the impact of extreme weather such as typhoons, the wind resistance of the longitudinal temporary restraint is further strengthened, and a wind-resistant torsion device, namely a lateral temporary restraint 21, is installed in the tower area as insurance to limit the lateral torsion of the steel beam under wind load;
[0079] Step 4: The upper base 15 of the reaction seat, the lower bracket 17 of the reaction seat, the connecting plate 16, the permanent damper base 12 of the pad stone, the permanent damper base 14 of the steel main beam and the temporary horizontal rod 20 are processed in the steel beam manufacturing plant according to the requirements of the design drawings; the upper base 15 of the reaction seat and the permanent damper base 14 of the steel main beam are welded at the corresponding positions of the bottom 7 of the steel main beam in the steel beam manufacturing plant;
[0080] Step 5: The steel beams in the tower area are positioned and installed according to the monitoring and design requirements. After acceptance, the vertical supports 8 are initially positioned and installed, and the connecting bolts between the vertical supports 8 and the steel main beam 4 are not installed for the time being;
[0081] Step 6: Select a time period when the temperature is stable at night to install the vertical temporary restraint, i.e., the vertical pad 19: First, mark the installation position of the vertical pad 19 on the vertical support pad 9 of the tower area, paying attention to the correspondence with the outer web 5 of the steel main beam and the inner web 6 of the steel main beam, and then install the vertical pad 19 to the bottom 7 of the steel main beam in layers with a thickness of 20 cm per layer, and finally make the vertical pad 19 close to the bottom 7 of the steel main beam, and use the support grouting material to fill the gap between the bottom of the vertical pad 19 and the vertical support pad 9 of the tower area;
[0082] Step 7: Install the temporary horizontal rod 20 for longitudinal temporary restraint. One end of the temporary horizontal rod 20 is first connected and fixed to the permanent damper base 14 of the steel main beam and the bolts are tightened. Then the other end of the temporary horizontal rod 20 is temporarily locked to the pad stone permanent damper base 12 on the tower area vertical support pad stone 9. The bolts can be inserted into the installation holes without tightening them temporarily.
[0083] Step 8: Install the reaction seat of longitudinal temporary restraint: the lower bracket 17 of the reaction seat and the upper base 15 of the reaction seat are bolted and fixed through the connecting plate 16, and the connecting bolts are tightened according to the construction pre-tension;
[0084] Step 9: After completion, tighten the connecting bolts between the temporary horizontal rod 20 and the permanent damper base 12 of the pad stone. After the bolts are tightened, use the support grouting material to fill the gap between the lower corbel 17 of the reaction seat and the vertical support pad stone 9 of the tower area, that is, fill the first gap 18 to prevent the reaction seat from shifting;
[0085] Step 10: Install the lateral support according to the designed position;
[0086] Step 11: During the night time when the temperature is stable, measure the actual size of the installation position of the temporary transverse restraint 21 on site, and focus on measuring the distance between the steel panel 28 and the stiffening plate 27 of the lower steel structure of the temporary transverse restraint and the upper flange 3 of the steel main beam 4, to ensure that after the temporary transverse restraint 21 is installed, the steel panel 28 of the lower steel structure of the temporary transverse restraint is tightly attached to the top of the upper flange 3 of the steel main beam 4, and the stiffening plate 27 distributed at the bottom of the steel panel 28 and the upper flange 3 of the steel main beam 4 have a fourth gap 30;
[0087] Step 12: Cut the lower steel structure of the temporary horizontal restraint 21 in the factory, and weld the steel panel 28 of the lower steel structure of the temporary horizontal restraint, the stiffening plate 27 and the anchor steel bar 24 distributed at the bottom of the steel panel 28 into a whole in the factory;
[0088] Step 13: First, install the lower steel structure of the transverse temporary restraint 21, ensure that the steel panel 28 of the lower steel structure of the transverse temporary restraint is tightly pressed against the upper flange 3 of the steel main beam 4, and leave a fourth gap 30 between the stiffening plate 27 distributed at the bottom of the steel panel 28 and the upper flange 3 of the steel main beam 4, and then pour the upper concrete 23 of the transverse temporary restraint during the temperature stable period at night, and focus on vibrating and compacting the layout position of the anchor steel bar 24; before pouring the upper concrete 23 of the transverse temporary restraint, use a rubber pad to fill the third gap 25 between the upper concrete 23 of the transverse temporary restraint and the bridge deck to achieve "soft contact";
[0089] Step 14: Finally, install the grouting plugging plate 26 at the bottom of the transverse temporary restraint 21, and use the support grouting material to fill the second gap 22 between the main tower and the transverse temporary restraint. At this point, the three-way temporary restraint construction of the steel-concrete composite beam tower area is completed.
[0090] The present invention is not limited to the above-mentioned optimal implementation mode. Anyone should be aware that any structural changes made under the inspiration of the present invention, and any technical solutions that are the same or similar to the present invention, fall within the protection scope of the present invention.
Claims
1. A three-way temporary restraint construction method for the tower area of a steel-concrete composite beam, characterized in that: The specific steps are as follows: Step 1: Analyze the temporary restraint reaction force of the tower area and the extreme weather wind load during the long cantilever erection of the steel-concrete composite beam, and calculate the maximum reaction force of the temporary restraint of the tower area under the most unfavorable state; Step 2: Considering the design concept of "permanent and temporary" temporary constraints in the tower area, a longitudinal temporary constraint is designed, that is, a temporary horizontal rod at the installation position of the permanent damper and a reaction seat consolidated with the vertical support pad stone of the tower area. The reaction seat is composed of an upper base of the reaction seat, a connecting plate and a lower bracket of the reaction seat; the vertical temporary constraint is a vertical pad, which is installed on both sides of the vertical support and participates in the force together with the vertical support; Step 3: Considering the impact of extreme weather such as typhoon weather, further strengthen the wind resistance of the longitudinal temporary restraint, set up wind-resistant torsion devices, i.e. lateral temporary restraints, in the tower area as insurance to limit the lateral torsion of the steel beam under wind load; Step 4: The upper base of the reaction seat, the lower bracket of the reaction seat, the connecting plate, the permanent damper base of the pad stone, the permanent damper base of the steel main beam and the temporary horizontal rod are processed in the steel beam manufacturing plant according to the requirements of the design drawings; the upper base of the reaction seat and the permanent damper base of the steel main beam are welded at the corresponding positions of the bottom of the steel main beam in the steel beam manufacturing plant; Step 5: The steel beams in the tower area are positioned and installed according to the monitoring and design requirements. After acceptance, the vertical supports are initially positioned and installed, but the connecting bolts between the vertical supports and the steel main beams are not installed for the time being; Step 6: Choose a time period with stable temperature at night to install temporary vertical restraints, namely vertical pads: first, mark the installation position of the vertical pads on the vertical support pads of the tower area, paying attention to the correspondence with the outer web of the steel main beam and the inner web of the steel main beam, and then install the vertical pads to the bottom of the steel main beam in layers according to the thickness of each layer of cm, and finally make the vertical pads fit tightly with the bottom of the steel main beam, and use the support grouting material to fill the gap between the bottom of the vertical pad and the vertical support pads of the tower area; Step 7: Install the temporary horizontal rod for longitudinal temporary restraint. First, connect and fix one end of the temporary horizontal rod with the permanent damper base of the steel main beam and tighten the bolts. Then temporarily lock the other end of the temporary horizontal rod with the permanent damper base of the pad stone on the vertical support pad stone of the tower area. Insert the bolts into the installation holes without tightening them for the time being. Step 8: Install the reaction seat with longitudinal temporary restraint: the lower bracket of the reaction seat and the upper base of the reaction seat are fixed by bolting through the connecting plate, and the connecting bolts are tightened according to the construction pre-tension; Step 9: After completion, tighten the connecting bolts between the temporary horizontal rod and the permanent damper base of the pad stone. After the bolts are tightened, use the support grouting material to fill the gap between the lower corbel of the reaction seat and the vertical support pad stone of the tower area, that is, fill the first gap to prevent the reaction seat from shifting; Step 10: Install the lateral support according to the designed position; Step 11: During the night when the temperature is stable, measure the actual size of the installation position of the temporary transverse restraint on site, and focus on measuring the distance between the steel panel and stiffening plate of the lower steel structure of the temporary transverse restraint and the upper flange of the steel main beam, to ensure that after the installation of the temporary transverse restraint is completed, the steel panel of the lower steel structure of the temporary transverse restraint is tightly attached to the top of the upper flange of the steel main beam, and the stiffening plate distributed at the bottom of the steel panel and the upper flange of the steel main beam have a fourth gap; Step 12: Cut the lower steel structure with temporary horizontal restraint in the factory, and weld the steel panel of the lower steel structure with temporary horizontal restraint, the stiffening plate and anchor steel bars at the bottom of the steel panel into a whole in the factory; Step 13: First, install the lower steel structure of the transverse temporary restraint, ensure that the steel panel of the lower steel structure of the transverse temporary restraint is tightly pressed against the upper flange of the steel main beam, and leave a fourth gap between the stiffening plate distributed at the bottom of the steel panel and the upper flange of the steel main beam, then pour the upper concrete of the transverse temporary restraint during the night when the temperature is stable, and focus on vibrating and compacting the layout position of the anchor steel bars; before pouring the upper concrete of the transverse temporary restraint, use rubber pads to fill the third gap between the upper concrete of the transverse temporary restraint and the bridge deck to achieve "soft contact"; Step 14: Finally, install the grouting plugging plate at the bottom of the transverse temporary restraint, and use the support grouting material to fill the second gap between the main tower and the transverse temporary restraint. At this point, the three-way temporary restraint construction of the steel-concrete composite beam tower area is completed.
2. The three-way temporary restraint construction method for the tower area of the steel-concrete composite beam according to claim 1 is characterized in that: The vertical temporary restraint in step 2 adopts double insurance of "vertical support" and "vertical pads on both sides of the vertical support". The bolts connecting the vertical support to the steel main beam are not installed temporarily to ensure that during the long cantilever construction of the steel-concrete composite beam, the main load-bearing component is the vertical pad in the tower area, and the vertical support does not participate in the load, ensuring the safety of the vertical support structure in the tower area. If the vertical pad in the tower area fails, the vertical support can play an insurance role.
3. The three-way temporary restraint construction method for the tower area of the steel-concrete composite beam according to claim 1 is characterized in that: The longitudinal temporary restraint in step 2 limits the "bidirectional" displacement of the steel beam, which not only limits the displacement of the main beam toward the side span but also limits the displacement of the main beam toward the middle span. It also has the function of resisting the horizontal rotation caused by wind loads. The temporary restraint in the tower area takes into account the design concept of "combining permanent and temporary". The temporary horizontal rod of the longitudinal temporary restraint uses the installation position of the permanent damper, and there is no need to add additional components to the steel beam.
4. The three-way temporary restraint construction method for the tower area of the steel-concrete composite beam according to claim 1 is characterized in that: The vertical pads on both sides of the vertical support in step 2 are installed in layers, and the vertical pads correspond to the inner web and outer web of the steel main beam. To ensure that the vertical pads are dense and stable, the vertical pads must first be brought into contact with and tightened against the bottom of the steel main beam, and then grouting is performed at the bottom of the vertical pads for leveling.
5. The three-way temporary restraint construction method for the tower area of the steel-concrete composite beam according to claim 1 is characterized in that: The order of installation of the three-way temporary restraints in the tower area in steps five to fourteen is to install the vertical temporary restraints first, then install the temporary horizontal bars for the longitudinal temporary restraints, fix the temporary horizontal bars at one end, and fix the other end of the temporary horizontal bars after the installation of the longitudinal temporary restraint reaction seats is completed and before the reaction seats are grouted. During the night time when the temperature is stable, grouting is performed to consolidate the gap between the reaction seats and the vertical support pad stones, and finally the lateral restraints of the tower area are constructed.
6. The three-way temporary restraint construction method for the tower area of a steel-concrete composite beam according to claim 1 is characterized in that: The longitudinal temporary restraint reaction seat in step 2 is composed of an upper base, a lower corbel, and a connecting plate. The upper base and the lower corbel are bolted together through a splicing plate to form a whole. The bolted structure can be quickly locked and is easy to disassemble and assemble.
7. The three-way temporary restraint construction method for the tower area of a steel-concrete composite beam according to claim 1 is characterized in that: In step nine and fourteen, the gap between the corbel under the reaction seat and the vertical support pad stone of the tower area, i.e. the first gap, and the gap between the main tower and the temporary horizontal restraint, i.e. the second gap, both need to be filled with support grouting material during the night when the temperature is stable.
8. The three-way temporary restraint construction method for the tower area of a steel-concrete composite beam according to claim 1 is characterized in that: In step 11, the temporary transverse restraint is designed as a double-layer structure, that is, the lower layer is a steel structure and the upper layer is a concrete structure; the temporary transverse restraint adopts the structural form of "the steel panel of the lower steel structure is pressed tightly against the upper flange of the steel main beam, a gap is left between the stiffening plate and the upper flange of the steel main beam, a gap is left between the upper concrete structure and the bridge deck and filled with rubber pads for soft contact, and the steel structure on the side adjacent to the main tower is consolidated with the main tower through the support grouting material" to ensure that the temporary transverse restraint does not participate in the load during the long cantilever construction of the steel-concrete composite beam, but in extremely severe weather, when the steel beam undergoes lateral torsion, the temporary transverse restraint is subjected to load together with the steel beam and the bridge deck.
9. The three-way temporary restraint construction method for the tower area of a steel-concrete composite beam according to claim 1 is characterized in that: In step 11, the temporary transverse restraint needs to be cut according to the actual size of the on-site installation location to ensure installation accuracy. The steel panel of the lower steel structure of the temporary transverse restraint is tightly pressed against the upper flange of the steel main beam, and a gap is left between the stiffening plate and the upper flange of the steel main beam. This allows the temporary transverse restraint to play a role in extremely severe weather. In non-extremely severe weather, the upper concrete structure and the bridge deck achieve "soft contact" through rubber pads and do not participate in the force.