A method for pouring concrete for prestressed box beam
By checking the preparation and adjusting the vibration method during the concrete pouring of the precast box girder, combined with the cross-laying of the bilateral webs and longitudinal vibration, the problems of web water ripples and appearance caused by unscientific vibration time were solved, and a more uniform result was achieved. Concrete vibration and higher appearance quality.
Patent Information
- Application Number
- CN202210948176.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-09
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2042-08-09
AI Technical Summary
In the existing concrete pouring method for precast box beams, the vibration time is fixed and unscientific, which makes it difficult to cure the water ripples in the web and is prone to appearance problems such as sand lines and honeycomb voids caused by over-vibration or insufficient vibration.
Ensure the stable construction status of the concrete through inspection and preparation, add attached vibrators and plug-in vibrators, adjust the vibration time and method according to the slump of the concrete, use cross-distribution of double-sided webs and longitudinal vibration to avoid plug-in vibrators Problems of difficult insertion and insufficient vibration ensure that the concrete is vibrated evenly.
It effectively solves the problem of insufficient vibration and water ripple laitance layer or sand line caused by the high position of the corrugated pipe at the end, avoids appearance defects caused by over-vibration or insufficient vibration, and improves the appearance quality of the box girder.
Smart Images

Figure CN115256632B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of concrete pouring distribution, in particular to a method for pouring distribution of prestressed box girder concrete. Background Art
[0002] Yunnan is located in the advantageous position of the economic center of South Asia and Southeast Asia. Yunnan has entered the tide of highway construction. The proportion of newly built highway bridges and tunnels is very high. In addition, the bridges are all prefabricated beams and slabs except for the interchange area and special cross-line structures. The number of beams and slabs is quite large, and the C50 high-grade concrete used is also highly concerned. Therefore, appearance quality is the most basic indicator in the construction of quality engineering, but it also accounts for the largest proportion of assessment weight. At present, the common method of pouring and distributing concrete for prefabricated box girders on site is "longitudinal segmentation, horizontal layering", "first chamfering the bottom web, then the web, then the top web, and finally the top plate, from one end to the other". The webs on both sides of the distributing machine are symmetrically distributed, and continuous pouring is carried out symmetrically with the horizontal layering process. The thickness of the horizontal layer shall not exceed 30cm, and the inserted vibrating rod and high-frequency vibrator are used for vibration. Moreover, the vibration time is a fixed time set, and there is no scientific adjustment according to the state of the concrete. This traditional method of pouring and distributing causes the web water ripples to become a common and difficult-to-cured appearance problem of prefabricated box girders. In order to meet engineering needs and create quality projects, a scientific and reasonable material pouring method is particularly important;
[0003] After searching, Chinese patent number CN103643641A discloses a method for pouring the main beam of a prestressed continuous beam bridge. Although the invention can achieve uninterrupted pouring, avoid repeated dismantling and installation of conveying pipelines, improve construction quality, shorten operation time, and reduce engineering risks, it is easy to have the problem that the position of the bellows at the end is high, which makes it difficult to insert the inserted vibrating rod and the vibration is not sufficient. At the same time, there will be appearance problems such as water ripple slurry layer or sand line, and there are sand lines and honeycomb cavities caused by over-vibration or insufficient vibration. For this reason, we propose a method for pouring and distributing prestressed box girder concrete. Summary of the invention
[0004] The purpose of the present invention is to solve the defects in the prior art and to propose a method for pouring and distributing concrete for a prestressed box beam.
[0005] In order to achieve the above object, the present invention adopts the following technical solutions:
[0006] A method for pouring and distributing concrete for a prestressed box beam, the concrete pouring and distributing method has the following specific steps:
[0007] (1) Inspection and preparation before pouring beams and slabs;
[0008] (2) Install steel skeleton, corrugated pipe and formwork;
[0009] (3) Determine the concrete vibration method and time;
[0010] (4) Carry out concrete pouring and laying;
[0011] (5) Remove the mold and spray it for maintenance;
[0012] (6) Prestress, grout and anchor the concrete.
[0013] As a further solution of the present invention, the specific steps of the inspection preparation in step (1) are as follows:
[0014] Step 1: Construction personnel check and confirm the quantity of raw materials, equipment and tools of the mixing station, and equipment and tools used in the construction to ensure that the concrete pouring can be completed continuously and smoothly;
[0015] Step 2: Strictly measure the moisture content of coarse and fine aggregates, accurately measure the changes in moisture content of coarse and fine aggregates caused by weather changes, check the gradation of coarse aggregate particles and the fineness modulus of fine aggregates, and ensure the stability of concrete construction;
[0016] Step 3: Check the quantity, size and position of the mold, embedded parts, concrete pads and steel bars. After ensuring the quality is qualified, the technician fills out the pouring application form and sends it to the laboratory, which then issues a batching list to the mixing station;
[0017] Step 4: Make sure the contact surface between the formwork and the concrete has been polished clean, free of other debris, and evenly coated with release agent to ensure that there are no gaps in the formwork that could cause leakage.
[0018] As a further solution of the present invention, the concrete vibration method and time in step (3) are specifically determined as follows:
[0019] Step 1: Construction workers added attached vibrators to ensure that the attached vibrators were evenly distributed over the entire length of the webs on both sides, with an interval of about two meters. The vibrators were densely distributed at the position of the diaphragm. They were opened and pushed forward section by section as the pouring progressed to ensure sufficient vibration. After that, φ50 inserted vibrators were equipped and one vibrator was placed on each side of the two webs for simultaneous vibration.
[0020] The second step: through a large amount of early pouring data combined with the appearance quality analysis and improvement test of the box girder after demolding, summarize the vibration time of the attached vibrator corresponding to different slumps of concrete within a certain range of changes, and generate a matching table of different slumps and attached vibration times.
[0021] As a further solution of the present invention, the concrete pouring distribution steps in step (4) are as follows:
[0022] S1.1: Starting from the end, lay the material back and forth within 4-6m of the webs on both sides, and lay the material to the first negative bending moment tensioning position. Then pour the concrete to the lower layer of steel bars of the top plate at one time, that is, beyond the chamfer position of the web and wing plate. The first bucket material is laid on the left web first, and the second and third bucket materials are laid on the right web. The laying stops after the top plate position is reached;
[0023] S1.2: The fourth bucket is prepared to the first bucket position on the left web, and the first attached vibrator is turned on for 20 seconds. During this period, the concrete at the vibration-dropped position is filled up to the position of the lower steel bars on the top plate while vibrating. After it is filled, it is pushed forward obliquely within 2-3m. The fifth bucket is prepared to the second bucket and the third bucket on the right web. The attached vibration is turned on, and the concrete at the vibration-dropped position is filled up to the position of the lower steel bars on the top plate while vibrating. The sixth bucket is moved to the left web position and pushed forward crosswise in sequence for longitudinal pouring.
[0024] As a further solution of the present invention, the specific steps of longitudinal pouring described in S1.2 are as follows:
[0025] S2.1: Insert the double-sided inserted vibrating rods on the top of the beam to the position of the corrugated pipe for vibrating, but do not vibrate all the way to the corrugated pipe. Move the vibrating rod up and down continuously during vibration until the concrete no longer sinks significantly and the surface slurry is flat and there are no bubbles. Stop immediately;
[0026] S2.2: When the web concrete is 4-6m away from the other end, close it in the opposite direction in the same way. Stop vibrating after the web concrete has been vibrated to the state and position required by the construction workers. Finally, the top plate is cast longitudinally in one go.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] Compared with the traditional pouring and distributing methods, the present invention uses continuous testing by construction personnel to determine the concrete vibration method and time. Then the construction personnel start from the end and distribute the concrete back and forth within a range of 4-6m on both sides of the web, distribute the concrete to the first negative bending moment tensioning mouth position, and then pour the concrete to the lower layer of steel bars on the top plate at one time, that is, exceeding the chamfer position of the web and the wing plate. The first bucket of concrete is distributed on the left web first, and the second and third buckets of concrete are distributed on the right web. After distribution to the top plate position, distribution is stopped. The fourth bucket of concrete is prepared at the first bucket of concrete on the left web, and the first attached vibrator is turned on for 20s. During this period, the concrete at the vibration-dropped position is filled up while vibrating to the lower layer of steel bars on the top plate. After distribution, it is pushed forward obliquely within a range of 2-3m. The fifth bucket of concrete is prepared at the second and third buckets of concrete on the right web, and the attached vibration is turned on to fill the concrete at the vibration-dropped position while vibrating to the lower layer of steel bars on the top plate. The bucket is switched to the left web position and pushed forward crosswise in sequence. The top of the beam cooperates with the double-sided inserted vibrating rods, which are inserted into the corrugated pipe position for vibration, but do not keep vibrating on the corrugated pipe. During vibration, the vibrating rod is continuously moved up and down until the concrete no longer sinks obviously, the surface slurry is flat, and there are no bubbles. Stop immediately, and then close in the same reverse direction when it is 4-6m away from the other end. When the web concrete is vibrated to the state and position required by the construction personnel, stop vibrating. Finally, the top plate is cast in one longitudinal direction. By making the web concrete cloth as a whole when it is vibrated, the problem of insufficient insertion and vibration caused by the high position of the corrugated pipe at the end is solved. The concrete at the vibration position is supplemented while the attached vibration is turned on, and the vibration is pushed forward at the same time to avoid the appearance problems such as water ripple floating slurry layer or sand line. The attached vibration time is scientifically adjusted according to the changes in the slump of the concrete on site to avoid sand lines and honeycomb cavities caused by over-vibration or insufficient vibration. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0030] Figure 1 A flowchart of a method for pouring and placing concrete for a prestressed box girder proposed by the present invention;
[0031] Figure 2 A process flow chart of a method for pouring and distributing concrete for a prestressed box girder proposed by the present invention;
[0032] Figure 3 The present invention provides a schematic diagram of a method for pouring and distributing concrete for a prestressed box girder. DETAILED DESCRIPTION
[0033] Reference Figure 1-3 A method for pouring and distributing concrete for a prestressed box beam, the specific steps of the method are as follows:
[0034] Inspection and preparation shall be carried out before pouring beams and slabs;
[0035] Specifically, the construction personnel checked and confirmed the quantity of raw materials, equipment and machinery of the mixing station, and equipment and machinery used in the construction to ensure that the concrete pouring can be completed continuously and smoothly, and strictly measured the moisture content of coarse and fine aggregates, accurately measured the changes in the moisture content of coarse and fine aggregates caused by weather changes, checked the grading of coarse aggregate particles and the fineness modulus of fine aggregate to ensure the stability of the concrete construction state, and then checked the quantity, size and position of molds, embedded parts, concrete pads and steel bars. After ensuring the quality is qualified, the technicians filled out the pouring application form and sent it to the laboratory, which issued a batching list to the mixing station. After that, they ensured that the contact surface between the formwork and the concrete has been polished clean, free of other debris and evenly coated with release agent to ensure that there are no gaps in the formwork that may leak slurry.
[0036] Install steel skeleton, corrugated pipe and formwork, and determine the concrete vibration method and time;
[0037] Specifically, the construction workers installed additional attached vibrators to ensure that they were evenly distributed along the entire length of the webs on both sides, with an interval of about two meters. They were densely distributed at the position of the cross diaphragm, and were opened and pushed forward section by section as the pouring progressed to ensure sufficient vibration. Afterwards, φ50 inserted vibrators were installed and one on each side of the two webs was vibrated simultaneously. Through a large amount of early pouring data combined with the analysis and improvement experiments on the appearance quality of the box girder after demolding, the vibration time of the attached vibrators corresponding to different slumps of concrete within a certain range of variation was summarized, and a matching table of different slumps and attached vibration times was generated.
[0038] It should be further explained that the matching table of different slumps and vibration time is as follows:
[0039]
[0040]
[0041] The above table allows construction workers to flexibly respond to fluctuations in concrete slump during pouring and carry out vibration operations in a scientific and well-founded manner.
[0042] Carry out concrete pouring.
[0043] Specifically, Figure 2-3As shown, the construction workers start from the end and spread the material back and forth within 4-6m of the webs on both sides, and spread the material to the first negative bending moment tensioning position, and then pour the concrete to the lower layer of steel bars on the top plate at one time, that is, beyond the chamfer position of the web and wing plate. The first bucket material is placed on the left web, and the second and third bucket materials are placed on the right web. The placement is stopped after the placement reaches the top plate position to avoid the bottom 20-30cm of the web plate caused by vibration after each bucket is discharged in layers. The fourth bucket is prepared for the first bucket position on the left web, and the first attached vibrator is turned on for 20s. During this period, the concrete at the vibration-dropped position is filled up while vibrating to the lower steel bar position of the top plate. After it is filled, it is pushed forward obliquely within 2-3m. The fifth bucket is prepared for the second bucket and the third bucket on the right web, and the attached vibration is turned on. The concrete at the vibration-dropped position is filled up while vibrating to the lower steel bar position of the top plate. The sixth bucket is changed to the left web position and is pushed forward crosswise in sequence for longitudinal pouring. By making the web concrete distribution material as a whole when it is vibrated, the problem of the high position of the corrugated pipe at the end causing the inserted vibrator to be difficult to insert and vibrate sufficiently is solved. The concrete at the vibration-dropped position is filled up while the attached vibration is turned on and pushed forward at the same time to avoid the appearance problems such as water ripple slurry layer or sand line. The attached vibration time is scientifically adjusted according to the changes in the slump of the concrete on site to avoid sand lines and honeycomb cavities caused by over-vibration or insufficient vibration.
[0044] It needs to be further explained that the top of the beam is equipped with a double-sided inserted vibrating rod, which is inserted into the position of the corrugated pipe for vibration, but do not vibrate it all the way onto the corrugated pipe. During vibration, the vibrating rod should be continuously moved up and down until the concrete no longer sinks significantly, the surface slurry is flat, and there are no bubbles. Stop immediately. Then, when it is 4-6m away from the other end, close it in the same reverse direction in the same way to avoid lack of aggregate in the concrete at the other end, and ensure the uniformity of the overall aggregate grading of the box beam. Stop vibrating after the web concrete is vibrated to the state and position required by the construction personnel. Finally, the top plate is cast longitudinally in one go.
[0045] In addition, it needs to be further explained that when pouring the top slab, attention should be paid to the vibration of the concrete at the negative bending moment tensioning mouth of the top slab to ensure that the tensioning mouth groove template does not move and prevent the groove from floating up or concrete from being poured into the groove.
[0046] Remove the mold and spray cure; prestress, grout and anchor the concrete.
[0047] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for pouring concrete for a prestressed box girder, characterized in that: The specific steps of the pouring material method are as follows: (1) Inspection and preparation before pouring beams and slabs; (2) Install steel skeleton, corrugated pipe and formwork; (3) Determine the concrete vibration method and time; (4) Carry out concrete pouring and laying; (5) Remove the mold and spray it for maintenance; (6) Prestressing, grouting and anchoring of concrete; The concrete vibration method and time in step (3) are specifically determined as follows: Step 1: Construction workers added attached vibrators to ensure that the attached vibrators were evenly distributed over the entire length of the webs on both sides, with an interval of about two meters. The vibrators were densely distributed at the position of the diaphragm. They were opened and pushed forward section by section as the pouring progressed to ensure sufficient vibration. After that, φ50 inserted vibrators were equipped and one vibrator was placed on each side of the two webs for simultaneous vibration. Step 2: Based on a large amount of early pouring data and the appearance quality analysis and improvement test of the box girder after demolding, the vibration time of the attached vibrator corresponding to different slumps of concrete within a certain range of variation is summarized, and a matching table of different slumps and attached vibration time is generated; The specific steps of pouring concrete in step (4) are as follows: S1.1: Starting from the end, lay the material back and forth within 4-6m of the webs on both sides, and lay the material to the first negative bending moment tensioning position. Then pour the concrete to the lower layer of steel bars of the top plate at one time, that is, beyond the chamfer position of the web and wing plate. The first bucket material is laid on the left web first, and the second and third bucket materials are laid on the right web. The laying stops after the top plate position is reached; S1.2: The fourth bucket is prepared to the first bucket position on the left web. The attached vibrator is turned on for the first time for 20 seconds. During this period, the concrete at the vibration-dropped position is filled up to the position of the lower steel bars on the top plate while vibrating. After it is filled up, it is pushed forward obliquely within 2-3m. The fifth bucket is prepared to the second bucket and the third bucket on the right web. The attached vibrator is turned on. The concrete at the vibration-dropped position is filled up to the position of the lower steel bars on the top plate while vibrating. The sixth bucket is moved to the left web position and pushed forward crosswise in sequence for longitudinal pouring.
2. A method for pouring and placing concrete for a prestressed box beam according to claim 1, characterized in that: The specific steps of the inspection preparation described in step (1) are as follows: Step 1: Construction personnel check and confirm the quantity of raw materials, equipment and tools of the mixing station, and equipment and tools used in the construction to ensure that the concrete pouring can be completed continuously and smoothly; Step 2: Strictly measure the moisture content of coarse and fine aggregates, accurately measure the changes in moisture content of coarse and fine aggregates caused by weather changes, check the gradation of coarse aggregate particles and the fineness modulus of fine aggregates, and ensure the stability of concrete construction; Step 3: Check the quantity, size and position of the mold, embedded parts, concrete pads and steel bars. After ensuring the quality is qualified, the technician fills out the pouring application form and sends it to the laboratory, which then issues a batching list to the mixing station; Step 4: Make sure the contact surface between the formwork and the concrete has been polished clean, free of other debris, and evenly coated with release agent to ensure that there are no gaps in the formwork that could cause leakage.
3. A method for pouring and placing prestressed box girder concrete according to claim 1, characterized in that: The specific steps of longitudinal pouring described in S1.2 are as follows: S2.1: Insert the double-sided inserted vibrating rods on the top of the beam to the position of the corrugated pipe for vibrating, but do not vibrate all the way to the corrugated pipe. Move the vibrating rod up and down continuously during vibration until the concrete no longer sinks significantly and the surface slurry is flat and there are no bubbles. Stop immediately; S2.2: When the web concrete is 4-6m away from the other end, close it in the opposite direction in the same way. Stop vibrating after the web concrete has been vibrated to the state and position required by the construction workers. Finally, the top plate is cast longitudinally in one go.