A BIM-based longitudinal construction method, device and electronic equipment for rotating steel truss bridge
Through the longitudinal shift construction method of rotary steel truss bridge based on BIM, the bridge information is obtained in real time and its posture and position is adjusted, which solves the deviation and collision problems caused by uneven stress during construction, and improves the construction safety and accuracy .
Patent Information
- Application Number
- CN202210940217.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-05
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2042-08-05
AI Technical Summary
During the construction of bridge rotary bodies, deviations and collisions occur frequently during longitudinal construction due to uneven stress on the bridge body, which affects construction safety and efficiency.
Using the longitudinal construction method of rotary steel truss bridge based on BIM, the attitude and positioning information of the bridge to be moved is obtained in real time, and its balance state is judged, and the guidance instructions and prompt information are output according to the preset adjustment rules to adjust the bridge posture. and position to ensure movement within preset ranges and reduce collision risk.
It effectively reduces deviations and collisions caused by uneven stress during longitudinal construction, improves the safety and accuracy of construction, and ensures the accuracy of the balanced state and position of the bridge during construction.
Smart Images

Figure CN115262420B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of building construction, and in particular to a BIM-based longitudinal shift construction method, device and electronic equipment for a rotating steel truss bridge. Background Art
[0002] With the continuous development of science and technology, new technologies for bridge construction without scaffolding continue to emerge, and rotation construction is one of them, among which the horizontal rotation method is the most widely used.
[0003] Recently, more and more cross-rail and cross-highway bridges have begun to use the rotation construction method. In order to ensure the smooth progress of the rotation process and reduce the collision with other buildings or another construction part during the rotation process, it is usually adopted to pre-assemble at an offset distance, and then move longitudinally to the designed position after the rotation is completed to reduce the possibility of collision during the rotation process.
[0004] However, during the longitudinal movement construction process, the bridge body will shift due to uneven force, and collisions may also occur during the longitudinal movement. Summary of the invention
[0005] In order to reduce the longitudinal movement deviation and collision caused by uneven force during the longitudinal movement construction process, the present application provides a BIM-based longitudinal movement construction method, device and electronic equipment for a rotating steel truss bridge.
[0006] In the first aspect, the present application provides a BIM-based longitudinal shift construction method for a rotating steel truss bridge, which adopts the following technical solution:
[0007] A BIM-based longitudinal shift construction method for a rotating steel truss bridge, the method comprising:
[0008] Obtain the posture information and positioning information of the bridge to be moved in real time;
[0009] According to the posture information, determining whether the bridge body to be moved is currently in a balanced state;
[0010] If not, based on a preset first adjustment rule, output a first guidance instruction and a first prompt information according to the posture information;
[0011] Based on a preset second adjustment rule, a second guidance instruction and a second prompt information are output according to the positioning information.
[0012] By adopting the above technical scheme, the posture information and positioning information of the bridge body to be moved are obtained in real time, and it is determined whether the bridge body to be moved is in a balanced state through the posture information. When the bridge body to be moved is not in a balanced state, the first guidance instruction and the first prompt information are output according to the first adjustment rule and the posture information. The first prompt information is used to prompt the staff of the current state of the bridge body to be moved, and the first guidance instruction is used to guide the construction to adjust the state of the bridge body to be moved so that it reaches a balanced state. Then, according to the second adjustment rule, the second guidance instruction and the second prompt information are output in real time according to the positioning information. The second guidance instruction is used to instruct the bridge body to be moved to move within a preset range while reducing the possibility of collision. The second prompt information is used to prompt the staff when it exceeds the preset moving range or is about to collide. By adopting the above scheme, the longitudinal deviation caused by uneven force during the longitudinal construction process and the collision during the construction process can be reduced.
[0013] Optionally, the method for obtaining the posture information and positioning information of the bridge body to be moved in real time specifically includes:
[0014] A positioning module is provided at a preset position of the bridge body to be moved, and a posture detection module is provided at the balance point of the steel truss bridge, wherein the preset position is the connection point between the bridge body to be moved and the fixed bridge body;
[0015] Receive and store the positioning information uploaded by the positioning module and the posture information uploaded by the posture detection module;
[0016] The positioning information and the posture information are retrieved.
[0017] Optionally, the method further includes:
[0018] Acquire construction information and establish a BIM model of the steel truss bridge according to the construction information;
[0019] Carry out construction simulation through 3dsMax software according to the BIM model;
[0020] The preset position and balance point are determined according to the construction simulation process.
[0021] Optionally, the method for judging whether the bridge body to be moved is currently in a balanced state according to the posture information specifically includes:
[0022] The posture information includes the angle between the side of the bridge body to be moved facing the ground and the horizontal plane;
[0023] When the included angle is within a first threshold range, it is determined that the bridge body to be moved is currently in a balanced state;
[0024] When the angle exceeds a first threshold range, it is determined that the bridge body to be moved is not currently in a balanced state.
[0025] Optionally, the method of outputting a second guidance instruction and a second prompt information according to the positioning information based on a preset second adjustment rule specifically includes:
[0026] The second guidance instruction includes a first adjustment instruction and a second adjustment instruction, and the second prompt information includes a first alarm information and a second alarm information;
[0027] Obtain the preset moving range of the positioning module and the preset safety distance between any two positioning modules;
[0028] Determine whether the movement of the bridge body to be moved is within a preset movement range according to the positioning information;
[0029] If not, output a first adjustment instruction and a first alarm message according to the current positioning information and the preset moving range;
[0030] According to the positioning information and the preset safety distance between any two positioning modules, it is determined whether the movable bridge body collides with the fixed bridge body;
[0031] When a collision occurs, the location of the collision is determined based on the positioning information;
[0032] If the collision occurs at a connection point, an end signal is output;
[0033] If the collision location is not a connection point, a second adjustment instruction and a second alarm message are output according to the positioning information.
[0034] Optionally, the method further includes:
[0035] Acquire on-site coordinate elevation information and synchronize the elevation coordinate information to the BIM model;
[0036] According to the BIM model, positioning information and posture information, the construction process is simulated in real time, and a display signal is output.
[0037] By adopting the above technical solution, the on-site coordinate elevation information is obtained, and the coordinate elevation information is synchronized to the BIM model. According to the BIM model, positioning information and posture information, the construction process is simulated in real time, and the display signal is output in real time. After the external device receives the display signal, the construction process is displayed in real time, so that the staff can understand the construction status in time.
[0038] In the second aspect, the present application provides a BIM-based rotating steel truss bridge longitudinal shifting construction device, which adopts the following technical solution:
[0039] A BIM-based longitudinal shifting construction device for a rotating steel truss bridge, comprising:
[0040] An acquisition module is used to acquire the posture information and positioning information of the bridge body to be moved in real time;
[0041] A judgment module, used to judge whether the bridge body to be moved is currently in a balanced state according to the posture information;
[0042] A first instruction output module is used to output a first guidance instruction and a first prompt information according to the posture information based on a preset first adjustment rule if no;
[0043] The second instruction output module is used to output a second guidance instruction and a second prompt information according to the positioning information based on a preset second adjustment rule.
[0044] In a third aspect, the present application provides an electronic device, which adopts the following technical solution:
[0045] An electronic device includes a memory and a processor, wherein the memory stores a computer program of a BIM-based longitudinal shifting construction method for a rotating steel truss bridge that can be loaded and executed by the processor.
[0046] In a fourth aspect, the present application provides a computer-readable storage medium, which adopts the following technical solution:
[0047] A computer-readable storage medium stores a computer program of a BIM-based longitudinal shifting construction method for a rotating steel truss bridge that can be loaded and executed by a processor.
[0048] In summary, the present application includes at least one of the following beneficial technical effects:
[0049] By acquiring the posture information and positioning information of the bridge body to be moved in real time, it is determined whether the bridge body to be moved is in a balanced state through the posture information. When the bridge body to be moved is not in a balanced state, the first guidance instruction and the first prompt information are output according to the first adjustment rule and the posture information. The first prompt information is used to prompt the staff of the current state of the bridge body to be moved. The first guidance instruction is used to guide the construction to adjust the state of the bridge body to be moved so that it reaches a balanced state. Then, according to the second adjustment rule, the second guidance instruction and the second prompt information are output in real time according to the positioning information. The second guidance instruction is used to instruct the bridge body to be moved to move within a preset range while reducing the possibility of collision. The second prompt information is used to prompt the staff when it exceeds the preset moving range or is about to collide. The above scheme is adopted to reduce the longitudinal deviation caused by uneven force during the longitudinal construction process and the collision during the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] Figure 1 It is a flow chart of the longitudinal shift construction method of a rotating steel truss bridge based on BIM provided in this application.
[0051] Figure 2 It is a structural schematic diagram of the BIM-based longitudinal displacement construction device of the rotating steel truss bridge provided in this application.
[0052] Figure 3 It is a structural schematic diagram of the electronic device provided by this application.
[0053] Explanation of the accompanying drawings: 200, BIM-based rotating steel truss bridge longitudinal displacement construction device; 201, acquisition module; 202, judgment module; 203, first instruction output module; 204, second instruction output module; 301, CPU; 302, ROM; 303, RAM; 304, I / O interface; 305, input part; 306, output part; 307, storage part; 308, communication part; 309, drive; 310, removable medium. DETAILED DESCRIPTION
[0054] The following is combined with Figure 1-3 This application is described in further detail.
[0055] Rotation construction is a type of bridge construction without support. Bridge rotation construction refers to a construction method in which the bridge structure is cast or spliced at a non-design axis position and then rotated into place. It can transform operations above obstacles into operations on the shore or near the ground. In order to reduce the collision between bridge bodies during the rotation process, one side of the bridge body is assembled at a certain distance away from the assembly position. After the rotation is completed, the bridge body is moved to the designed position through the longitudinal movement system for closing construction.
[0056] The longitudinal shift construction is achieved by setting 4 jacks at the block below the steel truss bridge to realize the longitudinal shift construction of the bridge body. However, due to the different support forces provided by each jack during the construction process, the bridge body may tilt or collide. In order to reduce the above situation, the embodiment of this application discloses a BIM-based longitudinal shift construction method for a rotating steel truss bridge. Figure 1 , the BIM-based longitudinal shift construction method of the rotating steel truss bridge includes:
[0057] S101: Acquire the posture information and positioning information of the bridge body to be moved in real time.
[0058] Specifically, firstly, the construction information is obtained, and the construction information includes the structure and size of each part of the bridge body to be constructed. The construction information can be manually input by the staff. The bridge body includes a fixed bridge body and a bridge body to be moved. After the construction information of the bridge body is obtained, a BIM model of the bridge body to be constructed is constructed according to the construction information. After the BIM model is established, the longitudinal movement construction process of the bridge body is simulated through 3dsMax software. During the construction simulation process, the preset position and the balance point are determined. The preset position is the connection point during the longitudinal movement of the bridge body, and the balance point is the support point of the jack during the longitudinal movement of the bridge body. After the preset position and the balance point are determined, a positioning module is set at the preset position, and a posture detection module is set at the balance point. In this embodiment, there are multiple preset positions and balance points.
[0059] After the setting is completed, the positioning information of the bridge to be moved is detected in real time through the positioning module and uploaded, and the posture detection module is used to detect the posture of the bridge to be moved in real time and uploaded. The server receives and stores the positioning information and posture information, and automatically retrieves them when needed.
[0060] S102: Determine whether the bridge body to be moved is currently in a balanced state according to the posture information.
[0061] Specifically, in this embodiment, the posture detection module uses an inclination sensor. The inclination sensor of the balance point is used to detect in real time the angle between the side of the bridge body to be moved facing the ground and the horizontal plane. When the angle is within a first threshold range, it is judged that the bridge body to be moved is in a balanced state. When the angle exceeds the first threshold range, it is judged that the bridge body to be moved is in an unbalanced state. The first threshold range and the second threshold range are set by the staff according to their work experience and stored in the server.
[0062] S103: Based on a preset first adjustment rule and according to the posture information, output a first guidance instruction and a first prompt information.
[0063] Specifically, according to the posture information uploaded by each posture detection module, the inclination direction of the bridge body to be moved and the size of the angle between the side of the bridge body to be moved facing the ground and the horizontal plane are determined according to the posture information uploaded by each posture detection module, and then the preset adjustment table is queried, and the first guidance instruction is output to control the corresponding jack to rise or fall until the size of the angle between the side of the bridge body facing the ground and the horizontal plane is adjusted to within the first threshold range and the adjustment is stopped. The adjustment table includes the corresponding relationship between the inclination direction of the bridge body, the size of the angle between the side of the bridge body facing the ground and the horizontal plane, and the guidance instructions. The corresponding guidance instructions can be determined from the adjustment table; at the same time, the server will output the first prompt information according to the posture information, and transmit the first prompt information to the monitoring platform. The first prompt information includes the posture information output by each posture detection module. The staff can know the posture information output by each posture detection module in real time through the monitoring platform. The staff can also determine the inclination direction of the bridge body to be moved and the size of the angle between the side of the bridge body to be moved facing the ground and the horizontal plane based on the current posture information; therefore, the inclination direction of the bridge body to be moved and the angle between the side of the bridge body to be moved facing the ground and the horizontal plane can be determined by the server itself or can be determined by the staff and then manually input.
[0064] By adopting the above steps, when the angle is not within the first threshold range during the construction process, it means that the bridge body to be moved is not in a balanced state, and the degree of imbalance exceeds the acceptable range. Therefore, there is reason to believe that the construction process is in an unsafe state; at this time, the first prompt information is output to inform the staff of the situation in time; at the same time, the first guidance instruction is output to make adaptive adjustments to the construction process, so that the construction process can be restored to a safe state in time, thereby improving the safety of the staff during construction.
[0065] S104: Based on a preset second adjustment rule, output a second guidance instruction and a second prompt information according to the positioning information.
[0066] Specifically, the second guidance instruction includes a first adjustment instruction and a second adjustment instruction, and the second indication information includes a first alarm information and a second alarm information. In this embodiment, the connection point is the point where the part of the bridge body to be moved and the fixed bridge body overlap after they are completely spliced during the longitudinal movement construction process. Positioning modules are set at the connection points, and the same label information is set for the positioning modules set on the corresponding connection points on the bridge body to be moved and the fixed bridge body. The label information includes the installation position of the positioning module. After the positioning module is set, the preset moving range of each positioning module on the bridge body to be moved and the safety distance between any two positioning modules are set. The preset moving range and safety distance are determined by the staff based on actual experience and input into the server for storage. In this embodiment, the positioning module is a GPS locator.
[0067] After the preset moving range and safety distance are set, according to the positioning information uploaded by the positioning module in real time, the Beidou system is used to determine the moving direction of the corresponding behavior module set on the bridge body to be moved and the distance between the corresponding two positioning modules based on the positioning module set on the fixed bridge body. According to the positioning information uploaded by multiple positioning modules, the moving direction of the bridge body to be moved and the distance from the installation position can be determined. When the movement of a certain positioning module exceeds its corresponding preset moving range, the first adjustment instruction and the first alarm information are output according to the actual movement of the positioning module, and the jack action is controlled to return it to the preset moving range. At the same time, the monitoring platform receives the first alarm information and displays the positioning information output by the current positioning module to prompt the staff.
[0068] According to the positioning information output by the positioning module, the distance between any two positioning modules can be calculated. When the distance between the two positioning modules is less than the preset safety distance, it proves that a collision has occurred. After the collision occurs, the location of the collision is determined according to the label information of the positioning module. If the location of the collision is a connection point, it proves that the construction is completed and an end signal is output; if the location of the collision is not a connection point, the second adjustment instruction and the second alarm information are output according to the location of the collision and the positioning information output by each positioning module. The second adjustment instruction controls the jack action to adjust the position of the bridge body to be moved, so that the distance between any two positioning modules is within the safety distance range. The monitoring platform receives the second alarm prompt instruction and displays the positioning information output by each positioning module to prompt the staff.
[0069] In order to realize real-time supervision of the construction process, the coordinate elevation information of the construction site is obtained, and the elevation information is synchronized to the BIM model. According to the BIM model and the positioning information and posture information obtained in real time, the construction process is synchronized through the Revit software for refined modeling and synchronization, and then synchronized to the monitoring platform. The staff can understand the construction process in real time through the monitoring platform.
[0070] Furthermore, multiple guidance instructions may be pre-stored in the service. The guidance instructions allow staff to simulate the construction process in advance and specify adjustment plans for each possible situation during the construction process. Therefore, when a collision or tilt occurs during the construction process, the posture of the mobile bridge is determined based on the positioning information and posture information. The server automatically matches the corresponding guidance instructions or the staff calls up the corresponding guidance instructions to control the movement of the jack and make adjustments.
[0071] The present application also discloses a BIM-based longitudinal construction device for a rotating steel truss bridge. Figure 2 The BIM-based rotating steel truss bridge longitudinal shifting construction device 200 includes:
[0072] An acquisition module 201 is used to acquire the posture information and positioning information of the bridge body to be moved in real time;
[0073] A judgment module 202 is used to judge whether the bridge body to be moved is currently in a balanced state according to the posture information;
[0074] A first instruction output module 203 is used to output a first guidance instruction and a first prompt information according to the posture information based on a preset first adjustment rule if no;
[0075] The second instruction output module 204 is used to output a second guidance instruction and a second prompt information according to the positioning information based on a preset second adjustment rule.
[0076] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working process of the described module can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.
[0077] The application embodiment discloses an electronic device. Figure 3 The electronic device includes a central processing unit (CPU) 301, which can perform various appropriate actions and processes according to the program stored in the read-only memory (ROM) 302 or the program loaded from the storage part 307 to the random access memory (RAM) 303. In the RAM 303, various programs and data required for system operation are also stored. The CPU 301, the ROM 302 and the RAM 303 are connected to each other through a bus. The input / output (I / O) interface 304 is also connected to the bus.
[0078] The following components are connected to the I / O interface 304: an input section 305 including a keyboard, a mouse, etc.; an output section 306 including a cathode ray tube (CRT), a liquid crystal display (LCD), etc., and a speaker, etc.; a storage section 307 including a hard disk, etc.; and a communication section 308 including a network interface card such as a LAN card, a modem, etc. The communication section 308 performs communication processing via a network such as the Internet. A drive 309 is also connected to the I / O interface 304 as needed. A removable medium 310, such as a magnetic disk, an optical disk, a magneto-optical disk, a semiconductor memory, etc., is installed on the drive 309 as needed, so that a computer program read therefrom is installed into the storage section 307 as needed.
[0079] In particular, according to an embodiment of the present application, the above reference flow chart Figure 1The described process can be implemented as a computer software program. For example, an embodiment of the present application includes a computer program product, which includes a computer program carried on a machine-readable medium, and the computer program contains program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed from a network through a communication part 308, and / or installed from a removable medium 310. When the computer program is executed by a central processing unit (CPU) 301, the above-mentioned functions defined in the device of the present application are executed.
[0080] It should be noted that the computer-readable medium shown in the present application may be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present application, a computer-readable storage medium may be any tangible medium containing or storing a program that can be used by or in combination with an instruction execution system, device or device. In the present application, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, which carries a computer-readable program code. This propagated data signal may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer-readable signal media may also be any computer-readable medium other than computer-readable storage media, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. The program code contained on the computer-readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wire, optical cable, RF, etc., or any suitable combination of the above.
[0081] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present application. In this regard, each box in the flow chart or block diagram can represent a module, a program segment or a part of the code, and the aforementioned module, program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from the order marked in the accompanying drawings. For example, two boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each box in the block diagram and / or flow chart, and the combination of the boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs the specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.
[0082] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of application involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the aforementioned application concept. For example, the above features are replaced with (but not limited to) technical features with similar functions applied in the present application.
Claims
1. A BIM-based longitudinal shift construction method for a rotating steel truss bridge, characterized in that: The method includes: A positioning module is provided at a preset position of the bridge body to be moved, and a posture detection module is provided at the balance point of the steel truss bridge, wherein the preset position is the connection point between the bridge body to be moved and the fixed bridge body; Receive and store the positioning information uploaded by the positioning module and the posture information uploaded by the posture detection module; Retrieving the positioning information and the posture information; Acquire construction information and establish a BIM model of the steel truss bridge according to the construction information; Carry out construction simulation through 3dsMax software according to the BIM model; Determine the preset position and balance point according to the construction simulation process; The posture information includes the angle between the side of the bridge body to be moved facing the ground and the horizontal plane; When the included angle is within a first threshold range, it is determined that the bridge body to be moved is currently in a balanced state; When the angle exceeds a first threshold range, it is determined that the bridge body to be moved is not currently in a balanced state; If not, based on a preset first adjustment rule, output a first guidance instruction and a first prompt information according to the posture information; Based on a preset second adjustment rule, outputting a second guidance instruction and a second prompt information according to the positioning information; The second guidance instruction includes a first adjustment instruction and a second adjustment instruction, and the second prompt information includes a first alarm information and a second alarm information; Obtain the preset moving range of the positioning module and the preset safety distance between any two positioning modules. The connection point is the point where the part of the bridge body to be moved and the fixed bridge body overlap after they are completely spliced during the longitudinal movement construction process. Positioning modules are set at the connection points, and the same label information is set for the positioning modules set at the corresponding connection points on the bridge body to be moved and the fixed bridge body. The label information includes the installation position of the positioning module. After the positioning module is set, the preset moving range of each positioning module on the bridge body to be moved and the safety distance between any two positioning modules are set; Determine whether the movement of the bridge body to be moved is within a preset movement range according to the positioning information; If not, after the preset moving range and safety distance are set, according to the positioning information uploaded by the positioning module in real time, the Beidou system is used to determine the moving direction of the corresponding behavior module set on the bridge body to be moved and the distance between the corresponding two positioning modules based on the positioning module set on the fixed bridge body. The moving direction of the bridge body to be moved and the distance from the to-be-installed position are determined according to the positioning information uploaded by multiple positioning modules. When the movement of a certain positioning module exceeds its corresponding preset moving range, the first adjustment instruction and the first alarm information are output according to the actual movement of the positioning module; According to the positioning information output by the positioning module, the distance between any two positioning modules can be calculated. When the distance between the two positioning modules is less than the preset safety distance, it proves that a collision has occurred; When a collision occurs, the location of the collision is determined based on the tag information of the positioning module. If the location of the collision is a connected point, it proves that the construction is completed and an end signal is output; If the collision location is not a connection point, a second adjustment instruction and a second alarm message are outputted according to the collision location and the positioning information outputted by each positioning module.
2. The BIM-based longitudinal shift construction method for a rotating steel truss bridge according to claim 1 is characterized in that: The method further includes: Acquire on-site coordinate elevation information and synchronize the coordinate elevation information into the BIM model; According to the BIM model, positioning information and posture information, the construction process is simulated in real time, and a display signal is output.
3. A BIM-based longitudinal shifting construction device for a rotating steel truss bridge, characterized in that: include: An acquisition module (201) is used to set a positioning module at a preset position of the bridge body to be moved, and to set a posture detection module at a balance point of the steel truss bridge, wherein the preset position is a connection point between the bridge body to be moved and the fixed bridge body; Receive and store the positioning information uploaded by the positioning module and the posture information uploaded by the posture detection module; Retrieving the positioning information and the posture information; A judgment module (202), configured to obtain construction information and establish a BIM model of the steel truss bridge according to the construction information; Carry out construction simulation through 3dsMax software according to the BIM model; Determine the preset position and balance point according to the construction simulation process; The posture information includes the angle between the side of the bridge body to be moved facing the ground and the horizontal plane; When the included angle is within a first threshold range, it is determined that the bridge body to be moved is currently in a balanced state; When the angle exceeds a first threshold range, it is determined that the bridge body to be moved is not currently in a balanced state; A first instruction output module (203) is used to output a first guidance instruction and a first prompt information according to the posture information based on a preset first adjustment rule if no; A second instruction output module (204), configured to output a second guidance instruction and a second prompt information according to the positioning information based on a preset second adjustment rule; The second guidance instruction includes a first adjustment instruction and a second adjustment instruction, and the second prompt information includes a first alarm information and a second alarm information; Obtain the preset moving range of the positioning module and the preset safety distance between any two positioning modules. The connection point is the point where the part of the bridge body to be moved and the fixed bridge body overlap after they are completely spliced during the longitudinal movement construction process. Positioning modules are set at the connection points, and the same label information is set for the positioning modules set at the corresponding connection points on the bridge body to be moved and the fixed bridge body. The label information includes the installation position of the positioning module. After the positioning module is set, the preset moving range of each positioning module on the bridge body to be moved and the safety distance between any two positioning modules are set; Determine whether the movement of the bridge body to be moved is within a preset movement range according to the positioning information; If not, after the preset moving range and safety distance are set, according to the positioning information uploaded by the positioning module in real time, the Beidou system is used to determine the moving direction of the corresponding behavior module set on the bridge body to be moved and the distance between the corresponding two positioning modules based on the positioning module set on the fixed bridge body. The moving direction of the bridge body to be moved and the distance from the to-be-installed position are determined according to the positioning information uploaded by multiple positioning modules. When the movement of a certain positioning module exceeds its corresponding preset moving range, the first adjustment instruction and the first alarm information are output according to the actual movement of the positioning module; According to the positioning information output by the positioning module, the distance between any two positioning modules can be calculated. When the distance between the two positioning modules is less than the preset safety distance, it proves that a collision has occurred; When a collision occurs, the location of the collision is determined based on the tag information of the positioning module. If the location of the collision is a connected point, it proves that the construction is completed and an end signal is output; If the collision location is not a connection point, a second adjustment instruction and a second alarm message are outputted according to the collision location and the positioning information outputted by each positioning module.
4. An electronic device, characterized in that: It comprises a memory and a processor, wherein the memory stores a computer program of the construction method according to any one of claims 1 to 2 which can be loaded and executed by the processor.
5. A computer-readable storage medium, characterized in that: A computer program for the construction method according to any one of claims 1 to 2 is stored and can be loaded and executed by a processor.
Citation Information
Patent Citations
An overall lifting transport method of steel truss girder sections of a steel truss girder cable-stayed bridge
CN105317008A
BIM technology-based railway large-span continuous beam swivel construction management and control method
CN111021265A
Posture adjusting system and posture adjusting method after bridge rotation
CN111350138A
BIM-based railway continuous beam swivel construction method
CN111877184A
BIM-based steel truss member splicing safety protection method, device and system
CN113821857A